Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
SRI NRIPATI GHOSHAL, FIRST LANDACQUISITION COLLECTOR & ORS.
Vs.
RESPONDENT:
PREMAVATI KAPUR (DEAD)BY LRS. & ORS. ETC.
DATE OF JUDGMENT: 23/07/1996
BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
G.B. PATTANAIK (J)
CITATION:
1996 SCALE (5)549
ACT:
HEADNOTE:
JUDGMENT:
THE 23RD DAY OF JULY,1996
Present:
Hon’ble Mr.Justice K.Ramaswamy
Hon’ble Mr.Justice G.B.Pattanaik
S.Muralidhar, Rathin Das, Advs. for appellent in C.A.No.
227/92
Preveen Swarup, Adv.(Ms.A.Subhashini, Adv.(NP), for
Union of India in C.A.No.3790/92
A.K.Ganguli, Sr.Adv., Parag P.Tripathi Rana Mukherjee, Ms.
Sumita Mukherjee, Indeevar Goodwill, Abha R. Sharma, Advs.
with him for the Respondents.
O R D E R
The following Order of the Court was delivered:
Sri Nripati Ghoshal First Land
Acquisition Collector a Ors. etc.
V.
Premavati Kapur (Dead)
by LRs. & Ors. etc.
WITH
CIVIL APPEAL NO.3790 OF 1992
Delay condoned.
Substitution allowed.
These appeals by special leave arise from the order of
the Division Bench of the Calcutta High Court dated July 31,
1990 made in Appeal from Original Order No. T.3734/86.
The undisputed facts are that the premises bearing
No.7, Chappel Road, Hastings, Calcutta was requisitioned on
November 29, 1971 under section 3(1) of the West Bengal
Premises Requisition and Control (Temporary Provision Act,
1947 (for short, ’the Bengal Act’) due to Bangladesh war.
The Indian Navy had taken possession thereof and has
remained in possession of the said premises. Subsequently,
it would appear, the respondents had filed Matter No.1295/79
in the Calcutta High Court questioning the legality of the
requisition. It would appear that proceedings were initiated
as early as in 1975 for acquisition as the property and the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
correspondence between various Departments was going on.
Notification under Section 4 (1) of the Land Acquisition
Act, 1894 (1 of 1984) (for short, the ’Act’) was published
on November 26, 1981. Enquiry under Section 5-A was
conducted. Thereafter, declaration under Section 6 was
published on November 25, 1982. The writ petition pending in
the High Court came up for hearing. A learned single judge
by his order dated April 8, 1983 had held that though there
was no public purpose for requisition under the Bengal Act,
since the acquisition was initiated under the Act four
months’ time was granted for completing the award enquiry
and to pass the award; in case of default, he directed the
appellants to hand over possession of the premises to the
respondents. In the meanwhile, the acquisition proceedings
were completed by making award on September 21, 1983. Notice
under Section 12 was issued to the respondents on September
23, 1983. Thus the acquisition under the Act had become
final. An oral application came to be made before the
learned Judge for extension of time on July 22, 1983 since
the time was to expire on August 8, 1983. But the learned
Judge declined to extend the time by his order dated August
2, 1983. Since the possession was not delivered, the
respondent had filed another writ petition in the High Court
which the learned single Judge had dismissed on November 12,
1986. On appeal, in the impugned order the Division Bench
set aside the order of the learned single Judge and issued
mandamus as indicated in the order. The primary findings
recorded by the Division Bench were that there was no public
purpose and that the acquisition was on public purpose and
that the acquisition was mala fide.
The question, therefore, is: whether the two findings
recorded by the Division Bench are correct in law? Shri
Ganguli, learned senior counsel for the respondents, sought
to support the findings of the Division Bench on the ground
that there are no bona fides on the part of the appellants
in pursuing the matter. In fact, when the respondent had
pointed out in the High Court that there was no public
purpose in requisitioning the property, they came forward
with the acquisition under the Act; when the learned single
Judge had directed the appellants to have the award enquiry
completed and the award made within four months, the same
were not done within the prescribed time. In spite of
initiation of contempt proceedings, the possession was not
delivered. These circumstances could be considered to show
that the acquisition was mala fide and that, therefore, in
the light of the above background, the High Court was right
in reaching the conclusion. We find no force in the
contentions.
It is seen that the acquisition proceedings under the
Act were initiated no doubt after the first writ petition
was filed challenging the requisition under the West Bengal
Act. But the notification under Section 4(1) and the
declaration published under Section 6 of the Act became
final before the learned single Judge had passed the order
on April 8, 1983. Thereby the public purpose, namely,
defence purposes, got crystalized before the judgment was
rendered by the learned single Judge. The learned single
Judge accepting the legal position, quite rightly, had given
time to complete the award enquiry and to pass the award.
Unfortunately, due to lethargy on the part of authorities to
have the funds made available, award could not be made for
non-depositing of the amount. The question, therefore,
emerges: whether the acquisition is mala fide? So long as
the public purpose subserves, the finding that the
acquisition is mala fide is ex-facie unsustainable. No doubt
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
there are laches on the part of the authorities, but so long
as the acquisition proceedings were legal and the defence
personnel remain in possession of the premises for the
defence purpose, the acquisition is for public purpose.
Therefore, it cannot be characterised to be mala fide. It is
seen that by the time the second writ petition, which is the
subject matter ultimately in this appeal, came to be filed,
the acquisition had become final; the award had become final
and the compensation was tendered. Under those
circumstances, the High Court, without going into the
validity in that behalf, was not right in setting aside the
acquisition on the specious finding that it is mala fide.
Therefore, the High Court has not properly consider that
aspect in the correct perspective in deciding the matter.
Pursuant to the interim direction granted by this Court
appellant have deposited rent at the rate of Rs 7500/- per
month beginning from 1.1.92. Shri Ganguli has brought to our
notice that the payments were not alleged to have been paid
for the earlier period of requisition. It is also brought to
our notice that the amount of compensation was not received
by the respondents. Under these circumstances, it would be
open to the Land Acquisition Collector to vary and, if found
correct, to adjust the amounts, deposited as per the orders
of the Court, towards the amount payable, if not already
paid for the period of requisition. If there is any further
amount due, that amount may also be directed to be paid to
the respondents within a specified time. The amount
deposited pursuant to orders of this court, if found excess,
may be adjusted towards the amount payable as compensation
for the acquired premises.
It is unfortunate that in spite of peremptory direction
to pass award and on non-compliance of order to deliver
possession of the building, no prompt action has been taken.
The officers have not shown diligence required in this case.
Even though the contempt proceedings were initiated for non-
delivery of possession, yet no steps had been taken even to
file appeal in this Court within the prescribed limitation.
That would show apathy or absolute indifference on the part
of the concerned officers in pursuing the proceedings. It
would be obvious that since they do not have personal
interest in the Governmental matters, they do not show the
required dispatch. It is our sad experience that invariably,
all cases of the Government, be that of Government of India
or State Governments, except presently in the case of the
Government of Punjab, are being filed with abnormal delay.
It would, therefore, be high time that all the Governments
should necessarily streamline the process of taking decision
in time to file appeals. The lack of responsibility and
indifference further gets compounded from the fact that
though the writ petitioner (3rd respondent in this case)
died on September 18, 1993 and notice was given by her
counsel to the counsel for the Union on October 4, 1993, no
steps were taken to bring the legal representatives on
record till August 19, 1994. In August 1994 the application
for substitution came to be filed but without any
explanation. These facts do indicate the absolute lack of
diligence and apathy or indifference in pursuing the matters
on behalf of the Union of India.
It is unfortunate that we have come across that even
the State Governments adopt the same indifferent attitude in
pursuing the public causes in filing the appeals in this
Court as well as in the High Courts and the courts below. It
is high time for the Government of India through the Cabinet
Secretary to constitute a legal cell centralising all the
cases to decide whether appeals should be filed and if so
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
have them filed in time or with utmost dispatch. The
officers responsible should be made accountable for the
delay. Same process is equally required to be adopted in
case of appeals to be filed in this Court or in the High
Courts by the respective State Governments and/or the Union
of India.
The Registry is directed to communicate this order to
the Cabinet Secretary and also to all the Chief Secretaries
of the State Governments; so also to the Attorney General of
India and the Advocates General of the concerned States so
that appropriate measures could be taken in this behalf.
The appeals are accordingly allowed, but, in the
circumstances without costs.