WESTERN COALFIELDS LIMITED, THROUGH ITS CMD AND ANOHTER vs. RAJESH S/O NANDLAL BIYANI, PROP. OF M/S SHREE SAI CONSTRUCTION COMPANY AND ANOTHER

Case Type: NaN

Date of Judgment: 09-06-2011

Preview image for WESTERN COALFIELDS LIMITED, THROUGH ITS CMD AND ANOHTER  vs.  RAJESH S/O NANDLAL BIYANI, PROP. OF M/S SHREE SAI CONSTRUCTION COMPANY AND ANOTHER

Full Judgment Text

0609ao85.11.odt
1
IN THE HIGH COURT OF JUDICATURE 
AT BOMBAY, NAGPUR BENCH, NAGPUR.
APPEAL AGAINST ORDER NO.85 OF 2011
1) Western Coalfields Limited, 
Through it's CMD, 
A Govt. Of India Undertaking, 
having it's Registered 
Office at Coal Estate, 
Civil Lines, Nagpur­01.
2) Western Coalfields Limited, 
through it's General Manager 
(Civil) Coal Estate, 
Civil Lines, Nagpur­01.       .......... Appellants.
                         Original Defendant Nos.1 & 2
VERSUS
1) Rajesh s/o Nandlal Biyani, 
Proprietor of M/s.Shree 
Sai Construction Company, 
A Registered Government 
Contractor and Civil 
Engineers, having it's 
Head Office at 
“Gokuldham” D.G.Tukum, 
Tadoba Road, 
Chandrapur­442 401 (MS).      .......... Respondent.
                           Original respondent No.1.
2) Oriental Bank of Commerce, 
(Govt.of India Undertaking) 
having it's Branch at 
“Gold Sukh” Kasturba Chowk, 
.....2/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
2
Chandrapur, 
Through it's Manager.         .......... Respondents.
                            Original Defendant Nos.3.
Shri A.M.Gordey, Senior Advocate assisted by 
Shri Deepak Gupta, Advocate for the 
appellants/Original Defendant Nos.1 & 2.
Shri J.P.Pendse, Counsel for the respondent 
no.1 original plaintiff.
CORAM  : R. K.DESHPANDE, J. 
DATE OF RESERVING THE JUDGMENT : 25/08/2011
DATE OF PRONOUNCING THE JUDGMENT : 06/09/2011.
JUDGMENT.
01) This   appeal   challenges   the   order   5.4.2011 
passed   by   the   Third   Joint   Civil   Judge,   Senior 
Division, Nagpur, allowing the application Exh.5 for 
grant   of   temporary   injunction,   restraining   the 
appellants   from   invoking   the   Bank   Guarantees 
furnished  on 19.2.2008  filed in Special  Civil Suit 
No.236 of 2011 by the respondent no.1/plaintiff. The 
appellants   are   the   defendant   nos.1   and   2,   the 
respondent no.1  is the plaintiff and the respondent 
.....3/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
3
no.2   is   the   Oriental   Bank   of   Commerce   and   the 
original defendant no.3. 
02) The facts not in dispute are stated below­­
On   18.5.2007,   the   appellants/original 
defendant nos.1 and 2 awarded the contract for the 
work of diversion  of Motaghat Nallah (Phase­II and 
Phase­III) at Padmapur Open Cast Mine of Chandrapur 
area, to the respondent no.1/plaintiff. An Agreement 
No.08/2007­2008 was entered into between the parties. 
The total cost of contract was of Rs.13.95 Crores. 
The period of completion of work prescribed under the 
contract   was   from   23.7.2007   to   28.10.2008.   On 
10.10.2007,   two   Bank   Guarantees   of   M/s.Mahesh 
Merchant   Bank   Limited,   Chandrapur,   said   to   be   a 
Scheduled Bank, were furnished by way of performance 
guarantees, by the plaintiff. During the progress of 
work, the respondent no.1 substituted the aforesaid 
two Bank Guarantees by two separate Bank Guarantees 
dated   19.2.2008   of   the   Nationalized   Bank   i.e. 
Oriental   Bank   of   Commerce   (the   respondent   no.2 
.....4/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
4
herein).   One   Bank   Guarantee   was   for   Rs.69,79,000/­ 
whereas other  was for Rs.1,54,94,580/­. Thus, it was 
for   total   amount   of   Rs.2,24,73,580/­   that   the   two 
guarantees were furnished and their validity is upto 
19.11.2011. The respondent no.1 completed 40% of work 
to the tune of Rs.5,95,96,000/­ upto 28.10.2008 and 
the   balance   60%   work,   costing   Rs.799.86   Lacs, 
remained incomplete.
03) On   5.3.2009,   the   appellants   issued   a   show 
cause notice to the respondent no.1 asking as to why 
the   penal   interest   should   not   be   recovered   on   the 
amount   of   Rs.2,24,73,580/­   for   a   period   of   five 
months during which the contract was continued on the 
basis of the forged and fake Bank Guarantees of non 
existent bank i.e. M/s.Mahesh Merchant Bank Limited. 
The   respondent   no.1   was   called   upon   to   deposit   an 
amount   of   Rs.16,85,528/­     as     penal     interest     @ 
18 %  per  annum,  on  the said amount for a period 
of five months. It is not disputed that this amount 
of   penal   interest   has   been   recovered   from   the 
.....5/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
5
respondent   no.1.   By   communication   dated   16.9.2010, 
the appellants terminated the contract for the reason 
of furnishing of fake Bank Guarantees of non existent 
bank   by   the   respondent   no.1.   Thereafter,   by 
communication   dated   17.2.2011,   addressed   to   the 
Oriental Bank of Commerce, the appellants invoked two 
Bank Guarantees of total Rs.2,24,73,580/­.
04) On 21.2.2011, the respondent no.1/plaintiff 
filed   Special   Civil   Suit   No.236   of   2011   for   a 
declaration that the invocation of Bank Guarantees by 
the appellants/defendant nos.1 and 2, was illegal and 
for further declaration that the communication dated 
17.2.2011  is not a valid demand. Further, the relief 
of injunction is claimed, restraining the defendants 
from invoking the Bank Guarantees and acting upon the 
communication dated 17.2.2011. An application (Exh.5) 
was   also   filed   for   grant   of   temporary   injunction 
under Order 39 Rule 1 and 2 read with Section 151 of 
the Code of Civil Procedure. The Trial Court granted 
exparte   injunction   on   21.2.2011,   restraining   the 
.....6/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
6
defendants from encashing the Bank Guarantees pending 
the decision of the application at Exh.5. The plaint 
was   thereafter   amended   and   in   addition   to   the 
existing   reliefs,   a   decree   for   an   amount   of 
Rs.5,16,69,618/­ was claimed along with the damages 
of Rs.1.00 Crore, against the appellants.
05) An exparte injunction  granted by the Trial 
Court on 21.2.2011, was as under­­
ORDER
1.   Defendants   No.1   and   2   are   hereby 
restrained   from   taking   step   from 
encashing   bank   guarantee 
No.OBC/CHP/BG/02020002808   dtd.19.2.08 
for Rs.69,79,000/­ valid upto 19.11.11 
and   bank   guarantee 
No.OBC/CHP/BG/02020002908   dtd.19.2.08 
for Rs.1,  94,580/­ valid upto 19.11.11 
towards additional performance security 
till their appearance and filing reply 
to the application at exh.5.
2. Defendant No.3 and its employee etc. 
are hereby restrained from making any 
payment to defendant Nos.1 and 2 as per 
above described bank guarantee till its 
appearance   and   filing   reply   to   the 
application exh.5.
2. Issue notices to defendants No.1 to 
.....7/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
7
3 as to why above ex­parte ad­interim 
injunction should not be confirmed till 
the   decision   of   suit   on   P.F.   r/o 
8.3.11.
3.   Plaintiff   is   directed   to   comply 
mandatory   provision   of   O.39   R.3(a)(b) 
of   Civil   Procedure   Code   within 
stipulated period of 24 hours.
4. Steno copy be provided to the party.
Nagpur                   (S.S.Deodhar)
rd
Date : 21.2.2011   3  Jt.C.J.Sr.Dn., Nagpur.
The Trial Court by an order impugned passed 
on 5.4.2011, confirmed the exparte injunction granted 
and  continued the same, pending the decision of the 
suit. The appellants are restrained from invoking the 
Bank   Guarantees   and   the   defendant   no.3   (respondent 
no.2 Bank) is restrained from making payment of Bank 
Guarantees. The Trial Court has held that the copies 
of two Bank Guarantees of Nationalized Bank, viz; the 
Oriental Bank of Commerce, issued on 19.2.2008, are 
placed   on   record   and   the   same   are   valid   upto 
19.11.2011. Out of these two Bank Guarantees, one is 
for an amount  of Rs.1,54,94,580/­, which was valid 
.....8/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
8
upto 19.11.2011  and the other is for an amount  of 
Rs.69,79,000/­,   which   was   valid   upto   Rs.19.5.2009. 
The letters dated 27.4.2009 and 28.4.2009, issued by 
the appellants/defendant nos.1 and 2 show that the 
Bank Guarantees are accepted and the respondent no.1 
has extended its validity upto 19.11.2011. 
06) The finding is recorded by the Trial Court 
that the invocation was on the ground of submission 
of fake Bank Guarantees of non existent Bank and not 
on the ground of delay in completion of the work. It 
is held that the case of the plaintiff is that the 
said act was done by his Power of Attorney holder and 
when the plaintiff came to know that the said Bank 
Guarantees are not in order, he voluntarily replaced 
the   same   and   submitted   the   fresh   Bank   Guarantees 
issued   by   the   Oriental   Bank   of   Commerce   (the 
respondent   no.2),   a   Nationalized   Bank,   which   are 
accepted by the appellants along with the extensions 
of their validity period.   It has further been held 
that at this stage, it cannot be said that the fake 
.....9/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
9
Bank Guarantees were furnished only with a view to 
obtain the work. The appellants  have recovered  the 
penal interest on account of submission of fake Bank 
Guarantees for a period of five months and criminal 
investigation will take its own course.
07) The   Trial   Court   has   further   held   that   the 
appellants/defendant nos.1 and 2 are required to show 
that they are entitled to recover the security amount 
from   the   respondent   no.1/plaintiff   because   of   the 
failure to execute the contract or negligence on the 
part   of   the   plaintiffs   in   executing   the   same, 
however, no such case has been made out. The Trial 
Court   has   recorded   a   finding   that   the   respondent 
no.1/plaintiff has prima­facie shown that there is no 
fault on his part, in delay caused in completion of 
the work and it is the appellants/defendant nos.1 and 
2 and the State Government, who were unable to remove 
the hindrances, as a result of which the respondent 
no.1/plaintiff could not execute the work. The Trial 
Court has, therefore, held that there is no question 
.....10/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
10
of recovery of any damages from the security deposit 
in respect of which the Bank Guarantees were provided 
and hence, the refusal to grant an injunction would 
result in frustrating  the claim of the plaintiffs. 
Hence, the order has been passed.
08) From   the   pleadings   of   the   parties,   the 
finding recorded by the Trial Court and the arguments 
advanced   before   this   Court,   the   undisputed   factual 
position needs to be culled out. The respondent no.1 
has   completed   40%   of   work   to   the   tune   of 
Rs.5,95,96,000/­ upto 28.10.2008. The invocation of 
the Bank Guarantees in question is not on the ground 
that the respondent no.1 has failed to complete 60% 
of work, costing of Rs.799.86 Lacs, upto 28.10.2008. 
It is the specific stand of the appellants in their 
written statement that non­completion of balance 60% 
of work by the respondent no.1 upto 28.10.2008, is 
totally   irrelevant   for   the   purposes   of   the 
controversy involved in the present  case. The Bank 
Guarantees have been invoked only for the reason that 
.....11/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
11
the   respondent   no.1   has   submitted   fake   Bank 
Guarantees for total amount of Rs.2,24,73,580/­ from 
the non existent of M/s.Mahesh Merchant Bank Limited, 
Chandrapur. 
09) It is also not in dispute that on account of 
loss   of   interest   for   submission   of   fake   Bank 
Guarantees   on   10.10.2007   to   19.10.2008   i.e.   for   a 
period of five months, the appellants have recovered 
the amount of penal interest of Rs.16,85,220/­ @ of 
18%   per   annum     on     total     amount       of       Bank 
Guarantees     Rs.2,24,73,580/­.   It   is   also   not   in 
dispute that the offences are registered against the 
respondent  no.1 and others  under Section 420, 468, 
469,   470,   471   read   with   Section   34   of   the   Indian 
Penal Code and the prosecution is in progress.
10) The   Trial   Court   has   recorded   the   finding 
that   on   the   basis   of   the   report   of   the   Committee 
appointed by the appellants for removal of hindrances 
and the finding is recorded about the failure of the 
.....12/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
12
appellants to discharge their obligations in respect 
of (i) the forest land clearance for execution of the 
work,   (ii)   the   problems   of   villages   of   Ketadi   and 
Mashala   have   not   been   resolved,   (iii)   the   P.W.D. 
State Highway Road Bridge of Chandrapur Tadoba Road, 
Near   Padmapur   Village   is   not   completed,   (iv)   the 
M.S.E.B. Bridge near Ketadi Village and also pipeline 
works  (Qty.81000 m3 approx)is not yet completed. It 
has further recorded the finding that the Committee 
appointed by the appellants has reported that it is 
unlikely that the State Government authorities will 
resolve the issue and allow to restart the work in 
near   future.   It   is   also   the   finding   that   the 
appellants   and the State Government are unable to 
remove the hindrances. All these findings recorded by 
the   Trial   Court,   have   not   been   assailed   in   this 
appeal. 
11) Shri A.M.Gordey, the learned Senior Counsel, 
has invited my attention to the preamble of the Bank 
Guarantees   to   urge   that   it   is   unconditional   and 
.....13/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
13
payable   without   any   demur   by   the   respondent   no.2 
Bank.   He   has   also   invited   my   attention   to   the 
Condition No.1 under the Bank Guarantee, which states 
that the Bank has agreed that the appellant Company 
shall be the sole judge as to whether the respondent 
no.1 has failed/neglected in performing any of the 
terms   and   conditions   of   the   said   contract   and   the 
decision of the appellant Company is made final and 
binding upon the parties. He further submits that the 
appellant, in whose favour the Bank Guarantees are 
furnished   by   the   respondent   no.2   Bank,   cannot   be 
prevented   by   way   of   an   injunction,   to   enforce   the 
Bank Guarantees on the pretext that the conditions of 
the agreement entered between the appellant and the 
respondent no.1 have not been fulfilled. He submits 
that   the   respondent   no.1   Company   cannot   be   the 
aggrieved   person   having   any   locus   to   raise   any 
dispute in respect of non­fulfillment of the terms of 
the   Bank   Guarantees.   He   further   submits   that   any 
dispute   in   respect   of   failure/negligence   in 
performing   the   terms   and   conditions   of   contract 
.....14/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
14
between the appellant beneficiary and the respondent 
no.1 Company is immaterial and of no consequence. 
12) In   support   of   the   proposition,   Shri 
A.M.Gordey, the learned Senior Counsel,   has relied 
upon the following decisions ­­
(i)Himadri Chemicals Industries Limited Vs. 
Coal Tar Refining Co., (2007) 8 SCC 110.
(ii)Vinitec Electronics Private Ltd. Vs. HCL 
Infosystems Ltd., (2008) 1 SCC 544. 
(iii)Mahatma Gandhi Sahakari Sakhar Karkhana 
Vs. National Heavy Engineering Co­op. Ltd., 
2007 DGLS (soft) 750 : 2007(6) S.C.C.470.
(iv)Mak   Impex   Chemicals   P.Ltd.   and   another 
Vs.   Union   of   India   and   others,   AIR   2003 
Bombay 88.
(v)Maytas   Infra   Limited   Vs.   Utility 
Energytech & Engineers Pvt.Ltd. & anr., 2009 
B.C.I.133.
(vi)and the decision in Appeal Against Order 
No.6/2011   delivered   by   me   on   26.7.2011   in 
the  matter   of   Coal   India   Ltd.   and   another 
Vs.   Chintamani   Agrotech   (India)   Ltd.   and 
others,
13) Inviting   my   attention   to   the   letter   dated 
.....15/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
15
18.5.2011   issued   by   the   appellant   awarding   the 
contract to the respondent no.1, Shri A.M.Gordey, the 
learned Senior Counsel, has urged that the specific 
condition in   the contract was that the respondent 
no.1 shall   submit  the valid Bank Guarantees of a 
Nationalized/Scheduled   Bank   by   way   of 
performance/additional   performance   security.   The 
respondent   no.1   has   submitted   the   fake   Bank 
Guarantees of non existent Bank and thus, it was the 
violation of the terms and conditions of the contract 
for   which,   the   Bank   Guarantees   were   invoked.   He 
further submits that the respondent no.1 has carried 
out the work only to the extent of Rs.595.93 Lacs, 
which is the 40% of the total work and the balance 
60% of the work costing of Rs.799.86 Lacs remained 
incomplete. He further submits that incomplete work 
is   to   be   awarded   to   the   another   contractor   and 
considering the inflation, the said cost is assessed 
at Rs.1182.52 approximately and as such an additional 
expenditure of Rs.382.66 Lacs, is legally recoverable 
from the respondent no.1. He submits that it is thus 
.....16/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
16
a   failure/negligence   in   performing   the   terms   and 
conditions of the contract by the respondent no.1, 
that the amount as assessed has become recoverable 
for which the Bank Guarantees have been invoked.
14) The   contention   of   Shri   J.P.Pendse,   the 
learned Counsel for the respondent no.1, is that the 
preamble of the Bank Guarantees clearly indicate that 
the contract of the Bank Guarantees in question, is a 
conditional   and   contingent   contract   depending   upon 
the fulfillment of the conditions specified therein. 
According to him, there should be a demand in writing 
stating that there is a specified amount which is due 
and payable by the respondent no.1 for the reason of 
the   failure/negligence   in   performing   the   terms   and 
conditions   contained   in   the   contract   by   the 
respondent   no.1.   Referring   to   the   letter   dated 
17.2.2011, impugned in the  Special Civil Suit No.236 
of 2011, he has urged that there is nothing on record 
to show that any amount is due and payable by the 
respondent no.1 to the appellant for the reason of 
.....17/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
17
failure/negligence   in   performing   the   terms   and 
conditions   contained   in   the   contract.   He   further 
submits that there is no demand as contemplated in 
the   preamble   of   the   said   agreement,   made   in   the 
impugned communication dated 17.2.2011. According to 
him,   the   terms   of   the   contract   of   Bank   Guarantees 
have to be strictly construed and the compliance in 
respect thereof needs to be seen. He submits that in 
the absence of compliance with the terms of the Bank 
Guarantees,   the   invocation   causes   an   irretrievable 
injury   to   the   respondent   no.1.   He   further   submits 
that the violation of the terms of the guarantee has 
to be regarded as species of the same genus as fraud, 
which disentitles a beneficiary to enforce the Bank 
Guarantee.
15) In   support   of   the   plea   that   the   Bank 
Guarantees   are   conditional,  Shri   J.P.Pendse,   the 
learned Counsel for the respondent no.1, has relied 
upon the decisions in the cases of­­
.....18/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
18
(a)  Hindustan   Construction   Co.   Ltd.   Vs. 
State   of   Bihar   and   others   with   State   of 
Bihar and others Vs. Hindustan Construction 
Co.   Ltd.   and   others,   reported   in   (1999)   8 
SCC 436
(b) Vinitec Electronics Private Ltd. Vs. HCL 
Infosystems Ltd., (2008) 1 SCC 544
(c)  National   Aluminium   Co.     Ltd.,   Vs. 
M/s.R.S.Builders   (India)   Ltd.   and   others, 
.
reported in AIR 1991 Orissa 314
16) In   the   decision   of   the   Apex   Court   in 
Hindustan  Construction  Co. Ltd. Vs. State of Bihar 
and others , the order passed by the Single Judge of 
this   Court   granting   injunction   restraining   the 
defendants   from   invoking   the   Bank   Guarantees   was 
restored by modifying  the decision  of the Division 
Bench of this Court vacating the injunction granted 
by   the   learned   Single   Judge   in   respect   of   the 
performance guarantee. Paras­9, 10 and 14 of the said 
judgment   are   relevant   and   the   same   are   reproduced 
below­­
Para­9  : “What is important, therefore, 
is that the bank guarantee should be in 
unequivocal   terms,   unconditional   and 
.....19/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
19
recite   that  the  amount   would  be   paid 
without   demur   or   objection   and 
irrespective of any dispute that might 
have   cropped   up   or   might   have   been 
pending   between   the   beneficiary   under 
the   bank   guarantee   or   the   person   on 
whose   behalf   the   guarantee   was 
furnished.   The   terms   of   the   bank 
guarantee   are,   therefore,   extremely 
material.   Since   the   bank   guarantee 
represents   an   independent   contract 
between the bank and the beneficiary, 
both the parties would be bound by the 
terms   thereof.   The   invocation, 
therefore,   will   have   to   be   in 
accordance with the terms of the bank 
guarantee,   or   else,   the   invocation 
itself would be bad.”
Para­10   :   “In   the   instant   case,   the 
whole matter can be disposed of purely 
on the basis of the terms of the bank  
guarantee.”
Para­14   :   “This   condition   clearly 
refers to the original contract between 
HCCL and the defendants and postulates 
that if the obligations, expressed in 
the contract, are not fulfilled by HCCL 
giving to the defendants the right to 
claim recovery of the whole or part of 
the   “advance   mobilisation   loan”,   then 
the Bank would pay the amount due under 
the   guarantee   to   the   Executive 
Engineer. By referring specifically to 
clause   9,   the   Bank   has   qualified  its 
liability to pay the amount covered by 
the   guarantee   relating   to   “advance 
mobilisation   loan”   to   the   Executive 
Engineer only if the obligations under 
the contract were not fulfilled by HCCL 
or HCCL has misappropriated any portion 
.....20/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
20
of the “advance mobilisation loan”. It 
is   in   these   circumstances   that   the 
aforesaid clause would operate and the 
whole   of   the   amount   covered   by   the 
“mobilisation   advance”   would   become 
payable on demand. The bank guarantee 
thus   could   be   invoked   only   in   the 
circumstances referred to in clause 9 
whereunder   the   amount   would   become 
payable only if the obligations are not 
fulfilled or there is misappropriation. 
That being so, the bank guarantee could 
not   be   said   to   be   unconditional   or 
unequivocal   in   terms   so   that   the 
defendants could be said to have had an 
unfettered   right   to   invoke   that 
guarantee and demand immediate payment 
thereof from the Bank. This aspect of 
the  matter   was   wholly   ignored   by  the 
High   Court   and   it   unnecessarily 
interfered   with   the   order   of 
injunction,   granted   by   the   Single 
Judge,   by   which   the   defendants   were 
restrained   from   invoking   the   bank 
guarantee.”
It has been held that in order to ascertain 
whether   the   Bank   Guarantees   are   conditional   or 
unconditional, the terms of the Bank Guarantees are 
extremely     material.     The     Bank     Guarantees 
represent   an   independent   contract   between   the   Bank 
and the beneficiary, and the parties would be bound 
by the terms thereof. The invocation therefore, will 
.....21/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
21
have to be in accordance with the terms of the Bank 
Guarantees   or   else   the   invocation   itself   would   be 
bad. The matter has to be disposed of purely on the 
basis of the terms of the Bank Guarantees.  If the 
Bank Guarantees furnished were conditional then the 
defendants   have   no   unfettered   right   to   invoke   the 
Bank Guarantees and to the demand immediate payment 
thereof from the Bank. 
17) In   the   decision   of   Vinitec   Electronics 
Private Ltd. Vs. HCL Infosystems Ltd. , the question 
considered was whether the Bank Guarantees furnished 
were unconditional and irrevocable. Paras­16 and 22 
of the said judgment are relevant and hence, the same 
are reproduced below­­
Para­16   :   “Shorn   of   all   the 
embellishments,   the   question   that 
really arises for our consideration is 
as to whether bank guarantee furnished 
is an unconditional and irrevocable one 
or   a   conditional   one?   It   may   not   be 
necessary to refer in detail the terms 
and conditions of the contract except 
to analyse the original clause of the 
bank guarantee dated 10.8.2001 and as 
.....22/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
22
well as the subsequent amendment of the 
relevant   clause   in   the   said   bank 
guarantee on 20.8.2001.”
  :   “In   the   present   case   the 
Para­22
amended clause does not refer to any of 
the clauses specifically as such but on 
the other hand the Bank had undertaken 
responsibility to pay any sum or sums 
within   the   guaranteed   limit   upon 
receipt   of   written   demand   from   the 
Company. The operative portion of the 
bank   guarantee   furnished   by   the   Bank 
does not refer to any of the conditions 
for payment under the bank guarantee. 
It   is   true   that   the   bank   guarantee 
furnished   makes   a   reference   to   the 
principal agreement between the parties 
in   its   preamble.   Mere   fact   that   the 
bank guarantee refers to the principal 
agreement in the preamble of the deed 
of   guarantee   does   not   make   the 
guarantee furnished by the Bank to be a 
conditional  one  unless  any  particular 
clause of the agreement has been made 
part of the deed of guarantee.“
It   is   thus   reiterated   that   the   clauses   in 
the   Bank   Guarantee   are   relevant   and   material   for 
determination   as   to   whether   the   Bank   Guarantees 
furnished   are   unconditional,   irrevocable   one   or 
conditional one. On the interpretation of clauses, it 
has to be decided as to whether the Bank Guarantees 
furnished are unconditional or conditional. However, 
.....23/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
23
a word of caution is that the mere fact that the Bank 
Guarantee refers to the principal agreement, does not 
make the Bank Guarantee to be conditional one, unless 
any particular clause of the agreement has been made 
part of the deed of guarantee. 
18) The Division Bench of the Orissa High Court 
has also dealt with the question of conditional Bank 
Guarantee in its judgment in  National Aluminium Co's 
case   cited   supra,   and   the   relevant   portion   of   the 
paras­6, 7,  8 and 11 of the said judgment delivered 
by Hon'ble Shri B.L.Hansaria, C.J., (as he then was) 
are reproduced below­­
Para­6   :   “If   the   bank   guarantee   be 
conditional,   the   same   becomes 
enforceable upon the fulfilment of the 
condition stipulated and in such a case 
the   beneficiary   must   allege   in   the 
demand   that   the   condition   has   been 
fulfilled. The latest decision of the 
Calcutta High Court is the one rendered 
in National  Thermal  Power  Corporation 
Ltd.   vs.   Hind   Galvanizing   and 
Engineering Co. Ltd., AIR 1990 Cal 421, 
in which the Bench has stated that as 
long as the demand of the beneficiary 
is in terms of the bank guarantee, it 
.....24/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
24
is not a defence that under the parent 
contract   the   beneficiary   of   the 
guarantee is not entitled to the amount 
from the bank.“
  : “In Synthetic   Foams  Ltd.  vs 
Para­7
Simplex   concrete   Piles   (India)   Pvt. 
Ltd.,  AIR  1988  Delhi,  207,  a learned 
single   Judge   has   stated   that 
misrepresentation,   suppression   of 
material   facts   and   violation   of   the 
terms of the guarantee can be regarded 
as species of the same genus as fraud 
which would disentitle a beneficiary to 
enforce the bank guarantee. It had been 
earlier   stated   in   M/s.B.L.R.Mohan   v. 
Punjab   State   Co­operative   Supply   & 
Marketing   Federation   Ltd.,   AIR   1982 
Delhi   357,   by   another   learned   single 
Judge  that  the  demand  under  the  bank 
guarantee must be in strict accord with 
the terms of the guarantee.” 
Para­8  : “We may also refer to a recent 
decision of the Punjab & Haryana High 
Court in National Project Construction 
Corporation   Ltd.   v.   M/s.Sadhu   and 
Company, AIR 1990 P & H 300, tht the 
demand under the bank guarantee has to 
be in accordance with the eventualities 
mentioned in the deed of guarantee, and 
it is conclusive as regards the amount 
due and payable by the bank.”
Para­11   :   “But   then,   the   bank 
guarantees at hand cannot be regarded 
as absolutely unconditional inasmuch as 
the   payment   under   guarantees   is 
dependent   upon   the   contractor 
committing default in performing any of 
the   terms   and   conditions   of   the 
contract or in the payment of any money 
.....25/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
25
due to the owner or in case the amount 
at   the   specified   rates   cannot   be 
deducted from the running bills of the 
contractor  by  the  owner  towards    the 
payment of Mobilisation Advance. As to 
the fulfilment of those conditions, we 
would state that the statement of the 
beneficiary would be taken at its face 
value   unless   the   contractor   be   in   a 
position to establish that the stand of 
the beneficiary is actuated by fraud, 
misrepresentation,   deliberate 
suppression   of   material   facts   or   the 
like which would give rise to special 
equities in favour of the contractor. 
So, in the absence of a case of fraud, 
misrepresentation,   deliberate 
suppression   of   material   facts   or   the 
like, to establish which a heavy onus 
lies   on   the   contractor,   a   bank 
guarantee like the one at hand has to 
be   honoured   by   the   bank   and   the 
beneficiary  cannot  be  restrained  from 
enforcement.   Further,   decision   about 
fraud, etc. has to be arrived at by the 
court approached by the contractor to 
restrain the beneficiary from enforcing 
the   bank   guarantee.   The   court   cannot 
await for this purpose the finding of 
the arbitrator.”
It has been held that if the Bank Guarantees 
be   conditional,   the   same   become   enforceable   upon 
fulfillment of the conditions stipulated and in such 
a case, the beneficiary must allege in the demand, 
that   the   conditions   have   been   fulfilled.   The 
.....26/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
26
violation of the terms of guarantee can be regarded 
as   the   species   of   the   same   genus   as   fraud,   which 
disentitles   a   beneficiary   to   enforce   the   Bank 
Guarantees. The demand for Bank Guarantees must be in 
strict accord with the terms of the Bank Guarantees 
and it has to be in accordance with the eventualities 
mentioned in the deed of guarantee.
19) In the context of the aforesaid position of 
law laid down by the Apex Court, Section 126 of the 
Indian   Contract   Act,   1872,     regarding   contract   of 
guarantee   needs   to   be   seen.   The   said   provision   of 
Section 126 is, therefore, reproduced below­­
Section   126 .   'Contract   of   guarantee', 
'surety',   'principal   debtor'   and 
A 'contract of guarantee' 
'creditor'­ “
is a contract to perform the promise, 
or discharge the liability, of a third 
person   in   case   of   his   default.   The 
person   who   gives   the   guarantee   is 
called   the   'surety';   the   person   in 
respect of whose default the guarantee 
is   given   is   called   the   'principal 
debtor',   and   the   person   to   whom   the 
guarantee   is   given   is   called   the 
'creditor'. A guarantee may be either 
oral or written.”
.....27/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
27
A   contract   of   guarantee   is   a   contract   to 
perform the promise or discharge the liability of a 
third person in case of his default. The person who 
gives the guarantee is called 'surety'; the person in 
respect of whose default the guarantee is given is 
called the 'principal debtor', and the person to whom 
the guarantee is given is called the 'creditor'.
20) Section 31 of the Indian Contract Act, 1872, 
defines   the   contingent   contract   and   the   same   is 
reproduced below­­
Chapter III  :  OF CONTINGENT CONTRACTS
“Section   31 .   “Contingent   contract” 
defined.­  A “contingent contract” is a 
contract to do or not to do something, 
if   some   event,   collateral   to   such 
contract, does or does not happen.”
Section 32 of the said Act, deals with the 
enforcement of the contracts contingent on an event 
happening,   and   the   same   is   also   relevant   hence, 
.....28/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
28
reproduced below­­
“Section   32.   Enforcement   of   contracts 
contingent   on   an   event   happening.­­
Contingent contracts to do or not to do 
anything if an uncertain future event 
happens,   cannot   be   enforced   by   law 
unless   and   until   that   event   has 
happened.
If   the   event   becomes 
impossible,   such   contracts   become 
void.”
A   contract   of   guarantee   is   an   independent 
contract between the Bank and the beneficiary thereof 
and if it is a contract, which permits the creditor 
to  invoke   the  Bank   Guarantee   upon   happening   of  an 
uncertain future event, then it becomes a 'contingent 
contract' as defined under Section 31 and it cannot 
be enforced by law unless and until that event has 
happened,  in   view  of   the  provision   of  Section   32. 
Till   happening   of   an   event,   it   merely   remains   a 
contract   which   is   unenforceable.   In   case   of   such 
contingent   contract,   the   beneficiary   has   no 
unfettered right to invoke the Bank Guarantees and to 
demand immediate payment. The terms of such contract 
.....29/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
29
will   have   to   be   strictly   construed   and   if   it 
prescribes the manner in which performance is to be 
claimed, it will have to be seen as to whether the 
performance is claimed, in the manner so prescribed. 
If the invocation is not in accordance with the terms 
and   the   manner   prescribed,   it   would   be   bad.   The 
violation of the terms can be regarded as the species 
of   the   same   genus   as   fraud   which   disentitles   a 
beneficiary to invoke the Bank Guarantees. 
21) In  the light  of the  aforesaid   position  of 
law, it is required to be found out from the terms of 
the Bank Guarantees in question as to whether it is a 
contingent   or   conditional   contract   or   an 
unconditional or irrevocable contract. A Proforma of 
Bank   Guarantee   in   lieu   of   security   deposit   relied 
upon by both the parties in support of their rival 
contentions contained under an Agreement No.08/2007­
2008, is reproduced below­­
On Stamp of Rs.100
.....30/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
30
PROFORMA OF BANK GUARANTEE IN LIEU OF 
SECURITY DEPOSIT.
M/s.Western Coalfields Limited,
Coal Estate, Civil Lines, Nagpur.
Dear Sir,
1.   In   consideration   of   M/s.Western 
Coalfields   Limited,   having   its 
Registered   Office   at   Nagpur 
(hereinafter called “The Company” which 
expression   shall   unless   repugnant   to 
the   subject   or   context   includes   its 
successors   and   assigns)   having   agreed 
under   the   terms   and   conditions 
contained   in   letter   no.......... 
dated   .......   Issued   in   favour   of 
M/s................   for   ........ 
(hereinafter   referred   to   as   'the 
contract'   to   accept   the   Deed   of 
guarantee   as   herein   provided   for 
Rs...... from the Schedule/Nationalized 
Bank (whose branches are scheduled at 
Nagpur) in lieu of security deposit to 
made   by   M/s...............   (here   in 
after   called   “the   Contractor”)   or   in 
lieu of deduction to be made from the 
contractor's   bill   for   due   fulfillment 
of the terms and conditions contained 
in the said contract by the contractor, 
we   the   ...........   Bank   (hereinafter 
referred   to  as   the   said  Bank)   having 
its Registered Office at ......... do 
hereby undertake and agreed to pay the 
company to the extent of Rs........ On 
demand stating that the amount claimed 
by the company is due and payable by 
the   contractor   for   the   reasons   of 
failure/negligence   in   performing   the 
terms and conditions contained in the 
contract   by   the   buyer   and   to 
.....31/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
31
unconditionally pay the amount claimed 
by  the   company   on   demand   without  any 
demur to the extent aforesaid.
1.  We   ..........  Bank   agree   that   the 
company shall be the sole judge as to 
whether   the   said   contractor   has 
failed/neglected   in   performing   any   of 
the  terms   and   conditions   of  the   said 
contract   and   the   decision   of   the 
company in this behalf shall be final 
and binding on us.
2. We the said Bank further agree that 
the   Guarantee   herein   contained   shall 
remain   in   full   force   and   effect 
upto   .......   And   any   claim   received 
after the said date shall in no case 
bind the Bank.
3. The Company shall have the fullest 
liberty   without   affecting   in   any   way 
the  liability   of   the   Bank   under   this 
guarantee   or   indemnity   from   time   to 
time   vary   any   of   the   terms   and 
conditions of the said contract or to 
extend the time of performance by the 
said contractor or to postpone any time 
and from time to time any of the powers 
exercisable   by   it   against   the   said 
contractor and either to enforce or to 
forbear from enforcing nay of the terms 
and   conditions   governing   the   said 
contract or securities available to the 
company and the said Bank shall not be 
released from its liability under these 
presents.
5.   Notwithstanding   anything   contained 
herein the liability of the said Bank 
under this guarantee is restricted to 
Rs..........   and   this   Guarantee   shall 
.....32/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
32
come   into   force  from   the   date   hereof 
and   shall   remain   in   full   force   and 
effect till ........ Unless the written 
demand or claim under this guarantee is 
made   by   the   Company   with   us   on   or 
before........   all   rights   of   the 
company   under   this   guarantee   shall 
cease to have any effect and we shall 
relieved   and   discharged   from   our 
liabilities hereunder. 
5. The said contractor hereby covenants 
with the company that the Company shall 
retain a sum of Rs......... or such sum 
as   may   be   arrived   at   based   on   the 
executed value of the work, as security 
deposit   for   the   fulfillment   of   the 
contract   to   the   satisfaction   of   the 
Company. 
IN WITNESS WHEREOF THE parties herein 
have set their hands and seals the date 
and year above written.
In   consideration   of   the   appellant 
M/s.Western Coalfields Limited, (the company) having 
agreed under the terms and conditions contained in 
the letter dated 18.5.2007 issued in favour of the 
contractor (M/s.Shree Sai Construction Company, the 
respondent   no.1)   the   deed   of   guarantee   has   been 
executed by the Bank (Oriental Bank of Commerce, the 
respondent no.2) for the fulfillment of the terms and 
.....33/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
33
conditions   contained   in   the   contract   by   the 
contractor (the respondent no.1). The preamble of the 
Bank   Guarantee   recites   that   the   Bank   (respondent 
no.2) has undertaken and agreed to pay the Company 
(M/s.Western   Coalfields   Limited),   the   amount 
stipulated   in   each   of   the   two   Bank   Guarantees   on 
demand stating that the amount claimed by it is due 
and   payable   by   the   contractor   for   the   reasons   of 
failure/negligence   in   performing   the   terms   and 
conditions   contained   in   the   contract   by   the 
contractor (respondent no.1) and to unconditionally 
pay the amount claimed by it on demand without any 
demur. 
22) From the contents of the Bank Guarantee it 
is   clear   that   the   contract   is   already   formed 
containing the terms and conditions. Hence, the terms 
of contract are extremely material and the same are 
required   to   be   looked   into.   The   obligation   of   the 
respondent   no.2   Bank   to   make   the   payment   of   the 
amount covered by the Bank Guarantees arises, only on 
.....34/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
34
the demand to be made in writing and this is apparent 
from clause 5 under the Bank Guarantee, which speaks 
about   the   written   demand   or   claim   under   the   Bank 
Guarantee. The demand in writing must state exactly 
the   amount   assessed   as   due   and   payable   by   the 
respondent   no.1   Company   for   the   reason   of 
failure/negligence of the respondent no.1 Company in 
performing   certain   specified   terms   and   conditions 
contained in the contract between the appellant and 
the respondent no.1. If the demand is not in writing 
stating the actual amount which is assessed and found 
to be due and payable for the reason stated in the 
Bank Guarantees, then there is no obligation to make 
payment.     Unless   there   is   a   failure/negligence   in 
performing the terms and conditions of contract, the 
amount   which   becomes   due   and   payable   by   the 
respondent   no.1   cannot   be   assessed   and   claimed. 
Hence, it is a 'contingent contract' as defined under 
Section   31   of   the   Contract   Act   and   it   becomes 
enforceable   only   upon   happening   of   the   event 
specified therein, as per Section 32 of the Contract 
.....35/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
35
Act.  
23) The  question   is  whether,   in  fact  there   is 
such   compliance   of   the   conditions   stipulated   under 
the Bank Guarantees in the present case. Undoubtedly, 
it   is   by   letter   dated   17.2.2011,   that   there   is   a 
demand made by the appellants to the respondent no.2 
Bank   for   payment   of   the   amount   of   Bank   Guarantees 
which has been impugned in the civil suit. The said 
letter   is   relevant   and   the   same   is,   therefore, 
reproduced below­­
Ref No.NGP/WCL/Civil/66­67/1106
Date 17.02.2011
To,
The Branch Manager
The Oriental Bank of Commerce,
“Gold Sukh”, Kasturba Chowk, Shree Ram 
Market, Chandrapur­442 401.
Sub : Encashment of Bank Guarantees.
Ref : A) BG NO.02020002908 dated
      19.02.2008 for Rs.1,54,94,580/­ 
      and 
      B) BG No.02020002808 
      dated 19.02.2008 for
      Rs.69,79,000/­.
.....36/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
36
Dear Sir,
Enclosed   find   herewith   photo 
copies   of   BG   No.0202002808   dated 
19.02.2008   for   Rs.69,79,000/­   and   BG 
No.0202002908   dated   19.02.2008   for 
Rs.1,54,94,580/­   both   valid   upto 
19.11.2011 for encashment.
You   are   hereby   requested   to 
send us an amount of Rs.2,24,73,580/­ 
which is total amount of both the BG's 
duly   encashed   through   Demand   Draft 
drawn   in   favour   of   M/s.Western 
Coalfields Limited payable at Nagpur.
On receipt of DD for the above 
amount,   the   original   Bank   Guarantees 
shall be returned to you.
                   Yours faithfully,
                          Sd/­
                        17.2.11
      General Manager (Civil Incharge
Copy to information to :
1. Director (Tech) P & P
2. Director (Fin)
Perusal of the contents clearly reflect that 
there is no demand in writing  as envisaged by the 
Bank Guarantees in question. What is the exact amount 
i.e. claimed by the appellant, which according to it, 
.....37/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
37
has become due and payable from the respondent no.1, 
has not been stated. In fact, there is no assessment 
of the amount which is said to have become due and 
payable in terms of the Bank Guarantees. It is not 
stated as to whether such amount has become due and 
payable   for   the   reasons   of   failure/negligence   in 
performing any of the specified terms and conditions 
contained in the contract between the appellant and 
the respondent no.1. The cause of action for seeking 
enforcement   of   the   obligation   on   the   part   of   the 
respondent   no.2   Bank   to   make   the   payment   of   the 
amount covered by the Bank Guarantees, has not at all 
been disclosed. The claim for seeking enforcement is 
also not in the manner prescribed under the contract 
of Bank Guarantees. There is nothing to show that the 
events   specified   for   invocation   of   Bank   Guarantees 
have   occurred.   Hence,   the   invocation   is   not   in 
accordance with the terms and conditions prescribed, 
the same is, therefore, bad and unenforceable. It is 
not   a   case   of   mere   reference   to   the   terms   of   the 
contract   entered   between   the   appellant   and   the 
.....38/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
38
respondent,   but   it   is   a   case   where   the   appellant 
Company is required to process its claim by assessing 
the amount due and payable by the respondent no.1 for 
the reason of failure/negligence to perform the terms 
and conditions contained in the contract, which forms 
a   condition   precedent   to   seek   enforcement   of   Bank 
Guarantees.   It   is   not   a   case   of   conferment   of   an 
unfettered right to demand immediate payment upon the 
appellant. 
24) The requirement of unconditional payment of 
the amount of Bank Guarantee without any demur, has 
nothing to do with the compliance of the conditions 
of   Bank   Guarantees   and   it   only   prohibits   the 
respondent no.2 Bank from raising any dispute as to 
compliance or fulfillment of the terms and conditions 
of   the   contract   between   the   appellant   and   the 
respondent   no.1   Company.   The   respondent   no.2   Bank 
cannot insist for proof of failure or negligence of 
respondent no.1 Company in performing the terms and 
conditions contained in the contract. It is in this 
.....39/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
39
background   that   the   Condition   No.1   has   been 
incorporated   in   the   Bank   Guarantees   agreeing,   that 
the appellant Company shall be the sole judge as to 
whether the said contractor has failed/neglected in 
performing   any   of   the   terms   and   conditions   of   the 
said   contract   and   the   decision   of   the   appellant 
Company   in   this   behalf   shall   be   binding   upon   the 
respondent   no.2   Bank.   Hence,   on   the   basis   of 
condition   no.1   in   the   Bank   Guarantee   it   cannot   be 
urged that it is an unconditional Bank Guarantee and 
confers   an   unfettered   right   upon   the   appellant   to 
invoke the Bank Guarantees and to demand immediate 
payment.
25) Shri A.M.Gordey, the learned Senior Counsel 
appearing for the appellant, has invited my attention 
to   the   para­7   of   the   written   statement,   which   is 
reproduced below­­
Para­7) :  The defendants submits that 
the plaintiff only has carried out the 
work to the extent of Rs.595.93 Lakhs 
and   the   work   to   that   extent   of 
.....40/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
40
Rs.799.86   Lakhs   is   still   incomplete 
which   has   to   be   awarded   to   another 
contractor   and   considering   the 
inflation the said cost is assessed at 
Rs.1182.52   Lakhs   approx   and   as   such 
the additional expenditure  is arrived 
at   Rs.382.66   Lakhs   which   is   legally 
recoverable from the plaintiff and as 
such   to   secure   the   amount   from   the 
plaintiff,   the   Bank   Guarantees   are 
invoked.   It   is   worthwhile   to   submit 
that the said figure is tentative and 
is   likely   to   increase   manifold.   The 
defendants   have   also   not   calculated 
the damage that may be caused due to 
the delay in completion of the project 
and   if   all   the   said   assessments   are 
made, the amount recovered is nothing 
but pea­nuts comparing to the size of 
the work awarded to the plaintiff.”
It   is   urged   that   it   is   the   amount   of 
Rs.382.66 Lacks, which has become due and payable by 
the   respondent   no.1   for   the   reason   of 
failure/negligence   in   performing   the   terms   and 
conditions  in the contract.  Prima­facie,  it is not 
possible to accept this argument for several reasons. 
Firstly, this is not the demand in writing reflected 
in   the   letter   dated   17.2.2011   invoking   the   Bank 
Guarantees   which   is   already   reproduced   above. 
.....41/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
41
Secondly, it is an undisputed factual position, that 
the invocation of the Bank Guarantees is not on the 
ground   that   the   respondent   no.1   has   failed   to 
complete 60% of work. On the contrary, specific stand 
is   that   non­completion   of   60%   of   work   is   totally 
irrelevant   for   the   purposes   of   the   controversy 
involved in the case. Thirdly, the finding recorded 
by   the   Trial   Court   about   the   failure   of   the 
appellants to discharge their obligations in respect 
of four items as are specified in para­10 above, has 
not been assailed along with the further finding that 
the appellants and the State Government are unable to 
remove the hindrances so as to enable the respondent 
no.1   to   complete   the   work.   Fourthly,   unless   the 
hindrances are removed by discharging the obligations 
by the appellants and the State Government, it may 
not be possible for any other contractor to complete 
the remaining incomplete work to the extent of 60% of 
work. Fifthly, the contract to complete the balance 
60%   of   work   is   yet   to   be   awarded   to   any   other 
contractor and lastly the amounts so assessed, is not 
.....42/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
42
for the reason of the alleged failure/negligence on 
the   part   of   the   respondent   no.1   in   performing   the 
terms and conditions of the contract. 
26) Shri A.M.Gordey, the learned Senior Counsel 
appearing for the appellants and Shri J.P.Pendse, the 
learned   Counsel   for   the   respondents   have   taken   me 
through the judgments relied upon by Shri A.M.Gordey, 
the   learned   Senior   Counsel,   which   are   listed   in 
earlier paras and delivered by the Apex Court and by 
this Court. In all these judgments, the finding is 
recorded  that the Bank Guarantees  in question  were 
unconditional and in the light of such proof of fact, 
that the Apex Court has laid down the principles for 
grant of injunction in the matter of invocation of 
the Bank Guarantees, which are contained in para­14 
of   the   decision   in   the   case   of   Himadri   Chemicals 
Industries Limited Vs. Coal Tar Refining Co., (2007) 
8 SCC 110,  which is reproduced below­­
“Para­14  :   From   the   discussions   made 
hereinabove relating to the principles 
.....43/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
43
for   grant   or   refusal   to   grant   of 
injunction to restrain enforcement of a 
bank guarantee or a letter of credit, 
we find that the following principles 
should   be   noted   in   the   matter   of 
injunction  to  restrain  the  encashment 
of   a   bank   guarantee   or   a   letter   of 
credit:
(i) While dealing with an application 
for   injunction   in   the   course   of 
commercial   dealings,   and   when   an 
unconditional bank guarantee or letter 
of   credit   is   given   or   accepted,   the 
beneficiary is entitled to realise such 
a bank guarantee or a letter of credit 
in   terms   thereof   irrespective   of   any 
pending disputes relating to the terms 
of the contract.
(ii) The bank giving such guarantee is 
bound   to   honour   it   as   per   its   terms 
irrespective of any dispute raised by 
its customer.
(iii)   The   courts   should   be   slow   in 
granting   an   order   of   injunction   to 
restrain   the   realisation   of   a   bank 
guarantee or a letter of credit.
(iv) Since a bank guarantee or a letter 
of   credit   is   an   independent   and   a 
separate   contract   and   is   absolute   in 
nature,   the   existence   of   any   dispute 
between the parties to the contract is 
not a ground for issuing an order of 
injunction  to  restrain  enforcement  of 
bank guarantees or letters of credit.
(v) Fraud of an egregious nature which 
would   vitiate   the   very   foundation   of 
such   a   bank   guarantee   or   letter   of 
.....44/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
44
credit   and   the   beneficiary   seeks   to 
take advantage of the situation.
(vi)   Allowing   encashment   of   an 
unconditional   bank   guarantee   or   a 
letter   of   credit   would   result   in 
irretrievable harm or injustice to one 
of the parties concerned.”
There   cannot   be   any   dispute   about   the 
proposition of law laid down by the Apex Court in the 
aforesaid   judgment,   which   follows   several   earlier 
judgments of the Apex Court. The law of precedents is 
well settled. A decision is an authority for what it 
actually decides and not for what logically follows 
from it. Every judgment must be read as applicable to 
the   particular   of   facts   proved   or   assumed   to   be 
proved  and   the   exposition   of   law  therein, 
is governed or qualified or controlled by the facts, 
which are held to be proved. The judgment is required 
to be understood in the light of the facts of that 
case and no more can be read into it, then what it 
actually says. Once it is held in the facts of the 
present case that it is a contingent contract of Bank 
Guarantees, then the law down by the Apex Court in 
.....45/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
45
the   judgments   relied   upon   by  Shri   A.M.Gordey,   the 
learned Senior Counsel, ceases to apply. 
27) The     contention   of   Shri   A.M.Gordey,   the 
learned Senior Counsel, is that the respondent no.1 
is not competent to make any grievance about the non­
fulfillment of the terms of the Bank Guarantees for 
the reason that he is not a party to the contracts of 
Bank   Guarantees.   According   to   him,   it   is   only   the 
respondent no.2 Bank which can make a grievance about 
non­fulfillment of the terms of the Bank Guarantees. 
He   submits   that   the   respondent   no.1   is   neither   a 
person aggrieved nor has any  locus standi  to complain 
about   the   violation   of   the   terms   of   the   Bank 
Guarantees.   The   contention   cannot   be   accepted.   The 
respondent  no.1  is the principal  debtor  within  the 
meaning of Section 126 of the Contract Act. It is at 
his   instance   that   the   conditional   Bank   Guarantees 
have been furnished by the respondent no.2 Bank in 
favour of the appellant creditor. It is the liability 
of the respondent no.1 which is being discharged by 
.....46/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
46
the respondent no.2 Bank. Hence, the respondent no.1 
has   right   to   know   and   complain   about   the   non­
fulfillment of the conditions of the Bank Guarantees. 
Merely   because   the   respondent   no.2   Bank   has   not 
raised   any   objection   about   non­fulfillment   of   the 
terms of the Bank Guarantees, that will not prevent 
the   respondent   no.1   from   raising   any   objection   in 
respect of it. Ultimately, the respondent no.2 would 
obviously recover the amount that shall be paid to 
the appellant, from the respondent no.1. Hence, the 
respondent   no.1   is   competent   and   has   locus   to 
challenge  the invocation  of the Bank  Guarantees  by 
the appellants.
28) Now,   coming   to   the   contention   of   Shri 
A.M.Gordey, the learned Senior Counsel, that there is 
failure   to   comply   with   the   conditions   regarding 
submission   of   valid   Bank   Guarantees   of   a 
Nationalized/Scheduled   Bank   by   way   of 
performance/additional   performance   security,   it   is 
not in dispute that the respondent no.1 has submitted 
.....47/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
47
two fake Bank Guarantees of non existent Bank namely 
M/s.Mahesh   Merchant   Bank   Limited,   Chandrapur,   on 
10.10.2007.   The   first   Bank   Guarantee   of 
Rs.69,79,000/­     was   by   way   of   security   for 
performance   of   contract   towards   5%   of   value   of 
awarded   contract   and   the   another   was   for 
Rs.1,54,94,580/­   towards   additional   performance 
security deposit and retention money to be recovered 
from the running bills.  Undisputedly, these two Bank 
Guarantees  have  been  substituted  by two fresh  Bank 
Guarantees of the same amount on 19.2.2009 issued by 
the   respondent   no.2   Oriental   Bank   of   Commerce,   a 
Nationalized Bank, which are valid upto 19.11.2011.
29) The claim of the respondent no.1 plaintiff 
is   that   his   Power   of   Attorney   obtained   fake   Bank 
Guarantees and submitted it to the appellant and as 
soon as it was discovered, the respondent no.1 on his 
own submitted fresh Bank Guarantees dated 19.2.2009 
of the Nationalized Bank. The case of the appellant 
is   that   the   fact   of   submission   of   fake   Bank 
.....48/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
48
Guarantees was discovered by the appellant. Keeping 
aside such dispute at this stage, the fact remains 
that   the   appellant   has   accepted   the   submission   of 
fresh Bank Guarantees, which are valid and operating 
till   19.11.2011   and   the   penal   interest   of 
Rs.16,85,220/­   @     18   %     per     annum   on   the   total 
amount   of   Bank   Guarantees   of   Rs.2,24,73,580/­   has 
been   recovered   from   the   respondent   no.1   for   the 
period five months from 10.10.2007 to 19.2.2008. The 
termination of contract is by letter dated 16.9.2010 
for the reason of furnishing fake Bank Guarantees of 
the non existent Bank by the respondent no.1. Though 
the   discovery   about   the   submission   of   fake   Bank 
Guarantees was on 19.2.2009 or may even be prior to 
that, the termination is after lapse of 17 months. 
The Bank Guarantees have not been invoked at the time 
of termination of contract on 16.9.2010, but it is 
after   a   lapse   of   five   months   on   17.2.2011.   Thus, 
prima­facie it is a case of forgiveness and recovery 
resulting  into condonation  of the violation  of the 
said term under  the  contract  without  resulting  any 
.....49/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
49
financial loss or implications to the appellant.
30) The Trial Court has prima­facie accepted the 
case of the respondent no.1 plaintiff that the act of 
submitting fake Bank Guarantees was done by the Power 
of   Attorney   holder   and   as   soon   as   it   came   to   the 
notice   of   the   respondent   no.1,   he   voluntarily 
replaced   the   same   with   valid   Bank   Guarantees   of   a 
Nationalized   Bank   i.e.   the   respondent   no.2.   The 
finding is recorded that the extension of the period 
of such Bank Guarantees   has also been accepted by 
the appellant and at this stage, it cannot be said 
that   the   fake   Bank   Guarantees   were   furnished   only 
with a view to obtain the work. The Trial Court has 
held   that   the   appellants   have   covered   the   penal 
interest   on   account   of   the   submission   of   the   Bank 
Guarantees   for   a   period   of   five   months   and   the 
criminal investigation pending against the respondent 
no.1 will take its own course. No fault can be found 
with such a view taken by the Trial Court.
.....50/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
50
31) The entire conduct of the appellant and the 
conspectus of facts depict that the invocation of the 
Bank Guarantees is, prima­facie not for the purpose 
or the reason stated in the Bank Guarantees, but is 
for some extraneous reasons, may be to cover up the 
lapses   on   the   part   of   the   appellant   in   performing 
their obligations. The contention of Shri J.P.Pendse, 
the learned Counsel for the respondent no.1,   that 
the invocation of the Bank Guarantees could have been 
only   during   the   subsistence   of   contract   or   at   the 
most   while   terminating   the   contract   on   16.9.2010, 
sounds correct. Undisputedly, the invocation of the 
Bank Guarantees is after lapse of five months from 
the date of termination of contract. Prima­facie in 
my view, the invocation of the Bank Guarantees much 
after   the   date   of   termination   of   contract,   is   an 
after thought and not bonafide.  The Trial Court has 
recorded the finding that there is no fault on the 
part of the appellant, in delay caused in completion 
of the work and it is the appellants/defendant nos.1 
.....51/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
51
and 2 and the State Government, who were unable to 
remove   the   hindrances   as   a   result   of   which   the 
respondent no.1/plaintiff could not execute the work. 
The Trial Court has held that in such a situation, 
there is no question of recovery of any damages from 
the   security   deposit   in   respect   of   which   the   Bank 
Guarantees have been furnished and refusal to grant 
an  injunction  would  result  in  frustrating  the 
claim   of     the     respondent   no.1/plaintiff.   In 
the  background  of  the  facts  of  this  case,  I 
do  not  find any fault with such a finding recorded 
by the Trial Court.
32) Once it is held that the Bank Guarantees are 
conditional or contingent and enforceable only upon 
happening   of   certain   events   and   that   those   events 
have   not   yet   happened,   the   Division   Bench   of   the 
Orissa   High   Court   in   its   judgment   in  National 
Aluminium Co's  case cited supra, has held that the 
violation   of   the   terms   of   the   guarantee   can   be 
regarded as species of the same genus as fraud, which 
.....52/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
52
disentitles   a   beneficiary   to   enforce   the   Bank 
Guarantees. Once it is held that the invocation of 
the Bank Guarantees is not for the purposes or the 
reasons mentioned in the Bank Guarantees, the refusal 
to   grant   an   injunction   would   result   in   causing   an 
irretrievable   injury   to   the   respondent   no.1   as   he 
would be deprived of huge amount of Bank Guarantees 
for   the   purposes   of   his   business.   Prima­facie,   it 
would   amount   to   an   unjust   enrichment   of   the 
appellants/defendant nos.1 and 2. Hence, no fault can 
be found with the order of injunction passed by the 
Trial Court. However, it will be with a rider that 
one month before the expiry of the validity period of 
both the Bank Guarantees, the respondent no.1 shall 
produce   renewal   of   validity   period   of   Bank 
Guarantees, during the pendency of the suit. If such 
renewal is not produced before the Trial Court, prior 
to   the   period   of   30   days   of   the   expiry   of   the 
validity period, the order of injunction granted by 
the Trial Court and confirmed by this Court, shall 
stand   automatically   vacated   without   further   orders 
.....53/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
53
from Court and any payment, if any, made by the Bank 
to   the   appellants/defendant   nos.1   and   2   shall   be 
subject   to   the   decision   in   the   suit.   In   such 
eventuality if the ultimate decision in the suit goes 
in   favour   of   the   respondent   no.1/plaintiff,   then 
there shall be an order of refund with interest @ 6% 
per annum from the date of receipt of payment by the 
appellants/defendant nos.1 and 2.
O R D E R
For   the   reasons stated above, the appeal 
is   partly   allowed.   The   order   of   injunction 
passed  on  21.2.2011  and  confirmed on 5.4.2011, by 
the Third Joint Civil Judge, Senior Division, Nagpur, 
in Special Civil Suit No.236 of 2011 is maintained 
subject to the condition that during the pendency of 
the civil suit, the   respondent   no.1   shall renew 
the   Bank   Guarantees   in question, 30 days before 
the expiry of its validity period  and  failure  to 
produce,     the     extension/renewal     of     validity 
period   shall   result   in   automatically   vacating 
the  order  of  injunction  passed  by  the  Trial 
.....54/­
::: Downloaded on - 02/06/2024 03:03:29 :::

0609ao85.11.odt
54
Court,  without  reference  to  the Court. No order 
as to costs.
                 JUDGE
BrWankhede
...../­
::: Downloaded on - 02/06/2024 03:03:29 :::