Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 13
CASE NO.:
Appeal (civil) 7522 of 2005
PETITIONER:
M/s Transmission Corporation of A.P. Ltd.
RESPONDENT:
M/s Lanco Kondapalli Power Pvt. Ltd.
DATE OF JUDGMENT: 15/12/2005
BENCH:
S.B. Sinha & P.P. Naolekar
JUDGMENT:
J U D G M E N T
[Arising out of S.L.P. (Civil) No.24857 of 2004]
S.B. SINHA, J :
Leave granted.
Background facts
The parties herein entered into a Power Purchase Agreement on
31.03.1997 for short gestation liquid fuel based power project of 355 MW.
The said agreement contained an arbitration clause in Article 14
thereof.
Dispute
The Plant was commissioned. In terms of the said agreement, the
power generated in the Plant constructed by the Respondent herein was to
be supplied to the Appellant Corporation. The price to be paid therefor by
the Appellant included ’capacity charges’ and ’variable charges’. Upon
commission of the Plant, various tests as regard capacity of the plant to
generate electricity were carried out. The Appellant herein had been paying
capacity charges on the output of the Plant which was fixed at 368.144 MW
from 08.11.2001. A notice, however, was issued by the Appellant alleging
that the capacity charges payable by it with reference to the installed
capacity should have been fixed at 334.75 MW x Rh (relative humidity)
factor with tolerance limit of + or \026 5% as per the agreement which works
out at 351.49 MW and on that premise as to why future payments should not
be made accordingly and why the previous bills should not be revised with
reference thereto. The Respondent by a letter dated 17.12.2003 demanded
withdrawal of the said notice from the Appellant.
Proceedings
In view of the threatened action on the part of the Appellant herein, an
application purported to be under Section 9 of the Arbitration and
Conciliation Act, 1996 (for short, ’the 1996 Act’) was filed before the City
Civil Court praying for a permanent injunction restraining the Appellant
herein from taking any unilateral decision pursuant to the said show cause
notice. Evidently, the said application was filed relying on or on the basis of
the arbitration clause contained in the said Power Purchase Agreement.
The Appellant, however, filed an application before the Andhra
Pradesh Electricity Regulatory Commission (for short, ’the Commission’)
originally constituted under the Andhra Pradesh Electricity Reform Act,
1998 (for short, ’1998 Act’), praying, inter alia, for fixing the installed
capacity of the Plant and for consequential reliefs.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 13
The said application before the Commission was filed by the
Appellant herein on the premise that the Commission alone has the
jurisdiction to arbitrate in respect of disputes and differences arising between
the parties or to nominate an arbitrator therefor in terms of Section 37(1) of
the 1998 Act corresponding to Section 86(1)(f) read with Section 174 of the
Electricity Act, 2003 (for short, ’2003 Act’). However, in the meantime, as
no arbitrator was appointed by the Appellant in terms of the arbitration
agreement contained in Article 14 of the Power Purchase Agreement, an
application purported to be under sub-sections (3) and (4) of Section 11 of
the 1996 Act was filed before the Chief Justice of the Andhra Pradesh for
appointment of an arbitrator. The said application is still pending.
A writ petition marked as Writ Petition No.7838 of 2004 was also
filed by the Respondent before the Andhra Pradesh High Court on or about
22.04.2004 praying for issuance of a writ of prohibition against the
Commission restraining it from proceeding to adjudicate the dispute between
the parties on the premise that the constitution of the Commission was
incomplete. In the said writ petition, an interim order was passed by the
High Court directing "interim stay of the impugned proceedings purported to
be taken by Respondent No.1 (Appellant herein) in terms of the impugned
notice".
The Respondent’s application for grant of injunction in the
proceedings initiated before the City Civil Court in the meanwhile was taken
up for hearing and by an order dated 11.08.2004, the said Interlocutory
Application was dismissed, holding that having regard to the provisions of
the 1998 Act and the 2003 Act, the Commission alone had the jurisdiction to
decide the dispute and not the City Civil Court.
Contentions of the Appellant
An appeal thereagainst was preferred by the Respondent before the
High Court which was marked as Appeal No.3269 of 2004, wherein by
reason of the impugned judgment and order dated 05.10.2004, the High
Court while setting aside the said order of the City Civil Court granted an
injunction restraining the Appellant herein from refixing the capacity of the
Plant at 334.75 MW x Rh Factor at the site till disposal of the OP by the City
Civil Court.
Mr. P.P. Rao, the learned Senior Counsel appearing on behalf of the
Appellant, would submit that the Respondent herein, although not being a
licensee within the meaning of the 2003 Act, was required to have a licence
as it supplied electrical energy to the Appellant herein.
It was urged that in view of the provisions contained in the 1998 Act
and the 2003 Act, not only the jurisdiction of the Civil Court is barred, any
dispute and difference between the two licensees and/or two generating
companies can be referred to an arbitration of the Commission only, as
envisaged under Section 86(1)(f) of the 2003 Act and in that view of the
matter, the High Court committed a serious error in passing an order of
injunction.
It was submitted that both under the 1998 Act as also under the 2003
Act, the Commission had the requisite jurisdiction to pass an interim order
also and, thus, the said Acts are self-contained Codes.
Mr. Rao contended that the High Court despite findings of the City
Civil Court to the effect that it had no jurisdiction to pass an interim order in
terms of Section 9 of the 1996 Act, did not address itself to the said question,
could not have proceeded to allow the appeal preferred by the Respondent
herein and granted ad interim order of injunction only on the premise that
the jurisdiction of the Commission to proceed with the arbitration in terms of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 13
the reference made by the Appellant herein is subjudice.
Contentions of the Respondent
Mr. C.A. Sundaram, the learned Senior Counsel appearing on behalf
of the Respondent, on the other hand, submitted that Sections 37 and 50 of
the 1998 Act have no application to the facts of the present case as it is not a
case where a dispute between the two licensees is involved. The dispute
between the parties being confined to the interpretation of the expression
’installed capacity’ within the meaning of the provisions of the agreement,
the Commission which is primarily concerned with framing of tariffs and
adjudication of disputes between licensees and others as envisaged, inter
alia, under Section 9, 29 and 33 of the Act can be said to have no jurisdiction
to decide disputes and differences between the parties arising under an
agreement. In view of the fact that the parties were ad idem as regard
construction of the said agreement as payments of the bills had been made
on the basis of the installed capacity 368.144 MW from 08.11.2001 to
10.12.2003, and having regard to the arbitration agreement contained in the
contract; without resolution of the dispute in terms thereof, the Appellant
could not have taken an unilateral action in changing the terms and
conditions thereof for the purpose of the payments of bills.
In any view of the matter, the Appellant itself having made the
following prayers before the Commission :
"In the aforesaid facts and circumstances, the
Applicant prays that Hon’ble Commission may pass
appropriate orders in respect of the following :
a) To fix the Installed Capacity of the plant,
M/s Lanco Kondapalli Power Limited, as 334.75 MW x
RH factor at the site Reference Conditions (as per PPA)
with tolerance limit of + 5%.
b) To allow AP TRANSCO to pay all future power
purchase bills (fixed charges, variable charges, Incentive
etc.) based on the capacity on 334.75 MW x RH factor
and as per all other provisions of PPA including tolerance
limit.
c) To allow APTRANSCO to revise all
previous power purchase bills (fixed charges, variable
charges incentive etc.) from inception based on the
capacity of 334.75 MW x RH factor and as per all other
provisions of PPA including tolerance limit;
and thus cannot now turn round and contend that it would do so unilaterally
without any award made in that behalf. The Respondent, thus, not only has
a prima facie case keeping in view that that a sum of Rs.132 crores is due to
the Respondent, the balance of convenience also lies in its favour.
Agreement
Clause 35 of Article 1 of the said agreement defines ’Installed
Capacity’ to mean :
"the maximum electrical generating capacity of the
Project or a Generating Unit, as the case may be, in
megawatts ("MW") as measured at the generator
terminals, determined from time to time pursuant to the
tests given in Schedule F, subject to adjustments for the
Ambient Reference Conditions.
Explanation 1 : Where the output of one or more
Generating Units of the Project or of the Project as a
whole, in final tests to be specified by the Board is higher
than the output initially guaranteed by the manufacturer
/supplier thereof, the output initially guaranteed by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 13
manufacturer/supplier will be the installed capacity
thereof, as from the date of such final tests. However,
where the output of one or more Generating Units of the
Project or of the Project as a whole, in final tests to be
specified by the Board is lower than the output initially
guaranteed by the manufacturer/supplier thereof, that
lower output alone will be the installed capacity thereof.
Explanation 2 : The installed Capacity furnished in the
Bid is taken as the nominal capacity and for installed
Capacity as determined as per Explanation 1 above, a
tolerance limit of plus or minus 5% is permitted."
The expression ’Project’ has been defined in sub-clause 47 of the said
agreement to mean :
"the combined cycle power station proposed to be
established at Kondapally, Krishna Dist., in Andhra
Pradesh, India, consisting of 2 (two) Generating Units,
which are designed for poly-fuel-firing and 1 (one) steam
Generating Unit, having a nominal installed capacity of
355 Mega Watts (ISO) adjusted to Ambient Reference
Conditions."
Schedule A appended to the said agreement provides for the technical
limits, clause 3 whereof defines ’Dynamic Parameters’ to mean :
"3. Dynamic Parameters
The Dynamic Parameters are the essential
operating characteristics which will define
the limits within which a Unit or the Project
is required to operate during normal
operation.
The Dynamic Parameters of each Unit and
the Project will initially be those projected
in the EPC Contract. During testing under
the EPC Contract, the Company will
establish Dynamic Parameters and it will
supply details of these to the Board. Subject
to the Dynamic Parameters being adjusted
and verified prior to the COD of each Unit
and the Project COD, the Dynamic
Parameters established by the Company
shall replace those projected in the EPC
Contract and shall be deemed incorporated
into this Schedule."
Relevant parts of Article 14 containing the arbitration agreement
between the parties read as under:
"Article 14
14.1 Information Dispute Resolution
(a) Each party shall designate in writing to the other
party is a representative who shall be authorized to
resolve any dispute arising under this Agreement
in an equitable manner.
(b) If the designated representatives are unable to
resolve a dispute under this Agreement within
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 13
fifteen (15) days, such dispute shall be referred by
such representatives to a senior officer designated
by the Company and a senior officer designated by
the Board, respectively, who shall attempt to
resolve the dispute within a further period of
fifteen (15) days.
(c) The parties hereto agree to use their best efforts to
attempt to resolve all disputes arising hereunder
promptly, equitably and in good faith, and further
agree to provide each other within reasonable
access during normal business hours to any and all
non-privileged records, information and data
pertaining to any such dispute.
14.2 Arbitration
(a) In the event that any dispute is not resolved
between the Parties pursuant to Article 14.1, then
such dispute shall be settled exclusively and finally
by arbitration. It is specifically understood and
agreed that any dispute that cannot be resolved
between the parties, including any matter relating
to the interpretation of this Agreement, shall be
submitted to arbitration irrespective of the
magnitude thereof, and the amount in dispute or
whether such dispute would otherwise be
considered justiciable or ripe for resolution by any
court or arbitral tribunal. This Agreement and the
rights and obligations of the Parties hereunder
shall remain in full force and effect pending the
award in such arbitration proceedings, which
award shall determine whether and when
termination of this Agreement if relevant shall
become effective.
xxx xxx xxx
(f) Any decision or award of an arbitral tribunal
appointed pursuant to this Article 14.2 shall be
final and binding upon the Parties and shall be the
sole and exclusive remedy between the Parties
regarding any claims, counterclaims, issues or
accountings presented or pled to the arbitrators.
The Parties waive any rights to appeal or any
review of such award by any court or tribunal of
the competent jurisdiction. The Parties agree that
any arbitration made may be enforced by the
Parties against assets of the relevant Party
wherever those assets are located or may be found,
and judgment upon any arbitration award may be
entered by any court of competent jurisdiction
thereof. The Parties expressly submit to the
jurisdiction of any such court.
(g) All arbitration awards shall be denominated in
Indian Rupees. If the arbitration award (or part
thereof) consists of any currency other than Indian
Rupees, then award (or part thereof) shall be
converted to Indian Rupees based on the
applicable market rate(s) of foreign exchange, not
exceeding such TT selling rate(s) as published by
the State Bank of India on the date of such
payment. Interest at a rate equal to the Working
Capital Rate plus two percent (2%) shall be due
and payable to the Party on receipt of an
arbitration award from the date thirty (30) days
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 13
after the date such award is made pursuant to this
Article 14.2 through the date of payment.
(h) Any arbitration proceedings or award rendered
hereunder and the validity, effect and
interpretation of this Article 14 shall be governed
by the laws of India and (to the extent applicable)
the New York Convention on the Recognition and
Enforcement of Arbitral Awards, June, 10, 1958,
to which England and India are parties.
(i) The Parties agree that any amount due under this
Article 14.2 shall be due as a separate debt and
shall not be affected by or merged into any
judgment being obtained for any other sum due
under or in respect of this Agreement."
Statutory provisions :
The State of Andhra Pradesh enacted the Andhra Pradesh. Electricity
Reforms Act, 1998, for providing the constitution of an Electricity
Regulatory Commission, restructuring of the electricity industry,
rationalization of the generation, transmission, distribution and supply of
electricity avenues for participation of private sector in the electricity
industry and generally for taking measures conducive to the development
and management of the electricity industry in an efficient, economic and
competitive manner and for matters connected therewith or incidental
thereto.
’Licensee’ has been defined in Section 2(e) of the 1998 Act as under :
"Licensee" or "licence holder" means a person licensed
under section 14 of the Act to transmit or supply energy
including APTRANSCO;"
It is not in dispute that the Commission was constituted in terms of the
Act. Section 37 of the said Act contains a non-obstante clause stating that
notwithstanding anything contained in the 1996 Act, any dispute arising
between the licensees shall be referred to the Commission. The Commission
may proceed to act as arbitrator or nominate arbitrator or arbitrators to
adjudicate and settle such disputes. Section 28 of the 1998 Act empowers the
Commission to issue an interim order as it deems proper for securing
compliance if it is satisfied that a licensee is contravening or is likely to
contravene any relevant condition or requirement of the licence.
The 2003 Act came into force with effect from 26.05.2003. Sub-
section (64) of Section 2 of the said Act defines the State Commission to
mean, inter alia, the State Electricity Regulatory Commission constituted
under sub-section (1) of Section 82 thereof. In terms of Section 82, a State
Government is enjoined with a duty to constitute a commission within six
months from the appointed day. The proviso appended to sub-section (1) of
Section 82, however, postulates that the commission earlier constituted shall
continue and its Chairperson, Members, Secretary and officers and other
employees shall continue to function for the purpose of the said Act.
Section 86 provides for functions of the State Commission. Clause (f) of
sub-section (1) thereof empowers the State Commission to adjudicate upon
the disputes between the licensees and generating companies and to refer
any dispute for arbitration. Section 158 of the said Act occurring in Part
XVI deals with dispute resolution, which reads as under :
"158. Arbitration.-Where any matter is, by or
under this Act, directed to be determined by arbitration,
the matter shall, unless it is otherwise expressly provided
in the licence of a licensee, be determined by such person
or persons as the Appropriate Commission may nominate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 13
in that behalf on the application of either party; but in all
other respects the arbitration shall be subject to the
provisions of the Arbitration and Conciliation Act, 1996
(26 of 1996)"
Sub-section (2) of Section 94 of the Act empowers the State
Commission to pass an interim order in any proceeding before it. The Civil
Court’s jurisdiction is barred under Section 145 of the said Act which reads
as under :
"145. Civil court not to have jurisdiction.-No civil
court shall have jurisdiction to entertain any suit or
proceeding in respect of any matter which an assessing
officer referred to in section 126 or on appellate authority
referred to in section 127 or the adjudicating officer
appointed under this Act is empowered by or under this
Act to determine and no injunction shall be granted by
any court or other authority in respect of any action taken
or to be taken in pursuance of any power conferred by or
under this Act."
In terms of the Section 185, the Electricity Regulatory Commissions
Act, 1998 was repealed but in terms of sub-section (3) thereof the
provisions of the enactments specified in the Schedule, not inconsistent
therewith shall apply to the States in which such enactments are applicable.
Item No.3 of the Schedule refers to the Andhra Pradesh Electricity Reform
Act, 1998.
Analysis of the agreement and the statutory provisions
The Appellant is a licensee within the meaning of both the 1998 Act
and the 2003 Act.
The question as to whether the Respondent should have taken a
licence or permit under the 2003 Act or not is not a matter which requires
our immediate attention. The Appellant is a licensee and the Respondent is
a generating company in terms of the provisions of the 2003 Act. Section 37
of the 1998 Act deals with disputes between the licensees.
Prima facie Section 50 of the 1998 Act, which bars the jurisdiction of
the Civil Court keeping in view the language employed therein, is required
to be read with Section 37 thereof. The resolution of the disputes between
the parties rests upon the proper interpretation of the said Power Purchase
Agreement and in particular the definition of ’installed capacity’. Who
would arbitrate in respect of the said dispute is the principal question. It is
no doubt true that in the event if it ultimately be held that the arbitration
clause contained in the contract between the parties dated 31.03.1997 stood
superseded in view of the provisions of the 1998 Act and the 2003 Act,
arguably, the question of Civil Court’s granting of an order of injunction in
terms of Section 9 or the High Court to determine the question as to who
should be appointed as an arbitrator, may not arise. As to whether Section
86(1)(f) of the 2003 Act confers an exclusive jurisdiction to decide all
disputes and differences between a licensee and a generating company is
open to question. It may or may not be that the said provision may have to
be read with other provisions contained in the power of the Commission to
resolve disputes between various parties as for example Sections 9, 20 or 29
thereof. But it would be matter of construction of the relevant provisions as
to whether by reason of Section 86(1)(f) of the 2003 Act, the Commission
derives a power so as to enable it to arbitrate also in relation to a dispute
arising out an agreement although the Commission may not have any role to
play whatsoever in respect thereof.
Determination
The learned Counsel for the parties, as noticed hereinbefore, have
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 13
argued before us on the interpretation of the provisions of the relevant
statutes and agreement for determining the effect and purport thereof.
As at present advised, however, we refrain ourselves from expressing
any opinion one way or the other having regard to the fact that the matter
ultimately must receive a detailed consideration at the hands of the High
Court both in the writ petition as also in the application filed by the
Respondent under Section 11 of the 1996 Act.
We do so for the reason that recently a 7-Judge Bench of this Court in
M/s S.B.P. & Co. v. Patel Engineering Ltd. & Anr. [(2005) 9 SCALE 1]
overruling an earlier Constitution Bench Judgment of this Court in Konkan
Railway Corporation Ltd. & Anr. v. Rani Constructions Pvt. Ltd. [2002) 2
SCC 388], held that the power of the Chief Justice or his nominee under the
1996 Act is a judicial power as opposed to the administrative power. The
contention of the Appellant that the City Civil Court or for that matter the
High Court have no jurisdiction in terms of the 1996 Act, therefore, must
finally be determined by the High Court itself. Such a question indisputably
will also be a subject-matter of determination by the High Court in the writ
proceedings pending before it.
However, it is not a case where any dispute has arisen in respect of a
statutory function of the Commission to frame tariff and in that view of the
matter the decision of this Court in West Bengal Electricity Regulatory
Commission v. CESC Ltd. [(2002) 8 SCC 715] cannot be said to have any
application whatsoever.
The ratio laid down in Grid Corporation of Orissa Ltd. v. Indian
Charge Chrome Ltd. [(1998) 5 SCC 438] whereupon Mr. Rao placed strong
reliance is not applicable in this case as therein it was found that the High
Court erroneously assumed that the Regulatory Commission had failed to
arbitrate under Section 37(1) of the 1998 Act, which was found to be
factually incorrect.
In A.P. Gas Power Corporation Ltd. etc. v. A.P. State Regulatory
Commission and Another etc. [(2004) 10 SCC 511], the question was as to
whether the Appellant therein was required to take, under the law, a licence
for utilization/sale or supply of power generated by it to the
participating/shareholding industries or to their sister concerns or the
industries to whom the shares of A.P. GPCL have been transferred by the
participating industries. It was held that such licence was necessary, stating
"\005It would surely be a supply to a non-participating
industry and in that event it would be necessary to have a
licence under the relevant provisions of law. If there is
such a legal requirement, merely an agreement amongst
certain parties would not exclude the application of law.
Provisions of law regulating the situation, would prevail
over any kind of agreement amongst some individuals as
a group or otherwise. We are, therefore, of the view that
such a clause in the Memorandum of Understanding
would not do away with the requirement of having a
licence for supply of electricity generated by A.P. GPCL
to such concerns which may be under the same group as
the participating industries but not the participating
industries themselves."
The Respondent, therefore, has raised triable issues. What would
constitute triable issues has succinctly been dealt with by the House of Lords
in its well-known decision in American Cyanamid Co v. Ethicon Ltd.
[(1975) 1 AER 504], holding :
"Your Lordships should in my view take this
opportunity of declaring that there is no such rule. The
use of such expression as ’a probability’, ’a prima facie
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 13
case’, or ’a strong prima facie case’ in the context of the
exercise of a discretionary power to grant an
interlocutory injunction leads to confusion as to the
object sought to be achieved by this form of temporary
relief. The court no doubt must be satisfied that the
claim is not frivolous or vexatious; in other words, that
there is a serious question to be tried."
It was further observed :
"Where other factors appear to be evenly balanced it
is a counsel of prudence to take such measures as are
calculated to preserve the status quo. If the defendant is
enjoined temporarily from doing something that he has
not done before, the only effect of the interlocutory
injunction in the event of his succeeding at the trial is to
postpone the date at which he is able to embark on a
course of action which he has not previously found it
necessary to undertake; whereas to interrupt him in the
conduct of an established enterprise would cause much
greater inconvenience to him since he would have to start
again to establish it in the event of his succeeding at the
trial.
*
The factors which he took into consideration, and in
my view properly, were that Ethicon’s sutures XLG were
not yet on the market; so that had no business which
would be brought to a stop by the injunction; no factories
would be closed and no workpeople would be thrown out
of work. They held a dominant position in the United
Kingdom market for absorbable surgical sutures and
adopted an aggressive sales policy."
We are, however, not oblivious of the subsequent development of law
both in England as well as in this jurisdiction. The Chancery Division in
Series 5 Software v. Clarke [(1996) 1 All ER 853] opined:
"In many cases before American Cyanamid the prospect
of success was one of the important factors taken into
account in assessing the balance of convenience. The
courts would be less willing to subject the plaintiff to the
risk of irrecoverable loss which would befall him if an
interlocutory injunction was refused in those cases where
it thought he was likely to win at the trial than in those
cases where it thought he was likely to lose. The
assessment of the prospects of success therefore was an
important factor in deciding whether the court should
exercise its discretion to grant interlocutory relief. It is
this consideration which American Cyanamid is said to
have prohibited in all but the most exceptional case. So it
is necessary to consider with some care what was said in
the House of Lords on this issue."
In Colgate Palmolive (India) Ltd. v. Hindustan Lever Ltd. [(1999) 7
SCC 1], this Court observed that Laddie, J. in Series 5 Software (supra) had
been able to resolve the issue without any departure from the true
perspective of the judgment in American Cyanamid. In that case, however,
this Court was considering a matter under Monopolies and Restrictive Trade
Practices Act, 1969.
In S.M. Dyechem Ltd. v. Cadbury (India) Ltd. [(2000) 5 SCC 573],
Jagannadha Rao, J. in a case arising under Trade and Merchandise Marks
Act, 1958 reiterated the same principle stating that even the comparative
strength and weaknesses of the parties may be a subject matter of
consideration for the purpose of grant of injunction in trade mark matters
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 13
stating :
"21\005Therefore, in trademark matters, it is now
necessary to go into the question of "comparable
strength" of the cases of either party, apart from balance
of convenience. Point 4 is decided accordingly."
The said decisions were noticed yet again in a case involving
infringement of trade mark in Cadila Health Care Ltd. v. Cadila
Pharmaceuticals Ltd. [(2001) 5 SCC 73].
We are, however, herein concerned with a different type of case.
Same standard would be applicable in a case involving Section 9 of the 1996
Act.
In this connection, we may notice a decision of this Court in Firm
Ashok Traders and Another v. Gurumukh Das Saluja and Others [(2004) 3
SCC 155]. Although therein the applicability of the arbitration agreement
was in question having regard to a Constitution Bench decision of this Court
in Jagdish Chandra Gupta v. Kajaria Traders (India) Ltd. [AIR 1964 SC
1882], this Court maintained an order appointing a Receiver albeit with
certain modifications on the premise that the right arising from the
partnership deed or conferred by the Partnership Act is being enforced in the
Arbitral Tribunal; the court under Section 9 is only formulating interim
measures so as to protect the right under adjudication before the Arbitral
Tribunal from being frustrated.
We have referred to Firm Ashok Traders (supra) not because we agree
with the principle laid down therein but only to suggest that Section 9 of the
1996 Act should be applied so that status quo may be directed to be
maintained having regard to the fact that the parties understood the
workability of the agreement in a particular manner.
A writ court can also grant injunction in exercise of its power under
Article 226 of the Constitution of India. If injunction is refused in this
proceeding, the interim order passed in the writ proceedings shall continue.
It may give rise to a stalemate. It may violate the well-known rule of
judicial comity.
In ’A Treatise on The Law Governing Injunctions’ by Spelling and
Lewis’ it is stated :
"Sec. 8. Conflict and Loss of Jurisdiction.
Where a court having general jurisdiction and having
acquired jurisdiction of the subject-matter has issued an
injunction, a court of concurrent jurisdiction will usually
refuse to interfere by issuance of a second injunction.
There is no established rule of exclusion which would
deprive a court of jurisdiction to issue an injunction
because of the issuance of an injunction between the
same parties appertaining to the same subject-matter, but
there is what may properly be termed a judicial comity
on the subject. And even where it is a case of one court
having refused to grant an injunction, while such refusal
does not exclude another coordinate court or judge from
jurisdiction, yet the granting of the injunction by a
second judge may lead to complications and retaliatory
action\005"
The High Court, therefore, while noticing the interim order passed in
the writ proceedings may have the said principle in mind.
In Wander Ltd. and Another v. Antox India P. Ltd. [(1990) Supp.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 13
SCC 727], it is stated :
"The interlocutory remedy is intended to preserve in
status quo, the rights of parties which may appear on a
prima facie case. The court also, in restraining a
defendant from exercising what he considers his legal
right but what the plaintiff would like to be prevented,
puts into the scales, as a relevant consideration whether
the defendant has yet to commence his enterprise or
whether he has already been doing so in which latter case
considerations somewhat different from those that apply
to a case where the defendant is yet to commence his
enterprise, are attracted."
[See also M/s Power Control Appliances and Others v. Sumeet
Machines Pvt. Ltd. [(1994) 2 SCC448 ].
The interim direction ordinarily would precede finding of a prima
facie case. When existence of a prima facie case is established, the court
shall consider the other relevant factors, namely, balance of convenience and
irreparable injuries. The High Court in its impugned judgment although not
directly but indirectly has considered this aspect of the matter when on merit
it noticed that the Appellant has raised a dispute as regard payment of an
excess amount of Rs.35 crores although according to the Respondent a sum
of Rs.132 crores is due to it from the Appellant and the Appellant had been
paying the amount for the last two years as per the contract.
Conduct of the parties is also a relevant factor. If the parties had been
acting in a particular manner for a long time upon interpreting the terms and
conditions of the contract, if pending determination of the lis, an order is
passed that the parties would continue to do so, the same would not render
the decision as an arbitrary one, as was contended by Mr. Rao. Even the
Appellant had prayed for adjudication at the hands of the Commission in the
same manner. Thus, it itself thought that the final relief would be granted
only by the Arbitrator.
The Commission is yet to apply its mind. Even before the
Commission, the Appellant has not made any application for a direction in
terms of sub-section (2) of Section 94 of the Act.
The Respondent has installed the Power Generation Plant. It has
continuously been supplying electrical energy to the Appellant.
Indisputably, it has to discharge its contractual obligation. The Appellant
being the only consumer, the Respondent has no other option but to supply
electrical energy to it. In the event, the dispute is referred to the arbitrator,
the equity between the parties can be adjusted. Without going into the
correctness or otherwise of the claim of the Respondent, we may notice, that
according to it, the Appellant owes a hefty sum of Rs.132 crores to it.
According to the Appellant, in the event, the disputes and differences
between the parties are determined in its favour, it may be held, that it has
paid an excess sum of Rs.35 crores only.
Clause 2 of Article 14 postulates that pending arbitration, the rights
and obligations of the parties shall remain in full force and effect pending
the award in such arbitration proceedings, which award shall determine
whether and when termination of the said agreement if irrelevant shall
become effective.
It is now well-settled that this Court would not interfere with an order
of the High Court only because it will be lawful to do so. Article 136 of the
Constitution vests this Court with a discretionary jurisdiction. In a given
case, it may or may not exercise its power. The question came up for
consideration before this Court in Chandra Singh and Others v. State of
Rajasthan and Another [(2003) 6 SCC 545] wherein it was observed:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 13
"42. In any event, even assuming that there is some force
in the contention of the appellants, this Court will be
justified in following Taherakhatoon v. Salambin Mohd.
wherein this Court declared that even if the appellants’
contention is right in law having regard to the overall
circumstances of the case, this Court would be justified
in declining to grant relief under Article 136 while
declaring the law in favour of the appellants."
[See also State of Punjab v. Savinderjit Kaur, (2004) 4 SCC 58]
The said principle was reiterated in N.K. Prasada v. Government of
India and Others [(2004) 6 SCC 299] stating:
"\005It is trite that in a given case, the Court may refuse to
exercise its discretionary jurisdiction under Article 136 of
the Constitution."
In Inder Parkash Gupta v. State of J&K and Others [(2004) 6 SCC
786], it was stated:
"42. In ordinary course we would have allowed the
appeal but we cannot lose sight of the fact that the
selections had been made in the year 1994. A valuable
period of 10 years has elapsed. The private respondents
have been working in their posts for the last 10 years. It
is trite that with a view to do complete justice between
the parties, this Court in a given case may not exercise its
jurisdiction under Article 136 of the Constitution of
India."
The same principle has been reiterated in State of Uttaranchal
Through Collector, Dehradun and Another v. Ajit Singh Bhola and Another
[(2004) 6 SCC 800] wherein it was stated:
"9\005Having regard to the manner in which the District
Magistrate took over possession of the premises, which
appears to us as at present advised, to be high-handed,
arbitrary and without any legal sanction we are not
persuaded to exercise our discretion under Article 136 of
the Constitution of India to set aside the interim order
passed by the High Court. It is well settled that this Court
will not exercise its discretion and quash an order which
appears to be illegal, if its effect is to revive another
illegal order."
We, therefore, are of the opinion that it is not a fit case where
interference with the High Court’s judgment would be a proper exercise of
jurisdiction under Article 136 of the Constitution of India.
We would, however, request the High Court to consider the
desirability of hearing both the writ petition as also the petition under
Section 11 of the 1996 Act filed by the Respondent herein as expeditiously
as possible and preferably within a period of six weeks from the date of
communication of this order.
It goes without saying that all the contentions of the parties shall
remain open and any observation made by the High Court in the impugned
order or by us herein must be considered to have been made for the purpose
of disposal of the interim prayer.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 13
The appeal is dismissed. No costs.