Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
CASE NO.:
Appeal (civil) 2522 1992
PETITIONER:
BISHANDAYAL AND SONS
Vs.
RESPONDENT:
STATE OF ORISSA & ORS.
DATE OF JUDGMENT: 07/12/2000
BENCH:
V.N.Khare, S.N.Variava
JUDGMENT:
L.....I.........T.......T.......T.......T.......T.......T..J
J U D G M E N T S. N. VARIAVA, J.
This Appeal is against a Judgment dated 15th May,
1992. Briefly stated the facts are as follows: In an
auction sale held by the Court Receiver, the 1st Respondent
purchased, for a sum of Rs. 2.32 lacs, all the assets of
one Mayurbhanj Spinning and Weaving Mills including plant
and machinery and land measuring Ac. 419.14,. The 1st
Respondent then proposed to sell off the Mill. The
Appellant by a letter dated 14th November, 1992 offered to
purchase the Mill with all its assets for consideration of a
sum of Rs. 2.31 lacs. During this period the State of
Orissa was under the President’s Rule. The Appellants thus
had a meeting with the Governor of Orissa wherein they were
asked to enhance the consideration to Rs. 2.32 lacs. The
Appellants by the letter dated 17th Marcy, 1973, addressed
to the Governor, conveyed their acceptance to purchase the
Mill with all its assets for Rs. 2.32 lacs. By a letter
dated 9th April, 1973, addressed by the Deputy Secretary to
the Government to the Director of Industries, the Director
of Industries was informed that the Government had decided
to sell the Mill to the Appellants for a sum of Rs. 2.32
lacs. It was, however, stated that the Director of
Industries was to ensure that correct assessment, of the
land required to run the unit by the Appellants, was made.
This was an internal communication, not addressed to the
Appellants yet the Appellants came to know of it. The
Appellants, obviously with a view to pressurize, address a
letter dated 18th April, 1973 to the Governor stating that
they had accepted the offer to purchase the Mill at the cost
of Rs. 2.32 lacs and purported to forward a Demand Draft in
a sum of Rs. 1,32,000/-. The 2nd Respondent by his letter
dated 21st April, 1973, addressed to the Appellants,
informed them that the Government had approved the proposal
to sell the Mill to the Appellant for a cost of Rs. 2.32
lacs and that they would be allotted land actually required
for running the Mill. By their letter dated 23rd April,
1973, the Appellants informed the 2nd Respondent that they
were surprised to learn that the land was to be allotted to
the extent actually required. They insisted that the entire
assets including the entire land was to be sold to them for
a sum of Rs. 2.32 lacs. The 2nd Respondent by the letter
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
dated 5th July, 1973 informed the Appellants that the
Government was willing to sell the entire land provided they
paid the full market value of the land and entered into a
lease and paid the premium and abided by the terms and
conditions of that lease. The Appellants on 17th July, 1973
gave an undertaking to apply to the local Tehsildar. On 2nd
August, 1973 the Appellants undertook to pay full value of
land and other charges and to abide by terms and conditions
of lease. As till date no agreement had been finalised by
letter dated 22nd October, 1973 the 2nd Respondent returned
the Demand Draft of Rs. 1.32 lacs to the Appellants.
Thereafter some correspondence was carried on between the
parties. Ultimately the Appellants gave a notice dated 26th
October, 1974, purporting to be a notice under Section 80 of
the Civil Procedure Code where under they claimed that a
complete contract had been arrived at to sell the Mill with
all lands to the Appellants for a sum of Rs. 2.32 lacs.
The Appellant then filed Suit No. 108 of 1976 in the Court
of Sub-Judge, Cuttack, claiming that a concluded contract
had been arrived at to sell the Mill and all its assets,
including Ac. 419.14 of land to the Appellants for a price
of Rs. 2.32 lacs. The Appellants claimed that they had
acquired valid right and title to the properties of the
Mill. The Appellants also claimed that the undertakings
given by them were void as they were obtained by
misrepresentation, fraud, undue influence and coercion. The
Appellants also sought an injunction against the Respondents
from selling away the Mill and its properties. At this
stage itself it is to be seen that the Appellants and the
Respondents were at cross purposes. Whilst the Appellant
was insisting on purchasing the Mill with all its land for a
price of Rs. 2.32 lacs only, the Government was only
offering the mill with such land as would be required for
running the Mill. Thus upto this stage there had been no
concluded contract or agreement. At the Appellate stage
counsel for Appellants fairly conceded that the prayers in
the Original Suit could not have been granted and that he
was not pressing for the same. This is recorded in paras 8
& 9 of the impugned Judgment. Thus we are not now concerned
with the Original Suit but with events which took place
thereafter. After the suit was filed a meeting was held in
the Chamber of Minister of Industries on 29th December,
1978. Minutes of the meeting of 29th December, 1978, inter
alia, records as follows : "3. After discussion the
following decision were taken :
(a) M/s. Bishandayal & Sons would pay the previously
fixed price of Rs. 2.32 lakhs towards plant, machinery &
building.
(b) They will be leased out an area of Ac. 40 of
land.
(c) They would pay premium @ 1/3rd of the market value
of land as prevailing in 1972.
(d) The suit will be withdrawn by the firm.
(e) After sale, the unit will be revived by the
party."
Copy of those minutes were given to the Appellants.
The Appellants applied for and were allowed to amend the
plaint on 11th September, 1981. It was now claimed that a
fresh agreement to sell had been arrived at on the basis of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
the decision taken in the meeting of 29th December, 1978.
The Appellants now sought Specific Performance of this
agreement. The Respondents filed an additional Written
Statement wherein they denied that there was any such
agreement. On 19th March, 1982 this suit was decreed by the
trial court. It was held by the trial court that there was
a completed contract between the Appellants and the
Respondents and that the Appellants had acquired rights over
the mill and its lands. Having come to that conclusion the
trial court still directed the Appellants to pay for 40
acres of land at the rate of Rs. 300 per acre. The trial
Court concluded that the Appellant was ready and willing to
perform its part of the contract and that the decision in
agreement arrived at on the meeting of 29th December, 1978
were mere confirmations of the previous contract. The trial
court also held that the condition regarding withdrawal of
suit was not a condition precedent and that there was valid
notice under Section 80 of the Code of Civil Procedure. The
Respondents then filed First Appeal No. 261 of 1992 in the
High Court of Orissa. This Appeal has been allowed by the
impugned Judgment dated 15th May, 1992. As has been set out
herein above, before the Appellate Court counsel for the
Appellant fairly and correctly conceded that the prayers in
the original plaint were not maintainable and could not have
been granted. As stated above counsel for the Appellants
fairly conceded that he was not pressing the prayers in the
original plaint. Thus clearly the decree of the trial court
holding that there was a concluded contract was wrong and
unsustainable, not only in law, but also on facts. Before
the Appellate Court the question was whether the Appellants
were entitled to specific performance of the agreement
alleged to have been arrived at in the meeting of 29th
December, 1978. The Respondents herein contended that there
was no agreement. They also contended that even if there
was an agreement the same was unenforceable in law as the
provisions of Article 299 of the Constitution of India had
not been complied with. It was also contended that by the
amendment of the plaint, an entirely new case had been
incorporated and no fresh notice under 80 of the Code of
Civil Procedure having been given the amended suit was not
maintainable. It was also contended that even if there was
an agreement one of the pre-conditions was that the suit
should be withdrawn and as the Appellants had not withdrawn
the suit, it could not be said that they were ready and
willing to perform their part of the contract and no relief
should have been granted to them on this count also. The
Appellate Court has, in the impugned Judgment held that an
agreement was arrived at. The Appellate Court has however
held that the agreement is not enforceable in law as it does
not comply with the provisions of Article 299 of the
Constitution of India. The Appellate Court has also upheld
the contentions of the Respondents herein, on Section 80
Code of Civil Procedure and on precondition of withdrawal of
Suit. Before us the Respondents have not disputed that, at
the meeting of 29th December, 1978, an agreement as
reflected in the minutes had been arrived at. Thus there is
no challenge to the findings in this behalf. However, it
has been contended that this is an agreement, which is
unenforceable in law as the provisions of Article 299 of the
Constitution of India have not been complied with. The
contentions regarding Section 80, Code of Civil Procedure
and precondition of withdrawal of suit have been pressed.
On behalf of the Appellants it is contended that it is not
open to the Respondents to take up the plea of non
compliance with Article 299, Constitution of India as no
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
such plea was taken in the written statement. In support of
this reliance was placed on the case of Kalyanpur Lime Works
Ltd. v. State of Bihar and other reported in AIR 1954 S.
C. 165. In this case the question was whether the
concerned contract conformed with the provision of Section
30 of the Government of India Act, 1915 Such a plea had not
been raised in the pleadings or in the memorandum of appeal
to the High Court but was taken for the first time during
arguments in this Court. This Court held that such a
question could not be allowed to be raised at the time of
the arguments, as it was a mixed question of law and fact
and no opportunity to adduce evidence was given to the other
side. Reliance was also placed upon the case of Union of
India vs. Surjit Singh Atwal reported in 1979 (1) S.C.C.
520. In this case there was a concluded contract for the
construction of a hard runway, taxi tracks and dispersal
roads The work under the contract had been completed and the
dispute between the parties was whether the Contractor was
entitled to special rates in respect of certain stone, which
were not available at the site. It was claimed that at a
meeting it had been agreed that the Plaintiff (therein)
would be entitled to extra price. The plea regarding
illegality of the contract had not been raised in the
written statement. In the written statement there was total
denial regarding the agreement to make payment of special
price. Thereafter an application for amendment of the
written statement was made to plead that there was failure
to comply with the provisions of Section 175(3) of the
Government of India Act, 1935. That application was
dismissed but it was observed that the plea could be raised
even without an amendment. The suit then went to trial.
The trial court dismissed the suit on the ground that there
was a new agreement in November 1947 and that this agreement
did not comply with the requirements of Section 175(3) of
the Government of India Act, 1935. In Appeal the Division
Bench held that there was no new agreement. The Appellate
Court held that the trial court was wrong in entertaining a
plea which had not been taken in the written statement. The
Appeal was accordingly allowed. This Court dismissed the
appeal to this Court on the ground that such a plea not
having been taken in the written statement could not be
raised after several years after the institution of the suit
as it would greatly prejudice the plaintiff. This Court
held if such a plea had been taken at the earlier stage, the
plaintiff could have come out with a certain alternate case
or raised certain other pleas, which right he had now lost.
This Court also held that such a plea was a mixed plea of
fact and law. Reliance was also placed upon the case of
Nirod Baran Banerjee vs. Dy. Commissioner of Hazaribagh
reported in 1980 (3) S.C.C. 5. In this case it was held
that the question whether Article 299 of the Constitution of
India was complied with is not a pure question of law but a
question depending on facts and since the point was not
pleaded either before the trial court or the High Court, it
cannot be raised in this Court for the first time. There
can be no dispute with the preposition of law. The question
whether a contract complies with Article 299 of the
Constitution of India or not is a mixed question of law and
fact. Undoubtedly in this case the plea has not been taken
in the written statement and not been urged before the trial
court. However, it was squarely urged before the Appellate
Court. At the stage i.e. when it was urged before the
Appellate Court, a contention could have been taken that
such a plea cannot be raised. Instead the Appellants took
out an application under Order 41, Rule 27, Code of Civil
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
Procedure, for a direction to the Respondents to produce the
original minutes in Court. That application was allowed by
the Appellate Court and the Respondents were directed to
produce the original minutes in Court. Thus the Appellate
Court made sure that no prejudice was being caused to the
Appellants. The Appellate Court made sure that Appellants
were not deprived of an opportunity to lay all facts before
the Court. The minutes were then produced in Court. It was
found that the original minutes did not contain the
signatures of either of the parties. The original minutes
were shown to the counsel for the Appellants and they were
satisfied that the minutes had not been signed by the
parties. Thus the Appellants themselves, on such a plea
being raised, called for the additional evidence and the
Appellate Court permitted it. The original minutes clearly
indicated that the provisions of Article 299 had not been
complied with. Further the witness of the Appellant had,
during his cross examination, admitted that apart from the
minutes there was no other written agreement between the
parties. It is not the case of the Appellants that the
agreement arrived at in the meeting of 29th December, 1978
had thereafter been approved or sanctioned either by the
President or the Governor. It is, therefore, clear that
even though there may have been some agreement the same was
not in compliance with the constitutional requirement under
Article 299 of the Constitution of India and is therefore
unenforceable in law. In a case such as this there is no
alternate plea that could be taken. None has been taken.
For this reason the Appellants would not be entitled to
specific performance of such an agreement. It must be seen
that all the cases relied upon by the Appellants were cases
where such a plea was not allowed to raised, for the first
time in this Court or in the Appeal Court on the ground that
the concerned party did not have an opportunity to meet such
a case. In this case the Appellants, on their application,
were permitted to have brought in Court the original
minutes. Unfortunately this did not assist them. Now they
can not be permitted to argue that such a plea could not be
raised. The next question for consideration is whether the
amended suit was not maintainable for want of notice under
Section 80 of the Code of Civil Procedure. In this behalf
the Appellants have relied upon the cases of Amar Nath Dogra
vs. Union of India reported in AIR 1963 S.C. 424, State of
Punjab vs. M/s. Geeta Iron & Brass Works Ltd. reported in
1978 (1) S.C.R. 746, Ghanshyam Dass and others vs.
Dominion of India and others reported in 1984 (3) S.C.C. 46
and Vasant Ambadas Pandit vs. Bombay Municipal Corporation
and others reported in AIR 1981 Bombay 394. In these cases
it has been held that a notice under Section 80 C.P.C. or
equivalent notices under Section 527 of the Bombay Municipal
Corporation Act are for the benefit of the Respondents and
the same can be waived as they do not go to the root of
jurisdiction in a true sense of the term. There can be no
dispute to the proposition that a notice under Section 80
can be waived. But the question is whether merely because
in the amended written statement such a plea is not taken it
amounts to waiver. This contention was argued before the
Appellate Court. Even otherwise we find that in the suit
itself Issue No. 4 had been raised as to whether or not
there was a valid and appropriate notice under Section 80.
Such a point having been taken in the original written
statement and an issue having been raised, it was not
necessary that in the amended written statement such a plea
be again taken. On behalf of the Respondents, reliance has
been placed on the case of Gangappa Gurupadappa Gugwad vs.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
Rachawwa and others reported in AIR 1971 S.C. 442, wherein
it has been held that where the plaintiff’s cause of action
is against a Government and the plaint does not show that
notice under Section 80 was served, it would be duty of the
Court to reject the plaint. In this case the original
notice was only in respect of a claim under the plaint as it
originally stood. That claim was on the basis that there
was a concluded contract and that the Appellants had already
acquired rights in the mill and the lands. As has been
fairly conceded those reliefs were not maintainable and were
given up before the Appellate Court. The amended plaint was
on an entirely new cause of action. It was based on facts
and events which took place after the filing of the original
plant. It was a fresh case. Now the claim was for specific
performance of the agreement alleged to have been entered
into on 29th December, 1978. Admittedly no notice under
Section 80 CPC was given for this case. As there was an
Issue pertaining to Notice under Section 80, the trial court
should have dealt with this aspect. The trial court failed
to do so. It was then pressed before the Appellate Court.
In our view the finding in the impugned Judgment that the
suit based on this claim was not maintainable is correct and
requires no interference. If a new cause of action is being
introduced a fresh notice under Section 80 CPC would be
required to be given. The same not having been given, the
suit on this cause of action was not maintainable. We also
find ourselves in agreement with the findings in the
impugned judgment that the condition regarding withdrawal of
the suit was a condition precedent. As the Appellants did
not withdraw the suit they could not be said to be ready and
willing to perform their part of the agreement arrived at on
29th December, 1978. For this reason also the claim for
specific performance could not have been enforced. In this
view of the matter, we see no reason to interfere with the
impugned Judgment. The Appeal stands dismissed. There
will, however, be no order as to costs.