Full Judgment Text
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4126 OF 2013
T.N. Generation & Distbn. Corpn. Ltd. …
Appellant
VERSUS
PPN power Gen. Co. Pvt. Ltd.
...Respondent
J U D G M E N T
SURINDER SINGH NIJJAR, J.
1. This statutory appeal under Section 125 of the
JUDGMENT
Electricity Act, 2003 (hereinafter referred to as the
“Act”) is directed against the final judgment and
nd
order dated 22 February, 2013 passed by the
Appellate Tribunal for Electricity (hereinafter referred
to as “APTEL” or “Appellate Tribunal”), at New Delhi
in Appeal No. 176 of 2011, whereby it has dismissed
the appeal preferred by the appellant against the
Page 1
2
th
final judgment and order dated 17 June, 2011 of
Tamil Nadu Electricity Regulatory Commission
(hereinafter referred to as the “State Commission”)
| 12 of | 2009. |
|---|
noticed in detail both by the State Commission and
the APTEL, therefore, we shall make a reference only
to the very essential facts necessary for deciding this
appeal.
2. The respondent, a generating company, has entered
into a Power Purchase Agreement (PPA) with the
rd
appellant on 3 January, 1997 for the supply of the
entire Electricity to be generated by the respondent
JUDGMENT
for a period of 30 years. The respondent
th
commenced commercial operations on 26 April,
2001. Under the PPA, the respondent has to submit
an annual invoice indicating the amounts owed under
the Tariff. The amounts receivable from the
appellant for the previous year are to be reconciled
against the sum of monthly estimated payment
Page 2
3
made by the appellant as soon as possible after the
end of each year. Accordingly, respondent started
th
raising monthly invoices from 26 April, 2001 for the
| plied by | it to the |
|---|
to the appellant, invoices of the respondent inter alia
included interest on debt sanctioned but not
disbursed, charges towards energy consumed at the
residential quarters at the generating station etc.
The appellant claims that substantial payments
towards the monthly invoices raised by the
Respondent for every month were paid against the
admitted amount in the invoice. The disputed
amount was withheld. The respondent accepted the
JUDGMENT
admitted amount paid against each invoice without
raising any dispute either with respect to the
disputed amount or the substantial payment made
by the appellant.
th
3. Government of India by Notification dated 30
March, 1992 incorporated a rebate scheme on
Page 3
4
the receivables. Under this scheme, the
purchaser, i.e., appellant is entitled to a rebate @
2.5% if the payment is released within 5 days
| date of | invoice |
|---|
payment is released within 30 days from the date
of invoice. Accordingly, while making the
payment of the admitted amount under each
invoice, the appellant deducted the 2.5% rebate,
as payments were made within 5 days from the
date of the receipt of the invoice. These
payments were accepted by the appellants. On
the other hand, respondent adjusted the amount
received by it in the following month against the
JUDGMENT
unpaid amount of the previous month. The
balance was carried forward by the respondent.
Since June, 2001, the appellant had been making
payments as noticed above, and the respondent
had been adjusting the same on a “FIFO” basis.
The appellant claims that the monthly invoices
raised by the respondent were only estimated
Page 4
5
invoices. On the other hand, the respondent
claims that the appellant, from inception only
made adhoc payments periodically against the
| voices r | aised. T |
|---|
claiming that the other did not provide any
details with regard to the amounts due and the
amounts paid. It is also the claim of the
respondent that the appellant had unilaterally
made several disallowances without informing
the respondent of the same.
4. It appears that both the parties were dissatisfied
with accounting details provided by the other.
JUDGMENT
Ultimately, the respondent issued a notice of
th
dispute resolution on 26 April, 2007 and
appointed its Vice President, Shri B.
Sundaramurthy as the representative.
Continuous correspondence was exchanged
between the parties from August, 2007 to March,
st
2009. On 1 April, 2009, respondent sent a
Page 5
6
Notice to the appellant in terms of Article 16 of
the PPA claiming amounts due/overdue from the
appellant and interest on late payments. The
| ves a | summar |
|---|
th
respondent till 30 March, 2009 other than
towards specified taxes, which was stated to be
subjudice, and, therefore, not included therein.
The balance of amount payable, according to the
respondent was Rs.1,787,272,534. The
appellant in reply informed the respondent on
th
16 April, 2009 that the matter was under
scrutiny and examination. Since, there was no
response, the respondent sent a reminder.
JUDGMENT
Instead of making the payment of the amounts
th
claimed, the appellant issued letter dated 4/5
May, 2009 claiming that according to its
accounts, sum of Rs.31.12 crores was due to the
th
appellant. On 8 May, 2009, the respondent
requested the appellant “to provide the
particulars and details forming the basis of your
Page 6
7
th
claim before 15 May, 2009.” The respondent
also requested the appellant to fix a meeting on
th
or before 19 May, 2009 to discuss the issues
| e the sa | me. A |
|---|
th
19 May, 2009 but the dispute was not resolved.
5. Since the dispute was not resolved, the
respondent filed the petition – D.R.P. No. 12 of
2009 before the State commission, seeking a
direction to the appellant to make a payment of
sum of Rs. 1,89,91,17,264 being a sum due as on
th
19 March, 2009, under the invoices raised under
the PPA and interest thereon in terms of Article
JUDGMENT
10.6 of the PPA from the due date till the date of
actual payment. After setting out the details of
the amounts due as narrated above, the
respondent claimed that, under Article 10.2(b) of
the PPA, in the event of any dispute as to all or
any of the portion of an invoice, the appellant
was required to pay the full amount of the
Page 7
8
disputed charges and thereafter serve a notice
on the respondent indicating the amount in
dispute. The dispute is to be resolved under
| which p | rovides |
|---|
of dispute. Firstly, under Article 16(1), by mutual
discussions through the designated
representatives of the parties. Secondly, in case
the parties are unable to resolve the dispute
pursuant to Article 16.1, it is to be resolved
through finally by arbitration in accordance with
Article 16.2.
6. Under Article 16.2, the arbitration has to be
JUDGMENT
conduced in accordance with the rules of
Conciliation and Arbitration of International
Chamber of Commerce (ICC), in effect on the
date of the agreement. The Arbitration Tribunal
is to consist of three arbitrators, of whom each
party should select one. The two arbitrators
appointed by the parties shall select the third
Page 8
9
arbitrator, to act as the Chairman of the Tribunal.
If the two arbitrators appointed by the parties,
fail to agree on a third arbitrator, the ICC Court of
| shall m | ake th |
|---|
arbitration shall be held in England. It is further
provided that notwithstanding Article 16.8, the
laws of England shall govern the validity,
interpretation, construction, performance and
enforcement of the provisions contained in
Article 16.2. The arbitration proceedings shall be
conducted and the award shall be rendered in
English language. It is further provided that the
rights and obligations of the parties shall remain
JUDGMENT
in full force and effect pending the award in any
arbitration proceedings. The costs of the
arbitration shall be determined by the arbitral
tribunal in accordance with the Rules. The
arbitration clause specifically provides that the
Indian Arbitration Act (Act No. X(10) of 1940/The
Arbitration and Conciliation Act, 1996 shall not be
Page 9
10
applicable to this arbitration provision, to any
arbitration proceedings or award rendered or
any dispute or difference arising out of or in
| the agre | ement. |
|---|
that award rendered hereunder shall be a foreign
award within the meaning of the Foreign Awards
Act, 1961.
7. Clause 16.2(i) specifically provides that the
parties hereby waive any rights of application or
appeal to the Courts of India to the fullest extent
permitted by law in connection with any question
of law arising in the course of arbitration or with
JUDGMENT
respect to any award made.
8. Clause 16.3 of the arbitration agreement
provides that the award of the arbitrators shall
be final and binding. The other provisions with
regard to the arbitration clause are incidental
and, therefore, not necessary to be mentioned.
Page 10
11
Article 17.8 of the PPA provides as under:-
“17.8 Governing Law: Subject to Sections 16.2(b)
and 16.2(e) hereof, this agreement and the rights
| nd gove | rned by |
|---|
of India.”
9. As noticed above, Article 16.2(b) provides that
the arbitration shall be conducted in accordance
with the ICC Rules notwithstanding Article 17.8.
Similarly, Article 16.2(e) provides for exclusion of
Article 17.8.
10. Upon completion of the pleadings and after
hearing the parties, the State Commission by an
JUDGMENT
th
order dated 17 June, 2011, allowed the petition
filed by the respondent for refund of the excess
rebate availed by the appellant contrary to the
terms of PPA and also ordered the respondent to
redraw the monthly invoices in accordance with
the directions issued by the State Commission.
Page 11
12
The State Commission held that it is competent
to adjudicate upon the dispute. The limitation
period prescribed in the Limitation Act, 1963
| apply t | o the p |
|---|
Commission, delay and laches would apply. The
appellant is liable to pay interest to the
respondent in terms of Clause 10.6 of the PPA till
payment. Conversely, if the appellant has made
excess payment against each monthly invoice
compared to the corresponding redrawn monthly
invoice, the respondent is liable to pay interest in
terms of Article 10.6 of the PPA. The rebate
would be admissible to the appellant, if the
JUDGMENT
redrawn monthly invoice and the original
payment made by the appellant against the
invoice of that month matches or if the appellant
has made excess payment, the respondents were
directed to redraw the annual invoice for 2001-
2002, 2002-2003, 2003-2004, 2004-2005, 2005-
2006 and 2006-2007, as at September of each
Page 12
13
year to capture the gains to the appellant on
account of lower interest rates and gains to the
respondent on account of higher floating rate.
| her dire | ctions w |
|---|
petition was accordingly disposed of.
11. Aggrieved by the aforesaid directions, the
appellant filed Appeal No. 176 of 2011before the
APTEL. Before the APTEL, in the appeal, the
appellant raised the following issues:-
(a) Entitlement of the Appellant to Rebate.
(b) Jurisdiction of the State Commission u/s 86(1)
(f) of the Act, 2003;
JUDGMENT
(c) First in First Out method; for adjustment of
payment.
(d) Limitation, delay and laches;
(e) Bar under Order 2 Rule 2 CPC;
(f) Non filing of Annual Invoices;
(g) Determination of capital cost;
(h) Deduction on the monthly invoices;
Page 13
14
(i) Excess Claims in the monthly invoice – unjust
enrichment;
(j) Interest on Late Payments.
12. After hearing the learned counsel for the
parties, APTEL has held that under Article
10.2(a), 10.2(b)(i) and 10.2(e), the appellant is
obliged to pay full amount of the invoice within
the due date to be eligible for the rebate of 2.5%
or 1% as the case may be. Admittedly, the
appellant neither paid the full amount for every
invoice nor raised the dispute within one year.
The appellant was held to be not eligible for
JUDGMENT
rebate for reduction of the invoice funds .
13. With regard to the second issue, i.e.,
jurisdiction and scope of Section 86(1)(f) of the
Act, relying on the judgment of this Court in the
case of Gujarat Urja Vikas Nigam Ltd. Vs.
Page 14
15
1
Essar Power Ltd. , it is held that the State
Commission has the discretion to decide as to
whether the dispute should be adjudicated by
| should | be refe |
|---|
The appellant can not dictate that the State
Commission ought to have referred the dispute
to an arbitrator. It is further held that the State
Commission can adjudicate all the disputes
including the dispute on money claims between
the Licensees and the Generating Companies. In
coming to the aforesaid conclusion, APTEL relied
on its earlier order rendered in Neyveli Ignite
Corporation Vs. Tamil Nadu Electricity Board
JUDGMENT
th
in Appeal No. 49 of 2010 dated 10 September,
2010.
14. On the third issue on the method adopted by
the respondent for adjustment of the payment
made by the appellant on the “FIFO” basis, APTEL
has approved the decision of the State
1
(2008) 4 SCC 755
Page 15
16
Commission that the respondent was justified in
adopting the aforesaid method, in accordance
with Section 60 of the Indian Contract Act, 1872.
15. On the fourth issue relating to the
applicability of the limitation Act or delay and
laches, it has been held that the Limitation Act
would not apply to the proceedings under the
Electricity Act. On facts, it has been held that the
issue of limitation does not arise since Sections
60 and 61 of the Indian Contract Act would
permit the creditor to adjust the amount on
“FIFO” method. APTEL has also held that the bar
JUDGMENT
under Order 2 Rule 2 of the CPC would not be
applicable in the facts of this case. With regard
to the non-filing of the annual invoices by the
respondent, it has been held that the respondent
should have filed the annual invoices in time.
Therefore, the direction issued by the State
Commission to the respondent to redraw the
Page 16
17
annual invoices has been affirmed. The seventh
issue related to determination of capital costs,
the State Commission in its order under appeal
| ed the a | ppellant |
|---|
full as claimed by the respondent without
determining the capital costs by getting the
petition for finalization of capital costs, which was
pending in the State Commission finally
adjudicated. APTEL has approved the findings of
the State Commission that the appellant had
adopted delaying tactics by not cooperating in
the finalization of the capital costs.
JUDGMENT
16. On issue No. 9, it has been held that as the
respondent has given up the claim on account of
capital costs incurred on Gas Boosting Station
and Conditioning System and that the Power
Company has been directed to redraw the
monthly invoices by the State Commission, the
issue would not survive. Finally, on issue No. 10,
Page 17
18
which related to interest on late payments, it has
been held that the respondent company is
entitled to interest on late payment of dues
| provision | s of the |
|---|
17. The present appeal is directed against the
aforesaid directions issued by APTEL.
18. We have heard learned counsel for the
parties.
19. Mr. R.F.Nariman, learned senior counsel
appearing for the appellant has submitted that
the disputes raised in the present proceeding are
JUDGMENT
not adjudicable by the State Commission. Mr.
Nariman submitted that the primary functions of
the State Commission being advisory, regulatory
and recommendatory, the adjudication permitted
under Section 86(1)(f) is only restricted to the
disputes which are fairly relatable to the primary
functions. The cardinal issue, according to Mr.
Page 18
19
Nariman, which ought to have been decided by
the State Commission, was with regard to the
nature of a dispute. The State Commission has
| ddress th | e issue |
|---|
unconnected to advisory functions. This was
necessary as the respondent had made only a
pure money claim which could only be
adjudicated either by the Civil Court or the
Arbitral Tribunal upon a reference being made to
that effect. Mr. Nariman submits that the State
Commission illegally declined to exercise its
discretion to refer the dispute to arbitration. The
dispute between the parties being purely of civil
JUDGMENT
nature required decision on complex issues of
fact and law. Since the dispute arises out of the
working and interpretation of the PPA, the State
Commission would not have sufficient knowledge
of law to adjudicate the issues involved.
20. The next submission of Mr. Nariman is that
Page 19
20
the State Commission cannot be an adjudicatory
body, as it does not have the trappings of a
court, which is normally manned exclusively by
| Under | Section |
|---|
requirement for the Chairperson or member of
the State Commission to be a Judge of a High
Court. The Members are required to be persons
of ability, integrity and standing who have
adequate knowledge of, and have shown
capacity in dealing with problems relating to
engineering, finance, commerce, economics, law
or management. Although sub-section (2)
permits the State Commission to appoint any
JUDGMENT
person as the Chairperson from amongst person
who is or has been a Judge of a High Court, no
appointment from the aforesaid category of
persons has been made to the State Commission.
Mr. Nariman pointed out that the State
Commission which heard the petition filed by the
respondent did not have a Judicial Member. He
Page 20
21
further submits that the State Commission
functioning without a Judicial Member is contrary
to the law laid down by this Court in Union of
India vs. R.Gandhi, President, Madras Bar
2
Association . Learned senior counsel
elaborated that by virtue of Section 94(1), the
State Commission has been vested with the
power of a Civil Court under the Code of Civil
Procedure. Under sub-section (2) of Section 94,
the State Commission has the power to issue
interim orders. Section 55 provides that all
proceedings before the State Commission shall
be deemed to be judicial proceedings within
JUDGMENT
Sections 193 and 228 of the IPC. It is further
provided that appropriate commission shall be
deemed to be a civil court for the purpose of
Sections 345 and 346 of the Code of Criminal
Procedure, 1903. (2 of 1974). By virtue of Section
146, the State Commission has been empowered
2
(2010 (11) SCC 1)
Page 21
22
to impose punishment including imprisonment,
fine and additional fine. He further emphasized
that the State Commission in deciding a lis,
| the res | pondent |
|---|
discharged judicial functions and exercised
judicial power of the State. Such exercise of
judicial power can be either by the Civil Court or
a Tribunal having atleast one Judicial Member.
The State Commission exercises judicial functions
of far reaching effect, therefore, it must have
essential trappings of a court. In support of this
submission, learned senior counsel relied on
3
Kihoto Hollohan vs. Zachillhu . Subsequently,
JUDGMENT
the appellant has submitted additional written
submission which can also be appropriately
noticed at this stage. It is submitted that the
aforesaid infirmity in the constitution of the State
Commission can not be cured on the basis that
the Appellate Tribunal would always be headed
3
(1992 Supp.(2) SCC 651)
Page 22
23
by either a sitting Judge/former Judge of the
Supreme Court or Chief Justice/former Chief
Justice of a High Court as well as having other
| mbers. I | n suppo |
|---|---|
learned senior counsel relied on Institute of
Chartered Accountants of India vs.
4
L.K.Ratna & Ors. and Union Carbide
Corporation & Ors. vs. Union of India &
5
Ors. . Learned senior counsel submitted that an
adjudication of a lis by a tribunal without a
judicial member would be an anathema to
judicial process. It would directly impinge on the
impartiality and the independence of the
JUDGMENT
Judiciary. It would also undermine the principle of
separation of powers which is sought to be
strictly maintained by the Constitution of India.
Mr. Nariman emphasized that this Court carved
out an exception to the rule of necessarily having
a Judicial Member of a Tribunal, only, in the case
4
(1986 ) 4 SCC 537
5
(1991) 4 SCC 584
Page 23
24
of highly specialized fact - finding tribunals. In
the written submissions, the appellant has also
relied upon judgments of this Court in Brahm
6
Dutt vs. Union of India , S.P. Sampath
7
Kumar vs. Union of India & Ors. . It is further
submitted by Mr. Nariman that the disputes
arising between the generating company and a
licensee are decided by the Commission by
holding meetings of the Members. In case the
members of the Commission are equally divided,
the Presiding Member would have the casting
vote. Such procedure, submits Mr. R.F. Nariman,
is unknown to judicial proceedings.
JUDGMENT
21. Mr. Nariman then submitted that the
Chairman of APTEL is required under Section 113
of the Electricity Act to be a person who is or has
been a Judge of the Supreme Court or the Chief
Justice of a High Court. A person can also be
6
(2005) (2) SCC 431
7
(1987) (1) SCC 124
Page 24
25
appointed as a Member of the Appellate Tribunal
who is or has been or is qualified to be a Judge of
the High Court. This, according to him, clearly
| t the adj | udicator |
|---|
by the State Commission as well as the Appellate
Tribunal are judicial in nature and ought to be
performed only by the tribunal which has either a
Chairman or a Member(s) who are or were Judges
of the Supreme Court or a High Court. Mr.
Nariman submitted that since the State
Commission was not constituted in accordance
with law and the order having been passed
without any judicial member, is a nullity non-est
JUDGMENT
in law. He submitted that the proceedings of the
Commission are coram non judice and, therefore,
liable to be set aside.
22. The next submission of Mr. Nariman is that
the claim of the respondent would have been
held to be time barred on reference to
Page 25
26
arbitration. The respondent made a money claim
in the year 2009 for the alleged dues starting
from the year 2001 onwards. Therefore, had the
| en refer | red to a |
|---|
dispute resolution clause, contained in Article 16
of the PPA, the proceeding of the arbitral tribunal
would be governed by the Limitation Act, 1963.
The State Commission has erred in law in holding
that by virtue of Section 2(4) of the Arbitration
Act, 1996, the applicability of Section 43 would
be excluded. This, according to Mr. Nariman, is
one more reason why the State Government
ought not to have entertained the money claim
JUDGMENT
of the respondent and ought to have relegated
the parties to arbitration. In any event, the claim
of the respondent ought to have been dismissed
for delay and laches. He submits that even if the
Limitation Act was not applicable, the maximum
period of time for filing a suit, in a Civil Court,
ought to be taken as a reasonable standard by
Page 26
27
which the issues with regard to such delay and
laches can be measured. In support of this
submission learned counsel relied on the
| of this | Court in |
|---|---|
8
Bhailal Bhai & Ors. . He made a reference to
the observations made by this Court at Para 273.
Learned senior counsel also relied on Municipal
Corporation of greater Bombay vs. Bombay
9
Tyres International Ltd. & Ors. and
10
Corporation Bank & Anr. vs. Navin J. Shah .
23. Mr. Nariman then submits that the “FIFO”
method of adjustment of payment was not
JUDGMENT
available to the respondents. It is submitted that
the reliance placed on Sections 60 and 61 of the
Contract Act by the respondents is misconceived.
He submits that the respondents have wrongly
claimed that they have been adjusting the
8
(1964 (6) SCR 261
9
1998 (4) SCC 100 (at page 104 para 9)
10
2000 (2) SCC 628 (at page 635 para 12)
Page 27
28
monthly payment made by the appellant not
against the monthly invoices but against the
earlier pending bills. The respondents are also
| laiming | that the |
|---|
duly informed that the payments have been
received on “FIFO” basis. Mr. Nariman points out
that the respondents are wrongly relied on letters
th nd
dated 25 June, 2001, 2 December, 2003 and
th
10 September, 2001. According to Mr. Nariman,
none of three letters support the case of the
respondents that the appellant had either agreed
to or acquiesced in the monthly payments made
by him within 5 business days of the presentation
JUDGMENT
of the monthly invoices being adjusted on the
FIFO basis. Mr. Nariman points out that the
th
respondent’s own letter dated 20 November,
2006 demolishes the case of respondent based
on FIFO. He further submits that if the parties are
agreed to the FIFO and had been acting on the
same, as claimed by the respondents, then there
Page 28
29
would have been no need for the respondents to
th rd
write letters dated 20 November, 2006 and 23
April, 2007 regarding their objections to the
| ce made | by the |
|---|
an explanation/clarification from the appellant
with respect to the payments made by the
appellant and referred to in the said letters. The
respondent was well aware that the appellant
had been making the monthly payments against
the respective monthly invoices. Therefore, the
respondents can take no benefit of Sections 60
and 61 of the Contract Act. Therefore, the
impugned order passed by the State Commission
JUDGMENT
as well as APTEL being based on these two
sections are unsustainable.
24. It is further submitted by Mr. Nariman that
the respondents have failed to file annual
invoices at the end of each year for the years
2001-2006. The invoices for these years were
Page 29
30
th
filed only on 18 July, 2007. This is in breach of
Clause 10.2(b)(ii) of the PPA which required the
respondents to submit annual invoices setting of
| of the a | mounts |
|---|
and reconciliation of the actual amounts
receivable from the appellant for the prior year
against the sum of monthly estimated payments
made by the appellant. Similarly, if payments are
due by the respondent to the appellant, the
stated amount has to be paid to the appellant
and vice versa. The State Commission rejected
the explanation given by the respondent for
failure to submit the annual invoices, but instead
JUDGMENT
of dismissing the claim of the respondents, a
direction has been made to redraw the annual
th
invoices of each year as on 30 September of
each year. Mr. Nariman further points out that
the respondent, upon redrawal of the invoices,
had agreed to refund/adjust a sum of Rs.45
crores, being the excess amount charged by the
Page 30
31
respondent from the appellant. The said amount
has not been paid till date.
| riman po | ints out |
|---|
between the parties in the present litigation is
only with regard to the question as to whether
the appellant was entitled to avail rebate of 2.5
% on the part payment of the monthly invoice
within 5 business days from the date of the
presentation of the monthly invoice. It is
submitted that in the initial petition filed by the
State Commission it was not the claim of the
respondent that the appellant wrongly availed
JUDGMENT
rebate of 2.5%. There were no pleadings to that
effect. Therefore, the findings and conclusions of
the State Commission are liable to be set aside.
Mr. Nariman submits that if one reads the PPA as
a whole, it would become apparent that the
payment of the full invoice amount within 5 days
of the date of raising of invoice is not a pre-
Page 31
32
condition for seeking a rebate of 2.5% of the
invoice amount. Clause 10.2(a) does not make it
a pre-condition for payment of the full amount of
| thin 5 b | usiness |
|---|
the rebate of 2.5%. Clause 10.2(b)(i) indicates
that the full amount is to be paid on the due date
of an invoice. Due date is defined in Article 10.2
(a) as 30 days from the date of handing over of
the invoice. Mr. Nariman then submits that a
conjoint reading of these clauses would show
that in order to be eligible for a rebate, at the
rate of 2.5%, the payment has to be made on the
th
30 day of the presentation of the invoice.
JUDGMENT
Therefore, any payment made within 5 business
days entitled the appellant to claim 2.5% rebate
on such payment. It is further submitted by Mr.
Nariman that rebate is nothing but refund of a
part of the interest loaded upfront on the
Working Capital. The estimated monthly tariff
invoice has two components – (i) the fixed
Page 32
33
capacity charges (FCC) and (ii) variable fuel
charges (VFC). The rebate of 2.5 % is allowed in
th
view of the notification dated 30 March, 1992
| the Mini | stry of P |
|---|
India, in exercise of powers under sub-section (2)
of Section 43 of the Electricity Supply Act, 1948.
The aforesaid notification has been made part of
the PPA as Schedule U thereof. Schedule A of the
PPA deals with Tariff. Interest on the receivable
equivalent to 2 months’ average billing for sale of
electricity is loaded upfront on the monthly
invoice. Part of this is refunded by way of rebate
of 2.5 % if payment is made within 5 days and at
JUDGMENT
th
1% if it is made after 5 days but upto the 29 day
from the presentation of the monthly invoice.
th
Interest of the respondent upto the 30 day
loaded upfront in the invoice. Thereafter the
interest of the respondent is protected from the
due date till payment is made in accordance with
the Clause 10.6(e) of the PPA. Therefore, the
Page 33
34
appellant is entitled to rebate if payment is made
th
within 5 days or within 29 day of the
presentation of the invoice. Lastly, it is submitted
| ariman t | hat the |
|---|
made the payment within 5 days only to avail
rebate of 2.5%. One such payment was made,
the respondent had the use of money for a period
of 25 days and correspondingly the appellant had
been deprived of the use of such money for a
period of 25 days every month. He submits that
absent the contract between the parties, the
appellant would have made the payment only on
th
the 30 day and not within 5 days. In any event,
JUDGMENT
60 days of interest on the Working Capital had
already been loaded upfront. Only 30 days
interest was being returned in the form of rebate
on the amount paid by the appellant within 5
days. In order to make the payment within 5
days, the appellant often had to avail the loan.
Out of Rs.240 crores, which the appellant has
Page 34
35
already paid to the respondent under the Orders
of the State Commission, almost Rs.235 crores is
rebate. The respondent is now claiming more
| 0 crores | towards |
|---|
rate on Rs. 240 crores paid by the appellant,
contrary to the provisions of the PPA. On the
basis of the above, he submits that allowing the
claim of the respondent for refund of the rebate
amount would amount to unjust enrichment.
Further, the award of interest on the aforesaid
amount of rebate would amounts to double
unjust enrichment.
JUDGMENT
26. On the other hand, it is submitted by Mr.
Harish Salve and Mr. Jayant Bhushan learned
senior counsel that orders passed by the State
Commission as well as the Appellate Tribunal are
just and proper and do not call for any
interference. The appellant has been granted
instalments to make the payment of Rs. 240
Page 35
36
crores. It is also pointed out that the following
order passed by the State Commission in the
independent legal proceeding relating to fixation
| cost on | 15th July, |
|---|
th
updated upto 20 August, 2013 for invoices
th
raised till 30 June, 2011, in a gross sum of
Rs.695 crores. After giving credit of Rs.145 crores
(including interest computed at the interest rates
applicable to PPN) the net claim, subject-matter
of the present appeal, stands at Rs.550 crores.
27. With regard to the submission of the
appellant relating to Section 86(1)(f), it is
JUDGMENT
submitted that the matter is no longer res
integra as it is squarely covered by the judgment
of this Court in Gujarat Urja Vikas Nigam Ltd.
( supra). It is submitted by Mr. Salve and Mr.
Bhushan learned senior counsel appearing for the
respondent that Section 86(1)(f) gives the
discretion the State Commission either to
Page 36
37
adjudicate the disputes itself or to refer the same
to arbitration. By making detailed reference to
the findings recorded by APTEL, Mr. Salve and Mr.
| ubmit th | at all th |
|---|
appellant are without any merit as it cannot be
supported either in facts or in law.
28. It is submitted by the learned senior counsel
that even Article 16(2) provides for international
arbitration under the ICC Rules. Article 16.2(h)
specifically excludes the application of the
Arbitration and Conciliation Act of 1996 and the
Arbitration Act of 1940. Article 16.2(e) provides
JUDGMENT
that the laws of England shall govern the
arbitration agreement in contra-distinction to
Indian law applying to the PPA. In any event, the
appellant cannot be permitted to claim a
reference of arbitration as a matter of right. He
points out that at the initial stage, the appellant
only referred to the existence of an informal
Page 37
38
dispute resolution provision and provision for
arbitration under Article 16 of the PPA. Having
taken such a preliminary objection, the appellant
| to subj | ect itself |
|---|
the State Commission. In fact the entire claim of
the respondent was answered by the appellant
on merit in the written statement, filed before the
State Commission. Even if the written
submissions before the State Commission, the
appellant principally contended that the matter
ought to be referred to the adjudication by a civil
court. The appellant failed to make any
application either under Section 8 or Section 45
JUDGMENT
of the Arbitration and Conciliation Act, 1996
seeking reference to arbitration. It is further
pointed out that this Court in Gujarat Urja
Vikas Nigam Ltd. ( supra) has clearly laid down
the law that the existence of an arbitration clause
in a contract does not act as an ouster of
jurisdiction of the jurisdictional forum. The
Page 38
39
appellant having submitted to the jurisdiction of
the State Commission and having invited the
findings cannot now seek to challenge the
| on th | e grou |
|---|---|
arbitration clause. Mr. Salve and Mr. Bhushan
relied on the judgment of this Court in Svenska
Handelsbanken vs. Indian Charge Chrome
11
Ltd. and Booz Allen & Hamilton Inc. vs. SBI
12
Home Finance Ltd. . It is further submitted
that the proceeding before the State Commission
would not be vitiated on the ground that its
constitution is contrary to the ratio of law laid
down in the case of R. Gandhi (supra). The
JUDGMENT
appellant has not even raised a single ground of
any prejudice being caused by the absence of a
judicial member before the State Commission. In
any event, the aforesaid submission contradicts
the appellant’s other submission that the matter
ought to have been referred to arbitration under
11
1994 (2) SCC 155
12
2011 (5) SCC 532
Page 39
40
the Arbitration Act. There is no requirement that
the arbitrator should be a judicial person. Even in
the absence of Electricity Act, 2003 and the
| bodies | contem |
|---|
instant dispute would have been subject matter
of an arbitration proceeding as per the provision
of the PPA and not a civil suit in the civil court.
29. Answering the submission of the appellant
that the respondent has illegally adjusted the
payments on the concept of FIFO. It is submitted
that the State Commission as well as the
Appellate Tribunal have correctly held that the
JUDGMENT
procedure adopted by the respondent is covered
under Section 60 and 61 of the Contract Act. Mr.
Salve and Mr. Bhushan submit that admittedly
the appellant did not make full payment in
relation to any of the invoices. The State
Commission as well as the Appellate Tribunal
have concurrent findings that the appellant was
Page 40
41
duly notified that the payment/part payment
made were being adjusted on FIFO basis. The
appellant never refuted or rejected to such
| adopted | by th |
|---|
appellant submitted that it was undergoing
temporary financial strain. It is also pointed out
by Mr. Salve and Mr. Bhushan that the invoices
were accepted in full. The statement was made
by the appellant that part payment being made
would not prejudice the right of respondent to
receive the full payment against the invoices.
The correspondence between the parties has
been noticed by the APTEL in extenso. Coming to
JUDGMENT
the legal position, Mr. Salve and Mr. Bhushan
submit that APTEL having considered the
statutory provisions as well as judicial precedents
have come to the conclusion that the appellant
was duly intimated that the payment made would
be applied by the respondents on FIFO basis.
Therefore, Section 59 of the Indian Contract Act
Page 41
42
would not be applicable. On the issue of
limitation, it is submitted that neither the
Limitation Act nor the principle of delay and
| uld appl | y to the |
|---|
submitted by Mr. Salve and Mr. Bhushan that the
provision of Limitation Act, 1963 would not be
applicable to the proceedings before the State
Commission. The Electricity Act, 2003 being a
complete code, which is self contained and
comprehensive, the provision of Limitation Act,
1963 would not apply. Mr. Salve and Mr. Bhushan
relied on the Consolidated Engineering
Enterprises Vs. Principal Secretary,
JUDGMENT
13
Irrigation Department & Ors. In support of
this submission, the Limitation Act would be
inapplicable to Tribunals and quasi-judicial
authorities. Replying to the submission of Mr.
Nariman that in arbitration proceedings, the
appellant would be entitled to the benefit of
13
(2008) 7 SCC 169
Page 42
43
Limitation Act, 1963, Mr. Salve and Mr.
Bhushan submit that in view of the specific
provisions contained in Section 2(4) of the
| and Con | ciliation |
|---|
of the Arbitration Act would not be applicable. In
any event, the matter is squarely covered by the
judgment in Gujarat Urja (supra) . Mr. Salve
and Mr. Bhushan reiterated that the issue of
limitation does not even arise in the present
dispute due to the FIFO adjustment effected by
the respondent.
30. Addressing the issue of the rebate being
JUDGMENT
available to the appellant, Mr. Salve and Mr.
Bhushan submit that APTEL has rendered
detailed findings on the issue. The submissions
made before this Court is a repetition of the
submissions made before the APTEL. They
submit that such findings recorded by the APTEL
can not be reopened in this Court except on the
Page 43
44
ground that such findings are either arbitrary or
based on no evidence. In fact, the appellant has
illegally arrogated to itself the right to adjudicate,
| rally ass | uming r |
|---|
available to it. Rather than complying with the
requirements of the PPA of making payment
within due date, the appellant had disallowed
certain payments on the ground that the claims
of the appellant were doubted. These actions of
the appellant were contrary to Articles 10.3 and
10.4 of the PPA which deals with Letter of Credit
and Escrow. Even if the claim of the appellant is
accepted that the invoices were only based on
JUDGMENT
the estimates the appellant had no authority of
making unilateral deductions in the monthly
invoices and make only ad-hoc payments
contrary to the provisions of PPA. It is submitted
that the monthly invoices consists of both actual
as also estimates in respect of certain items. The
annual invoices raised on the basis of a
Page 44
45
reconciliation at the end of the year, since
actuals become known in respect of such
portions of monthly invoices, which were
| on the | basis of |
|---|
Salve and Mr. Bhushan then submit that interest
on late payments have been rightly granted both
by the State Commission as well as the APTEL.
The interest has been calculated on the basis of
Article 10.6 of the PPA. Since the loans taken by
the respondent are payable at compounded
interest rates, the later payment interest payable
by the appellant would also be at the
compounded interest rate as per Article 10.6 of
JUDGMENT
the PPA. Mr. Salve and Mr. Bhushan relied on the
judgment of this Court in Central Bank of India
14
Vs. Ravindra & Ors. and Indian Council for
15
Legal Action Vs. Union of India
31. During the course of hearing, the appellant
14
(2002) 1 SCC 367
15
(2011) 8 SCC 161
Page 45
46
had taken out I.A. No. 5 of 2013 and I.A. No. 6 of
2013. I.A. No. 6 is for the impleadment and I.A.
No. 5 is for the direction.
| I.A. Nos. 5 and 6 of 2013<br>32. It is submitted by Mr. Sa<br>that in I.A. No. 6, the ap<br>prayer to implead IOCL as t<br>application can not be allow<br>party to the contract. The<br>third party is only an e<br>proceedings by the appellan |
that IOCL is either necessary or a proper party for
JUDGMENT
adjudication of the disputes arising between the
appellant and the respondents.
33. I.A. No. 5 of 2013, according to Mr. Salve and
Mr. Bhushan has been filed with the sole object of
avoiding payments. The appellant has made wild
allegations of fraud without any foundational
Page 46
47
facts being pleaded either before the State
Commission or before the APTEL. The appellant
ought not to be permitted to resolve such
| The appli | cation a |
|---|
and Mr. Bhushan deserves to be dismissed.
34. We have considered the submissions made
by the learned counsel for the parties. In our
opinion, the issues raised by the appellant with
regard to the constitution of the State
Commission and its discretion to either
adjudicate or refer a particular dispute to
arbitration is no longer res integra . Therefore,
JUDGMENT
even though, Mr. Nariman has very forcefully
contended that the issue ought to be
reconsidered, we are not inclined to adopt such a
course. In our opinion, this Court has
comprehensively addressed all the issues, on the
scope and ambit of Section 86 in general and
Section 86(1)(f) in particular of the Act. We are
Page 47
48
also not inclined to accept the submission that
since the appellant had made a request for a
reference of the dispute to arbitration, the State
| n ought | to have |
|---|
We are also not able to accept the submission of
Mr. Nariman that the State Commission was
dealing with only a pure and simple money claim.
We also do not find much substance in the
submission that the issues having been raised
being complex and intricate ought to have been
left to be decided either by the Arbitral Tribunal
or by the Civil Court. APTEL in the impugned
order, in our opinion, has correctly culled out the
JUDGMENT
ratio of the judgment of this Court in Gujarat
Urja (supra) . It is also correctly held that the
appellant can not dictate that the State
Commission ought to have referred the dispute
to arbitration.
35. In the aforesaid judgment, the question that
Page 48
49
arose before this Court was whether the
application for appointment of an arbitrator
under Section 11 of the Arbitration and
| n Act, 1 | 996 was |
|---|
of the statutory provisions contained in the
Electricity Act, 2003.
36. It was submitted on behalf of the appellant
(licensee) that by Virtue of Section 86(1)(f) of the
Act of 2003, the dispute between the licensees
and the generating companies can only be
adjudicated upon by the State Commission either
by itself or by an arbitrator to whom the
JUDGMENT
Commission refers the dispute. Therefore, the
High Court had no jurisdiction under Section
11(6) to refer the dispute between the licensees
and the generating company to an arbitrator,
since such power of adjudication of reference has
been specifically vested in the State Commission.
Since the Electricity Act is a special law, dealing
Page 49
50
with arbitrations of dispute between the
licensees and the generating companies, the
provision of Section 11 of the Arbitration and
| n Act wo | uld be i |
|---|
Court has, therefore, committed an error of
jurisdiction in allowing the application under
Section 11(6) and referring the matter to
arbitration to a Former Chief Justice of India. On
the other hand, it was submitted on behalf of the
generating companies that the provisions of the
Electricity Act are in addition to and not in
derogation of any other law for the time being in
force. The provisions contained in Sections 173
JUDGMENT
and 174 would not affect the applicability of the
Arbitration Act, 1996, in view of the provisions
contained in Section 175 of the Electricity Act.
Upon consideration of the aforesaid submission,
this Court has held as follows:-
“26. It may be noted that Section 86(1)( f ) of the
Act of 2003 is a special provision for adjudication
Page 50
51
| and<br>means | “to ref<br>“or”. It |
|---|
27. In our opinion in Section 86(1)( f ) of the
Electricity Act, 2003 the word “and” between the
words “generating companies” and the words
“refer any dispute” means “or”, otherwise it will
lead to an anomalous situation because obviously
the State Commission cannot both decide a
dispute itself and also refer it to some arbitrator.
Hence the word “and” in Section 86(1)( f ) means
“or”.
28. Section 86(1)( f ) is a special provision and
hence will override the general provision in
Section 11 of the Arbitration and Conciliation Act,
1996 for arbitration of disputes between the
licensee and generating companies. It is well
settled that the special law overrides the general
law. Hence, in our opinion, Section 11 of the
Arbitration and Conciliation Act, 1996 has no
application to the question who can
adjudicate/arbitrate disputes between licensees
and generating companies, and only Section 86(1)
( f ) shall apply in such a situation .
JUDGMENT
37. This Court also negated the submission that
Page 51
52
the provision contained in Section 86(1)(f) would
be violative of Article 14 (See Para 30-31).
| ering t | he prov |
|---|
Sections 173, 174 and 175 of the Electricity Act,
this Court observed that since Section 86(1)(f)
provides a special manner of making reference to
an arbitrator in disputes between a licensee and
a generating company, by implication all other
methods are barred. Considering the
applicability of Sections 174 and 175, this Court
has held that Section 174 would prevail over
Section 175 in matters where the where there is
JUDGMENT
any conflict (but no further). In our opinion, the
observations made by this Court in Paragraphs
59 and 60 are a complete answer to the
submissions of Mr. Nariman that upon an
application being made, the State Commission
was bound to refer the matter to arbitration.
Page 52
53
39. Section 86(1)(f) specifically confers
jurisdiction on the State Commission to refer the
dispute. Undoubtedly, the Commission is
| exercis | e its disc |
|---|
not arbitrarily. In the present case, the State
Commission upon consideration of the entire
matter has exercised its discretion. However, in
our opinion, the APTEL ought not to have brushed
aside the submissions of the appellant with the
observation that the State Commission having
exercised its discretion, the issue need not be
investigated by the APTEL. It would always be
open to APTEL to examine as to whether the
JUDGMENT
State Commission has exercised the discretion
with regard to the question whether the dispute
ought to have been referred to arbitration, in
accordance with the well known norms for
exercising such discretion. APTEL exercises
jurisdiction over the State Commission by way of
a First Appeal. Therefore, it is the bounden duty
Page 53
54
of the Appellate Tribunal to examine as to
whether all the decisions rendered by the State
Commission suffer from the vice of arbitrariness,
| bleness | or perve |
|---|
apart from examining as to whether the State
Commission has exercised powers in accordance
with the statutory provisions contained in
Electricity Act, 2003. Having said this, we are not
inclined to interfere with the conclusions reached
by APTEL, as in our opinion, the jurisdiction has
not been exercised by the State Commission
arbitrarily, whimsically or against the statutory
provisions.
JUDGMENT
40. We, however, find substance in the
submission of Mr. Nariman that adjudicatory
functions generally ought not to be conducted by
the State Commission in the absence of a Judicial
Member. Especially in relation to disputes which
are not fairly relative to tariff fixation or the
Page 54
55
advisory and recommendatory functions of the
State Commission.
| titution | Bench o |
|---|
Hollohan (supra) has examined the nature of
the power of the Speaker or the Chairman under
paragraph 6(1) of the Tenth Schedule of the
Constitution of India which contains “PROVISIONS
AS TO DISQUALIFICATION ON GROUND OF
DEFECTION” of a Member of either House of
Parliament. Upon consideration of the entire
matter, it was observed as follows :
“95. In the present case, the power to
decide disputed disqualification under
Paragraph 6(1) is pre-eminently of a judicial
complexion.”
JUDGMENT
42. The Constitution Bench relied on the earlier
judgment of this Court in Harinagar Sugar Mills Ltd.
16
vs. Shyam Sundar Jhunjhunwala . In that case,
16
1962 (2) SCR 339
Page 55
56
Hidayatullah, J. said
| s arisin<br>g the | g under<br>powers |
|---|
JUDGMENT
Again in para 99, it is observed as follows :
“99 . Where there is a lis — an affirmation
by one party and denial by another — and
the dispute necessarily involves a decision on
the rights and obligations of the parties to it
and the authority is called upon to decide it,
there is an exercise of judicial power. That
authority is called a Tribunal, if it does not
have all the trappings of a Court. In
Page 56
57
Associated Cement Companies Ltd. v. P.N.
36
Sharma this Court said: (SCR pp. 386-87)
| as been<br>can be d<br>herent | confer<br>escribe<br>power |
|---|
43. In view of the aforesaid categorical statement of
law, we would accept the submission of Mr. Nariman
JUDGMENT
that the tribunal such as the State Commission in
deciding a lis, between the appellant and the
respondent discharges judicial functions and exercises
judicial power to the State. It exercises judicial
functions of far reaching effect. Therefore, in our
opinion, Mr. Nariman is correct in his submission
that it must have essential trapping of the court. This
Page 57
58
can only be achieved by the presence of one or more
judicial members in the State Commission which is
called upon to decide complicated contractual or civil
| uld norm | ally hav |
|---|
Civil Court. Not only the decisions of the State
Commission have far reaching consequences, they are
final and binding between the parties, subject, of
course, to judicial review.
44. As noticed earlier, Section 84(2) enables the State
Government to appoint any person as the Chairperson
from amongst persons who is, or has been, a Judge of a
High Court. Such appointment shall be made after
JUDGMENT
consultation with the Chief Justice of the High Court.
The provision contained in Section 84(2) is
notwithstanding the provision contained in Section
84(1). In our opinion, the State Government ought to
have exercised its power under sub-section (2) to
appoint one or more Judicial Members on the State
Commission especially when complicated issues are
Page 58
59
raised involving essentially civil and contractual
matters. A Constitution Bench of this Court in the case
of R.Gandhi (supra) recognized that :
| that the<br>ibunals | legislatu<br>with refe |
|---|
“90. But when we say that the legislature has
the competence to make laws, providing
which disputes will be decided by courts, and
which disputes will be decided by tribunals, it
is subject to constitutional limitations,
without encroaching upon the independence
of the judiciary and keeping in view the
principles of the rule of law and separation of
powers. If tribunals are to be vested with
judicial power hitherto vested in or exercised
by courts, such tribunals should possess the
independence, security and capacity
associated with courts. If the tribunals are
intended to serve an area which requires
specialised knowledge or expertise, no doubt
there can be technical members in addition
to judicial members………….”
JUDGMENT
45. Keeping in view the aforesaid observations of this
Court, in our opinion, the State of Tamil Nadu ought to
Page 59
60
make necessary appointments in terms of Section 84(2)
of the Act. We have been informed that till date no
judicial Member has been appointed in the Tamil Nadu
| on. We | are of |
|---|
matter needs to be considered, with some urgency, by
the appropriate State authorities about the desirability
and feasibility for making appointments, of any person,
as the Chairperson from amongst persons who is, or
has been, a Judge of a High Court.
46. We have noticed earlier that Section 113 of the Act
mandates that the Chairman of APTEL shall be a person
who is or has been a Judge of the Supreme Court or the
JUDGMENT
Chief Justice of a High Court. A person can be appointed
as the Member of the Appellate Tribunal who is or has
been or is qualified to be a Judge of a High Court. This
would clearly show that the legislature was aware that
the functions performed by the State Commission as
well as the Appellate Tribunal are judicial in nature.
Necessary provision has been made in Section 113 to
Page 60
61
ensure that the APTEL has the trapping of a court. This
essential feature has not been made mandatory under
Section 84 although provision has been made in Section
| ment of | any pers |
|---|
from amongst persons who is or has been a Judge of a
High Court. In our opinion, it would be advisable for the
State Government to exercise the enabling power
under Section 84(2) to make appointment of a person
who is or has been a Judge of a High Court as
Chairperson of the State Commission.
47. These observations, however, do not in any manner
affect the jurisdiction exercised by the State
JUDGMENT
Commission in the present matter. It has been rightly
pointed out by the respondent that having filed the
written statement in reply to the petition filed by the
respondent, the appellant willingly participated in the
proceedings and invited the findings recorded by the
State Commission. It would be too late in the day, to
interfere with the jurisdiction exercised by the State
Page 61
62
Commission in these proceedings.
48. The next submission of Mr. Nariman is that the
| pondents | would |
|---|
time barred on reference to arbitration. We are not able
to accept the aforesaid submission of Mr. Nariman. On
the facts of this case, in our opinion, the principle of
delay and laches would not apply, by virtue of the
adjustment of payments being made on FIFO basis.
The procedure adopted by the respondent, as observed
by the State Commission as well as by the APTEL,
would be covered under Sections 60 and 61 of the
Contract Act. APTEL, upon a detailed consideration of
JUDGMENT
the correspondence between the parties, has confirmed
the findings of fact recorded by the State Commission
that the appellant had been only making part payment
of the invoices. During the course of the hearing, Mr.
Salve has pointed out that the payment of entire
invoices was to be made each time which was never
adhered to by the appellant. Therefore, the
Page 62
63
respondents were constrained to adopt FIFO method.
Learned senior counsel also pointed out that there was
no complaint or objection ever raised by the appellant.
| to the | metho |
|---|
respondents on the method of FIFO, was only raised in
the counter affidavit to the petition filed by the
appellant before the State Commission. According to
learned senior counsel, the plea is an afterthought and
has been rightly rejected by the State Commission as
well as the APTEL. We also have no hesitation in
rejecting the submission of Mr. Nariman on this issue. In
any event, the Limitation Act is inapplicable to
proceeding before the State Commission.
JUDGMENT
49. The submission of the appellant that the Limitation
Act would be available in case the reference was to be
made to arbitration, in our opinion, is also without
merit. Firstly, the State Commission exercised its
jurisdiction to decide the dispute itself. The matter was
not referred to arbitration, therefore, the Limitation act
Page 63
64
would not be applicable. Secondly, Section 43 of the
Arbitration and Conciliation Act would not be applicable
even if the matter was referred to arbitration by virtue
| the Arbi | tration A |
|---|
of the Arbitration Act reads as under :
“This part except sub-section (1) of section
40, sections 41 and 43 shall apply to every
arbitration under any other enactment for the
time being in force, as if the arbitration were
pursuant to an arbitration agreement and as
if that other enactment were an arbitration
agreement, except in so far as the provisions
of this Part are inconsistent with that other
enactment or with any rules made
thereunder.”
50. By virtue of the aforesaid provision, the provision
with regard to the Limitation Act under Section 43
JUDGMENT
would not be applicable, to statutory arbitrations
conducted under the Electricity Act, 2003. We are
unable to accept the submission of Mr. Nariman that
the State Commission failed to exercise its discretion by
not making a reference to arbitration and the request
made by the appellant. Such a submission cannot be
countenanced in the particular facts of this case.
Page 64
65
Having taken the plea that the matter ought to be
referred to arbitration, the appellant chose to contest
the claim of the respondent on merits and filed the
| nt before | the St |
|---|
only this, the appellant participated in the entire
proceedings and invited the findings on merits.
Therefore, the appellant cannot now be permitted to
raise such a plea. This view of ours will find support in
two earlier judgments of this Court. In Svenska
Handelsbanken (supra) it has been observed as
follows:
“53. It may be that even after entering into
an arbitration clause any party may institute
legal proceedings. It is for the other party to
seek stay of the suit by showing the
arbitration clause and satisfying the terms of
the provisions of law empowering the court to
stay the suit……..”
JUDGMENT
Admittedly, in this case the appellant did not file
any application under Section 8 or Section 45 of the
Arbitration Act, 1996. No prayer for stay of the
proceedings was filed.
Page 65
66
51. In the case of Booz Allen & Hamilton Inc. (supra)
this Court observed a follows:
| gh Secti<br>mit for fil | on 8 do<br>ing an a |
|---|
on the substance of the
dispute, the scheme of the Act and the
provisions of the section clearly indicate that
the application thereunder should be made at
the earliest. Obviously, a party who willingly
participates in the proceedings in the suit and
subjects himself to the jurisdiction of the
court cannot subsequently turn around and
say that the parties should be referred to
arbitration in view of the existence of an
arbitration agreement. Whether a party has
waived his right to seek arbitration and
subjected himself to the jurisdiction of the
court, depends upon the conduct of such
party in the suit.”
JUDGMENT
These observations are squarely applicable to the
facts in this case.
52. Even if the reference had been made under
Article 16 of the PPA, the applicability of the Arbitration
Act, 1996 and the Arbitration Act of 1940 have been
specifically excepted under Article 16(2)(h). In the
Page 66
67
earlier part of the judgment, we have noticed that
Article 16 indeed provides for informal resolution of
disputes by way of arbitration. However, Article 16(2)
| the arbit | ration s |
|---|
accordance with the ICC Rules. Under those rules, ICC
Court of arbitration is to make the appointment of the
Arbitral Tribunal. To make the matters worst for the
appellant, it has been provided in Article 16.2(e) that
the seat of the arbitration shall be in London. This fact
alone would make Part I of the Arbitration Act, 1996
inapplicable to the arbitration proceedings. There is a
further provision that notwithstanding Article 17(8), the
laws of England shall govern the validity, interpretation,
JUDGMENT
construction, performance and the enforcement of the
provision contained in Article 16(2). Clearly then, the
applicability of Arbitration Act, 1996 is totally ruled out
by the parties. This Court in Bhatia International vs.
17
Bulk Trading S.A. & Anr . has clearly held that the
parties are at liberty by agreement to opt out of any or
17
2002 (4) SCC 105
Page 67
68
all the provisions of 1996 Act. It would be useful to
make a reference to the observations made by this
Court in paragraph 21 and 32 which are as follows:
| gislature<br>f Part I w | is emp<br>ould app |
|---|
JUDGMENT
“32. To conclude, we hold that the provisions
of Part I would apply to all arbitrations and to
Page 68
69
| held ou<br>ld apply | t of Ind<br>unless |
|---|
The aforesaid observations will be fully applicable
to the facts and circumstances of this case as the
th
agreement is prior to 6 September, 2012. The
declaration of law in Bharat Aluminium Company vs.
18
Kaisar Aluminium Technical Services Inc. that
JUDGMENT
Part I of the arbitration would not be applicable to
International Commercial Arbitration outside India
applies to the Arbitration Agreements executed after
th
6 September, 2012. Though by virtue of the provisions
contained in Article 16 of the PPA, the legal effect
remains the same, that is applicability of 1996 Act is
18
2012 (9) SCC 552
Page 69
70
ruled out, therefore, the appellant cannot claim the
benefit of Section 43 of the Arbitration Act, 1996.
| not find | any mer |
|---|
Mr. Nariman that the appellants have wrongly adopted
the system of FIFO for adjustment of the payments
made by the appellant. The State Commission as well
as the APTEL having considered the matter in detail, we
are inclined to accept the submission of Mr. Salve and
Mr. Bhushan that it would not be appropriate to re-
examine the issue in these proceedings. Under Section
125 of the Electricity Act, 2003, the appeal lies in the
Supreme Court on any one or more of the grounds
JUDGMENT
specified in Section 100 of the Code of Civil Procedure,
1908. Therefore, unless the court is satisfied that the
findings of fact recorded by the State Commission are
perverse, irrational and based on no evidence, it would
not interfere. The findings recorded by the State
Commission and APTEL would not give rise to a
substantial question of law. In any event, the appellant
Page 70
71
never refuted or rejected the practice adopted by the
respondent. Rather the appellant claimed that it was
under temporary financial strain and, therefore,
| ake only | part p |
|---|
having been accepted in full, the appellant unilaterally
withheld some of the payments on the ground that the
claims were disputed. Under Article 10 of the PPA, the
appellant was required to make the payment for the
entire invoice and, thereafter, raise the dispute. The
appellant had been duly informed that the part
payments made would be adjusted by the respondents
under the FIFO system. It has been correctly held that
in such circumstances, Section 59 of the Contract Act
JUDGMENT
would not be applicable. We see no reason to interfere
with the conclusions reached by the APTEL.
54. The real dispute between the parties seems to be
on the question whether the appellant was entitled to
avail 2.5% rebate on part payment of the monthly
invoices within 5 business days. We have noticed
Page 71
72
earlier that it was a pre- condition under Article 10 that
the payment of the monthly invoice had to be made in
full. In addressing the issue of rebate, APTEL has come
| on that | merely |
|---|
payment had been made in relation to monthly invoices
would not entitle the appellant to claim the rebate of
2.5% on the invoice amount. We see no reason to
interfere with the findings recorded by the APTEL.
Under Article 10.2(b)(i), the payments have to be made
in full for every invoice by due date. Under Article
10.2(e), the payment had to be made in full when due
even if the entire portion or a portion of the invoice is
disputed. Under Article 10.3(a) to (c) of the PPA, Letter
JUDGMENT
of Credit is to be established covering three months
estimated billing, one month prior to Commercial
Operation Date. Under Article 10.3 (d) of the PPA, an
Escrow Account is to be established by the appellant in
favour of the Power Company into which collections
from designated circles are to flow in and be available
as collateral security. Under Article 10.4, the
Page 72
73
Government of Tamil Nadu has guaranteed all of the
financial obligations of the appellant. Under Article 10.2
(e) of the PPA agreement, the right to dispute any
| pellant i | s limited |
|---|
date of such invoice. Thus it would be evident that even
if the amount of invoice is disputed, the appellant is
obliged to make full payments of the invoice when due
and then raise the dispute. Undoubtedly, early payment
is encouraged by offering rebate of 2.5% if paid within
5 days of the date of the invoice. Similarly, 1% rebate
would be available if the payment of the entire invoice
is made within 30 days . The rebate is in the form of
incentive and is an exception to the general rule
JUDGMENT
requiring payment in full on due date. Therefore, in our
opinion, the appellant had no legal right to claim rebate
at the rate of 2.5% not having paid the entire invoice
amount within 5 days . Similarly, the appellant would be
entitled to 1% rebate if payment is made within 30 days
of the invoice. We are of the opinion that the findings of
APTEL on this issue do not call for any interference.
Page 73
74
55. In fact, in our opinion, the appellant has illegally
arrogated to itself the right to adjudicate by unilaterally
| risdictio | n not a |
|---|
required to comply with Article 10 of the PPA which
provides for Compensation Payment and Billing. We are
also not able to accept the submission of Mr. Nariman
that invoices could not be paid in full as they were only
estimated invoices. It is true that reconciliation is to be
done annually but the payment is to be made on
monthly basis. This cannot even be disputed by the
appellant in the face of its claim for rebate at the rate
of 2.5% for having made part payment of the invoice
JUDGMENT
amount within 5 days . We also do not find any merit in
the submission that any prejudice has been caused to
the appellant by the delayed submission of annual
invoice by the respondents. Pursuant to the directions
issued by the State Commission, the monthly invoice
and annual invoice for the respective years have been
th
redrawn as on 30 September each year. Therefore, the
Page 74
75
benefit of interest has been given on such annual
invoices. With regard to the issue raised about the
interest on late payment, APTEL has considered the
| d come t | o the co |
|---|---|
is payable on compound rate basis in terms of Article
10.6 of the PPA. In coming to the aforesaid conclusion,
APTEL has relied on a judgment of this Court in Central
19
Bank of India vs. Ravindra & Ors. . In this
judgment it has been held as follows:
“………The essence of interest in the opinion
of Lord Wright, in Riches v. Westminster
Bank Ltd. All ER at p. 472 is that it is a
payment which becomes due because the
creditor has not had his money at the due
date. It may be regarded either as
representing the profit he might have made if
he had had the use of the money, or,
conversely, the loss he suffered because he
had not that use. The general idea is that he
is entitled to compensation for the
deprivation; the money due to the creditor
was not paid, or, in other words, was withheld
from him by the debtor after the time when
payment should have been made, in breach
of his legal rights, and interest was a
compensation whether the compensation was
liquidated under an agreement or statute. A
Division Bench of the High Court of Punjab
JUDGMENT
19
2002 (1) SCC 367
Page 75
76
| ms is the<br>or reten | return<br>tion by |
|---|
56. Similar observations have been made by this Court
JUDGMENT
in Indian Council of Enviro-Legal Action vs. Union
20
of India & Ors. wherein it has been held as follows:
“178. To do complete justice, prevent
wrongs, remove incentive for wrongdoing or
delay, and to implement in practical terms
the concepts of time value of money,
restitution and unjust enrichment noted
above—or to simply levelise—a convenient
20
2011 (8) SCC 161
Page 76
77
approach is calculating interest. But here
interest has to be calculated on compound
basis—and not simple—for the latter leaves
much uncalled for benefits in the hands of
the wrongdoer.
| her, a re<br>kept in<br>interest | lated co<br>mind an<br>takes i |
|---|
180. Some of our statute law provide only
for simple interest and not compound
interest. In those situations, the courts are
helpless and it is a matter of law reform
which the Law Commission must take note
and more so, because the serious effect it
has on the administration of justice. However,
the power of the Court to order
compound interest by way of restitution is
not fettered in any way. We request the Law
Commission to consider and recommend
necessary amendments in relevant laws.”
JUDGMENT
57. The late payment clause only captures the
principle that a person denied the benefit of money,
that ought to have been paid on due dates should get
compensated on the same basis as his bank would
charge him for funds lent together with a deterrent of
0.5% in order to prevent delays. It is submitted by Mr.
Page 77
78
Salve and Mr. Bhushan that bankers of the respondents
have applied quarterly compounding or monthly
compounding for cash credits during different periods
| RBI norm | s. Articl |
|---|
followed the norms of the bank. This can not be said to
be unfair as the same principle would also apply to the
appellants.
58. This now bring us to applications for impleadment
of IOCL and for direction. I.A.No.6 of 2013 is for the
impleadment of IOCL. It is submitted that during the
pendency of these proceedings, the respondents have
received rebates, discounts, credits, refunds in the fuel
JUDGMENT
price being extended by fuel supplier i.e. Indian Oil
Corporation Ltd. (IOCL). Such benefits have been
received by the respondent from January 2001 till date
It is pleaded that the respondents have failed to give
details about the discounts and credits received the
benefit of which ought to have been passed on to the
appellant. Therefore, IOCL be made parties to
Page 78
79
respondent No.2 to the present appeal. I.A.No.5 of 2013
seeks direction to IOCL to furnish details of all the
documents of the matter. Further directions are also
| esponden | t to ref |
|---|
crores paid by the appellant under the order passed by
the State Commission along with interest at the rate as
mentioned in PPA.
59. The respondents in a common counter statement to
the applications have submitted that the applications
are not maintainable. The applications have been
evidently preferred purely as dilatory tactics, to delay
and deny substantial payments that are due and
JUDGMENT
payable to the respondent pursuant to the orders
passed by the State Commission which have been
upheld by APTEL. We are not inclined to entertain either
of the applications at this stage. The issue sought to be
raised in both the applications ought to have been
raised by the appellant at the relevant time. The
applications are, therefore, accordingly dismissed.
Page 79
80
60. For the foregoing reasons, we see no merit in the
appeal and the same is accordingly dismissed.
…………………………….J.
[Surinder Singh Nijjar]
……………………………J.
[A.K.Sikri]
New Delhi;
April 04, 2014.
JUDGMENT
Page 80