Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
GRID CORPORATION OF ORISSA LTD. & ANR.
Vs.
RESPONDENT:
BALASORE TECHNICAL SCHOOL
DATE OF JUDGMENT: 30/03/1999
BENCH:
S.R.Babu, S.N.Phukun
JUDGMENT:
RAJENDRA BABU, J. :
On April 28, 1961, the respondent entered into an
agreement with the appellant for supply of electrical energy
in which the contract demand was specified at 68 KWs and
unless a certain percentage of the contract demand was
utilised the respondent would be liable to pay minimum
charges as specified in the agreement. On July 18, 1966,
the tariff specified in the agreement was revised in terms
of Section 49 of the Electricity Supply Act and such tariff
as prescribed for general purpose tariff was made applicable
to the respondent. However, no bill in terms of the revised
rate as applicable to general purpose tariff was issued and
a bill for additional amount payable was sent to the
respondent. The respondent contended that the contract
demand should be reduced from 68 KWs to 31 KWs. With effect
from July 25, 1973, the respondent did not pay any amount to
the appellant in respect of the energy consumed either at
the revised rate effective from 1966 or at the old rate as
specified in the agreement and continued to consume the
energy without any payment at all. On account of
non-payment of the energy charges, supply was disconnected
to the respondent after due notice under Section 24 of the
Indian Electricity Act, 1910. The respondent challenged the
disconnection and the demand raised by the Board by invoking
the arbitration clause of the original agreement of 1961 and
filed O.S.No.127/77 under Sections 8 and 20 of the
Arbitration Act for reference of disputes to arbitration.
The Subordinate Judge, who considered this matter, allowed
the claim of the respondent and an appeal was preferred to
the High Court. In the appeal, a joint memo was filed to
the effect that the respondent shall enter into a fresh
agreement with the appellants and upon such agreement being
executed the appellants would resume supply to the
respondent; the respondent shall pay the charges from the
date of reconnection at the new tariff rate applicable to
the respondent; and arrears alleged to be due and claimed
by the appellants, if ultimately accepted by the Arbitrator
and made rule of the court shall be paid by the respondent.
On February 1, 1980, the respondent executed a fresh
agreement which contained a recital in clause 27 thereof
which provided that the arrears under the old agreement
shall be deemed to be arrears under the new agreement. The
Subordinate Judge appointed Justice H.Mohapatra, a retired
Judge of the High Court as the Arbitrator and referred five
questions involving law and facts for consideration of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
Arbitrator. On February 19, 1983, the Arbitrator made an
award after perusing the claims and counter-statement of the
parties and material on record and answered all the five
questions against the appellants and further held that no
amount was payable by the respondent towards charges for
consumption of electricity, although admittedly it had been
consumed until the date of disconnection, that is, December
30, 1976, and no amount had been paid either at the revised
rate or at the original rate with effect from February 16,
1973. When objection was filed under Sections 30 read with
Section 33 of the Arbitration Act, the Subordinate Judge set
aside the award principally on the ground that the award
runs contrary to the agreement. On appeal by the respondent
under Section 39 of the Arbitration Act, the High Court set
aside the order made by the Subordinate Judge and confirmed
the award made by the Arbitrator except in regard to one
aspect, namely, that the Orissa Sate Electricity Board is
not entitled to be paid anything by the respondent in
respect of their claims in relation to the agreement. The
High Court having noticed that the observations was outside
the reference confirmed the award on all other questions.
Hence this appeal. In this Court, on each of the question
referred to the Arbitrator answer is sought to be given by
contending that the view taken by the Arbitrator was wholly
outside the scope of the contract and hence perverse or
award made was without jurisdiction. However, the learned
counsel for the respondent contended that the view taken by
the High Court is in conformity with several decisions of
this Court including N.Chellappan vs. Secretary, Kerala
State Electricity Board & Anr., 1975 (1) SCC 289. It is
submitted that even if the Arbitrator had made a mistake
either in law or in fact in determining the matters referred
and such mistake does not appear on the face of the award,
the award cannot be interferred notwithstanding the mistake.
It is only when a proposition of law is stated in the award
and which is the basis of the award and that is erroneous
can the award be set aside or remitted on the ground of
error of law apparent on the face of the record. The
appellants, however, contended that the Arbitrator cannot
ignore the law or misapply it in order to do what he thinks
as just and reasonable even though it was a case of
non-speaking award. The courts are entitled to examine the
contract even though the contract was not incorporated into
the award and an Arbitrator being a creature of the contract
must operate within the four corners of the contract and
cannot travel beyond it either by misinterpreting the
contract or otherwise. In this case, the High Court is of
the view that a civil court does not sit on appeal against
the award and the power of the court when an award is
challenged is rather limited. The award of the Arbitrator
is ordinarily final and conclusive as long as the Arbitrator
has acted within its authority and according to the
principle of fair play. An Arbitrators adjudication is
generally considered binding between the parties for he is a
Tribunal selected by the parties and the power of the court
to set aside the award is restricted to cases set out in
Section 30 of the Arbitration Act. It is not open to the
Court to speculate where no reasons are given by the
Arbitrator, as to what impelled him to arrive at his
conclusion. If the dispute is within the scope of the
arbitration clause it is no part of the province of the
court to enter into the merits of the dispute. If the award
goes beyond the reference or there is an error apparent on
the face of the award it would certainly be open to the
court to interfere with such an award. In New India Civil
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
Erectors (P) Ltd.vs. Oil & Natural Gas Corporation, 1997
(11) SCC 75, this Court considered a case of non-speaking
award. In that case the Arbitrator had acted contrary to
the specific stipulation/condition contained in the
agreement between the parties. It was held that the
Arbitrator being a creature of the contract must operate
within the four corners of the contract and cannot travel
beyond it and he cannot award any amount which is ruled out
or prohibited by the terms of the agreement. In that
contract it was provided that for construction of housing
unit, in measuring the built-up area, balcony areas should
be excluded. However, the Arbitrator included the same
which was held to be without jurisdiction. In the same
manner it was also held that the price would be firm and not
subject to any escalation under whatsoever ground till the
completion of the work and awarding any sum as a result of
escalation was not permissible. To the same effect is the
decision in Associated Engineering Co. vs. Government of
Andhra Pradesh & Anr., 1991 (4) SCC 93. It was stated that
if the Arbitrator commits an error in the construction of
the contract, that is an error within his jurisdiction. But
if he wanders outside the contract and deals with matters
not allotted to him, he commits a jurisdictional error and
an umpire or Arbitrator cannot widen his jurisdiction by
deciding a question not referred to him by the parties or by
deciding a question otherwise than in accordance with the
contract. A conscious disregard of the law or the
provisions of the contract from which he has derived his
authority vitiates the award. The principle of law stated
in N.Chellappans case (supra) on which a strong reliance
has been placed by the learned counsel for the respondent
would make it clear that except in cases of jurisdictional
errors it is not open to the court to interfere with an
award. That proposition is unexceptionaable. However, from
a reading of the decisions of this Court referred to earlier
it is clear that when an award is made plainly contrary to
the terms of the contract not by misinterpretation but which
are plainly contrary to the terms of the contract would
certainly lead to an inference that there is an error
apparent the award results in jurisdictional error in the
award. In such a case the courts can certainly interfere
with the award made by the Arbitrator.
In the present case, the view taken by the High Court
as to the construction of Section 3 of the Orissa
Electricity Supply Act appears to us to be correct. In that
provision the proceedings which relate to a challenge to the
power of the Board to enhance the tariff are subject matter
of arbitration. Such proceedings would abate and not in
other cases. The High Court, while considering the question
whether the Orissa Electricity Supply Board is not entitled
to be paid anything by the respondent in respect of their
claims relating to the agreement dated April 28, 1961 was
outside the scope of arbitration but failed to see that the
amounts due under the agreement dated April 28, 1961 became
part of the agreement entered into subsequent to the joint
memo filed before the High Court. In the agreement dated
February 1, 1980, clause 27 provided that the arrears under
the old agreement shall be deemed to be arrears under the
this agreement . Therefore, if the award made by the
Arbitrator was incorrect in regard to that aspect of the
matter, other questions referred to the Arbitrator formed
integral part of the same and, therefore, the entire award
had to be set aside. Even otherwise in respect of each of
the question referred to the Arbitrator, the answers given
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
by him would indicate that the same has been given in utter
disregard of the contract and, therefore, the view taken by
the Subordinate Judge in this case appears to be correct and
the High Court ought to have accepted the same.
In the result, the order made by the High Court is set
aside and the order made by the Subordinate Judge stands
restored and the matter shall stand remitted to the
Arbitrator for fresh consideration in accordance with the
law and in the light of this order. No order as to costs.