Full Judgment Text
REPORTABLE
2023 INSC 931
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO…………………/2023
[ARISING OUT OF SLP (CIVIL) NO. 8791/2020]
M/S UNIBROS …APPELLANT
VS.
ALL INDIA RADIO …RESPONDENT
J U D G M E N T
DIPANKAR DATTA, J.
1. Leave granted.
2. This appeal, at the instance of M/s Unibros (“appellant”, hereafter),
th
registers a challenge to the judgment and order dated 9 December, 2019
in FAO (OS) 229/2010 passed by the High Court of Delhi (“High Court”,
hereafter) dismissing an appeal carried by the appellant under section 37
of the Arbitration and Conciliation Act, 1996 (“the Act”, hereafter). Vide the
impugned judgment, a Division Bench affirmed the judgment and order of
th
a learned Single Judge dated 25 February, 2010 whereby an objection of
the All India Radio (“respondent”, hereafter) under section 34 of the Act
th
was allowed resulting in setting aside of an arbitral Award dated 15 July,
2002 to the extent it awarded loss of profit to the appellant.
Signature Not Verified
Digitally signed by
NEETA SAPRA
Date: 2023.10.19
16:05:01 IST
Reason:
3. The relevant facts, discerned from the records, reveal that the
appellant was awarded a work contract by the respondent to carry out
Page 1 of 17
construction of Delhi Doordarshan Bhawan, Mandi House, Phase-II, New
th
Delhi. The work was scheduled to commence on 12 April, 1990 and reach
th
completion on 11 April, 1991; however, it suffered a delay of roughly 42½
th
months and was finally completed on 30 October, 1994. Disputes and
differences emerged between the parties owing to such delay, which were
subsequently referred to an Arbitrator (“Arbitrator”, hereafter) for
resolution.
4. The trajectory of the case, leading to the present stage, is set out
hereunder:
a) Arbitration proceedings having been initiated, the Arbitrator vide
th
award dated 11 February, 1999 (“First Award”, hereafter)
decided various claims and counter-claims filed by the parties.
Claim Nos. 10, 11, and 12 were collectively addressed under
section 73 of the Indian Contract Act, 1872 (“Contract Act”), as
they all centred around the issue of delay and the resultant losses.
Vide Claim No. 10, the appellant claimed a sum of Rs.
50,00,000.00 (Rupees fifty lakh) owing to the marked escalation
in prices/rates for the work executed beyond the stipulated
contract period. Vide Claim No. 11, the appellant implored the
Arbitrator to award Rs. 41,00,000.00 (Rupees forty-one lakh) to
cover substantial expenses associated with the establishment,
machinery, centring/shuttering, and other vital aspects of the
project. Additionally, vide Claim No. 12, the appellant urged that
a compensation of Rs. 2,00,00,000.00 (Rupees two crore) be
Page 2 of 17
granted as redress for the loss of profit endured due to the
appellant’s protracted retention on the contract without any
corresponding increase in monetary benefits earned. Despite the
Arbitrator's rejection of Claim Nos. 10 and 11, the appellant was
awarded a sum of Rs. 1,44,83,830 (Rupees one crore, forty-four
lakh, eighty-three thousand, eight hundred and thirty) towards
Claim No. 12, along with an interest of 18% per annum under
th
Claim No. 13 from 12 May, 1997 to the date of actual payment.
The Arbitrator supported this award based on the undisputed fact
that the delay in completing the work beyond the stipulated
contract period was caused by the respondent and against the
stipulated contract period of 12 months, the appellant was
retained by the respondent for the execution of the work for an
additional period of 3½ years leading to loss of the appellant’s
profit earning capacity during the said extended period. The loss
of profit was worked out based on a profit allowance of 7½% per
year, which the Arbitrator held to be reasonable in a civil works
contract. Applying Hudson’s formula, the Arbitrator arrived at the
final compensation for loss of profit, the computation of which is
outlined below:
| Period of delay | 42.5 months | ||||
|---|---|---|---|---|---|
| Contract value | Rs. 5,45,27,386.00 | ||||
| Contract period | 12 months | ||||
| Contractor’s profit (7 ½ % per year) | Rs. 40,89,554.00 | ||||
| Contractor’s expected profit per | Rs. 3,40,796.00 | ||||
| month | |||||
| The total amount of loss of profit | The total amount of loss of profit | The total period of delay x Contractor’s | |||
| expected profit per month | |||||
| Rs. 1,44,83,830.00 |
Page 3 of 17
b) Aggrieved by the aforesaid First Award, primarily to the extent it
awarded Rs.1,44,83,830.00 towards loss of profit to the appellant,
the respondent filed an objection under section 34 of the Act
before the High Court impugning the decision pertaining to Claim
th
Nos. 12 and 13. Vide judgment and order dated 20 May, 2002,
the First Award was set aside and the aforesaid claims were
remitted to the Arbitrator for re-consideration and for passing a
fresh award. The operative part of the judgment passed by the
learned Single Judge reads thus:
“24. * Except for placing on record the Hudson’s formula and a
passage from the book law (sic, Law) on Building and Engineering
Contracts, no other evidence is placed on record by the respondent
to show that the profit percentage as claimed towards loss of profit
was a realistic one at that times and consequently there was no
change in the market and also that the work of at least the same
general level of profitability would have been available to the
respondent at the end of the stipulated contract period. Therefore,
evidence in respect of the said claim appears to be definitely not
available on record. In absence of any credible evidence and when
claims under Claim Nos. 10 & 11 were rejected on the ground that
no sufficient evidence had been placed on record by the
respondent indicating increase in the prices/rates for the work
executed after the stipulated contract period and also on account
of establishment, machinery, centering/shuttering etc., Claim
No.12 was allowed by the arbitration (sic, arbitrator) without even
considering whether the respondent has placed credible and
reliable evidence as required to be proved. *
25. * Not only there was lack of credible and required evidence
placed on record by the respondent in support of Claim No.12 as
set out in the extracts from the book Law of Building and
Engineering Contracts, and (sic) the arbitrator also took into
consideration such factors which could not and should not be (sic,
have) influenced his mind. Therefore, the award was passed by the
arbitrator against the fundamental policy of Indian Law attracting
the provisions of Section 34 (2)(b) (ii) of the Act. I set aside the
award given by the arbitrator against Claim No.12 and remit the
same for re-consideration by the arbitrator and to pass a fresh
award in respect of the said claim without being in any manner
influenced by such factors and on the basis of the evidence
available on record. Since the award passed by the arbitrator is set
aside to the aforesaid extent, the award of interest in Claim No. 13
Page 4 of 17
in respect of the amount of Claim No. 12 also stands set aside and
quashed and the same are remitted for reconsideration and
decision. Subject to the aforesaid modifications in the award, the
remaining part of the award is upheld.”
(emphasis ours)
th
c) The Arbitrator passed a fresh award dated 15 July, 2002
(“Second Award”, hereafter) maintaining the award for loss of
profit and interest to the appellant vide First Award. By referring
to the communications between the parties, the Arbitrator
reiterated that the respondent had failed to provide the complete
site and drawings within the stipulated contract period, leading to
delays. As per established legal principles, the party responsible
for the breach of the contract is liable for reasonably foreseeable
losses. Considering the appellant's status as an established
contractor, handling substantial projects, the Arbitrator inferred
that it was reasonable to assume earning of expected profits
elsewhere by the appellant. Employing the doctrine that within a
contract, gains prevented qualify as loss sustained, the Arbitrator
observed that the appellant was not required to establish the exact
amount of gain or loss with absolute certainty; instead, presenting
fairly persuasive and the best available evidence under the
particular circumstances of the case would suffice.
d) The respondent filed a petition under Section 34 of the Act,
seeking to set aside the Second Award. The learned Single Judge
th
of the High Court vide judgment and final order dated 25
February 2010 allowed the objection under Section 34 and
Page 5 of 17
rejected the appellant's claim under Claim No. 12 with an
observation that there was no sufficient evidence presented by the
appellant to establish the claimed loss of profit; the lack of records
regarding the alleged utilization of men, material, machinery,
overheads, and other resources in the contract performance that
could have otherwise been used for other profitable contracts
raised doubts about the legitimacy of the claimed losses under
Claim No. 12. With an observation that the Union of India was
forced into litigation due to the appellant's misconceived claim, the
Single Judge awarded costs of Rs. 50,000.00 (Rupees fifty
thousand) in favour of the respondent, payable within four weeks
from the date of the final order and interest of 9% per annum in
case of non-compliance. Findings returned by the learned Single
Judge are extracted below:
“4. I have gone through the entire Award. The Award … as a loss
under this Claim 12.
5. In this view of the … in the arbitration proceedings.
7. * I accept the objections to the Award and the Award dated
15.7.2002 of the Arbitrator is set aside and the claim of the
contractor under Claim 12 will accordingly stand dismissed. In the
facts and circumstances of the case, I award costs of Rs.50,000/-
in favour of the petitioner and against the respondents…
Accordingly, in the facts of the present case, I deem it fit to award
interest on the costs.”
e) Dissatisfied with the findings of the learned Single Judge, the
appellant preferred an appeal before the Division Bench of the
High Court under Section 37 of the Act. While dismissing the
appeal vide the impugned judgment, the Division Bench was of
Page 6 of 17
the view that no evidence was produced on behalf of the appellant
to support the plea of loss of profit during the period when the
work was prolonged; findings returned by the Arbitrator are,
therefore, contrary to law, more particularly the Contract Act
which governs matters related to loss of profit. Having found no
infirmity or illegality, the judgment of the learned Single Judge
was confirmed, and the appeal was dismissed, being devoid of any
merit.
SUBMISSIONS OF THE PARTIES
5. Taking exception to the decisions of the Single Judge as well as the
Division Bench, Mr Sameer Rohatgi, learned counsel appearing on behalf of
the appellant advanced the following submissions:
a) The learned Arbitrator had arrived at a just and reasoned
conclusion after carefully perusing the materials and evidence on
record and in the absence of any perversity or caprice, the courts
cannot interfere with the award. Relying on Associated Builders
1
vs. Delhi Development Authority , learned counsel submitted
that the arbitrator is the sole judge of the quality and quantity of
evidence and the High Court, under section 34 of the Act, cannot
act as a first appellate or a revisional court by interfering with
arbitral awards in the absence of perversity.
1
(2015) 3 SCC 49
Page 7 of 17
2
b) Bharat Cooking Coal Limited vs. L.K. Ahuja was placed in
support of the contention that the High Court has a limited scope
of interference in awards passed by an arbitrator. Learned counsel
placed reliance on the specific excerpt of this Court's decision,
which is extracted below for facility of reference:
“11…When the arbitrator has applied his mind to the pleadings, the
evidence adduced before him and the terms of the contract, there
is no scope for the court to reappraise the matter as if this were an
appeal and even if two views are possible, the view taken by the
arbitrator would prevail. So long as an award made by an arbitrator
can be said to be one by a reasonable person no interference is
called for. However, in cases where an arbitrator exceeds the terms
of the agreement or passes an award in the absence of any
evidence, which is apparent on the face of the award, the same
could be set aside.”
c) According to Section 34, an award cannot be modified but can only
be set aside under specific grounds outlined in the provision.
Unlike the Arbitration Act of 1940, which explicitly allowed for
modification, the Act of 1996, modelled on the UNCITRAL Model
Law on International Commercial Arbitration 1985, does not grant
the court the power to modify awards under Section 34. This aligns
with the legislative intent of minimizing judicial intervention in
arbitral awards. Reliance in support of the said contention was
placed on The Project Director, NHAI vs. M. Hakeem and
3
Another ;
2
(2004) 5 SCC 109
3
(2021) 9 SCC 1
Page 8 of 17
4
d) M/s AT Brij Paul Singh & Ors. vs. State of Gujarat was relied
upon to submit that a contractor is entitled to damages for loss of
expected profit on the remaining work and only a broad evaluation
is required to assess the amount of damages instead of going into
minute details; and
e) Hudson’s formula has received legal acceptance and is generally
used by courts and other judicial bodies in awarding loss of profit.
Learned counsel further submitted that Hudson’s formula works
on the numbers and figures contemplated in the contract as
envisaged by the parties at the time of signing of the contract
rather than the actuals during the ongoing work. Therefore, the
actual number of men, material and machinery allocated by the
appellant for the work bears no relevance whatsoever in
calculating the loss of profit incurred by the appellant due to the
breach of contract by the respondent, else Hudson’s formula would
be rendered redundant. Reliance was placed on McDermott
5
International Inc. vs. Burn Standard Co. Ltd. and Ors to
draw support.
6. Mr. Sanjay Jain, learned Additional Solicitor General (“ASG”,
hereafter) appearing on behalf of the respondent submitted that the arbitral
award was passed in an arbitrary and whimsical manner, and was rightly
rejected both by the Single Bench and the Division Bench. Urging this Court
4
(1984) 4 SCC 59
5
(2006) 11 SCC 181
Page 9 of 17
to dismiss the appeal and confirm the decisions of the Division Bench as
well as the Single Judge, the ASG advanced the following submissions:
a) The present case being that of delay simpliciter, Hudson’s formula
will have no application to award any amount for loss of profit
without the aggrieved party leading any evidence as a condition
precedent to the application of the said formula.
b) The application of Hudson’s formula hinges upon three essential
conditions:
i. Firstly, the profit awarded to the contractor must have been
realistically attainable elsewhere had it been free to leave the
contract at the appropriate time;
ii. Secondly, the contractor should not have consistently
underestimated his costs during pricing, ensuring that the
profit percentage was genuinely viable at that point;
iii. Thirdly, there should have been no subsequent changes in the
market, such that work of a comparable level of profitability
would have been available to the contractor at the time of the
conclusion of the contract.
c) It was further submitted that to fulfil the aforesaid conditions,
satisfactory and cogent evidence is a sine qua non even if the loss
is not of a remote or imaginary nature. In the absence of cogent
evidence substantiating a genuine loss of profit or opportunity, it
would be unjustifiable to permit the contractor to capitalize solely
on the application of a formula.
Page 10 of 17
d) In the present case, the ASG submitted, no evidence was led by
the appellant, far less, any credible or cogent evidence, to prove
that it was capable of earning such price elsewhere by way of any
other contract that was available to it at that time, which it could
not execute due to prolongation of the contract; such an award,
being perverse, conflicts with the public policy of India under
Section 34(2)(b)(ii) of the Act.
e) The Arbitrator's actions present a perplexing situation: while
dismissing Claim Nos. 10 (compensation for increased prices/rates
after the contract period) and 11 (compensation for the
establishment, machinery, centring/shuttering, etc.) due to the
absence of credible evidence, the Arbitrator, on the other hand,
proceeded to grant damages for loss of profit under Claim No. 12.
This prompts a crucial question: If there was insufficient evidence
to support Claim Nos. 10 and 11, what other evidence could
possibly justify awarding loss of profit under Claim No. 12?
f) Mechanical application of Hudson’s formula would serve no
purpose and burden the exchequer was the ASG’s concluding
submission.
ANALYSIS AND FINDINGS
7. We have considered the submissions advanced by learned counsel
for the parties and also perused the materials on record.
Page 11 of 17
8. The appeal is directed towards dismissal of the appellant's claim for
compensation relating to loss of profits (Claim No. 12). It is undeniably
established that the appellant's claim for loss of profit stems from the delay
attributed to the respondent in completing the project. It is further evident
that the loss of profit sought in the present case is primarily based on the
grounds that the appellant, having been retained longer than the period
stipulated in the contract and its resources being blocked for execution of
the work relatable to the contract in question, it could have taken up any
other work order and earned profit elsewhere.
9. The contentions advanced on behalf of the appellant tasks us to
resolve a recurring issue which, while not unprecedented, has consistently
confronted the courts leading it to navigate various circumstances under
which a claim for loss of profit may be allowed in cases of delay simpliciter
in the execution of a contract.
10. However, the contentions so raised, need not detain us for too long.
Quite apart from the appeal raising the question as to whether a claim on
account of loss of profit is liable to succeed merely on the ground that there
has been delay in the execution of the construction contract, attributable to
the employer, the question that first needs to be answered on facts and in
the circumstances is whether the Second Award is in conflict with the public
policy of India (as held by the learned Single Judge, since affirmed by the
Division Bench) .
Page 12 of 17
11. What would constitute “public policy of India” has been lucidly
6
explained by this Court in ONGC Ltd. vs. Saw Pipes Ltd :
“31…, the phrase ‘public policy of India’ used in Section 34 in context is
required to be given a wider meaning. It can be stated that the concept of
public policy connotes some matter which concerns public good and the public
interest. What is for public good or in public interest or what would be
injurious or harmful to the public good or public interest has varied from time
to time. However, the award which is, on the face of it, patently in violation
of statutory provisions cannot be said to be in public interest. Such
award/judgment/decision is likely to adversely affect the administration of
justice.”
12. Subsequent decisions of this Court have interpreted “public policy of
India” to include, among others, compliance with fundamental policy of
Indian law, statutes and judicial precedents, need for judicial approach,
compliance with natural justice, Wednesbury unreasonableness and patent
illegality. We may refer to the decision in Associated Builders (supra) in
this behalf.
13. Having read the Second Award, we have no hesitation to hold that
it fares no better than the First Award, for, it is equally in conflict with the
th
public policy of India. We have noticed from the order dated 20 May, 2002
of the learned Single Judge that while remitting Claim No.12 for re-
consideration, the Arbitrator was warned not to be influenced by the factors
that weighed in his mind while making the First Award. The Arbitrator was
also required to proceed only on the basis of the evidence on record. Yet,
regrettably, what we find is that the Arbitrator went on to ignore the judicial
decision of the High Court with impunity. He once again emphasized on
delay caused by the respondent in completion of the works entrusted to the
6
(2003) 5 SCC 705
Page 13 of 17
appellant by not providing complete site and drawings within the stipulated
contract period and that non-handing over of site certainly constituted
fundamental breach of contract vitiating the entire contract. He then
referred to Hudson’s espousal of fundamental breach of contract which,
according to him, was the standard text in all engineering and building
contracts. It is, therefore, apparent that the factors which weighed in the
Arbitrator’s mind in the first round and the second round are one and the
same. To avoid any charge of being branded as a mirror image of the First
Award insofar as Claim No.12 is concerned, the Second Award appears to
have been expressed in language and form different from the earlier one
without, however, there being any change in substance.
14. It is elementary, though it has to be restated, that a judicial decision
of a superior court, which is binding on an inferior court, has to be accepted
with grace by the inferior court notwithstanding that the decision of the
superior court may not be palatable to the inferior court. This principle, ex
proprio vigore , would be applicable to an arbitrator and a multi-member
arbitral tribunal as well, particularly when it is faced with a judicial decision
(either under section 34 or section 37 of the Act) ordering a limited remand.
In the wake of authority of judicial determination made by the Courts of
law, any award of an arbitrator or a tribunal that seeks to overreach a
binding judicial decision, in our opinion, does conflict with the fundamental
public policy and cannot, therefore, sustain.
15. Considering the aforesaid reasons, even though little else remains
to be decided, we would like to briefly address the appellant’s claim of loss
Page 14 of 17
of profit. In Bharat Cooking Coal (supra) , this Court reaffirmed the
principle that a claim for such loss of profit will only be considered when
supported by adequate evidence. It was observed:
“24. ... It is not unusual for the contractors to claim loss of profit arising out
of diminution in turnover on account of delay in the matter of completion of
the work. What he should establish in such a situation is that had he received
the amount due under the contract, he could have utilised the same for some
other business in which he could have earned profit. Unless such a plea is
raised and established, claim for loss of profits could not have been granted.
In this case, no such material is available on record. In the absence of any
evidence, the arbitrator could not have awarded the same.”
(emphasis ours)
16. To support a claim for loss of profit arising from a delayed contract
or missed opportunities from other available contracts that the appellant
could have earned elsewhere by taking up any, it becomes imperative for
the claimant to substantiate the presence of a viable opportunity through
compelling evidence. This evidence should convincingly demonstrate that
had the contract been executed promptly, the contractor could have secured
supplementary profits utilizing its existing resources elsewhere.
17. One might ask, what would be the nature and quality of such
evidence? In our opinion, it will be contingent upon the facts and
circumstances of each case. However, it may generally include independent
contemporaneous evidence such as other potential projects that the
contractor had in the pipeline that could have been undertaken if not for the
delays, the total number of tendering opportunities that the contractor
received and declined owing to the prolongation of the contract, financial
statements, or any clauses in the contract related to delays, extensions of
Page 15 of 17
time, and compensation for loss of profit. While this list is not exhaustive
and may include any other piece of evidence that the court may find
relevant, what is cut and dried is that in adjudging a claim towards loss of
profits, the court may not make a guess in the dark; the credibility of the
evidence, therefore, is the evidence of the credibility of such claim.
18. Hudson’s formula, while attained acceptability and is well understood
in trade, does not, however, apply in a vacuum. Hudson’s formula, as well
as other methods used to calculate claims for loss of off-site overheads and
profit, do not directly measure the contractor's exact costs. Instead, they
provide an estimate of the losses the contractor may have suffered. While
these formulae are helpful when needed, they alone cannot prove the
contractor's loss of profit. They are useful in assessing losses, but only if
the contractor has shown with evidence the loss of profits and opportunities
it suffered owing to the prolongation.
19. The law, as it should stand thus, is that for claims related to loss of
profit, profitability or opportunities to succeed, one would be required to
establish the following conditions: first, there was a delay in the completion
of the contract; second, such delay is not attributable to the claimant; third,
the claimant’s status as an established contractor, handling substantial
projects; and fourth, credible evidence to substantiate the claim of loss of
profitability. On perusal of the records, we are satisfied that the fourth
condition, namely, the evidence to substantiate the claim of loss of
profitability remains unfulfilled in the present case.
Page 16 of 17
20. The First Award was interfered with by the High Court for the reasons
noted above. The Arbitrator, in view of such previous determination made
by the High Court, could have granted damages to the appellant based on
the evidence on record. There was, so to say, none which on proof could
have translated into an award for damages towards loss of profit. A claim
for damages, whether general or special, cannot as a matter of course result
in an award without proof of the claimant having suffered injury. The arbitral
award in question, in our opinion, is patently illegal in that it is based on no
evidence and is, thus, outrightly perverse; therefore, again, it is in conflict
with the “public policy of India” as contemplated by section 34(2)(b) of the
Act.
21. For the reasons aforesaid, we find no merit in this appeal. The same
stands dismissed. However, cost awarded by the learned Single Judge is
made easy.
………………………………J
(S. RAVINDRA BHAT)
……………………………….J
(DIPANKAR DATTA)
New Delhi;
th
19 October, 2023.
Page 17 of 17