Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 7373 of 1996
PETITIONER:
STATE BANK OF SAURASHTRA
RESPONDENT:
P.N.B. PUNJAB NATIONAL BANK
DATE OF JUDGMENT: 26/04/2001
BENCH:
B.N. KIRPAL & RUMA PAL & BRIJESH KUMAR
JUDGMENT:
JUDGMENT
2001 (3) SCR 236
The Judgment of the Court was delivered by
KIRPAL J. This is an appeal filed against the judgment of the Special Court
constituted under the Special Court (Trial of Offences relating to
Transactions in Securities) Act, 1992 whereby the suit filed by the
respondent was decreed and it was inter alia ordered that the appellant
herein should purchase units which had been agreed to be sold to the
respondent and deliver the same to it.
Briefly stated the facts are that the respondent paid Rs. 26,82,00,000 to
the appellant on 10th September, 1991 for purchase of 2 crore units of the
Unit Trust of India at the rate of Rs. 13 41p. per unit Subsequently, on
23rd October, 1991 it paid further sum of Rs; 75,83,12,500 as consideration
for the purchase of 5.50 crore units at the rate of Rs; 13.7875 per unit
In respect of the aforesaid two transactions the appellant issued to the
respondent two bankers’ receipts one bearing No. 53 dated 10th September,
1991 and the other being No 81 dated 23rd October, 1991. According to the
said bankers’ receipts the units were to be delivered by the appellant to
the respondent against the discharge in the said receipts.
It is an admitted case of the parties that the units in respect of which
payment was received by the appellant were never delivered to the
respondent Considerable correspondence was exchanged between the parties
but what is of relevance is a letter dated 1st July, 1992 whereby the
respondent asked the appellant to pay to it a sum of Rs. 134.42 crores by
3rd July, 1992. It was further stated that any delay in payment would then
attract interest at the rate of 24 per cent per annum or call money rate
whichever was higher. Prior to the issuance of this letter, correspondence
between the parties showed that the appellant was promising to give the
delivery of the units but by this letter of 1st July, 1992 the respondents
claimed compensation as calculated in the annexure to this letter. The
computation of the claim was given according to which the respondent
treated the breach of the contract to have taken place on 30th May, 1992
and on that basis it claimed difference in price between the rate what was
paid and the rate of the Unit Trust of India as on 30th of May, 1992.
No amount was paid by the appellant, whereupon the respondent filed a suit
inter alia claiming the delivery of the units in respect of which the
payment had been made. An alternative prayer which was made was for damages
for a sum of Rs. 249,19,00,549 plus further interest at the rate of 17.5
per cent per annum on the said sum till the date of payment. As already
indicated herein above by the impugned judgment dated llth March, 1996 the
Special Court, Bombay granted the relief of specific performance which
required the appellant to buy 7.5 core units for which payment had been
made and in addition thereto it was also required to purchase and sell to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
the respondent the units representing the right issue which the respondent
was deprived of availing of because of the non-delivery of the units. Costs
of Rs, 27.87,000 were also awarded. Hence this appeal.
We have heard the counsel for the parties at length, During the pendency of
the appeal at the time of admission an interim order was passed on 8th May,
1996, By this order the appellant was directed to pay to the respondent-
bank Rs. 182 crores or jn the alternative it was required to transfer units
of the Unit Trust of India worth Rs. 182 crores calculated on the
repurchase price. In addition thereto the appellant was directed to
transfer units worth Rs. 30 crores, It is an admitted case of the parties
that pursuant to the aforesaid direction between May and June 1996 units
worth about Rs. 210 crores were handed over to the respondent and in
addition there to an amount of the RJS. 2 crores was also paid by the
appellant. According to the appellant, the amount payable by it came to
about Rs. 182 crores.
It is not necessary for us to go into the correctness of the various issues
decided by the Special Court. The appellant admit that the respondent, to
whom delivery of the units was not made, would be entitled to the refund of
the money plus damages thereon calculated in accordance with he principles
contained in Section 73 of the Indian Contract Act, 1872.
Considering the fact that there was an alternative plea for damages, on the
facts of the present case it would have been appropriate for the Special
Court to have computed and awarded the damages in addition to ordering
refund rather than requiring the appellants to purchase the units and give
the same to the respondent. In other words, a decree for specific
performance in the manner in which it was passed was probably not
appropriate especially when the respondent could be compensated with the
return of money and award of reasonable damages.
As, now there is no dispute on the principle applicable namely, that the
amount of Rs. 102,65,]2,500 which was paid by the respondent had to be
refunded to it and the respondent was also entitled to get reasonable
amount of compensation or damages, what is now required to be done is only
to quantify the same. This is what we propose to do.
The aforesaid letter dated 1st July, 1992 written by the respondent when
read alongwith the computation sheet accompanying the said letter clearly
shows that the respondent regarded that the appellant had committed the
breach of contract on 3Oth May, 1992. it is on this basis that it claimed,
in addition to the return of money, damages being the difference between
the price of the units paid and the price as on 30th May, 1992. It appears
to us that what the respondent would be entitled to, in addition to the
refund of Rs. l02, 65,l2,500 , is interest at the lending rate on the
aforesaid amount from the date of payment till the date of filing of suit
i.e. 8th September, 1994, In addition thereto, the respondent would also be
entitled to pendente lite and future interest calculated at the rate of
17.5. per cent per annum, as claimed by it in the plaint. We have got the
calculation done from the representatives of the parties and it appears
that calculated in this manner and also keeping in view the difference in
the price per unit as on 30th May, 1992 and the rate at which the units had
been agreed to be purchased, the total sum payable by the appellant to the
respondent would be about Rs. 212 crores. Inasmuch as units worth Rs. 210
crores have been given by the appellant to the respondent in addition to
payment of about Rs. 2 crores in cash, no further amount would now be
payable.
We, accordingly, modify the decree passed by the Special Court and direct
that a sum of Rs. 212 crores was payable by the appellant to the respondent
and as we value the said amount has already been received by the respondent
the decree stands satisfied. We make it clear that the disposal of this
appeal does not in any way approve or disapprove the reasoning of the
Special Court.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
The appeal is disposed of in the aforesaid terms. Cross appeal of the
respondent and Interlocutory Application also stand disposed of. Parties to
bear their own costs.