Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
U.P.S.E.B.
Vs.
RESPONDENT:
ATMA STEELS & ORS.
DATE OF JUDGMENT: 20/01/1998
BENCH:
B.N. KIRPAL, S.P. KURDUKAR
ACT:
HEADNOTE:
JUDGMENT:
THE 20TH DAY OF JANUARY, 1998
Present:
Hon’ble Mr. Justice B.N.Kirpal
Hon’ble Mr. Justice S.P.Kurdukar
D.A.Dave, A.B.Rohtagi, Sr. Advs., Pradeep Misra, R.B.Misra,
Kamlendra Misra, Advs, with them for the appellant.
A.K.Singh, Viohal Dixit, Advs, for the Respondents.
O R D E R
The following Order of the Court was delivered:
Special leave, granted in both the matters. The
respondent obtains electricity from the appellant. On 10th
December, 1992 a surprise check was made at the respondent’s
place and it was found that in the potential transformer
(PT) a fuse had been blown off with the result that it was
not suppling any electricity from primary cable to secondary
cable and as a consequences thereof, the quantum of
electricity consumed was not being correctly recorded in the
meter. A notice was issued requiring the respondent to show
cause as to why charges for less consumption be bot charged
for the period December 1991 to December 1992. In order to
avoid the disconnection of the electricity, the respondent,
with the permission of the authority, installed a new PT on
the respondent undertaking to pay in future for the supply
given to it.
On 20th December 1992 respondent gave a reply to the
show cause notice and inter also raised a dispute that the
PT and the meter panelling were not working properly. After
taking into consideration the reply, the Executive Engineer
on 22nd January 1993 made an assessment of Rs. 57,77,891,38
and raised a bill. Thereupon the respondent filed a suit in
the Court of Civil Judge, Ghaziabad challenging the said
assessment. The Civil judge passed an ex-parte ad-interim
injunction restraining the appellant from recovering the
assessment amount and from disconnecting the supply. In the
written statement filed by the appellant herein the demand
of Rs. 57,77,891,38 was justified. According to the
appellant the respondent, while the suit was still pending,
filed an application before the Chief Electrical Inspector
on 20th February 1993 purporting to be under section 26 of
the Indian Electricity Act, 1910 requiring the Inspector to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
exercise his Jurisdiction under the said provision and to
quash the aforesaid assessment which had been made b y the
Executive Engineer. On 6th April, 1993 the respondent filed
an application before the Civil Judge, Ghaziabad, inter-
alia, prayed that the electricity which had been
disconnected should be restored and the respondent be
permitted to pay the aforesaid demand by instalments. Along
with the application 12 post dated cheques were filed and
the respondent gave an undertaking to the Court to the
effect that if after the acceptance of the cheques and
restoration of electricity any cheque is not encashed or it
is dishonoured then the appellant herein will h ave the
right to disconnect the electricity of the respondent
without any notice. This application was made while
reserving the right of the respondent to make a reference
for arbitration. On the same day, the Trial Court accepted
the application and ordered the reconnection of the
electricity and it was specifically mentioned in this order
that the conditions mentioned in the respondent’s
application will form part of the order. 3 days thereafter,
the suit itself was withdrawn.
The Chief Electrical Inspector took cognizance of the
application which was filed before it and issued notice to
the appellant herein. Though reply was filed, to the said
application, the respondent filed a Writ Petition before the
Allahabad High Court which was disposed of on 5th November.
1993 with a direction to the Electrical Inspector to decide
t he reference within 6 weeks.
By the order dated 15th April, 1994 the Electrical
Inspector allowed the application after coming to the
conclusion that the fuse in one of the PT had blown off but
the amount which was demanded by the appellant was not
reasonable, Curiously enough, having come to the conclusion
that the meter had not recorded the correct amount of the
consumption of electricity because of the blowing off the
fuse the Electrical Inspector did not himself assess as to
what should have been the correct amount payable by the
respondent.
The appellant then filed an appeal before the State
Government under sec. 36(2) of the Indian Electricity Act,
1910. This appeal was allowed with the appellate authority
coming to t he conclusion that transformer could bot be
regarded as a meter and therefore the Electrical Inspector
had no jurisdiction under sec. 26(6) of the said Act to
entertain the application of the respondent. This finding
was again challenged by the respondent by way of a writ
Petition and the High Court, by the impugned Judgment came
to the conclusion that the transformer had to be regarded as
a meter within the meaning of that word in sec.26(7) and the
appellate authority was not justified in coming to the
conclusion that the Electricity Engineer had no jurisdiction
to decide the application. The appellate authority’s order
having been set aside, the matter was remanded by the High
Court but with the direction hat the appeal should be
decided b y the competent authority preferably by a
technical hand nominated by the State Government other than
the Energy Secretary.
We have heard the counsel for the parties and seen the
material on record and we see no reason to disagree with the
conclusion of the High Court regarding the Inspector
entertaining the application under sec.26(7) specially in
view of the fact that inthe Manual on H.T. Consumers
Metering published by the Central Board of Irrigation and
Power regarding the potential transformer with relation to
salient feature of metering equipments it is stated as under
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
:-
" (i) The metering equipments consist of CT and PT
units. For LT meters (i.e., for 3 phases 4 wire) only three
single phase VTs are required. For HT metering 3 phases PT
and tow CTs in R & B phases are required. CTs and PTs or
only CTs for LT metering are to be tested for their correct
polarity and ratio as per their terminal markings and name
plate details respectively, beside their insulation
resistance etc. since the CT and PT ratios have a direct
relation with the consumption recorded by a meter."
It is clear that the only function of the PT in a given
case like the present where the power is being supplied to
the respondent at 11000 Volt, is to reduce it to 110 Volt so
no to enable the meter to record the amount of power which
is consumed by the industry. It is common ground that the
existing meter could not record the power consumed unless
there was stepping down of the voltage from 11000 to 110.
This stepping down was done by the PT. It is also not in
dispute that after the recording of the consumption by the
meter the power, which was reduced from 11000 to 110 Volt,
is not used by the respondent. This clearly shows that the
only function of the PT was to enable the ascertaining or
regulating of the amount of energy supplied to the
respondent. This instrument namely the PT has, Therefore, to
be regarded as a meter in view of the provisions of sub-
section (7) of sec.26 and the second proviso, in particular,
and therefore the High Court was right in coming to the
conclusion that the Electrical Inspector had the
jurisdiction to exercise his powers under sec.26(7) of the
Act. The order of the apple late authority, therefore, was
rightly set aside.
The High Court, however, was not justified in issuing a
direction that the appeal should be heard by a technical
hand and by a person other than the Energy Secretary. Under
sec 36, sub-section (2) and appeal which is filed against
the order of the Electrical Inspector h as to be heard by an
Advisory Board. Who is to hear the appeal is for the
Government to decide and therefore a direction indicating as
to who in the Government should hear is ordinarily not in
conformity with the provision of sec.36(2) and was not
called for on the facts and in the circumstances of this
case. Therefore, the Judgment of the High Court to this
extend cannot be sustained.
The High Court also over looked the fact that the
respondent had secured a favorable order from the Civil
Judge, Ghaziabad on its own giving an undertaking t hat he
would pay the amount demanded by the responded if the
electricity is ordered to be reconnected. The undertaking so
given formed part of the order when the said application was
accepted and reconnection directed. In view of the conduct
of the respondent, who of course had reserved its right to
take recourse to arbitration as it disputed the demand of
the appellant, the High Court ought to have put the
respondent to terms while directing the hearing of the
appeal.
In our opinion, the respondent cannot be absolved of
its obligation to pay the amount demanded, as agreed by it
in the undertaking which it had furnished to the Civil
Judge, Ghaziabad. We accordingly direct that the appellant
would be entitled to realise the amount outstanding as per
the demand dated 20th January 1993. We are informed that a
part of the demand has paid inasmuch as 5 out of 12 cheques
which were tendered were encashed and for the balance amount
a Bank guarantee has been Furnished. The appellant will be
at liberty to encash the said Bank guarantee. The direction
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
of the High Court remanding the case to the appellate
authority for decision on merits is upheld. If the appeal is
dismissed the respondent would b e entitled to refund of the
excess amount paid by it but if ultimately the whole or part
of the demand raised by the appellant is upheld then the
respondent will be liable to pay interest. Similarly, if the
appeal is dismissed the respondent will be entitled to
interest on the amount to be refunded to him. The rate of
interest in either case will be 24%.
Both the appeals are disposed off. There will b e no
order as to costs.