Full Judgment Text
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
2024 INSC 557
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 8985 OF 2022
VIDYA AND OTHERS …APPELLANT(S)
VERSUS
M/S PARSVNATH DEVELOPERS LTD. …RESPONDENT(S)
J U D G M E N T
B.R. GAVAI, J.
th
1. This appeal challenges the order dated 29 September,
2022 passed by the National Consumer Disputes Redressal
Commission, New Delhi (hereinafter referred to as the
‘Commission’) in Consumer Case No. 1557 of 2016 wherein
the Commission partly allowed the complaint preferred by
the complainants-appellants herein and directed the sole
respondent herein, to refund the entire sum deposited by the
complainants-appellants with interest at the rate of 9% per
annum from the date of respective deposit till the date of
Signature Not Verified
Digitally signed by
Deepak Singh
Date: 2024.07.29
15:54:30 IST
Reason:
refund, within a period of two months from the date of the
said order.
1
2. The facts, in brief, giving rise to the present appeal are
as under:
2.1. M/s Parsvnath Developers Limited (hereinafter referred
to as the ‘Developer’), a company registered under the
Companies Act, 1956, and engaged in the business of
development and construction of inter alia residential
projects as well as projects for the Delhi Metro Rail
Corporation, launched a group housing project (hereinafter
referred to as ‘the project’) titled ‘Parsvnath Paramount’ at
Subhash Nagar (near Subhash Nagar Metro Station), New
Delhi in the year 2008 and widely publicized the same.
2.2. Upon gaining knowledge of the project, the
complainants-appellants booked a 3BHK flat in the said
project and to that end, deposited a sum of Rs.16,03,066/-
th
on 15 July, 2008. Subsequently, the complainants-
appellants paid second instalment of an identical sum on
th
14 August, 2008.
2.3. Subsequently, the complainants-appellants and the
respondent-Developer entered into a Flat Buyer Agreement
th
(hereinafter referred to as ‘the Agreement’) on 10 October,
2008 and in furtherance of the same, the complainants-
2
appellants were allotted Flat No. 301 situated in Tower 3 of
the project, which had an approximate area of 1805 sq. ft.
The total payable price of the flat was determined to be Rs.
1,28,24,525/- calculated at the rate of Rs. 7105/- per sq. ft.
of the saleable/super built-up area. An additional sum of Rs.
3,00,000/- was to be paid for the mandatory covered car
parking space in the concerned tower. Clause 11(a) of the
Agreement clarified that the construction of the flat would be
completed within a period of 30 months of commencement of
construction of the particular Tower in which the flat was
located, with a further grace period of 6 months.
2.4. The complainants-appellants opted for a ‘Construction
Linked Payment Plan’ under which 25% of the sale price was
payable within 30 days of booking, 60% of the sale price and
the additional sum for the covered car parking space was
payable in 6 installments and 15% of the sale price was
payable in another 3 installments. In pursuance of the same,
the complainants-appellants paid a total sum of
th
Rs.1,30,62,971/- in the intervening period between 15 July,
st
2008 and 21 December, 2013, as per the demand of the
respondent-Developer. The aforesaid amount deposited by
3
the complainants-appellants amounted to about 95% of the
total sale price of the flat.
2.5. In the meanwhile, the respondent-Developer unilaterally
transferred the said Flat No. 301 situated in Tower 3, which
had been initially allotted to the complainants-appellants, to
Flat No. 702 situated in Tower 2, admeasuring 1942 sq. ft.,
in April, 2011.
2.6. Subsequently, the respondent-Developer raised a
demand for the payment of VAT amounting to Rs. 60,141/-
th
which was duly paid by the complainants-appellants on 29
January, 2014. A second payment of an identical sum was
th
made on 13 March, 2014.
2.7. In the interregnum, the period of 36 months set out in
the Agreement, including the grace period of 6 months, had
expired.
2.8. On failure of the respondent-Developer to handover the
possession of the flat within the expected deadline, despite
timely payments, the complainants-appellants made several
attempts to contact the respondent-Developer to enquire
about the progress of the project but received no substantial
update. Thereafter, the complainants-appellants visited the
4
site in June, 2015 and discovered that no construction work
was ongoing.
2.9. Aggrieved by the halt in construction, the complainants-
th
appellants in a letter dated 15 June, 2015, addressed to the
respondent-Developer, enquired about the time-frame within
which the construction would be completed and possession
would be handed over to them. Further, the complainants-
appellants enquired about the manner in which they would
be compensated on account of the delay in delivery of
possession.
2.10. The respondent-Developer in subsequent letters
th th
dated 29 June, 2015 and 5 July, 2015 informed the
complainants-appellants that the delay in construction was
on account of technical issues and recession in the real-
estate sector owing to which construction for the project had
suffered. However, the respondent-Developer, assured the
complainants-appellants that they had persisted with the
construction and the same would be completed at the
earliest and the complainants-appellants would be informed
about the tentative date for making an offer of possession,
thereafter. So far as the compensation claimed for was
5
concerned, the same was to be governed by the terms and
conditions laid down in the Agreement. However, the
respondent-Developer failed to directly address the specific
queries that had been raised by the complainants-appellants.
2.11. Subsequently, the complainants-appellants
addressed two further letters to the respondent-Developer on
th th
28 October, 2015 and 6 January, 2016, respectively, once
again raising queries as to when the construction would be
completed and the possession would be handed over to them,
whether the construction would be completed at all and the
manner in which the complainants-appellants would be
compensated for the delay in conclusion of the project.
However, the respondent-Developer did not respond to the
said letters.
2.12. Aggrieved thereby, the complainants-appellants
filed a complaint before the Commission being Consumer
Case No. 1557 of 2016 praying for a refund of the entire
amount paid by them as per the current market value along
with interest at the rate of 24% per annum, thereon, from the
date of booking the flat till the date of payment as well as
compensation amounting to Rs. 1,37,36,350/- along with
6
interest at the rate of 24% per annum thereon, among other
reliefs.
2.13. The learned Commission, by the impugned order,
partly allowed the said Consumer Case No. 1557 of 2016 in
the afore-stated terms, with costs of Rs. 1 lakh.
3. Being aggrieved thereby, the present appeal.
4. We have heard Shri Sanjay Jain, learned counsel
appearing on behalf of the complainants-appellants and Shri
Jayant Muth Raj, learned Senior Counsel appearing on
behalf of the respondent-Developer.
5. Shri Jain, learned counsel appearing for the
complainants-appellants submitted that the learned
Commission erred in awarding the interest only at the rate of
9% per annum. He submitted that the Agreement provided
that, in case there is delay in payment by the flat purchaser,
the respondent-Developer was entitled to condone the same
by charging interest at the rate of 24% per annum of the
amount in default. He further submitted that the proforma
agreement was fully tilted in favour of the respondent-
Developer. The Agreement provided that, in case of delay in
completion of the project by the respondent-Developer, it was
7
liable to pay interest only at the rate of 12% per annum. It is
submitted that there is no logic in making the flat purchaser
liable for payment of interest at the rate of 24% per annum
whereas the respondent-Developer was liable to pay interest
only at the rate of 12% per annum.
6. Shri Jain therefore submitted that, applying the
principle of parity, the learned Commission ought to have
awarded the interest at the rate of 24% per annum. It is
submitted that, in any case the interest at the rate of only 9%
per annum is not sustainable in law.
7. Per contra, Shri Jayant Muth Raj, learned Senior
Counsel appearing on behalf of the respondent-Developer
submitted that the delay in completion of the project was not
deliberate. He submitted that, since there was a delay in
sanctioning of the plans by the Delhi Development Authority,
the project could not be completed. It is therefore submitted
that the case was duly covered under the force majeure
clause and as such, interest even at the rate of 9% was not
liable to be imposed upon the respondent-Developer.
8. We have perused the order passed by the learned
Commission. Insofar as the contention of the respondent-
8
Developer that since there was a delay in sanctioning the
layout plans, it was covered under force majeure clause is
concerned, this Court, in the case of DLF Home Developers
Limited (earlier known as DLF Universal Limited) and
Another v. Capital Greens Flat Buyers Association and
1
Others has held to the contrary. Therefore, the contention
in that regard is without substance. We find that the learned
Commission has rightly directed the respondent-Developer to
refund the entire amount deposited by the complainants-
appellants. However, we find that, insofar as award of
interest at the rate of 9% per annum is concerned, the
learned Commission was not justified in the facts of the case
to award a lesser interest than even the one agreed upon in
the Agreement. Undisputedly, the facts of the case show that
the project was delayed inordinately. The complainants-
appellants were made to suffer for long, for no fault of them.
In spite of making the entire payment, they were deprived of
the possession within the stipulated time.
1
(2021) 5 SCC 537
9
9. In our view, the learned Commission, at least, ought to
have awarded interest at the rate of 12% per annum in view
of clause 7(b) of the Agreement.
10.
In the result, the appeal is partly allowed. The direction
made by the learned Commission for refund of the entire
amount deposited by the complainants-appellants is upheld.
However, the direction with regard to interest is modified to
the extent that it shall be paid at the rate of 12% per annum
from the date of respective deposit till the date of refund.
The unpaid amount in terms of the aforesaid shall be paid
within a period of three months from the date of this
judgment.
11. Pending application(s), if any, shall stand disposed of.
..............................J.
(B.R. GAVAI)
..............................J.
(SANDEEP MEHTA)
NEW DELHI;
JULY 29, 2024
10