MAHANAGAR GAS LTD. vs. BABULAL UTTAMCHAND AND CO

Case Type: N/A

Date of Judgment: 28-08-2012

Preview image for MAHANAGAR GAS LTD. vs. BABULAL UTTAMCHAND AND CO

Full Judgment Text


2012:BHC-OS:10639-DB
app-349-12.sxw
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL (LODGING) NO.349 OF 2012
IN
ARBITRATION PETITION NO. 958 OF 2010 
Mahanagar Gas Limited
Having its office at
MGL House, Bandra Kurla Complex,
Bandra (East), 
Mumbai­400 051 ... Appellant
Versus
M/s. Babulal Uttamchand & Co. 
108, Shyamkamal A.Agarwal Market
Tejpal Road, Vile Parle,
Mumbai­400 057 ... Respondent
Mr. Pradeep Sancheti, Senior Advocate with Mr. S.A.Bhalwal i/by M/s. Vyas 
& Bhalwal for the appellant.
Mr.Chidanand Kapil i/by Ms.shilpa Kapil for the respondent.
           CORAM : MOHIT S. SHAH, C.J.  &
                       N.M. JAMDAR, J.
Tuesday, August 28, 2012
  ORAL JUDGMENT (Per Chief Justice)    
This appeal is directed against the judgment and order dated 9 
March 2012 of the learned Single Judge dismissing the arbitration petition 
of the appellant herein under section 34 of the Arbitration and Conciliation 
Act, 1996 with the only modification of reducing the future rate of interest 
from 18% to 12% from the date of the award (5 March 2010) till realisation 
on the claim as well as the counter­claim.
2. The appellant awarded the respondent (the claimant) the work 
of project management and construction of pipeline network for domestic 
supply   of   natural   gas   in   the   area   of   Santacrtuz     by   work   order   dated 
SRK 1 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
12 October 2002.   The said work was to be completed within three years 
from the date of letter of acceptance.   The work was valued at Rs.3.87 
crores.  The respondent, accordingly, mobilised the requisite resources and 
made   investment.     The   respondent   was   also   required   to   enter   into   the 
agreement with the customers for providing gas connections.
3. The appellant failed to provide gas to the customers though the 
pipeline work was completed by the respondent.  The delay in supply of gas 
for   about   18   months   resulted   in   non­payment   by   the   customers   and 
consequent   non­payment   for   the   work   done   to   the   respondent.   The 
respondent contended that on account of the breach of terms of contract by 
the appellant, the full work could not be completed in the stipulated period. 
The respondent raised claims before the Arbitrator. The appellant also filed 
counter­claims.     After   the   pleadings   were   completed,   one   witness   was 
examined by either party.  The claims made by the respondent herein before 
the Arbitrator were as under:­
(i) Work done not paid Rs. 35,00,000
(ii) Refund of security deposit Rs. 20,00,000
(iii) Material procured but not utilized Rs.   4,00,000
(iv) Supply of copper pipe Rs.   3,74,680
(v) Delay in payment Rs.      98,748
(vi) Loss of Profit Rs. 26,70,726
(vii) Less of Advance Rs. 20,00,000
(viii) Loss of infrastructure Rs. 28,00,000
(ix) Underutilization of Overheads Rs. 69,44,072
(x) Underutilization of Machinery Rs.   8,01,239
(xi) Underutilization of labour Force Rs. 85,46,575
(xii) Loss of business opportunities Rs. 26,70,797
(xiii) Cost Rs.   5,00,000
                                                       ­­­­­­­­­­­­­­­­­­­­­­
                                                       Rs.3,33,06,837
                                                       ­­­­­­­­­­­­­­­­­­­­­­
(xiv)  Interest @ 24% p.a. on the amount claimed.”
SRK 2 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
4. On   the   other   hand,   the   appellant   also   made   counter­claims 
under the various heads.  It is not necessary to refer to all the heads as the 
Arbitrator   made   the   award   with   the   counter­claim   only   for   a   figure   of 
Rs.7,17,445/­   under   the   head   of   material   reconciliation   penalties   and 
recoveries and no amount was awarded under the other heads.
5. It is the case of the claimant that after about 60 hearings took 
place, at the meeting of the Arbitral Tribunal on 7 August 2008, the parties 
agreed to sit together to arrive at the agreed figure of the balance amount 
payable to the claimants on account of the work done but not paid for 
(Claim No.1) and the amount payable from the claimant to the respondent 
on account of material reconciliation recoveries (counter­claim No.18).  On 5 
January   2009,   the   learned   counsel   for   the   parties   filed   jointly   signed 
statement alongwith detailed working informing the Arbitral Tribunal that 
both of them had arrived at an agreed figure of Rs.35,37,176/­   as the 
amount payable to the claimant from the appellant on account of work done 
but not paid (Claim No.1) and at a figure of Rs.7,17,445/­ as the amount due 
from the claimant on account of the recovery against Material Reconciliation 
Account (Counter­claim No.18) and filed the jointly signed statement which 
was taken on record. The Arbitral Tribunal accordingly, made the award for 
the aforesaid amounts in favour of the respective parties. The consent terms 
specifically provided that the same were without prejudice to the rights and 
contentions of the parties  qua all other claims.  
6. Learned Arbitrator Dr. Justice B.P. Saraf (Retd.) acting as the 
sole arbitrator ultimately made the following award after giving reasons:­
“30. In the premises, I make the following award:
Claims of the Claimant:
(i) The   Respondent   do   pay   to   the   Claimant   a   sum   of 
Rs.35,37,176/­   (Rupees   Thirty   Five   Lakh   Thirty   Seven 
Thousand   One   Hundred   Seventy   Six   only)   as   agreed 
between the Claimant and the Respondent, on account of 
work done but not paid with interest calculated thereon at 
SRK 3 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
st
the rate of 12 per cent per annum from 1  January 2006 
to the date of the award.
(ii) The   Respondent   do   pay   to   the   Claimant   a   sum   of 
Rs.25,23,873/­ (Rupees Twenty Five Lakhs Twenty Three 
Thousand Eight Hundred Seventy Three only) on account 
of loss of profit with interest calculated thereon at the rate 
st
of 12 per cent per annum from 1   January 2006 to the 
date of the award.
(iii) The   Respondent   do   pay   to  the   claimant   a   sum   of   Rs. 
26,04,129/­ (Rupees Twenty Six Lakh Four Thousand One 
Hundred Twenty  Nine only) on account  of  costs of  the 
arbitration.
(iv) The Respondent do pay to the Claimant further interest on 
the sum directed to be paid to the claimant by this award 
at the statutory rate of 18 per cent per annum as set out 
in section 31(7)(b) of the Act from the date of the award to 
the date of payment.
Counter­claims of the Respondent
(v) The   Claimant   do   pay   to   the   Respondent   a   sum   of 
Rs.7,17,445/­ (Rupees Seven Lakhs Seventeen Thousand 
Four   Hundred   Forty   Five   only),   as   agreed   between   the 
Claimant   and   the   Respondent,   on   account   of   Recovery 
against   Material   Reconciliation   Account   with   interest 
calculated thereon at the rate of 12 per cent per annum 
st
from 1  January 2006 to the date of the award.
(vi) The Claimant do pay to the Respondent further interest on 
the   sum   directed   to   be   paid   by   this   award   to   the 
Respondent at the statutory rate of 18 per cent per annum 
as set out in section 31(7)(b) of the Act from the date of the 
award to the date of payment.”
7. The learned Single Judge has held that the award does not call 
for any interference except the modification made as regards the rate of 
interest.  The learned Arbitrator had awarded further interest at the rate of 
18% per annum from the date of the award till the date of payment.  The 
learned   Single   Judge   has   reduced   the   said   rate  to  12%   per   annum   as 
indicated hereinabove.
SRK 4 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
8. The learned counsel for the appellant has challenged the award 
as   confirmed   by   the   learned   Single   Judge   and   has   made   the   following 
submissions:­
(i) The claimant had not led any evidence in support of the 
claim for loss of profit. Relying on the decision of the learned 
Single Judge of this Court in Mazgaon Dock Ltd. v. Offshore 
Hook­up and Construction Services (India) Pvt. Ltd. (Arbitration 
Petition   No.295   of   2007)   decided   on   20   August   2011),   it   is 
contended that the Arbitrator should have drawn an adverse 
inference   against   the   respondent   for   withholding   the   best 
evidence which was within his special knowledge.  It is obvious 
that before submitting his offer pursuant to the tender notice, 
the respondent must have worked out the figure and it was for 
the respondent to lead evidence as to what was the margin of 
profit   expected   by   him   while   submitting   his   offer.     But   that 
evidence was not led.
(ii) The Arbitrator had awarded costs at 90% of the fees of the 
Arbitrator   and   the   fees   of   the   Techno­legal   Consultant   and 
advocate and other expenses aggregating to Rs. 28,93,476/­. It 
is submitted that since the respondents had made a total claim 
of   Rs.3.33   crores   but   the   learned   Arbitrator   awarded   only 
Rs.35.37 lakhs under the first head of work done but not paid 
and Rs.26.70 lakhs under the head “Loss of Profit”, the learned 
Arbitrator  ought   not   to  have  awarded   90%   of   the   cost.  It   is 
submitted that the learned Arbitrator having made the award to 
the   extent   of   only   about   20%   of   the   total   claim   of   the 
respondent, the costs should not have been awarded at 90%.
SRK 5 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
(iii) As   regards   interest,   the   Arbitrator   erred   in   awarding 
interest on the amount of Rs.35,37,176 which was an agreed 
amount   between   the   parties   and,   therefore,   on   such   agreed 
amount, no interest can be awarded from the date of the claim 
till the date of the award.
(iv) It was also contended that no interest could have been 
awarded on the amount of loss of profit because that amount 
was ascertained for the first time while making the award.
9. On the other hand, the learned counsel for the respondent has 
opposed the appeal and submitted that as per the settled legal principles, 
this Court would not interfere with the arbitration award by sitting in appeal 
over   such   award   and   by   reappreciating   the   evidence   on   record.     It   is 
submitted that while filing the consent terms of 2 January 2009, it was 
made clear by the parties that the settlement for the respondent's claim 
under item No.1 work done and not paid at Rs.35,37,176/­ was without 
prejudice to the rights and contentions of the parties qua the other claims 
and, therefore, the respondent was not debarred from making any other 
claim including the claim for cost and interest on other amount.
10. As   regards   the   claim   under   the   loss   of   profit,   the   learned 
counsel for the respondent claimant has relied on the decision of the Apex 
Court in Dwaraka Das v. State of M.P. and another, (1999) 3 SCC 500 and 
MSK Projects India (JV) Limited v. State of Rajasthan and another, (2011) 10 
SCC 573.  It is submitted that the claim made by the contractor for recovery 
of   amount   of   damages   as   expected   profit   out   of   contract   cannot   be 
disallowed on the ground that there was no proof that he suffered actual 
loss to the extent of amount claimed on account of breach of contract.
SRK 6 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
11. As regards the challenge to the amount under the head “costs”, 
the learned counsel for the respondent­claimant submitted that the matter 
was heard by the Arbitrator at as many as 71 sittings and the appellant 
agreed to pay the amount under Claim No.1 quantified at Rs.35.37 lakhs 
only after about 60 sittings.  It is, therefore, submitted that the appellant 
having allowed the arbitration sittings to be held as for many as 60 sittings 
before agreeing to pay for the work done but not paid, the learned Arbitrator 
was justified in awarding costs at the rate of 90% of the total costs towards 
the fees of the Arbitrator and the fees of the Techno­legal Consultant and 
advocate fees. 
12. Before we proceed to examine rival contentions we must keep in 
mind the scope an of appeal under the Arbitration Act. In the appeal, the 
order passed by learned Single Judge under Section 34 of the Act refusing to 
interfere with the award of the learned Arbitrator, is challenged. Scope of 
section 34 of the Act is well settled. It is on very limited grounds that the 
award   of   Arbitrator   can   be   set   aside   by   the   Court   under   Section   34. 
The scope of an appeal from order passed under section 34 of the Act will be 
governed by the same limitations imposed on the exercise of the power 
under section 34, if not,  more stringent. 
 
13. The first controversy is as regards the 10% damages awarded to 
the   Respondent.   According   to   learned   counsel   for   the   Appellant   the 
Respondent did not produce on record any material to show how he is 
entitled to the damages on account of loss of profit. According to the learned 
counsel loss of profit and it's quantum cannot be presumed and the party 
must prove it by producing adequate evidence on record.  Reliance is placed 
on   the   judgment   of   the   learned   Single   Judge   in   Mazgaon   Dock   Limited 
(supra) to contend that since no evidence was produced by the claimant, 
adverse inference ought to have been drawn and the learned Single Judge 
SRK 7 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
ought to have remanded the matter to the Arbitrator on this issue.  Learned 
counsel urges that we should remand the matter to the learned Arbitrator, 
to decide this issue.  This submission is countered by the learned counsel 
for Respondent by relying on the judgments of the Apex Court which lay 
down guidelines for computing the loss of business when breach of contract 
is alleged.  
14. The judgment rendered by the learned Single Judge in   Mazgaon 

Docks (supra) was rendered in the facts of that case.   In that case the claim 
was made by sub­contractor. As per the clause provided in the agreement 
therein, the sub contractor was not entitled to damages for breach of the 
contract.   In   the   present   case   there   is   no   such   negative   clause   and   a 
fundamental breach of the contract is alleged. These distinguishing facts 
have been noticed by the learned Single Judge who has rightly come to the 
conclusion that the ratio rendered in  Mazgaon Docks  case (supra) was not 
applicable to the facts of the present case.   
15. In the present case the contract which was awarded in favour of 
the Respondent was in respect of laying down pipelines for providing gas to 
the consumers.   The Respondent accordingly mobilized the resources and 
made substantial investment.  The respondent entered into agreement with 
the   customers   for   providing   gas   connections.   For   about   18   months   the 
appellant   did   not   provide   gas   to   the   customers   through   the   pipelines 
constructed by the respondent­claimant. Providing gas through the pipelines 
was the fundamental feature of the agreement between the parties. This 
basic clause of the contract was breached by the appellant. Once such 
fundamental feature is breached, there would be justification for providing 
to the aggrieved  party arise and for that purpose provisions of the Contract 
Act come into operation.  The contractor is entitled to claim damages for loss 
of profit which he is expected to earn by undertaking the works contract, 
and such claim of expected profits is admissible once improper breach of 
SRK 8 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
contract is demonstrated.   The Apex Court in the case of  A.T. Brij Paul Singh 
1
v. State of Gujarat,  observed: (SCC pp.64­65, paras 10­11)
  “What would be the measure of profit would depend 
upon facts and circumstances of each case. But that there 
shall be a reasonable expectation of profit is implicit in a 
works contract and its loss has to be compensated by way of 
damages if the other party to the contract is guilty of breach 
of contract cannot be gainsaid. In this case we have the 
additional reason for rejecting the contention that for the 
same type of work, the work site being in the vicinity of each 
other   and   for   identical   type   of   work   between   the   same 
parties,   a   Division   Bench   of   the   same   High   Court   has 
accepted 15 per cent of the value of the balance of the works 
contract would not be an unreasonable measure of damages 
for loss of profit.
  Now if it is well­established that the respondent was 
guilty of breach of contract inasmuch as the rescission of 
contract by the respondent is held to be unjustified, and the 
plaintiff­contractor   had   executed   a   part   of   the   works 
contract, the contractor would be entitled to damages by way 
of loss of profit. Adopting the measure accepted by the High 
Court in the facts and circumstances of the case between 
the same parties and for the same type of work at 15 per 
cent of the value of the remaining parts of the work contract, 
the damages for loss of profit can be measured."
This judgment is followed in the case of  
Dwarkadas V/s.State of MP and 
2
another .    The Apex Court in   MSK Projects India (JV) Limited V/s.State of 
3
Rajasthan and Another ,  observed as under: 
38. In common parlance, "reimbursement" means and implies 
restoration of an equivalent for something paid or expanded. 
Similarly, "Compensation" means anything given to make the 
equivalent. (See:   State of Gujarat v. Shantilal Mangaldas and 
Ors.   MANU/SC/0063/1969   : AIR 1969 SC 634;   Tata Iron and 
Steel   Co.   Ltd.   v.   Union   of   India   and   Ors.   ;   Ghaziabad 
Development Authority (Supra); and  H.U.D.A v. Raj Singh Rana, 
(Supra). However, in  Dwaraka Das v. State of Madhya Pradesh 
and Anr.   MANU/SC/0088/1999  : AIR 1999 SC 1031, it was held 
that a claim by a contractor for recovery of amount as damages 
1 (1984) 4 SCC 59
2 (1999)3 scc 500
3 (2011)10 SCC 573
SRK 9 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
as   expected   profit   out   of   contract   cannot   be   disallowed   on 
ground that there was no proof that he suffered actual loss to 
the extent of amount claimed on account of breach of contract.
39. In   A.T.   Brij   Paul   Singh   and   Ors.   v.   State   of   Gujarat, 
MANU/SC/0081/1984 : AIR 1984 SC 1703,  while interpreting the 
provisions of Section   73  of the Indian Contract Act, 1972, this 
Court held that damages can be claimed by a contractor where 
the   government   is   proved   to   have   committed   breach   by 
improperly   rescinding   the   contract   and   for   estimating   the 
amount   of   damages,   court   should   make   a   broad   evaluation 
instead of going into minute details. It was specifically held that 
where   in   the   works   contract,   the   party   entrusting   the   work 
committed breach of contract, the contractor is entitled to claim 
the damages for loss of profit which he expected to earn by 
undertaking the works contract. Claim  of expected profits is 
legally   admissible   on   proof   of   the   breach   of   contract   by   the 
erring party. It was further observed that what would be the 
measure of profit would depend upon facts and circumstances of 
each case. But that there shall be a reasonable expectation of 
profit  is  implicit  in a  works contract  and its loss has to  be 
compensated   by   way   of   damages   if   the   other   party   to   the 
contract is guilty of breach of contract cannot be gainsaid.
40. In   B.S.N.L   v.   Reliance   Communication   Ltd. 
MANU/SC/1000/2010 : (2011) 1 SCC 394 , this Court held as 
under:
“53.  Lastly,   it   may   be   noted   that   liquidated   damages 
serve the useful purpose of avoiding litigation and promoting 
commercial certainty and, therefore, the court should not be 
astute   to   categorise   as   penalties   the   clauses   described   as 
liquidated damages.”
41.  This   Court   further   stated   in   Oil   and   Natural   Gas 
Corporation Ltd. v. SAW Pipes Ltd.  (Supra):  
“64. ...This section is to be read with Section   74 , which deals 
with penalty stipulated in the contract, inter alia (relevant for 
the   present   case)   provides   that   when   a   contract   has   been 
broken, if a sum is named in the contract as the amount to be 
paid in case of such breach, the party complaining of breach is 
entitled,   whether   or   not   actual   loss   is   proved   to   have   been 
caused, thereby to receive from the party who has broken the 
contract reasonable compensation not exceeding the amount so 
named.   Section   74   emphasizes   that   in   case   of   breach   of 
contract,   the   party   complaining   of   the   breach   is   entitled   to 
SRK 10 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
receive reasonable compensation whether or not actual loss is 
proved to have been caused by such breach.”
16. Thus, it is clear from the dicta of the Apex Court reproduced 
above   that   the   claim   for   damages   by   a   party   is   admissible   once   it 
demonstrates   that   the   other   party   has   committed     breach   of   the 
fundamental terms of the contract. In the Government contracts which are 
undertaken by the contractor for earning profits, it is implicit that once 
there   is   breach,   the   object   of   earning   profit   is   nullified.     Once   such 
fundamental breach occurs, the party is presumed to have suffered loss of 
profit.   In   the   case   of   MSK   Project   India   (supra)   the   Apex   Court   has 
categorically laid down that the claim by contractor for damages as expected 
profit out of contract, cannot be disallowed on the  ground that there was no 
proof that he has suffered actual loss. The Apex Court in the case of  A.T. 
Brij Paul Singh V/s.State of Gujrat , held that in case of Government contract 
where   the   Government   commits   breach   by   improperly   rescinding     the 
contract   the   Court   should   carry   out   a   broad   evaluation   regarding   the 
damages instead of going into minute details.  In   the   present   case   the 
Respondent had made a claim for loss of profit. The Arbitrator was not 
expected to go through the minute details to ascertain the exact   figure of 
damages.   The Arbitrator applied rough and ready formula to arrive at the 
damages   payable.     Once   the   Arbitrator   arrives   at   a   figure,   even   by 
guesswork, the Court may not interfere with it, if it is not unreasonable.
17. The   Apex   Court   in   the   case   of   Mohd.Salamatullah 
4
V/s.Government of AP , while dealing with the grant of damages in the case 
of breach of contract, held that the appellate Court was not justified in 
interfering with the quantification of damages, even if they were based on 
guesswork.   In the present case the Arbitrator has granted 10% damages 
towards the loss of profit. We do not intend to interfere with the award of 
4   (1977) 3 SCC 590
SRK 11 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
grant  of damages.  Not only  it appears reasonable  to us in facts of  the 
present case, we must also bear in mind the scope of appeal under section 
37 of the Arbitration Act.   
18. The second objection of the learned counsel for appellant was 
regarding payment of costs. The learned Arbitrator awarded Rs.26,04,129/­ 
on account of costs of arbitration to be paid by the Appellant. Learned 
counsel for the appellant makes a grievance that many reliefs claimed for by 
the   Respondent   were   not   granted   by   the   Arbitrator   and   in   fact   the 
substantial claim of Rs.35,37,176/­ was arrived at by an agreement between 
the parties. Thus, learned counsel contended that the costs were excessive. 
Learned counsel for the Respondent submitted that though the substantial 
claim   was   arrived   at   by   way   of   consensus   between   the   parties,   the 
concession  was  given   by  the   appellant   only   after   about   60   sittings.   He 
submits   that   it   is   not   as   if     in   the   preliminary   stages   itself,   that   the 
appellant had conceded to the claim. 
19. We   have   been   informed   that   around   71   sittings   of   arbital 
tribunal took place.   In that context, if the amount of Rs.26,04,129/­ is 
spread   over   71   sittings,   the   resultant   cost   awarded   per   sitting   is   not 
exorbitant or unreasonable.  The learned Arbitrator also took note of the fact 
that the appellant itself had claimed an amount of Rs.19 lakhs towards the 
fees of the advocates alone.   However, we do find some substance in the 
argument of the learned counsel for the appellants that once  most of the 
claims of the respondent were rejected and the appellant had agreed to 
settle   the   substantial   claim,   the   learned   Arbitrator   was   not   justified   in 
directing the appellant to pay 90% of the costs.   Even if the share of the 
appellant towards payment of cost is pegged down to 70% and the figure is 
rounded off, it would come to about Rs.20 lakhs.  We propose to reduce the 
costs payable by the appellant to the respondent  to Rs.20 lakhs. 
SRK 12 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
20. The last contention advanced on behalf of the appellant was in 
respect of payment of interest. It was contended that the learned Arbitrator 
ought not to have awarded interest on the amounts awarded from the date of 
the claim till the award.
21. It   was   contended   on   behalf   of   the   appellant   that   since   the 
parties   arrived   at   the   settlement   on  5   January   2009   agreeing   that   the 
amount of Rs.35,37,176/­ was to be paid by the appellant to the respondent 
for item (i) – “work done not paid”, there was no justification to grant interest 
from 1 January 2006.
It is not possible to accept the above submission.   In the first 
place, when the parties arrived at the above agreement on 5 January 2009, 
the   respondent­claimant   had   made   it   more   than   amply   clear   that   the 
settlement for the respondent's claim under item (i) ­ “work done not paid” at 
Rs.35,37,176/­ was without prejudice to the rights and contentions of the 
parties qua the other claims.  The other claims included claim no.(xiv)  for 
interest at the rate of 24% per annum on the amounts claimed.  Hence, the 
learned   Arbitrator   was   justified   in   granting   interest   on   the   amount   of 
Rs.35,37,176/­ under item (i) ­ “work done not paid” for the period from the 
date of the claim till the date of the award, i.e. from 1 January 2006 till 5 
March 2010.
22. Learned   counsel   for   the   appellant,   however,   submitted   that 
when the claimant has been awarded compensation for loss of profit on the 
basis of guess work and not on the basis of any evidence led by the claimant 
before the learned Arbitrator, no interest should have been awarded from the 
date of the claim till the date of the award.
23. Learned counsel for the respondent­claimant, however, opposed 
the above submission and contended that loss of profit occurred when the 
SRK 13 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
contract was breached and while passing the award the learned Arbitrator 
only recognized this fact.  It was not as if the loss of profit occurred when it 
came to be computed by the learned Arbitrator.
24. We are of the view that while the submission made by each 
party   has   some   merit,   the   matter   needs   to   be   examined   with   some 
circumspection.  Though ordinarily an arbitration award would not deserve 
to be interfered with merely because another view is possible, in the facts 
and circumstance of the case it may not be unreasonable not to award 
interest   from   the   date   of   the   claim   till   the   date   of   the   award   giving 
compensation for loss of profit when the claimant had not led any evidence 
such as calculations made at the time of submitting the tender.   On the 
other   hand,   where   the   claimant   has   led   evidence   before   the   learned 
Arbitrator to quantify the compensation for loss of profit upon wrongful 
termination of the contract, the learned Arbitrator should award interest 
from the date of the claim till the date of the award.  Since, in the facts of 
the present case, the claimant had not led specific evidence and the learned 
Arbitrator has awarded compensation for loss of profit on the basis of mere 
estimates, we are of the view that interest should not be awarded to the 
claimant on the amount of compensation for loss of profit from the date of 
claim till the date of award.  In any case, we make it clear that the claimant 
is entitled to interest on the amount of compensation for loss of profit from 
the date of award till the date of payment.
25. As regards the future rate of interest, i.e. interest for the period 
from the date of the award till the date of payment, it has already been 
reduced by the learned Single Judge from 18% to 12% per annum.  In the 
absence of any cross objection, there is no occasion for considering this 
aspect.  
26. In view of the above discussion, we are of the view that the 
award made by the learned Arbitrator does not call for any interference 
SRK 14 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::

app-349-12.sxw
except the following modifications:­
i) The   amount   on   account   of   costs   to   be   paid   to   the 
respondent­claimant shall be Rs.20 lakhs.  
ii) As far as the interest is concerned, the same shall be 
calculated at the rate of 12% per annum from the date of 
the claim  till   the date of the award on the principal 
amount awarded by the Arbitral Tribunal i.e. Rs.35.37 
lakhs for the work done and not paid under claim No. (i) 
and also at the rate of 12% per annum from the date of 
the   award   till   the   date   of   payment   on   the   principal 
amount of Rs.35.37 lakhs.
iii) Interest shall be paid at the rate of 12% per annum from 
the date of the award till the date of payment on the 
amount of Rs.25.23 lakhs under the head “loss of profit”, 
and not for any period prior to the date of the award.
iv) As regards the future rate of interest, the learned Single 
Judge has already reduced the rate of interest from 18% 
to 12% and that part of the judgment stands confirmed.
  The appeal is accordingly partly allowed only to the aforesaid 
extent.
    CHIEF JUSTICE
   
        N.M. JAMDAR , J .
SRK 15 of 15
::: Downloaded on - 26/06/2024 07:31:32 :::