Full Judgment Text
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Reserved on: 4 July,2023
rd
Pronounced on: 23 August, 2023
+ FAO (COMM) 48/2022
CASA2 STAYS PRIVATE LIMITED ..... Appellant
Through: Mr. Tishampati Sen, Ms. Riddhi
Sancheti, Mr. Anurag Anand & Mr.
Himanshu Kaushal, Advocates.
versus
BBH COMMUNICATIONS INDIA PRIVATE LIMITED
..... Respondent
Through: Mr. Amit Tyagi & Mr. Mukul
Tyagi, Advocates.
CORAM:
HON'BLE MR. JUSTICE SURESH KUMAR KAIT
HON'BLE MS. JUSTICE NEENA BANSAL KRISHNA
J U D G M E N T
NEENA BANSAL KRISHNA, J
1. The present Appeal under Section 37(1)(b) of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as the “Act, 1996” ) read
with Section 13(1A) of the Commercial Courts Act, 2015 has been filed
on behalf of the appellant, against the Judgment dated 19.02.2022 of the
learned District Judge, Commercial Court-02, South District, Saket, New
Delhi, wherein the Objections under Section 34 of the Act, 1996 filed by
the appellant against the Arbitral Award dated 20.10.2020 and Additional
Arbitral Award dated 17.12.2020 passed by the learned Arbitrator, was
dismissed.
2. The facts in brief are that the respondent, a Company engaged in
FAO(COMM) 48/2022 Page 1 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
the business of Advertising and other related works, entered into the
contract with the appellant-Company engaged in the Hospitality business
under the brand name of “Fab Hotels” . The Agreement dated 26.04.2018
was executed between the parties, wherein the respondent had agreed to
provide advertising services as detailed therein. The term of the Contract
was from 19.03.2018 till 18.06.2018 for a period of three months. Some
of the relevant terms of the Agreement dated 26.04.2018 are as under: -
“1. The services were to be provided by the respondent to the
appellant for a sum of Rs. 1,55,00,000/-, 50% of the amount
was payable before the commencing of project and the
balance on the completion of work as per the Purchase
Order.
2. Anything in addition to the agreed scope as per Schedule
I, would be charged extra subject to the prior approval by the
client.
3. The GST and Government taxes were payable
additionally, but either party could terminate the Contract
upon the material breach by either party. In case, the breach
was not cured within the period of 10 days from the receipt of
notice from the non-defaulting party.
4. All the invoices were payable within 30 days of invoice
date. In case, there was no dispute in respect of the said
invoices. However, if a dispute or query on invoice had to
be raised and communicated to the agency within 5 working
days of the presentation of the invoice, failing which, the
invoice vide which amount was claimed, was to be assumed
correct and due for payment . Interest @ 12% per annum
was chargeable on the overdue amount.”
3. Admittedly, a sum of Rs. 91,45,000/- (inclusive of GST at18%)
(50% of the contract amount) was paid in advance. The respondent after
handing over master TVC to the appellant, raised invoice for the
FAO(COMM) 48/2022 Page 2 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
remaining 50% amount i.e., Rs. 77,55,000/- + 18% GST totalling to Rs.
91,45,000/-. The appellant admittedly paid a sum of Rs. 69,60,000/- in the
Bank Account of the respondent and retained the balance amount of Rs
20,65,000.
4. The respondent immediately brought this to the notice of the
appellant vide e-mail dated 05.07.2018 and sought clarification and
confirmation about the balance amount which was confirmed,
acknowledged and admitted by the respondent’s official, namely, Mr.
Nishant Gupta vide E-mail dated 06.07.2018 and by another official,
namely, Mr. Sandeep Thukral vide his e-mail dated 09.07.2018. Yet, the
amount was not paid.
5. The claimant/respondent has further stated that apart from these
amounts, there were additional works done for which separate Purchase
Orders, were raised upon the appellant. The details of the Purchase Orders
are as under: -
| S. No. | Purchase Order<br>No. | Date | Remarks & Amount | Invoice<br>Raised& Date |
|---|---|---|---|---|
| 1. | CASA/APR/08 | 25.04.2018 | Travel expenses of Ms.<br>Reema Asrani for sum of Rs.<br>12,980/- | Rs. 7,042/- |
| 2. | CASA/APR/11 | 27.04.2018 | Rs. 1,52,220/- | Rs. 1,18,598/-<br>&<br>13.07.2018 |
| 3. | CASA/APR/008 | 13.07.2018 | 2 HD copies of electronic<br>upload for sum of Rs. 6,041/- | Rs. 6,041/-<br>&<br>18.05.2018 |
| 4. | CASA/JUN/11 | 13.06.2018 | Production in 6 languages and<br>royalty (Hindi & English) and<br>caller tune for TVC for sum<br>of Rs. 4,30,700/- | Rs. 4,30,700/-<br>&<br>22.06.2018 |
| 5. | CASA/JUN/24 | 20.06.2018 | TVC in Tamil, Bengali and | Rs, 82,010/- |
FAO(COMM) 48/2022 Page 3 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
| Malyalam languages for of<br>sum Rs. 82,010/- | &<br>11.07.2018 | |||
|---|---|---|---|---|
| Total | Rs. 6,44,391/- |
6. The total amount thus found due from the appellant came to Rs.
27,09,392/- along with interest @ 12% being Rs. 5,35,368/- upto January,
2020. Despite making demands for due amount, the appellant failed to pay
the amount. Left with no option, the respondent invoked Arbitration in
terms of Clause 16 of the Agreement dated 26.04.2018.
7. The appellant in its Statement of Defence did not dispute the
execution of the Agreement or advance payment of 50% of the Contract
amount i.e.Rs. 91,45,000/-. It was also not denied that the balance amount
of Rs. 91,45,000/- remained out of which, an amount of Rs. 69,60,000/-
was paid as a goodwill gesture but it is denied that deduction of Rs.
20,65,000/- was made in view of the shortcomings and the failure of the
respondent to provide the services in terms of the Agreement.
8. The main contention raised by the appellant before the learned
Arbitrator was that the TVC and other deliverables under the Agreement
were not delivered by the respondent within the agreed time-frame. The
Out of Home (OOH) and print execution had not been delivered even by
July, 2018 and the respondent resiled from taking responsibility for
execution of OHH.
9. Further, the respondent coerced the appellant into giving additional
costs for the approval of music and other items before the appellant’s
advertising campaign which was to go live on an online platform, namely,
Hotstar. It was contended that the respondent unilaterally changed the
background music without caring for the appellant’s view. These issues
FAO(COMM) 48/2022 Page 4 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
delayed the campaign by two to three weeks.
10. Moreover, the respondent changed the scope of work without
transparency and without approval from the appellant and, therefore, the
final TVC delivered was different from the presentation made while
entering into the contract.
11. It was submitted that the appellant wanted to negotiate directly with
the Production House engaged by the respondent for some outdoor photo
shoot which was outside the scope of the TVC. However, the respondent
withdrew their support completely and did not render the requisite
assistance to the appellant. The respondent also retaliated by charging the
maximum amount for travel and stay for completing the work under the
Agreement by seeking approval from the appellant for the best 5-Star
accommodations. It was the stance of the appellant that the respondent
ought to have limited these expenses.
12. It was further submitted that the respondent raised Invoices for
extra charges for re-recording the advertisement in certain languages and
that it did not deliver the product in some cases. The appellant, thus
claimed that the respondent was not entitled to the balance amount.
13. The learned Arbitrator considered the e-mails that formed the
foundation for the rival contentions and were not disputed by both the
parties, made the following awards: -
“the claimant is held entitled to Rs. 27,09,392/- as principal
amount and @ 12% amount as interest on this amount from
1.9.2018 to 29.2.2020 amounting to Rs. 4,87,690/-. The
claimant is entitled to 10% interest from 1.3.2020 to
20.10.2020 on Rs. 27,09,332/- amounting to Rs. 1,,73,100/-.
The total amount payable by the respondent to claimant
FAO(COMM) 48/2022 Page 5 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
comes to Rs. 33,70,182/-. In case the respondent pays this
amout within 60 days of this order, no further interest to be
paid. In case of failure of respondent to pay the amount, the
respondent would be liable to pay 10% interest on the
awarded amount of Rs. 33,70,182/- w.e.f. 21.10.2020 till
realization.”
14. An additional Award dated 17.12.2020 was made by the learned
Arbitrator in the following terms: -
“The claimant is entitled to following costs: -
a) Arbitrators fee paid by the claimant.
b) Venue booking charges and steno charges paid by the
claimant.
c) Counsel fee to the tune of Rs. 1 lac.”
15. Aggrieved by the Award dated 20.10.2020 and additional Award
dated 17.12.2020, the appellant preferred an Objection under Section 34
of the Act, 1996 before the learned Commercial Judge who dismissed the
same vide Judgment dated 19.02.2022. Thus, the appellant has preferred
the present appeal.
16. Submissions heard
17. The main grounds agitated in the present Appeal under Section
37(1)(b) of the Act, 1996 are firstly, the appellant was not given an
opportunity to address the oral arguments in terms of Section 24 of the
Act, 1996 and which amounts to violation of principle of natural justice,
resulting in miscarriage of justice.
18. vital evidence by way of additional E-mails dated
Secondly,
29.06.2018 and 29.06.2018 have been ignored and overlooked by the
learned Arbitrator while adjudicating the claim of the respondent.
FAO(COMM) 48/2022 Page 6 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
19. Now coming to the first objection, the importance of the rule of
audi alteram partem in arbitration proceedings is axiomatic from a
reading of Section 34(2) (a) (iii) of the Act, 1996 which sets out the
grounds for setting aside an Award which includes circumstances where a
party was not given proper notice of the appointment of an arbitrator or
of the arbitral proceedings or was otherwise unable to present his case.
The Apex court in Ssangyong Engineering and Construction Co. Ltd. vs
National Highway Authority of India, 2019 15 SCC 131 reiterated “the
right to a hearing” as a ground to set aside an arbitral award.
20. Now coming to the facts in hand, the assertion of the appellant that
no opportunity to present its case was given, has also been vehemently
countered. It has been pointed out that learned counsel for the respondent
that the learned counsel for the appellant was always available on the
dates fixed by the learned Arbitrator. The record shows that the matter had
been fixed via e-mail dated 13.08.2020 on 02.09.2020 for oral final
arguments, on which date, learned counsel for the appellant sought an
adjournment on account of ill-health which was not objected to by the
counsel for the respondent. The matter was consequently adjourned to
14.09.2020 at 03:00 P.M. for final arguments. No time limit was fixed for
addressing the arguments by either party. Only after the arguments were
concluded by the counsel for the respondent, did the appellant’s counsel
seek an adjournment on the ground that she had another arbitration listed
at the same time and she would thus, be unable to address the arguments
on the said date.
21. Despite the belated information, the learned Arbitrator while
FAO(COMM) 48/2022 Page 7 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
appreciating the difficulty of the counsel for the appellant to address the
oral arguments, gave opportunity to both the parties to submit their written
arguments within two weeks. However, the appellant failed to submit the
written arguments and made a request for further time vide e-mail dated
27.09.2020. Accordingly, the learned Arbitrator gave further indulgence
by granting an extension vide his e-mail dated 28.09.2020; yet, no written
arguments were filed on behalf of the appellant.
22. The entire conduct as narrated above, reflects that the learned
Arbitrator being fully conscious of the principle of natural justice, had
given multiple opportunities to the learned counsel for the appellant to
address arguments. The claim of the appellant that there has been denial
of opportunity to address arguments, is bereft of any merit.
23. Pertinently, the dispute inter se parties was based on the documents.
With that being the case, merely because the oral arguments were not
addressed by the appellant, does not lead to inevitable denial of principles
of natural justice, without further explaining if any pertinent aspect was
left unconsidered. A reference may be made to the observations of the
Hon’ble Supreme Court in the case of Sohan Lal Gupta vs. Asha Devi
(2003) 7 SCC 492, wherein it was observed that principles of natural
justice should not be stretched too far.An Arbitrator has a right to manage
the proceedings and to give directions to the parties to be present on a
particular date, time and place and this would be sufficient compliance of
the principles of natural justice. It was further observed that even
otherwise, no party has absolute right to insist on his convenience in every
respect. The matter is within the discretion of the Arbitrator and Court can
FAO(COMM) 48/2022 Page 8 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
intervene only in the event of positive abuse. Similar observations have
been made by Kerala High Court in the case of Impex Corporation And
Ors. vs Elenjikal Aquamarine Exports AIR 2008 Ker 119.
24. Therefore, the Arbitrator had given an opportunity to the appellant
to address the oral arguments, but the same is not availed by the party.
Moreover, the appellant also failed to file written arguments despite two
opportunities. In the aforesaid circumstances it cannot be held that there
was denial of principle of “audi altrem partem”. Sufficient opportunities
were granted though not utilized by the appellant.
25. The objection is connected with the first limb of arguments.
second
It is claimed that because no opportunity of addressing the arguments was
availed by the appellant, the true facts on the merit of the case could not
be considered.
26. It was argued that the e-mails sent on 28.06.2018 and 29.06.2018
have not been considered and also significant aspects of non-compliance
of the terms of the Agreement by the respondent have been overlooked.
27. This argument also does not have any basis. The learned Arbitrator
had considered the rival contentions and noted that the Agreement
specifically contained the list of deliverables. The appellant neither in its
Statement of Defence nor in its Reply to the Notice dated 29.08.2019
claimed that the deliverables were not delivered in time. In fact, the
exchange of e-mails between the appellant and the respondent on
19.05.2018 reflected that the 60-second Master Film for YouTube/Digital
was sent to the appellant for their record as well. The appellant-Mohit
Gupta vide E-mail dated 19.05.2018, in fact, acknowledged the work by
FAO(COMM) 48/2022 Page 9 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
writing “Thanks Yashi. Great work in delivering this. Keep it up” . The
e-mail dated 20.5.2018 of the appellant reflected that pre-launch screening
was done by the appellant to its full satisfaction.
28. The learned Arbitrator therefore, rightly concluded that the e-mails
dated 19.05.2018 and 20.05.2018 of the appellant reflected the due
execution of the work under the Agreement. The appellant has also
referred to the two E-mails dated 28.06.2018 and 29.06.2018 which read
as under: -
“E-mail dated 28.06.2018
Yashi Vikram <Yashi. vikram@bbh-india.in> 28 Jun 2018 12:36
To Mohit, Mohit, Shreekant, Vaibhav, S.
Hi Mohit
Sending across a presentation with 5 shots that we recommend to
capture through the still shoot: (not legible)
Basis approval on these, we will brief the production
house/photographers.
Once the project is awarded for a photographer, we will get into
the nitty-gritty of the shoot (cast, costume, location etc.) through
a PPM.
The break-up of film production post is attached.
Let us know about Marudhar.
Thanks.
E-mail dated 28.06.2018
Yashi Vikram <Yashi. vikram@bbh-india.in> 28 Jun 2018 13:29
To Mohit, Mohit, Shreekant, Vaibhav, S.
Hi Mohit
Awaiting way forward to this.
Have lined up the photographers already.
Thanks.
FAO(COMM) 48/2022 Page 10 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
E-mail dated 29.06.2018
Yashi Vikram <Yashi. vikram@bbh-india.in> 29 Jun 2018 19:36
To Mohit, Mohit, Shreekant, Vaibhav, S.
Hi Mohit
Sending across a presentation with 5 shots that we recommend to
capture through the still shoot.
Basis approval on these, we will get into the nitty-gritty of the
shoot (cast, costume, location etc.) through a PPM.
The break-up of film production post is attached.
Let us know about Marudhar.
Thanks.
E-mail dated 29.06.2018
Yashi Vikram <Yashi. vikram@bbh-india.in> 29 Jun 2018 13:29
To Mohit, Mohit, Shreekant, Vaibhav, S.
Hi Mohit
Awaiting way forward to this.
Have lined up the photographers already.
Thanks.”
29. The learned Arbitrator had duly appreciated the evidence to arrive
at the conclusion that though reference was made by the appellant to the
E-mails dated 28.06.2018 and 29.06.2018, but neither of those e-mails had
any mention of the incomplete work.
30. The learned Arbitrator has also considered the dues under Invoices
for five Purchase Orders which were raised for the additional work that
was carried out by the respondent. These additional Purchase Orders were
in terms of the Clause 5 (f) of the Contract between the parties. Again,
the appellant has not been able to produce any evidence or document to
show that the work specified in those five Purchase Orders, were not done
FAO(COMM) 48/2022 Page 11 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
by the respondent or that respondent was not entitled to the amounts under
the Purchase Orders.
31. The appellant took a plea that the Final Invoice dated
13.07.2018was exorbitantly priced. The Invoice was in reference to the
Purchase Order dated 27.04.2018 which quoted the price at Rs.1,52,220. It
is not disputed that five Purchase Orders were approved and not
questioned by the appellant. The final Invoice dated13.07.2018for a sum
of Rs.1,18,598 was raised, based on the Purchase Order 27.04.2018 and
was much less than the initial quotation. Further, in terms of the Contract,
if there was any objection to any of the invoices, it had to be taken within
five days. The learned Arbitrator has rightly appreciated the rival
contentions while passing the impugned Award.
32. The Objections taken by the appellant have been rightly found to be
without merit in the Petition under Section 34 of the Act, 1996 by the
learned Commercial Judge, who has in detail, considered the aforesaid
contentions.
33. Neither before the learned Commercial Judge in the Objections
under Section 34 of the Act, 1996, nor in the present Appeal has the
appellant been able to show any perversity in the findings of the learned
Arbitrator. Axiomatically, the Petition under Section 34 of the Act, 1996
and the present Appeal seeks re-appreciation of the evidence, which is not
permissible.
34. The Supreme Court in Anglo American Metallurgical Coal vs
MMTC Limited, (2021) 3 SCC 308 found that any attempt to challenge an
order issued under Section 34 of the Act, 1996 is prohibited from going
FAO(COMM) 48/2022 Page 12 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
beyond the parameters outlined in Section 34 of the Act, 1996. In other
words, the court is not permitted to independently evaluate the merits of
the award; instead, it must just confirm that the court’s use of its authority
under Section 34 of the Act, 1996 has not gone beyond what is allowed
under the Statute. Therefore, this Court must be extremely cautious and
hesitant to disrupt such concurrent conclusions in cases where an Arbitral
Award has been made and validated by the Court under Section 34 of the
Act, 1996. Further, it is beyond the scope of Section 37 of the Act, 1996
for courts to re-appreciate the evidence when the arbitrator has passed a
reasoned award by drawing plausible conclusions based on the evidence
and interpretation of the law as held in Delhi Airport Metro Express Pvt.
Ltd. Vs. Delhi Metro Rail Corporation Ltd. (2021) SCC OnLine SC 695.
Given the settled law on the re-appreciation of evidence, the onus of
establishing any perversity in the finding of the learned Arbitrator was on
the Appellant, which it has clearly failed to discharge.
35. We find no merit in the present appeal challenging the impugned
Judgment dated 19.02.2022 under Section 34 of the Act, 1996, Arbitral
Award dated 20.10.2020 and Additional Arbitral Award dated 17.12.2020
passed by the learned Arbitrator, and the same is hereby dismissed.
(NEENA BANSAL KRISHNA)
JUDGE
(SURESH KUMAR KAIT)
FAO(COMM) 48/2022 Page 13 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56
JUDGE
S.Sharma
AUGUST 23, 2023/
FAO(COMM) 48/2022 Page 14 of 13
Signature Not Verified
DigitallySigned By:SAHIL
SHARMA
Signing Date:23.08.2023
14:33:56