Full Judgment Text
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
1
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.8606 OF 2019
(Arising out of Special Leave Petition (Civil)No.5413 of 2019)
THE MANAGER, THE MAHARASHTRA STATE
COOPERATIVE BANK LTD. …Appellant
VERSUS
FARMER BANK EMPLOYEES COOPERATIVE
HOUSING SOCIETY LTD. AND ORS. …Respondents
WITH
CIVIL APPEAL Nos.8607-08 OF 2019
(Arising out of Special Leave Petition (Civil)Nos.5414-5415 of 2019)
THE FARMER BANK EMPLOYEES COOPERATIVE
HOUSING SOCIETY LTD. …Appellant
VERSUS
THE MANAGER, THE MAHARASHTRA STATE
COOPERATIVE BANK LTD. AND ORS. …Respondents
J U D G M E N T
Uday Umesh Lalit, J.
Signature Not Verified
Digitally signed by
INDU MARWAH
Date: 2019.11.14
17:26:56 IST
Reason:
1. Leave granted.
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
2
2. These Appeals arise out of (i) the judgment and order dated
08.02.2018 passed in First Appeal No. 255 of 2016 and (ii) order dated
24.09.2018 passed in Review Application No. 333 of 2018 in said First
Appeal by the National Consumer Disputes Redressal Commission, New
Delhi (‘the National Commission’, for short).
3. The Appellant-Bank is the apex bank of all District Central
Cooperative Banks in State of Maharashtra and is also a scheduled bank in
terms of the Banking Regulation Act, 1949. In response to an
advertisement published by the Respondent No.2 (Nagpur Improvement
Trust) offering an extent of land admeasuring 2709.701 square metres
consisting of 14 plots, the Appellant made an application and was allotted
said land on 02.11.1973 against the premium of Rs.90,300/-. One of the
conditions for allotment was that the plot shall be used for residential
purposes. The possession of the plot was immediately handed over. Soon
thereafter, the Appellant applied for variation in sub-division and requested
that the entire land be divided into 16 plots instead of 14 plots as was
initially contemplated. The request was allowed and the land was sub-
divided into 16 plots.
4. The Appellant, thereafter, constructed 28 tenements on 14 plots out
of 16 plots while the other two plots were kept vacant. With the idea of
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
3
making tenements available to the persons working with the Appellant in
the category of peons, applications were invited from interested persons. It
appears that only 19 persons satisfied the requirements and therefore 9
persons belonging to the category of clerks were also accommodated. All
the 28 tenements were thus allotted to 28 employees of the Appellant
sometime in March 1976. Upto the stage of allotment not a single paisa
was paid by any of the employees. These employees were given the
facility of financial support by the Appellant where interest was charged at
concessional rate and home loans were made available to them.
5. Though the allotment of said 28 tenements was done in March
1976 itself and possession was given, the Society of the employees did not
get any lease executed as there were existing loans which were yet to be
cleared by each of the employees. The lease in respect of the entire extent
of land was therefore got executed in the name of the Appellant by
Respondent No.2, the period of lease being 03.11.1973 to 31.03.2004.
After the loans were repaid, the Executive Committee of the Appellant
passed Resolution No.3 on 21.1.2004 resolving that since the loans were
repaid, the tenements and the concerned plots be transferred in the names
of those employees or their legal heirs by completing all legal formalities.
Though, the Resolution was passed on 21.01.2004, the formalities could
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
4
not be completed and as the period of lease had come to an end, the lease
was got renewed from Respondent No.2 in favour of the Appellant on
15.02.2011 for further period of 30 years from 01.4.2004 to 31.03.2034.
6. On 16.04.2012 the Society of the employees i.e. the Respondent
No.1 herein filed Complaint No.10 of 2012 before the State Consumer
Disputes Redressal Commission, Nagpur (‘the State Commission’, for
short) under Section 12 of the Consumer Protection Act, 1986 (hereinafter
referred to as ‘the Act’) submitting inter alia that:-
“5. The management of Non-applicant No.2 bank decided
to undertake housing scheme for the employees working as
peons with Non-applicant No.2. And, therefore, in
response to an advertisement in local newspaper in the
year 1973 published by the Non-applicant No.1 offering
residential plots to the general public in the old Subhedar
Layout locality under Khasara No.58 & 59, known as
Sakkardara Street expansion scheme, the Non-applicant
No.2 contracted the Non-applicant No.1 to purchase 14
plots for its employees in peon category. The proposal of
Non-applicant No.2 was accepted by Non-applicant No.1
and 14 plots bearing Nos.83 to 96 were allotted to Non-
applicant No.2 Bank for a total consideration of
Rs.90,300/- (Rupees Ninety thousand Three Hundred Only)
admeasuring 2709.701 sqr. Mtr i.e. 29,167 sqr. Ft. of area.
Initially it was proposed by the Board of Directors of the
Non-applicant No.2 to construct 2 tenements on each plot
totalling 28 tenements. However, the then Local manager
at the Regional Office, Nagpur of Non-applicant No.2 got
the 14 plots divided into 16 plots with the approval of Non-
applicant No.1. The plots were renumbered as 83-96 + 89A
and 90A.
6. The Non-applicant No.2 started collecting monthly
subscription from those employees who registered their
names to participate in the scheme, with a view to create
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
5
their 10% contributory fund to avial 90% of loan facility as
against the cost of their respective tenements.
7. Thereafter, Non-applicant No.2 engaged M/s Planarch
an Architectural firm and got the tenement plans sanctioned
from Non-applicant No.1. The Non-applicant No.2 then
engaged Shri N.T. Vyas, a building contractor, to construct
28 tenements with its own funds. However, the Non-
applicant No.2 restricted the construction of tenements to
28 only instead of 32 and 14 plots and 2 plots remained
vacant as because the Board of Director of Non-applicant
No.2 Bank at Head Office at Mumbai did not approve the
subdivision of plots from 14 to 16.
8. At the time of completion of construction of 28
tenements, only 19 peons confirmed their participation and,
therefore, 9 employees from clerical cadre were
accommodated in the scheme and allotment of tenements
was done in March 1976. In fact, if the Non-applicant
No.2 would have constructed 4 more tenements, the same
could have been allotted to those desirous employees in
future. However, for the reason best known, the Non-
applicant No.2 kept 2 plots vacant, for the past 38 years.
9. The Non-applicant No.2 initially incurred all expenses
relating to completion of the project as mentioned below:-
| Sr.No. | Particular | Amount (Rs.) | Security<br>Deposit | Total (Rs.) |
|---|---|---|---|---|
| 1. | Cost of Land | 90,300.00 | -- | 90,300.00 |
| 2 | Ground Rent<br>(1974-75) | 1,806.00 | -- | 1,806.00 |
| 3 | Security<br>Deposit<br>(NIT) | -- | 800.00 | 800.00 |
| 4. | Steel | 47,845.48 | -- | 47,845.48 |
| 5 | Cement | 87,634.40 | -- | 87,634.40 |
| 6 | Contractor’s<br>Bill | 3,69,855.19 | -- | 3,69,855.19 |
| 7 | Architect<br>Feed | 19,364.80 | -- | 19,364.80 |
| 8 | Supervisor’s<br>charges | 3,600 | --- | 3,600 |
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
6
| 9 | Water Meter | 1,736.00 | 3,920.00 | 5,656.00 |
|---|---|---|---|---|
| 10 | Electricity<br>Connection | 3,280.00 | 1,400.00 | 4,680.00 |
| 11 | Debentures<br>Purchased for<br>Electricity | -- | 2,800.00 | 2,800.00 |
| 12 | Other<br>expenses | 116.00 | -- | 116.00 |
| Total | 6,25,537.87 | 8,920.00 | 6,34,457.87 |
The total cost of the project including cost of land was
worked out at Rs.6,34,457.87 and by dividing this amount
by 28 the cost of each tenement was worked out at
Rs.22,659.20 which obviously includes the proportionate
cost of 2 vacant plots admeasuring 3600 sq.ft. of area. The
Board of Directors of the Non-applicant No.2 Bank in its
meeting held on 12.01.1977 approved the cost of project
and cost of each tenement and also approved housing loan
to each employee as per their eligibility. It was also
resolved by the Board of Directors to transfer the entire
property in the name of society along with loan amount
sanctioned to 28 members and started effecting recovery of
loan through society via their monthly salaries. However,
due to sub-division of 14 plots into 16 plots and
constructing only 28 tenements, every member had to
sacrifice the benefit of 12 sq.ft. of permissible construction
are even after paying the cost and suffered a permanent
irreparable loss.
…
11. As stated earlier, the Non-appliant No.2 paid the price
of 16 plots. The expenditure incurred on construction and
for other purposes was initially borne by Non-applicant
No.2. However, both the Non-applicant No.1 and Non-
applicant No.2 cheated the Complainant and its members
by executing the lease deed of 16 plots for a period of 30
years commencing from 03.11.1973 to 31.03.2004 in
favour of Non-applicant No.2. This document of lease was
executed on 26.04.1979 i.e. 3 years after handing over the
possession of tenements in March 1976 and further after its
own decision of 12.01.1977 taken by the Board of
Directors of Non-applicant No.2 Bank to transfer the
property in favour of Complainant Society. However, the
annual lease rent is being paid by the Complainant society
since beginning and up till now over Rs.70,000/- are paid
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
7
towards rent without any title to the land. Now, therefore,
the Complainant or its members do not possess any title to
the property they are occupying even though they have
discharged their loan liability way back on their respective
superannuation or on the expiry of term of repayment of
loan. Out of 28 allottees, 20 members have died and the
question of succession to the property has arisen before the
Complainant Society. However, the Complainant Society
is totally helpless to resolve the issue as the title of the said
16 plots of land is with the Non-applicant No.2.”
In para 13 of the complaint, various options were suggested by
Respondent No.1, one of the suggested options namely option ‘e’ being:-
“The Non-applicant No.2 could have constructed 4
more tenements on remaining two vacant plots out of
16 plots and could have allotted them to the interested
employees easily as because a large number of
employees of Non-applicant No.2 have sought housing
loan benefit from Non-applicant No.2 thereafter for
their housing needs. The Non-applicant No.2 could
have also refunded the cost of two vacant plots
originally shared by 28 employees or adjusted to their
loan accounts.”
The prayers made in the Complaint were as under:-
“i. Direct the Non-applicant No.1 to renew
the lease of 16 Plots No. 83 to 96 and 89A and
90A in favour of the Complainant-Society
within two months from the date of order.
ii. Direct the Non-applicant No. 2 to pay the
cost for renewal of lease of 16 plots to the
Complainant-Society immediately as and when
demanded by the Complainant Society.
iii. Direct the Non-applicant No. 2 to pay the
price of two vacant plots, if it desires to retain
for construction, as per prevailing market price
which amounts to Rs.98,00,000/- (Rupees
Ninety Eight Lakhs Only).
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
8
iv. Direct the Non-applicant No. 3 to accept
and register the document of Sale Deed that
would be executed by Complainant Society in
favour of each member or legal heirs of the
deceased members free of stamp duty and
registration charges as per Government
notification dated 14.03.1980.
v. Direct the Non-applicant No.1 and 2 to
pay Rs.1,00,000/- each to Complainant Society
for harassment and mental agony caused to
members over the years.
vi. Saddle the cost of Rs.20,000/- on Non-
applicant No.2 bank for filing the complaint.”
7. In its written statement the Appellant denied the claim made by the
Respondent No.1 and submitted that the dispute raised by the Respondent
No.1 could not be a consumer dispute within the meaning of the Act and,
in any case, the complaint was barred by time as per Section 24A of the
Act.
8. It was observed by the State Commission that the entire cost of
construction of tenements and other charges were paid by the concerned
employees and as such nothing was due from those employees; that the
Appellant was a service provider in terms of the Act and the complaint was
maintainable. Finding the Appellant to be deficient in rendering of service
in that it had not got the lease deed of the plots executed in favour of the
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
9
Respondent No.1 well-in-time and had thereby caused loss to the
Respondent No.1, the complaint was allowed with following directions:-
“ii. It is directed that OP No.2 shall take
suitable steps to get renewed & registered the
lease deed of plot Nos. 83 to 96, 89A & 90A
described in the complaint through the OP No.1
NIT, in favour of the complainant society within
two months from receipt of copy of this order.
iii. The complainant shall bear expenses of
renewal and registration of that lease deed as per
the rates applicable as on 26.04.1979 and the OP
No.2 Bank shall bear the additional expenses for
the same as required on the date of the renewal
and registration of that lease deed.
iv. The OP No.2 bank shall also pay
compensation of Rs.10,000/- to the complainant
towards physical and mental harassment caused
to its members and shall also pay cost of this
complaint amounting to Rs.5,000/- to the
complainant.”
9. The Appellant, being aggrieved, filed First Appeal No. 255 of 2016
before the National Commission. Submissions raised by the Appellant
were noted as under:-
“5. Heard the learned counsel for the parties
and perused the record. Learned counsel for the
appellant stated that the State Commission has
given total financial responsibility for getting the
lease deed executed in favour of the Respondent
No.1. It was also stated as the matter was under
litigation, the bank has already got the lease
extended for another 30 years from the
Respondent No.2 in favour of the original
allottee i.e. bank. Now, the only question
remains that the lessee is to be transferred to the
Respondent No.1 Society. It was also contended
by the learned counsel that out of the 16 plots
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
10
only 14 plots have been utilized and the two
plots are still vacant and have not been allotted
to any employee. Thus, these two plots remain
the property of the bank and that cannot be
leased to the Respondent No.1 Society.
6. Therefore, it is not possible to implement
the order of the State Commission fully. It is
further argued for the appellant that the State
Commission has ordered all the expenses in
registration of the lease deed to be borne by the
appellant bank over and above the expenses of
registration in 1979. It is a common known
practice that the purchaser has to bear the burden
of stamp duty and registration charges.
Therefore, even if the lease deed is transferred in
the name of Respondent Society, the expenses
are to be borne by the society or the Society
members and not the appellant bank. It was
requested by the learned counsel that on both
these counts, the order of the State Commission
is not justified and needs to be set aside.”
The discussion was as under:-
“10. I have given a thoughtful consideration to
the arguments advanced by the learned counsel
for the parties and have examined the record. It
is true that out of 14 plots, the bank has got 16
plots made, however on the same land 14 plots
have been allotted and 2 plots have been left out.
The State Commission has passed the order in
respect of the plot Nos. 83 to 96, 89A to 90A.
The question is now of transferring the lease
deed of Respondent No.1 and its members.
Lease deed has been renewed in the name of the
Bank, there should be no difficulty in
transferring the lease to Respondent No.1
Society or its members as the case may be
according to the provisions of rules of NIT or
any other relevant law.
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
11
11. So far as the question of expenditure for
transferring of lease deed is concerned, in my
view, as the registration will be done under the
current law and the current law does not exempt
Cooperative Society for any stamp duty,
therefore, the stamp duty will have to be paid by
the consumers as is the law of the land.
However, as the Respondent No.1 has lost the
opportunity of getting free registration done
under the old law, due to deficiency and delay
caused by the action or omission of the appellant
bank, the appellant bank is ordered to share 50%
of the total expenditure including registration
charges and the stamp duty or any other
charges/expenses in connection with the
registration of lease deed in favour of the
Respondent No.1 Society. Accordingly, the
order dated 27.01.2016 of the State Commission
be complied with by both the parties within a
period of three months. The compensation and
cost as awarded by the State Commission is
upheld.”
10. In this Appeal, we heard Mr. M.Y. Deshmukh, learned Advocate
for the Appellant, Mr. Kishor Ram Lambat, learned Advocate for the
Respondent No.1 and Mr. Satyajit A Desai, learned Advocate for the
Respondent No.2.
11. The facts on record clearly indicate that neither the Respondent
No.1 nor any of its members were involved when the initial allotment was
made by the Respondent No.2 in favour of the Appellant, when 16 plots
were carved out from the allotted land and 28 tenements were constructed.
The tenements were constructed by the Appellant to take care of the needs
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
12
of its employees for housing. The facility of loans was also extended to
each of the allottees and the finance was made available at comfortable
rate of interest. It is accepted that there was absolutely no profit motive
behind the exercise and the Appellant did not even demand any interest in
respect of funds employed by it and what was sought to be recovered was
only the element of actual costs incurred by it.
12. It is also clear from the record that the Resolution to transfer the
land in favour of the employees or the legal heirs was passed by the
Appellant on 21.01.2004. There is nothing on record to indicate that any
requisition or demands were made by the Society to have the land
transferred and yet there was any delay on part of the Appellant in acting in
terms of the Resolution. There was, thus, no deficiency on part of the
Appellant or refusal on its part to act in terms of the aforesaid Resolution
dated 12.01.1977. If, as a result of any delay in execution of the document
in favour of the Society for which the Appellant was not responsible, the
Society would now be required to pay stamp duty at an enhanced rate, that
by itself does not give any entitlement to seek relief against the Appellant.
13. It is true that the tabular chart extracted in para 9 of the complaint
denotes that the cost of land as well as the actual expenditure incurred in
erecting 28 tenements aggregated to Rs.6,34,457.87, which was divided by
28, being number of tenements, to arrive at what would be the actual cost
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
13
relatable to each of those tenements. After receiving financial
accommodation and other advantages, each one of the tenement holders
had made good such amount. It was, therefore, contended that all the
tenement holders together had some interest in said two vacant plots.
However, the documents on record do not indicate any intention on
part of the Appellant that any interest in respect of said two plots was
intended to be created. The idea was to make available tenements to the
concerned on no profit no loss basis and not to let them have those two
plots and enable them to profiteer out of the transaction. That is precisely
why one of the alternatives suggested by the Respondent No.1 to resolve
the dispute was option ‘e’ in para 13 as extracted hereinabove. The relief
in the complaint gives measure of the value of those plots which was stated
to be in the region of Rs.98 lakhs in the year 2012. The nature of reliefs
claimed by Respondent No.1 indicates that apart from 28 tenements and
the land appurtenant thereto, the Respondent No.1 was also desirous of
securing interest in respect of said two plots.
14. As stated above, it was never the intent of the Appellant and there
is nothing on record to even suggest that the idea was to transfer interest in
respect of those two plots in favour of the employees or the Society formed
by the employees. This issue was squarely raised before the National
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
14
Commission but the matter was not considered at all. Be that as it may, we
have gone through the record and do not find any indication or even a
whisper that any decision was taken to transfer interest in relation to those
two plots as well.
15. The fact of the matter however remains that some contribution
towards cost of land was made by all the tenement holders. If the amount
representing cost of land was Rs.90,300/- and had there been 32 tenements,
individual share of every tenement holder would have come to
approximately Rs.2,822/-. However, dividing said amount by number 28,
the contribution that each of the tenement holder actually paid was
Rs.3,225/-; which would mean that roughly Rs.400/- extra were charged
from each one of them. Accepting the plea taken by the Respondent No.1
in option ‘e’ in para 13 as mentioned hereinabove, interest of justice, in our
view, would be met if the appellant is directed to make over to every
tenement holder a sum of Rs.10,000/- in compensation for having
recovered Rs.400/- over and above what logically could have been
recovered from each one of them. It is, of course, left to the appellant
either pay to each tenement holder a sum of Rs.10,000/- or transfer the
entire land to the Society.
16. It was seriously argued that the role played by the appellant was
not that of a service provider and all that it had done was to extend a
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
15
helping hand so that its employees could satisfy their housing needs. It
was also submitted that there was absolutely no profit element and in fact
the appellant had incurred considerable expenditure towards interest
burden for having invested some money over a period of time which
element was never sought to be recovered. It is, thus, seriously disputed
and submitted that the instant matter could not have been gone into by fora
under the provisions of the Act. However, at this length of time, we do not
deem it appropriate to relegate the Respondent No.1 to any other remedy.
Therefore, in peculiar circumstances of the case, we have proceeded on the
footing that the matter was maintainable before the fora under the Act. But
as stated earlier, there was absolutely no deficiency on part of the
Appellant and no justification in imposing any costs and directing the
Appellant to pay compensation to the Respondent No.1.
17. We, therefore, allow these Appeals and set aside the orders passed
by the State Commission and the National Commission. In substitution of
the directions issued, we direct:-
a) The appellant shall pay to each of the tenement holders (or to
the heirs/successors, in case the original tenement holders are
no more) a sum of Rs.10,000/- within three weeks from today;
OR
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
16
in the alternative the Appellant shall execute an appropriate
deed conveying interest in favour of the Respondent No.1 in
respect of 28 tenements and the entire land admeasuring
2709.701 square meters, as stated hereinabove, within six
weeks.
b) If the Appellant pays to each of the tenement holders (or to the
heirs/successors, in case the original tenement holders are no
more) a sum of Rs.10,000/-, the Respondent No.1-Society
shall be entitled to have an appropriate deed conveying
interest in favour of the Respondent No.1 in respect of 28
tenements and the proportionate land appurtenant thereto
within six weeks from today. In such eventuality, the Appellant
shall continue to have right, title and interest in respect of
portion of land representing those two plots over which no
tenements have been constructed and it shall continue to have
propriety interest and shall be entitled to deal with that
portion.
c) In either case the stamp duty in respect of such documents
shall be borne by the Respondent No.1 and the concerned
Civil Appeal No.8606 of 2019 @ SLP(C)No. 5413 of 2019 etc.
The Manager, The Maharashtra State Cooperative Bank Ltd. vs. Farmer Bank
Employees cooperative housing Society Ltd. & Ors.
17
documents shall be executed by the Appellant and the
Respondent No.2 in favour of the Respondent No.1.
18. The Appeals are allowed in aforesaid terms. No costs.
……………………….J.
(Uday Umesh Lalit)
……………………….J.
(Indira Banerjee)
New Delhi;