Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
SIHOR ELECTRICITY WORKS LTD.
Vs.
RESPONDENT:
THE GUJARAT ELECTRICITY BOARD AND ANR.
DATE OF JUDGMENT:
29/01/1969
BENCH:
RAMASWAMI, V.
BENCH:
RAMASWAMI, V.
SHAH, J.C.
GROVER, A.N.
CITATION:
1969 AIR 770 1969 SCR (3) 438
1969 SCC (1) 423
ACT:
Electricity (Supply) Act, 1948, Ss. 2(8) and 19(1)(b) (ii)-
Expression ’maximum demand’-Construction of-Conditions
precedent for enabling Electricity Board to make direct
supply in area of a licensee.
HEADNOTE:
The appellant carried on the business of generating and
distributing electrical energy within a specified area
tinder a licence granted to it under the Indian Electricity
Act, 1910. The respondent, Gujarat Electricity Board agreed
with the second respondent company to give direct supply of
electricity to its factory which was within the area of
supply of the appellant. The appellant brought a suit
against the respondents for declaration that the agreement
between the first and the second respondents without its
consent was illegal and ultra vires the powers of the first
respondent under the Electricity (Supply) Act, 1948, and
sought an injunction restraining the first respondent from
implementing the decision.
The appellant’s case was that the first respondent was not
entitled to give direct supply to the second respondent as
the "maximum demand" of the appellant at the time of the
request of the second respondent was 262 to 349 KVA between
September and December, 1959, and therefore. make than twice
the "maximum demand" of the second respondent which had
never exceeded 40 to 45 KVA. The first respondent
contended, however, that the "maximum demand" of the
appellant company at the time of request was less than twice
the "maximum demand" of 398 KVA asked for by the second
respondent from the first respondent. The trial court held
that the first respondent’s decision to give direct supply
to the second respondent was ultra vires its power under
section 19 (1)(b)(ii) of the Act. However, the first
appellate court allowed an appeal and the High Court
dismissed a further appeal holding, inter alia, that by
virtue of s. 19(1)(b)(ii) the comparison required to be made
was between the maximum demand of the licensee on the Board
at the time of request for direct supply based on
electricity actually supplied and taken during some
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
reasonable period immediately preceding the time of request
for direct supply, and the maximum demand which the
applicant wants to keep the Board ready on tap when
supplying electricity to the applicant.
On appeal to this the Court,
HELD : The appellant was entitled to the grant of a decree
in terms of the trial court’s decree.
The "maximum demand" as defined in section 2(8) of the Act
has relation only to an existing state of facts and there
can be no maximum demand in relation to a future period. On
a true construction of section 19(1)(b)(ii), what is
required to be compared for determining the applicability of
the clause with the maximum demand of the licensee on the
Board at the time of request for direct supply, was the
"maximum demand" by the applicant on the licensee at that
time and not any hypothetical or anticipated demand which
the applicant may call upon the Board be ready to supply.
The phrase "supplied and taken" in s. 2(8) shows that the
ascertainment of maximum demand is dependent upon the
electricity actually supplied and taken. in any particular
period in the past and not electricity which may be supplied
and taken in a future period, [444B]
439
There was no force in the respondent’s contention that the
words "asked for by any such person" must be construed to
mean any hypothetrical or anticipated demand which the
applicant may call upon the Board ,to be ready to supply.
Such an interpretation would be inconsistent with the
definition of "maximum demand" in section 2(8) of the Act.
There was no reason why the phrase "maximum demand" in
section 19 (1) (b) (ii) of the Act should be given two
different meanings one for the licensee and the other for
the consumer asking for the maximum demand. It cannot be
supposed that the legislature contemplated that the phrase
"maximum demand" should be given two different meanings in
the same clause. [444G]
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeals Nos. 452 and
453 of 1966.
Appeals by special leave from the judgment and order, dated
July 4, 1964 of the Gujarat High Court in Second Appeals
Nos. 33 and 34 of 1964.
P. A. Mehta, B. K. Mehta, K. L. Hathi and Atiqur Rehman,
for the appellant (in both the appeals).
I. N. Shroff, for respondent No. 1 (in both the appeals).
H. L. Anand and K. B. Mehta, for respondent No. 2 (in both
the appeals).
The Judgment of the Court was delivered by
Ramaswami, J. The appellant, the Sihor Electricity Works
Ltd., is a public limited company carrying on the business
of generating and distributing electrical energy under the
licence granted to it under the Indian Electricity Act,
1910, having its supply area within the limits of Sihor Town
situated in the district of Bhavnagar in Saurashtra. The
first respondent is the Gujarat Electricity Board which is a
Corporation constituted under the Electricity (Supply) Act,
1948 for the purposes of generation, supply and
distribution of electricity in the State. of Gujarat. The
second respondent is the Saurashtra Electrical and Metal In-
dustries (Private) Ltd., a private limited company carrying
on the business of manufacturing electrical accessories etc.
and having its factory at Sihor within the area of supply of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
the appellant company. The appellant company was originally
generating and distributing electricity but at the relevant
time it was a distributing licensee distributing the energy
purchased in bulk from the first respondent within its area
of supply.
The appellant brought a suit against the respondents in the
Court of Civil Judge (Junior Division) of Sihor being Civil
Suit No. 45 of 1960 to obtain a declaration that the
decision of the first respondent as contained in its letters
dated 3rd June, 1960 and 24th October, 1960 to give direct
supply to the factory of the second respondent within the
area of supply of the appellant and without its consent was
illegal and ultra vires its powers under
440
the Electricity (Supply) Act, 1948 (Act No. 54 of 1948)
(hereinafter called the Act), and for a permanent injunction
restraining the first respondent from implementing the said
decision. The case of the appellant was that the first
respondent was not entitled to give direct supply to the
second respondent as the ’maximum demand’ of the appellant
at the time of request of the second respondent was more
than twice the ’maximum demand’ asked. for by the second
respondent. The appellant company alleged that the maximum
demand of the appellant company in the relevant period,
namely, September 1959 to December 1959 was between 262 to
349 KVA while the maximum demand of the second respondent
had never exceeded 40 to 45 KVA. The first respondent
contested the suit on the ground that the decision was legal
and proper because the maximum demand of the appellant com-
pany at the time of request was less than twice the maximum
demand ’asked for’ by the second respondent from the first
respondent. It was contended that the demand ’asked for’ by
the second respondent was 398 KVA, and, therefore, the first
respondent was entitled in law to give direct supply to the
second respondent. The trial Judge held that the decision
of the first respondent to give direct supply of electricity
to the second respondent was ultra vires the power of the
first respondent under section 19(1) (b) (ii) of the Act and
was, therefore, null and void and gave a declaration to that
effect in favour of the appellant. The trial Judge,
however, refused to grant the consequential relief of
injunction on the ground that the Board being a public
authority could be expected to respect the law laid down by
the Court and it was, therefore, not necessary to issue any
injunction against the respondents, Aggrieved by the decree
passed by the trial Judge the two respondents filed separate
appeals in the District Court. The appellant preferred a
cross-objection contending that the trial Judge was in error
in refusing to grant injunction. The appeals and the cross-
objection were heard by the District Judge of Bhavnagar and
by a common judgment delivered on 12th October, 1963, the
District Judge accepted the contentions urged on behalf of
the respondents and allowed the appeals. The-District Judge
held that the jurisdiction of the Civil Court to entertain
the suit was excluded by reason of s. 76(1) of the Act and
the dispute between the parties being a dispute covered by
that section could be determined only in the manner provided
by that section, viz., by arbitration. The District Judge
also decided that the maximum demand asked for by the second
respondent was in excess of 50 per cent of the maximum
demand of the appellant at the time of request for direct
supply and the first respondent was entitled to give direct
supply of electrical energy to the second respondent under
s. 19(1) (b) (ii) of the Act. The District Judge
accordingly found that the suit was liable to fail not only
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
for want of jurisdiction but also on merits and accordingly
allowed the appeals and
441
dismissed the suit. Thereafter, the appellant preferred
appeals to the High Court of Gujarat being Civil Second
Appeals Nos. 33 and 34 of 1964. The said appeals came for
hearing before Mr. Justice P. N. Bhagwati, who dismissed the
same by a common judgment dated 4th July, 1964. The learned
Judge took the view that the Court had jurisdiction to hear
the suit as the provision for arbitration under s. 76 of the
Act was inserted in the statute not in the interest of
public good but for the benefit of individuals and therefore
either party can waive the right to insist on arbitration.
The learned Judge, however, held that the true effect of s.
19(1)(b)(ii) was that "the comparison required to be made
was between the maximum demand of the licensee on the Board
at the time of request for direct supply which would of
course be maximum demand based on electricity actually
supplied and taken during some reasonable period immediately
preceding the time of request for direct supply and the
maximum demand which the applicant wants to keep the Board
ready on tap when supplying electricity to the applicant".
These appeals are brought by special leave from the judgment
of the Gujarat High Court dated 4th July,, 1964 in Second
Appeals Nos. 33 and 34 of 1964.
The question of law presented for determination in this case
is whether the High Court was right in holding that section
19(1) (b) (ii) of the Act prescribed that a comparison must
be made between the actual maximum demand of the licensee
company and the anticipated maximum demand of the consumer
before the Electricity Board can decide to give direct
supply to the consumer within the area of supply of the
licensee company.
Section 19(1) of the Act states
"The Board may, subject to the provisions of
this Act, supply electricity to any licensee
or person requiring such supply in any area in
which a scheme sanctioned under Chapter V is
in force;
Provided that the Board shall not-
(a) supply electricity for any purpose
directly to any licensee for use in any part
of the area of supply of a bulk-licensee
without the consent of the bulk-licensee,
unless the licensee to be supplied has an
absolute right of veto on any right of the
bulk-licensee to supply electricity for such
purpose in the said part of such area, or
unless the bulk-licensee is unable or
unwilling to supply electricity for such
purpose in the said part of such area on
reasonable terms and conditions and within a
reasonable time, or
(b) supply electricity for any purpose to
any persons, not being a licensee for use in
any part of the
442
area of supply of a licensee without the
consent of the licensee, unless-
(i) the actual effective capacity of the
licensee’s ’generating station computed in
accordance with paragraph IX of the First
Schedule at the time when such supply was
required was less than twice the maximum
demand asked for by any such person; or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
(ii) the maximum demand of the licensee,
being a distributing licensee and taking a
supply of energy in bulk is, at the time of
the request, less than twice the maximum
demand asked for by any such person; or
(iii) the licensee is unable or unwilling to_
supply electricity for such purpose in the
said part of such area on reasonable terms and
conditions and within a reasonable time. "
Section 2(8) of the Act defines ’maximum
demand’ as follows
’Maximum demand’ in relation to any period
shall,
unless otherwise provided in any general or
special order of the State Government, mean
twice the largest number of kilowatt-hours or
kilo-volt-ampere-hours supplied and taken
during any consecutive thirty minutes in that
period".
Section 18 deals with general duties of the
Board and reads
"Subject to the provisions of this Act, the
Board shall be charged with the general duty
of promoting the coordinated development of
the generation, supply and distribution of
electricity within the State in the most effi-
cient and economical manner, with particular
reference to such development in areas not for
the time being served or adequately served by
any licensee, and without prejudice to the
generality of the foregoing provisions it
shall be the duty of the Board-
(a) to prepare and carry out schemes
sanctioned under Chapter V;
(b) to supply electricity to owners of
controlled stations and to licensees whose
stations are closed down under this Act;
(c) to supply electricity as soon as
practicable to any other licensees or persons
requiring such supply and whom the Board may
be competent under this Act so to supply-it
Section 26 of the Act clothes the Board with all powers and
obligations of a licensee under the Electricity Act, 1910,
with this
443
exception that certain sections, including section’ 22
relating to the duties and obligations of a licensee,, are
declared not to apply to the Board. Since section 22 is
excepted from its application to the Board,, it is evident
that unlike a licensee under the Electricity Act, 1910, the
Board is under no obligation to supply electricity to any
person applying to it for supply. Section 49 of the Act
empowers the.Board to fix the terms and conditions on which
it will supply electricity to a person other than a licensee
and that power is conferred in wide terms subject only to
the provisions of the Act and any regulations which may be
made by the Board in that behalf.
The legal position therefore, is that the Board cannot
supply electricity to any licensee or a person other than a
licensee unless the Board is competent to do so under the
Act. Under Section 19(1) the Board would ordinarily be
competent to supply electricity to a licensee or to a person
requiring such supply in any area in which a scheme
sanctioned under Chapter V is in force. But there are two
provisos which limit the general power of the Board to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
supply electricity. Proviso (a) relates to a case of a
licensee requiring supply of electricity in any part of the
area of supply of a bulk licensee. Proviso (b) is material
to the present case. This proviso enjoins the Board not to
supply electricity for any purpose to any person other than
a licensee for use in any part of the area of the licensee
unless the case falls within any of the three clauses,
namely, clauses (i), (ii) and (iii). The intention of the
legislature seems to be that if any person requires supply
of electricity for any purpose for use, in any part of the
area of supply of a licensee, he must approach the licensee
in the first instance and the licensee alone must have the
right to supply electricity to him unless of course the
licensee consents to his taking of supply of electricity
from the Board in which event the Board would, be free to
supply electricity to him. This provision was apparently
enacted with a view to protect the interest of the licensee
who has incurred capital expenditure in putting up
generating plants,. transformers, mains and transmission
lines and who should be therefore entitled to secure a
reasonable return by having a sufficient number of consumers
to take the electricity which may be generated by the
licensee or which may be taken in bulk by the licensee from
the Board. But the legislature engrafted certain exceptions
to this rule by enacting clauses (i), (ii) and (iii) and
providing that in cases covered by any of these clauses, the
Board shall be at liberty to supply electricity to any
person applying to it for supply despite the want of consent
of the licensee. It is common ground that the exceptions
set out in clauses (i) and (iii) do not apply to the present
case and the only exception relied on by the respondents is
that. set out in clause (ii). On behalf of the respondents
it was contended that the High Court has taken a correct
view with regard to the interpretation of S. 19 (1) (b) (ii)
of the
444
Act and the first respondent was entitled to supply
electricity to the second respondent without the consent of
the appellant as the conditions of clause (ii) of the sub-
section have been satisfied. We are unable to accept this
argument. In our opinion, the ’maximum demand’ as defined
in section 2(8) of the Act has relation only to an existing
state of facts and there can be no maximum demand in
relation to a future period, and, therefore, on a true
construction of section 1 9 ( 1 ) (b) (ii) of the Act what
is required to be’ compared for determining the
applicability of the. clause with the maximum demand of the
licensee on the Board. at the time of request for direct
supply, was the ’maximum demand’ by the applicant on the
licensee at that time and not any hypothetical or
anticipated demand which the applicant may call upon the
Board be ready to supply. It is manifest that section 2(8)
of the Act gives a technical meaning to the expression
’maximum demand’ by, defining it as twice the largest number
of kilowatt hours or kilo-volt-ampere hours supplied and
taken during any consecutive thirty minutes in any
particular period. It follows from the language of the
definition that the concept of maximum demand is a concept
based on existing facts and it is not possible to think of a
maximum demand in relation to a future point of time.
Reference should be made in this connection to the phrase
"supplied and taken" in section 2(8) of the Act. This
phrase also shows that the ascertainment of maximum demand
is dependent upon the electricity, actually supplied and
taken in any particular period in the past and not
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
electricity which may be supplied, and taken in a future
period. In other words, the ’maximum demand’ as defined in
s. 2(8) of the Act has always reference to a past period and
there can be no maximum demand in relation to a future
period. On behalf of the respondents attention was invited
to the words "asked for by any such person" in section 19(1)
(b) (ii) of the Act. But these words are inserted in the
section merely by way of description and they must be
construed, to mean that the Board will make direct supply
only when the applicant makes a request for such direct
supply from the Board and not otherwise. It is not possible
to accept the argument of the respondents that the words
"asked for by any such person" must be construed to mean any
hypothetical or anticipated demand which the applicant may
call upon the Board to be ready to supply. Such an
interpretation would be inconsistent with the definition of
’maximum demand’ in section 2(8) of the Act. We also see no
reason why the phrase ’maximum demand’ in section 19(1)(b)
(ii) of the Act should be given two different meanings one
for the licensee and the other for the consumer asking for
the maximum demand. It cannot be supposed that the
legislature contemplated that the phrase ’maximum demand’
should be given two different meanings in the same clause.
445
It was pointed out on behalf, of the respondents that if the
phrase maximum demand’ in section 1.9 ( 1) (b) (ii) of the.
Act is given the technical meaning as mentioned. in section
2(8) of the Act,, hardship may be caused in, certain cases.
It was said that an applicant, may not be taking
electricity, supplied by the licensee and may still be
desirous of taking electricity from the Board for the-first
time. Such an applicant would have no maximum demand at the
time of request for direct supply but when asking for direct
supply, he is required to intimate to the Board what is the
maximum demand he would require. It was said that the
applicant may have a potential peak demand which the
licensee may not be able to supply. In such a case it was
riot reasonable to require the applicant to approach the
licensee in the first instance and thereafter make an
application to the Board. It was also argued that there was
no reason why the applicability of clause (ii) should be
restricted only to persons taking electricity supplied by
the licensee. In our opinion, there is no warrant for this
argument. As we have already indicated the language of
section 19 (1 ) (b) (ii) of the Act must be construed in the
light of the definition of ’maximum demand’ contained in
section 2(8) of the Act. Upon that construction it is clear
that the applicability of clause (ii) is restricted to
persons taking electricity supplied by the licensee. There
is also no hardship caused to an applicant who may not take
electricity supplied by the licensee and who may be
desirous,of taking electricity for the first time from the
Board in view of his anticipated requirements. It is open
to such an applicant to take recourse to the provision of
clause (iii) of section 19 (1) (b) of the Act which provides
that the Board may supply electricity direct without the
consent of the licensee if the later is unable and unwilling
to supply electricity for the purpose of the applicant on
reasonable terms and conditions and within a reasonable
time. In our opinion, no anomaly or inconvenience would
result if the construction contended for on behalf of the
appellant with regard to section 19 (1) (b) (ii) of the Act
is accepted.
If our interpretation of s. 1 9 ( 1 ) (b) (ii) of the Act is
correct, the appellant is entitled to the grant of a decree
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
in terms of the trial Court’s decree. It is’ pointed out by
Mr. Justice Bhagwati in his judgment that right up to the
end of December, 1959 the maximum off take of electricity by
the second respondent from the appellant was not more than-
50 KVA. The maximum demand of the licensee on that period
was 291 KVA, and so, the conditions of s. 1 9 (1) (b) (ii)
of the Act were not satisfied. It follows that the first
respondent was not entitled under that clause to supply
electricity direct to the second respondent.
For the reasons expressed we hold that the judgment of the
Gujarat High Court in Second Appeals Nos. 33 and 34 of 1964
Sup CI/69-10
446
dated 4th July, 1964 and of the District Judge of Bhavnagar
dated 12th October, 1963 should be set aside and the
judgment and decree of the Civil Judge (Junior Division) at
Sihor dated 3 1st March, 1960 should be restored. The
appeals are accordingly allowed with costs in this Court and
the High Court.
R.K.P.S. Appeals allowed.
447