Full Judgment Text
Non-Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 8645 OF 2014
(Arising out of Special Leave Petition (Civil) No.16210 of
2014)
Orissa Manganese & Minerals Ltd. …Appellant
Versus
Synergy Ispat Pvt. Ltd. …Respondent
J U D G M E N T
Chelameswar, J.
1. Leave granted.
JUDGMENT
th
2. Aggrieved by the judgment dated 16 May 2014 of the
High Court of Calcutta in A.P.O.T. No.460/2012, the
respondent therein filed this appeal.
3. The impugned order is a reversing order in appeal
th
against the judgment and order dated 5 September, 2012
of single Judge of the Calcutta High Court in A.P.
1
Page 1
No.245/2012 by which the learned single Judge rejected an
application filed under Arbitration & Conciliation Act, 1996
holding that the appellant was not entitled to interim
| s claim f | or speci |
|---|
agreement to sell iron ore.
4. The factual background of the case is as follows.
5. The appellant herein secured a mining lease originally
from the State of Bihar (now Jharkhand) in the year 1996.
However, the appellant could not secure the necessary
approval under the Forest Conservation Act, 1980.
Therefore, the mining operation had to be kept under
suspension.
JUDGMENT
6. Sometime in the year 2005-2006, at the instance of the
respondent herein, the appellant entered into two
agreements. According to the appellant (we say so because
what exactly is the purport of the agreements is a matter
pending consideration in arbitration, therefore, we do not
wish to make any definite statement in that regard), one of
2
Page 2
the agreements is that the mining activity pursuant to the
mining lease secured by the appellant (referred to supra),
shall be carried on by M/s. Metsil Exports Pvt. Ltd. (Metsil)
| associa | te comp |
|---|
herein on various terms and conditions, the details of which
may not be necessary. The agreement is dated 27.2.2005
between the appellant herein and Metsil. The agreement is
styled as ‘Raising Contract’. The second agreement is
between the appellant and the respondent herein for the
sale of iron ore extracted by Metsil for being utilised in a
sponge iron plant to be jointly set up by the appellant and
the respondent herein. According to the appellant, both the
contracts are inter dependent. Failure of the first contract
JUDGMENT
automatically results in failure of the second contract.
nd
7. However, the appellant claims to have realised on 22
June, 2007 that the ‘Raising Contract’ by which the activity
of mining was sought to be entrusted to Metsil is in violation
of Rule 37 of the Mineral Concession Rules, 1960, therefore,
the appellant sent letters to the respondent as well as to the
3
Page 3
Metsil purporting to terminate both the contracts. It is
stated at the Bar that, admittedly, Metsil never questioned
the termination of the contract. However, the respondent
| pute the | legality |
|---|
appellant in terminating the agreement for sale of iron ore.
The respondent filed an application (A.P. No.922/2011) under
Section 9 of the Arbitration and Conciliation Act, 1996
praying, inter alia, for an order of injunction restraining the
appellant herein from selling iron ore to the third party. It
may be mentioned here that subsequent to the decision of
the appellant to terminate both the agreements, the
appellant commenced the mining operation from January
2009. The learned single Judge of the Calcutta High Court,
JUDGMENT
by his order dated 14.11.2011, declined to grant any ad
interim order as sought by the respondent. By an order
dated 14.3.2012, the said A.P. No.922/2011 was disposed of.
8. Thereafter, the respondent preferred another
application in A.P. No.245/2012 in which an interim order
came to be passed on 29.3.2012 restraining the appellant
4
Page 4
herein from selling any part of the iron ore extracted from
the mines in question without first offering the entire extract
to the respondent. Aggrieved by the same, the appellant
| tter in ap | peal un |
|---|
the Arbitration and Conciliation Act, 1996 before a Division
Bench of the High Court in A.P.O.T. No.184/2012. By a
consent order dated 17.4.2012 in the abovementioned
A.P.O.T., the parties agreed for the appointment of one Shri
Pradeep Kumar Ghosh, Senior Advocate, as the Arbitrator to
adjudicate upon the dispute between the parties. The said
A.P.O.T. came to be finally disposed of by an order dated
9.5.2012 with a direction that the appellant would sell iron
ore to the respondent, if the respondent so opted, at the
JUDGMENT
prevailing market price during the pendency of the
arbitration proceedings.
9. The respondent herein filed an Special Leave Petition(C)
No.20425/2012 in this Court challenging the order dated
9.5.2012 passed in A.P.O.T. No.184/2012. The said SLP was
5
Page 5
disposed of by an order dated 27.7.2012, the relevant
portion of the order reads as follows:
| ally modify t<br>s will conti | he order pa<br>nue till the |
|---|
The above observations of the Division Bench fully protect the interest of
both parties………..”
10. A.P.O.T. No.245/2012 eventually came to be disposed
of by an order dated 5.9.2012. The relevant portion of the
order reads as follows:
“The Petitioner is not entitled to any interlocutory injunction in aid the
claim for specific performance of the selling agreement that it has carried
to the arbitral reference. In the light of the prima facie view taken that the
Metsil and the petitioner combine had entered into a composite
arrangement with the respondent, the petitioner’s knowledge of the alleged
breach of the agreement by the Respondent would date back several
months before it made the polite enquiry with the respondent by its letter
of December 24, 2009. Such delay would amount, in the circumstances to
latches and conduct encouraging the respondent to believe in the
petitioner’s endorsement and acceptance of the breach. The petitioner is
not entitled to any order in furtherance of its claim on account of the
negative covenant since the selling agreement cannot be seen to be a
stand-alone contract. In any event, the negative covenant in clause 14.1 of
the selling agreement entitled the petitioner to exclusively obtain the ore
extracted from the Ghatkuri mines by Metsil and the petitioner ought to
have been aware, in the light of the facts now brought on record by the
JUDGMENT
6
Page 6
respondent, that the raising agreement with Metsil had been terminated by
the respondent.”
11. Aggrieved by the same, the respondent carried the
| A.P.O.T<br>High Co | . 460/2<br>urt had |
|---|
the single Judge in A.P. No.245/2012, thereby, allowing
Section 9 application filed by the respondent in part. The
operative portion of the order reads as follows:
“The respondent is restrained by an order of injunction to sell the iron ores
excavated from the disputed mines to any third party without first offering
to the appellant and is, further, directed to maintain accounts of the iron
ores raised from the said mines since the commencement of the mining
operation subject, however, to the result of the arbitral proceeding.
We make it clear that the findings arrived at by the Hon’ble Single Judge
and, also, by us are limited for the purpose of disposal of the application
under Section 9 of the Arbitration and Conciliation Act and are without
prejudice to the rights and contentions of the parties before the learned
arbitrator.”
JUDGMENT
12. We have heard Shri Kapil Sibal, learned senior counsel
appearing for the appellant and Shri Salman Khurshid,
learned senior counsel appearing for the respondent.
13. The impugned order is an order passed in a proceeding
arising in an application under Section 9 of the Arbitration &
Conciliation Act, 1996. The arbitration proceedings between
the parties herein are admittedly pending where the main
7
Page 7
question is - whether the respondent is entitled to seek
specific performance of the agreement dated 27.02.2005 by
which the appellant agreed to sell iron ore excavated from
| the agr | eement |
|---|
the answer to the said question is in affirmative then the
next question would be – what is the rate at which the
appellant is required to sell the iron ore to the respondent?
14. By the order under appeal, the High Court directed the
appellant not to sell the iron ore to any third party without
first offering the same to the respondent herein and also to
maintain accounts of the iron ore raised by the appellant
from the said mines from the date of commencement of the
mining operation.
JUDGMENT
15. It is the categoric stand of the appellant herein in the
SLP that during the pendency of this litigation, the appellant
has already set up a beneficiation-cum-pelletisation plant
where the entire quantity of iron ore extracted by the
appellant is being consumed as a raw material. Therefore,
the question of the appellant selling the iron ore to any third
8
Page 8
party does not arise at all. Consequently, the second
question of offering the ore for sale to the respondent before
selling it to a third party equally does not arise.
| notice | on18.7. |
|---|
appeal, it was directed by the Court that the appellant “will
maintain record/account of all the ore consumed” by the
appellant “during the pendency” of this matter.
17. When the matter was taken up for hearing it was once
again reiterated by the appellant that they have in fact been
captively consuming the entire iron ore extracted from the
mines in question.
18. Shri Sibal, learned senior counsel appearing for the
JUDGMENT
appellant made a submission at the bar that this Court may
record an undertaking made by the appellant that the
appellant will not sell any part of the iron ore extracted from
the mines in question to any third party during the pendency
of the arbitration proceedings. He also made a submission
9
Page 9
that the entire iron ore extracted would be consumed
captively in the plant belonging to the company.
| r the re | sponden |
|---|
respondent has existing export obligations incurred on the
basis of the agreement between the parties herein (referred
to supra) and, therefore, the appellant must be directed to
sell the iron ore excavated by it to the respondent at the
current market rate subject to the condition that the
respondent is entitled to recover the differential amount
between the current market price and the amount agreed
upon between the parties by the agreement in question, in
the event of the respondent’s success in the arbitration
JUDGMENT
proceedings.
20. In view of the categorical assertion made by the
appellant and the undertaking that the appellant would
consume the entire iron ore excavated captively, we do not
see any reason to give any direction to the appellant to sell
the iron ore to the respondent during the pendency of the
10
Page 10
arbitration. Such a direction, in our opinion, would virtually
amount to the enforcement of the agreement in issue
without adjudication of the right of the respondent to seek
| of the a | greeme |
|---|
appellant company were to be selling the iron ore excavated
by it to any third party, there was some justification by the
respondent to seek an interim direction to the appellant to
sell the ore to the respondent, subject ofcourse to the
determination of the cause finally in the arbitration
proceedings. But it is not the case here.
21. The learned senior counsel for the respondent further
submitted that in case an interim order is not granted, even
if the respondent eventually succeeds in the arbitration
JUDGMENT
proceedings and obtains an award for the specific
performance of the agreement in question, the success
would remain only on paper as huge amount of mineral
excavated by the appellant would already have been sold by
that time and there is no way of the respondent obtaining
the said mineral.
11
Page 11
22. No doubt, if the respondent eventually succeeds in the
arbitration, it would be entitled to specific performance of
| on for th | e loss su |
|---|
of the non supply of the minerals by the appellant during the
pendency of the arbitration proceedings.
23. For the abovementioned reasons, we dispose of this
appeal recording an undertaking of the appellant that during
the pendency of the arbitration proceedings the appellant
will not sell any part of the iron ore excavated from the
mines covered by the agreement in question and such ore
would be consumed captively by the appellant in its plant
JUDGMENT
and the appellant would maintain a complete account of the
minerals excavated and consumed captively by the
appellant.
24. In the facts and circumstances of the case, there will be
no order as to costs.
12
Page 12
…………………………. J .
(J. Chelameswar)
…….………………..…. J .
(A.K. Sikri)
New Delhi;
September 12, 2014
JUDGMENT
13
Page 13