Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
STATE OF U.P. & ORS
Vs.
RESPONDENT:
BRIDGE & ROOF CO. (INDIA) LTD.
DATE OF JUDGMENT: 20/08/1996
BENCH:
B.P.JEEVAN REDDY, K.S. PARIPOORNAN
ACT:
HEADNOTE:
JUDGMENT:
THE 20TH DAY OF AUGUST, 1996
Present:
Hon’ble Mr.Justice B.P. Jeeven Reddy
Hon’ble Mr.Justice K.S.Paripoornan
Rakesh Dwivedi, Additional Advocate General for the State of
U.P., R.B.Misra, Sudhanshu and Kamlendra Mishra, Advs. for
the appellants.
A.K.Ganguli, Sr.Adv., Sudhir Chandra, Arvind Varma and
Ms.Suruchi Aggarwal, Advs. with him for the Respondent
J U D G M E N T
The following Judgment of the Court was delivered:
STATE OF U.P. & ORS.
V.
BRIDGE & ROOF COMPANY (INDIA) LIMITED
J U D G M E N T
B.P.JEEVAN REDDY.J,
Leave granted.
This Appeal is directed against the judgment of a
Division Bench of the Allahabad High Court disposing of he
writ petition filed by the respondent with certain
directions. The arguments before us ranged far and wide and
several questions have been raised though none of them are
reflected in the judgment under appeal. It is averred that
all these contentions were indeed urged before the High
Court. Be that as it may, having regard to the importance of
the questions raised herein, which is said to be arising in
that Court frequently, it has become necessary to refer to
the contentions urged.
The respondent - Bridge & Roof Company (India) Limited
- is a public sector corporation. It entered into a works
contract with the Government of Uttar Pradesh for
rehabilitation and improvement of a certain stretch of road
in Uttar Pradesh. The tender notice was issued on September
1, 1990. The date of opening the tenders was specified as
December 17, 1990. The tenders were opened and the
respondent’s tender was accepted on May 1, 1991. The work
has since been completed. The dispute is only about certain
payments which the respondent claims are due to it whereas
the appellant Government of Uttar Pradesh - says that it is
entitled t? retain.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
According to the terms of the contract, the rates
quoted by the contractor were deemed to be inclusive of the
sales tax, if any, on the constructional plant, material and
supplies required for the purposes of the contract. The
relevant clause Sub-clause (4-a) of Clause ?8 of the
Contract, quoted at Pages 25 and 26 of the Paper-book]
stated in the; alia that "4(a): Nothing in the contract
shall relieve the contractor from the responsibility to pay
any Trade Tax that may be levied under the U.P. Trade Tax
Act, 1948 as amended from time to time in performance of
this contract; During pursuance of the contract the engineer
in charge or any other person responsible for making payment
to the contractor shall, at the time of making the payment
to the contractor either in cash or in say other manner,
deduct an amount equal to the amount specified in section 8-
D of the aforesaid Act as in force, for the. time being to
wards part, or as the case may be, full satisfaction of the
tax payable under the said Act on account of the contract;
the amount presently specified in the said section is 4%
(four per cent) of the amount payable to the contractor."
Another clause [sub-clause (2) of Clause 78 quoted at page
24 of the Paperbook] stated that "(2) The tendered amount by
the contractor shall include, all excise duties, custom
duties, import duties, sales tax, and other taxes that may
be levied according to the laws said regulations for the
time being in force as on the date 30 days prior to the
closing date for submission of bids in the Employer’s
country on the constructional plants, materials and
supplies(both permanent, temporary and consumable) acquired
for the purpose of the contract.Nothing in the contract
shall relieve the contractor his responsibilities to pay any
tax that may be levied in the Employer’s country on profits
made by him in respect of the contract."Clause 70 of the
contract provided for process adjustment.It would be
sufficient if we notice sub-clause (4)of said clause (quoted
at Page 47 of the Paperbook)- It reads:(4) If ,after the
date thirty day priors to the date of Opening Of tenders for
the work, there in India,changes to any National or state
state ordinance Decree or their Law or any regulation or bye
law of any local or other duly constituted authority or the
introduction of any such state other than under subclause
(1a),(2) and (3)of this clause, in the executing of the
works such additional or reduced cost shall be certified by
the Engineer after examining the records provided by the
claimant and shall be paid by or credited to the employer
and the contract process adjusted accordingly.
notwithstanding the foreign input, such additional or
reduced cost shall not be separately paid or credited of the
same shall already have been taken into an accounted in the
indexing of any input to the price adjustment Formula in
accordance with sub-clause (1),(2) and (3) of this clause."
Section 3 of the U.P.Sales Tax Act,1948 [the
Act]creates the liability to tax at the specified rates on
the turn-over of sales of Purchases, of both,of every
dealer.Section 3-F introduced by U.P.Act 25 of 1985 pursuant
to the constitution 46th Amendement Act provides for rate of
tax on the goods used or involved in the execution of a
works contract.It reads:
"[3-F Rate of tax on the right
to use any goods or goods involved
in the execution of a works
contract--Notwithstanding anything
contained in Section 3-A, or
Section 3-AAA, or Section 3-D,
15a.[Words "or Section 3-G",
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
omitted by U.P.Act 28 of 1991,
S.6(w.e.f. 19.2.1991) and deemed to
have been omitted (w.e.f.
13.9.1985).] the turnover relating
to the business of transfer of the
right to use any goods for any
purpose or of transfer the property
in the goods [whether as goods or
in some other form]15b involved in
the execution of a works contract
shall be determined in the manner
prescribed and shall be liable to
tax at such rate, not exceeding
fifteen per cent, as the State
Government may, by notification,
declare, and different rates may be
declared for different goods or
different classes of dealers ]"
Section 7-D provides for composition of tax liability.
Subject to the directions issued by the State Government,
the Commissioner of Sales Tax is empowered to agree to
accept a lumpsum in lieu of the amount of tax payable by the
dealer under the Act. It reads:
"[7-D Composition of tax
liability. Notwithstanding anything
contained in other provisions of
this Act, but subject to such
directions as the State Government
may from time to time issue in that
behalf, the Commissioner of
SalesTax may agree to accept a lump
sum in lieu of the amount of tax
that may be payable by a dealer in
respect of each goods or class of
goods and for such period as may be
agreed upon:
Provided that any change in
the rate of tax which may come into
force after the date of such
agreement shall have the effect of
making a proportionate change in
the lump sum agreed upon in
relation to that part of the period
of agreement during which the
changed rate remains in force.]"
Section 8-D provides for deduction of tax from the
amount payable to works contractors. Sub-section (1)
provides that every person responsible for making payment to
any dealer/contractor shall deduct, at the time of making
payment to the contractor, a sum equal to 4% of the sum
mentioned therein. The Proviso to sub-section (1) inserted
by U.P. Amendment Act 28 of 1991, with effect from February
19 1991, empowers the Commissioner to direct that the
deduction provided by sub-section (1) shall be made at Such
lesser rate as may be specified in the order made by him or
that no such deduction shall be made. Section 8-D further
provides that the amount so deducted shall be remitted to
the Government and shall be treated as tax paid by the
contractor/dealer. Any failure to deduct the amount as
provided by sub-section (1) makes the person [responsible
for deducting] liable to pay the said amount. He is also
liable to pay such penalties as may be imposed for his
failure to deduct and/or remit. It would be appropriate to
read sub-section (1) of Section 8-D alongwith its proviso.
"[8-D, Tax deduction from the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
amount payable to works contractor
-(1) Notwithstanding anything
contained in sub-section (2) of
Section 8-A, every person
responsible for making payment to
any dealer (hereinafter in this
Section referred to as the
contractor) for discharge of any
liability on account of valuable
consideration payable for the
transfer of property in goods
(whether as goods or in any other
form) in pursuance of a works
contract, not being a building
contract of such class or value as
may be notified by the State
Government in public interest in
this behalf, shall, at the time of
making such payment to the
contractor, either in cash or in
any other manner, deduct an amount
equal to four per centum of such
sum towards part or as the case may
be, full satisfaction of the tax
payable under this Act on account
of such works contract:
Provided that the Commissioner
of Sales Tax may, if satisfied that
it is expedient in the public
interest so to do and for reasons
to be recorded in writings order
that in any case or class of cases
no such deduction shall be made or,
as the case may be, such deduction
shall be made at a lesser rate."
It is stated before us that pursuant to Section 7-D of
the Act the Government devised a composition scheme on April
5, 1991. It was amended late on November 20, 1991 .
The respondent appears to have applied to the
Commissioner of Sales Tax, U.P. for composition of his tax
liability under the said contract and for reducing the rate
of deduction of tax at source. This application was made in
terms of section 7-D and the Proviso to Section 8-D (1).
Upon this application, it is averred, an order of
composition was passed. What is relevant is that the Deputy
Commissioner (in exercise of the powers delegated to him by
the Commissioner) ordered [vide his order dated May 27,
1992] that "at the time of payment of balance amount from
the above contract price, the sales tax should be deducted
at the rate of one per cent". A copy of this order was also
communicated to the concerned Superintending Engineer of the
P.W.D. It is admitted case of both the parties that the
composition scheme devised by the Government on 5.4.91 [as
amended on 20.11.91] is valid and effective only till and
inclusive of 31st March, 1995 but not thereafter.
In September 1995, the respondent filed C.M.W.P.C 9
No.24837 of 1995 in the Allahabad High Court with the
following prayer:
"(a) to issue a writ in the nature
of Mandamus commanding the
respondent No.2 (Superintending
Engineer) restraining them from
deducting a sum of Rs.82,24,969/-
from the Bill No.44-RA Bill dated
20.5.95/31.7.95 (Annexure-4) of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
petitioner company."
After setting out the relevant facts, the respondent
contended in the said writ petition that the proposed
deduction of the sum of Rs.82,24,969/- from the petitioner’s
bills, purporting to act under Clause 70(4) of the contract
is misconceived and untenable because the rate of sales tax
has not been reduced in the present case as contemplated by
Clause 70(4) but that only the rate of deduction at source
has been reduced. The respondent’s case was that the change
in the rate of deduction at source or the composition of the
respondent’s liability to pay tax under Section 7-D is of no
concern to the Government. The Government must deduct only
one per cent upto 31.3.1995 as directed in the order dated
May 27,-1992 and leave the rest to the respondent and the
Sales Tax authorities. The respondents in the writ petition
(appellants herein) filed a counter disputing the several -
contentions raised in the writ petition and justifying the
retention of the sum of Rs.82,24,969/-. According to
appellants,the said amount need not be paid to the sales Tax
Department also. By virtue of the composition agreement
between the respondent and the sales Tax department under
section7-D,read with the order of the Deputy Commissioner
under the proviso to section 8-D (1),the tax liability of
the respondent has been reduced with respect to the works
contract between them,within the meaning of clause 70(4) of
the contract and, therefore,they submitted, the benefit of
said reduction should go to the Government as provided by
the contract.
The High court did not deal with the several
contentions aforesaid. It disposed of the writ petition
observing that inasmuch as "the commissioner in his order
has accepted the paper for composition as requested by the
petitioner and has directed the deduction of one in lieu of
four per cent, (and) only that amount is to be deducted from
the amount required to be paid to the petitioner under the
bill in question and the same will cover the period upto
31st March,1995 and not thereafter and the payment under the
bill shall be made accordingly." The High court then
observed that inasmuch as the order of the commissioner
under the Proviso to section 8-D (1) has not been challenged
by the Government, the writ petition is liable to be
disposed of with the direction aforesaid,viz.,that the
Government shall deduct only one per cent of the bill in
question upto 31st March, 1995.
Mr. Rakesh Dwivedi ,learned Additional Advocate General
for the State of U.P.,urged the following contentions:-
(1) Under the terms of the contract the tendered amount
quoted by the respondent included sales Tax at 4%. The
Government was under a statutory obligation to deduct this 4
per cent and remit the same to the sales Tax Department.The
contractor was entitled only to the remaining 96 per cent of
the contact amount since the rate of tax payable by the
respondent-contractor has been reduced to one per cent from
4 per cent under an order of composition passed under
section 7-D, it is a situation attracting sub-clause (4) of
clause 70 of the contract.According to it the benefit of any
reduction in the rate of sales tax shall operate to the
benefit of the Government just as any enhancement in the
rate of sales tax would be a liability upon the Government.
The Government was,therefore, justified in retaining the
said amount of Rs.82,24,969/-.
(2) The direction of the high court to deduct only one per
cent is a case of stating the obvious.But that order is
being construed by the respondent an order allowing the writ
petition as prayed for. If so understood, the order of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
High court results in unjust enrichment of the respondent at
the cost of public exchequer besides being contrary to the
provisions of the statute and terms of the contract between
the parties.
Shri A.K.Ganguli and Mr.Sudhir Chandra,learned
advocates of the respondent, on the other hand,submitted
that the Government is nit concerned with the sales tax
liability of the respondent.That is a matter between the
respondent and the sales tax Department.The obligation of
the Government under the contract was only to deduct 4 per
cent from the amount payable to the respondent under the
contract.But since the said obligation to deduct has been
reduced from 4 per cent to one per cent by an order made
under the proviso to section 8-D (1) the Government should
deduct only at the rate of one per cent and pay over the
balance of the contract amount rest to the respondent.The
Government is not concerned with the order of composition
made under section 7-D (1).What all has happened under the
composition order is that instead of ascertaining the value
of the goods transferred in the execution of the work
contract.Counsel say that this has been done in the interest
of simplication of assessment procedure and as a measure of
government policy. This does not result in reduction in the
rate of tax; it is only a convenient and simplified formula
for quantifying the tax.Hence,they submit,thereis no
question of the Government getting the benefit of any
reduction in the rate of tax.
In our opinion,the very remedy adopted by the
respondent is misconceived. It is not entitled to any relief
in these proceedings,i.e,in the writ petition filed by
it.The High court appears to be right in not pronouncing
upon any of the several contentions raised in the writ
petition by both the parties and in merely reiteration the
effect of the order of the Deputy commissioner made under
the proviso to section 8-D (1).
Firstly, the contract between the parties is a contract
in the realm of private law. It is governed by the
provisions of the contract Act or may be,also by certain
provisions of the sale of Goods Act.Any dispute relating to
interpretation of the terms and conditions of such a
contract cannot be agitated, and could not have been
agitated,in a writ petition. That is a matter either for
arbitration as provided by the contract of for Civil court
as the case may be. whether any amount is due to the
respondent from the appellant-Government under the contract
and,if so,how much and the further question whether
retention or refusal to pay any amount by the Government is
justified, or not are all matters which cannot be agitated
in or adjudicated upon in a writ petition. The prayer in the
writ petition,viz.,to restrain the Government from deducting
particular amount from the writ petitioner’s bill(s) was not
a prayer which could be granted by the High court under
Article 226.Indeed, the High Court has not granted the said
prayer.
Secondly, whether there has been a reduction in the
statutory liability on account of a change in law within the
meaning of sub-clause (4) of clause 70 of the contract is
again not a matter to be agitated in the writ petition. That
is again a matter relating to interpretition of a term of
the contract and should be agitated before the arbitrator in
the civil court,as the case maybe. If any amount is wrongly
wrongly withheld by the Government,the remedy of the
respondent is to raise a dispute as provided by the contract
or to approach the civil court, as the case may be according
to law. Similarly if the Government says that any over-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
payment has been made to the respondent, its remedy also is
the same.
Accordingly, it must be held that the writ petition
filed by the respondent for the issuance of a writ on
Mandamus restraining the Government from deducting or
withholding a particular sum, which according to the
respondent is payable to it under the contract, was wholly
misconceived and was not maintainable in law [See the
decision of this Court in Assistant Excise Commissioner
v.Isaac Peter (1994 (4) S.C.C.104), where the law on the
subject has been discussed fully.] The writ petition ought
to have been dismissed on this ground alone.
We must mention in this behalf that the order of
composition of tax liability, if any, under Section 7-D of
the Act has not been placed before us. [We presume that it
is an order separate from the order dated May 27 1992. But,
even if it is not, it makes no difference to what we were
saying hereafter.] Whether such composition agreement
results in reduction of tax liability within the meaning of
Clause 70(4) of the Contract is again a matter concerning
the interpretation of a term of the Contract. Accordingly,
the question to whom the benefit of reduction in tax should
go’ is not a matter for a writ petition, for the very same
reasons as are mentioned hereinbefore. Now coming to the
order made by the Deputy Commissioner under the proviso to
Section 8-D (1) cf the Act, all that it says is that the
Government shall deduct tax at source only at the rate of
one per cent instead of at the rate of 4 per cent. The said
order-, having been made under the statute, relieves the
government of its obligation to deduct at source at the rate
of 4 per cent. In other words, by virtue of the said order,
no action can be taken against the government [Appellants]
for not deducting at the rate of 4 per cent under Section 8-
D. Learned counsel for the respondent contend that the order
under the proviso to Section 8-D(1) does not determine the
tax liability of the respondent, which liability, they say,
will be determined only in the assessment proceedings. May
be they are right or may be, not. We need not express any
opinion on these submissions because, as already pointed out
hereinabove, the said question depends upon the
interpretation of the terms of the contract between the
parties. Just because the interpretation of orders made
under Section 7-D or Section 8-D(1) may also fall for
consideration while construing the terms of the contract
does not convert the controversy into a public law issue. It
is yet a matter within the realm of private law and,
therefore, outside the purview of the writ petition. The
Arbitrator under the contract or the civil court, as the
case may be - can go into and decide both questions of fact
as well as questions of law.
There is yet another substantial reason for not
entertaining the writ petition. The contract in question
contains a clause providing inter a1ia for settlement of
disputes by reference to arbitration [Clause 67 of the
Contract]. The Arbitrators can decide both questions of fact
as well as questions of law. When the contract itself
provides for a mode of settlement of disputes arising from
the contract, there is no reason why the parties should not
follow and adopt that remedy and invoke the extra-ordinary
jurisdiction of the High Court under Article 226. Tree
existence of an effective alternative remedy - in this case,
provided in the contract itself - is a good ground for the
court to decline to exercise its extra-ordinary jurisdiction
under Article 226. The said Article wag not meant to
supplant the existing remedies at law but only to supplement
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
them in certain well-recognised situations. As pointed out
above, the prayer for issuance of a writ of mandamus wastes
wholly misconceived in this case since the respondent was
not seeking to enforce any statutory right of theirs nor was
it seeking to enforce any statutory obligation cast upon the
appellants. Indeed, the very resort to Article 226 - whether
for issuance of mandamus or any other writ, order or
direction - was misconceived for the reasons mentioned
supra.
So far as the High Court’s direction to deduct at the
rate of one percent is concerned, it may be case of stating
the obvious, as contended by the appellants. But it must
also be realised that more than that could not have been
legitimately granted in a writ petition. It must also be
noticed that the declaration granted is effective only for a
limited period, i.e., March 31, 1995. It does not apply to
payments made on or after April 1, 1995, What does it mean
in the facts and circumstances of the case, we do not know.
Whatever it means, it cannot certainly be construed as a
direction to the appellants to pay over the said sum of
Rs.82,24,969/- to the respondent as claimed by it or as
upholding the basis of the respondent’s claim put forward in
the writ petition.
Before parting with this appeal, we must mention that
counsel for both the parties have urged several other
contentions of fact and law and relied upon several other
clauses of the Contract apart from those mentioned supra. We
have not set them out herein because, in our opinion, they
are outside the ken of a writ petition. It shall be open to
the parties to urge and rely upon them at the proper stage
and before the appropriate forum.
For the reasons mentioned hereinabove, the appeal is
dismissed subject to the observations and clarifications
aforementioned. It shall be open to he respondent, if it so
chooses, to either raise a dispute and ask for reference of
the dispute to arbitration as provide by the contract or to
approcah the civil court according to law, as the case may
be,in the circumstances of the case there shall be no order
as to costs.