Full Judgment Text
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on March 03, 2015
Judgment delivered on March 10, 2015
+ O.M.P. 280/2012
RELIANCE BROADCAST NETWORK LIMITED
..... Petitioner
Through: Mr.K. Datta, Advocate with
Mr.Ashish Verma and
Mr.Rahul Malhotra,
Advocates
Versus
BROADCAST ENGINEERING AND CONSULTANTS
INDIA LTD AND ANOTHER ..... Respondent
Through: Mr.Rajeev Sharma, Adv. &
Mr.R.Gogna, CGSC along
with Mr.Vipul,
Ms.L.Gangmei, Ms.Tanisha,
Advs. for Ministry of
Information & Broadcasting
(UOI)
+ O.M.P. 273/2012
RADIO ONE LIMITED ..... Petitioner
Through: Mr.Rajiv Nayar, Sr.
Advocate with Mr.Kirat
Singh Nagra and
Mr.Kartik Yadav, Advocates
Versus
BROADCAST ENGINEERING CONSULTANTS INDIA
LTD ..... Respondent
Through: Mr.Rajeev Sharma, Adv.
with Ms.Radha Lakhmi R.,
OMP 280/2012 & connected petitions Page 1 of 50
Adv. for R-1
Mr.R.Gogna, CGSC along
with Mr.Vipul,
Ms.L.Gangmei, Ms.Tanisha,
Advs. for Ministry of
Broadcasting (UOI)
+ O.M.P. 287/2012
MALAR PUBLICATIONS LTD ..... Petitioner
Through: Mr.Abhishek Malhotra,
Mr.Debashis Mukherjee,
Adv.
Versus
BROADCAST ENGINEERING AND CONSULTANTS
INDIA LIMITED & ANR ..... Respondent
Through: Mr.Rajeev Sharma, Adv. &
Mr.Vivek Goyal, CGSC with
Mr.M.Tapan Sharma, Adv.
for UOI/R2
+ O.M.P. 295/2012
PURAN MULTIMEDIA LTD ..... Petitioner
Through: Mr.K. Datta, Advocate with
Mr.Ashish Verma and
Mr.Rahul Malhotra,
Advocates
Versus
BROADCAST ENGINEERING AND CONSULTANTS &
ANR ..... Respondent
Through: Mr.Rajeev Sharma, Adv.
with Ms.Radha Lakshmi R.,
Adv. for respondent No.1
Mr.R.Gogna, CGSC along
with Mr.Vipul,
OMP 280/2012 & connected petitions Page 2 of 50
Ms.L.Gangmei, Ms.Tanisha,
Advs. for Ministry of
Information & Broadcasting
(UOI)
Judgment reserved on March 05, 2015
Judgment delivered on March 10, 2015
+ O.M.P. 291/2012
DHAMAAL 24 RADIO NETWORK LTD. ..... Petitioner
Through: Mr.Abhishek Malhotra, Adv. with
Mr.Nitin Bhatia, Adv.
Versus
PRASAR BHARTI ..... Respondent
Through: Mr.Rajeev Sharma, Adv.
+ O.M.P. 294/2012
DHAMAAL 24 RADIO NETWORK LTD. ..... Petitioner
Through: Mr.Abhishek Malhotra, Adv. with
Mr.Nitin Bhatia, Adv.
Versus
BROADCAST ENGINEERING AND CONSULTANTS INDIA
LTD. AND ANR ..... Respondent
Through: Mr.Rajeev Sharma, Adv.
CORAM:
HON'BLE MR. JUSTICE V.KAMESWAR RAO
V.KAMESWAR RAO, J.
1. This batch of petitions have been filed under Section 9 of the
Arbitration and Conciliation Act, 1996 (Act, in short), inter alia,
OMP 280/2012 & connected petitions Page 3 of 50
claiming a common interim measure in the nature of direction to the
Broadcasting Engineering and Consultants India Ltd. (BECIL, in
short)/Prasar Bharti to issue No-Objection Certificate to them, or a
direction for giving permission, to enable them to apply for migration to
Phase III in terms of FM Radio Policy dated July 25, 2011. Since the
issue(s) which arise(s) for consideration in this batch of petitions is
identical, they are being disposed of by this common order.
FACTS:
2. All the petitioners herein operate FM Radio Stations in different
cities of the country under FM Radio (Phase II) policy of Ministry of
Information and Broadcasting (MIB, in short) dated July 13, 2005.
Before Phase II policy was framed, there was a Phase I policy. Under
the Phase II policy, the case of a new entrant was also considered. The
policy stipulated a process of granting permission by issuance of a
Letter of Intent to enable the company to obtain frequency allocation,
SACFA clearance, achieve financial closure, and appoint all key
executives, enter into an agreement with DD/AIR/BECIL and deposit
the requisite amount towards land/tower lease rent, Common
Transmission Infrastructure (CTI, in short) etc. and comply with the
requisite conditions of eligibility for signing the “Grant of Permission
OMP 280/2012 & connected petitions Page 4 of 50
Agreement” (GOPA). The “grant of permission agreement” was
executed between the MIB and the petitioners herein on different dates.
The policy also contemplated mandatory for all Phase II operators to co-
locate transmission facilities in all the 91 cities on terms and conditions
to be prescribed separately. Out of 91 cities, in 84 cities, the facilities
had to be co-located on existing AIR/DD towers, while in remaining 7,
the policy contemplated new towers to be got constructed by the MIB
through BECIL. The new towers were to be constructed at Chennai,
Delhi, Kolkata, Mumbai, Bangalore, Hyderabad and Jaipur.
3. Pending creation of co-location, facility by BECIL, the successful
bidders in the 7 cities were permitted to operationalize their channels on
individual basis for a period of two years or till the co-location facility is
commissioned, whichever is later, at the end of which, they were to shift
their operations to new facilities. Permission to run individual channel
were to be granted to each successful bidder only after it had entered
into an agreement with BECIL and made full payment towards its share
in the common infrastructure. The BECIL acted as a system integrator
for providing a common transmission infrastructure to enable the
petitioners herein to obtain SACFA clearance and frequency allocation
etc. The petitioners herein entered into „project management
OMP 280/2012 & connected petitions Page 5 of 50
agreements‟ (PMA) with the BECIL on different dates, the details of
which shall be given in the judgment later.
4. The PMA was primarily to provide project management services,
to build, install, commission and completion of the common
transmission infrastructure. The PMA contemplated payment of fee to
BECIL for providing project management services. The common
transmission infrastructure in terms of Annexure I included the
following:
Antenna system; RF Feeder cable and accessories; combiners; Antenna
switch frame; power supply system for the total set up; building works
to house CTI as also the building for LOI holder; individual transmitters,
rigid lines and accessories, Air conditioning arrangements, earthing
system for CTI, fire fighting equipment for CTI, technical furniture at
CTI.
5. Suffice to state, the common transmission infrastructure did not
include the tower to be constructed by BECIL on behalf of MIB. Clause
17.1 stipulated a dispute resolution mechanism through the process of
arbitration by a Sole Arbitrator to be nominated by the Secretary, MIB.
6. None of the petitioners have signed agreements for tower rental.
On July 25, 2011, the MIB had issued an order in the nature of policy
OMP 280/2012 & connected petitions Page 6 of 50
guidelines in pursuance to a decision of Union Cabinet with a purpose to
expand the FM Radio Broadcasting Services through private agencies
called the FM Radio Phase III. The guidelines stipulates migration of the
existing permission holders i.e. the petitioners herein, to Phase III,
subject to the provisions contained therein, which includes payment of
all outstanding dues pertaining to the government, Prasar Bharti and
BECIL in relation to existing FM radio permission/operations; signing
of fresh „grant of permission agreement‟ (GOPA). In any case, if the
existing permission holder does not execute the fresh agreement within
the given time, it shall be construed to mean that he does not want to
migrate to the FM Phase III regime and therefore shall continue to be
governed by Phase II policy provisions. The counsels for the parties
state that the last date for getting NOC is March 9, 2015 and the
deadline to sign the GOPA has been extended till March 23, 2015. I
may only point here that this Court in the order dated July 3, 2014, has
recorded that the deadline to migrate has been extended till March 31,
2015.
PLEADINGS OF THE PARTIES:
OMP 280/2012
7. It is the case of the petitioner that, it operates FM radio stations at
OMP 280/2012 & connected petitions Page 7 of 50
45 cities in the country. For the said purpose, it had paid to the MIB a
fee of Rs. 160 Crores as a one time entry fee and an amount of Rs. 30
Crores towards licence fee till March 2011. It had on March 23, 2006
entered into a PMA for common transmission infrastructure for the FM
radio Phase II at Delhi and similar agreements were entered for all 45
cities, in which, it operates. It is the case of the petitioner that the
respondent No. 1 is falsely claiming from it monitoring charges, which
were payable as per clause 13.1 of the GOPA. According to the
petitioner, the respondent No. 1 has failed to provide monitoring as
contemplated in GOPA. It has charged arbitrary interest @ 19.5 percent
on the outstanding amount. The petitioner has also raised an issue of
failure on the part of the respondent No. 1 to set up a CTI structure at
Kolkata and the advance paid to the respondent No. 1, was Rs.
1,08,00,000/-. The petitioner also raised an issue with regard to CTI
tower at Chennai, stating that, the same is inadequate as its height is 130
meters instead of 175 meters, prescribed in clause 12.2 of GOPA. In
other words, it is the petitioner‟s case that there exist genuine
commercial disputes between the parties. It is noted, that the petitioner
has invoked clause 17.1 of the PMA, seeking settlement of disputes
through arbitration.
OMP 280/2012 & connected petitions Page 8 of 50
8. The respondent No. 1 has filed its reply. It may not be necessary
for this Court to go into the details of the averments made in the reply
by the said respondents in view of an additional affidavit filed by the
respondent No. 1 on February 23, 2015. In para 4 and 5 of the additional
affidavit, the respondent No. 1 has stated as under:
“4. I state that there have been other dealing
between the parties in terms whereof tower rental,
monitoring charges in respect of monitoring of technical
compliances and content and Studio Transmission Links
(STL) charges are payable by the petitioner to respondent
No. 1. The said dealings are not under the Project
Management Agreements.
st
5. I state that upto 31 December, 2014 an
amount of Rs. 1,30,44,538/- was payable by the petitioner
towards tower rental for the Tower at Chennai for the
period 01.04.2008 to 31.03.2015 along with interest on
delayed payments of Tower Rentals amounting to Rs.
1,32,81,909/-. In addition, an amount of Rs.2,62,901/-
was due from the petitioner towards interest on STL
outstandings. The total amount due from the petitioner
upto 31.12.2014 was Rs. 2,65,89,348/-”.
The petitioner, in response to the affidavit has denied the amount
claimed by the respondent No. 1.
OMP 273/2012:
OMP 280/2012 & connected petitions Page 9 of 50
9. The case of the petitioner in this petition is that it is a private FM
radio broadcaster in India and operates under the brand name “Radio
One” operating in 7 Indian cities namely Mumbai, Delhi, Kolkata,
Chennai, Bangalore, Pune and Ahmedabad. Under the Phase II scheme,
it entered into a separate PMA for the 7 cities on March 20, 2006 and
April 15, 2006 with the respondent for setting up of CTI. It is also
averred that the petitioner was also required to enter into agreements for
use of Tower Aperture on payment of rent as per the said policy.
Pursuant to the PMA, the petitioner has paid approximately Rs. 7.3
Crores to the respondent for setting up of Common Transmission
Infrastructure (CTI). It is the petitioner‟s case that the respondent
delayed the setting up of Common Transmission Infrastructure, and in
the case of Kolkata, had not even built the same, thus, breaching the
time frame specifically provided under the project agreements. Such
delay caused grave prejudice and loss to the petitioner. The petitioner‟s
case is that it has been taking up the issue of delay in handing over the
site by the respondent and thus, insofar as Kolkata is concerned, an
amount of Rs. 1,08,00,000/- need to be refunded back, which has not
been done till date. Insofar as the refusal to enter into rental agreements
OMP 280/2012 & connected petitions Page 10 of 50
for the use of tower aperture at the cities of Chennai and Delhi, it is the
case of the petitioner that they had not executed solely on account of the
respondent having illegally and wrongfully levied rentals on the CTI
sites, which are not contractually payable to the respondent. Suffice to
state, the petitioner has been disputing the invoices raised by the
respondent. It is their case, that even the consortium of broadcasters
including the petitioner made several representations in respect of
claims made by the respondent, which have not been addressed to. The
petitioner states that in view of the new policy, enunciated by the MIB,
the migration from Phase II to Phase III is possible if a No-Objection
certificate is granted by the Prasar Bharti/BECIL, which presupposes the
payment of all dues by the petitioner. In other words, the respondent is
insisting upon the dues by the petitioner otherwise the petitioner would
not be eligible for seeking migration to Phase III, and as such,
compelled it to file the present petition, seeking an order, directing the
respondent to issue the petitioner a No due certificate, without prejudice
to its rights and contentions, pending the outcome of the arbitration
proceedings. I note, that, the petitioner has filed an application under
Section 11(6) of the Act i.e. Arb. P. 88/2015, which stands adjourned.
10. The respondent–BECIL has filed its reply to the petition.
OMP 280/2012 & connected petitions Page 11 of 50
11. On February 23, 2015, the respondent filed an affidavit wherein, it
has taken the following stand:
“4. I state that there have been other dealings between
the parties in terms whereof tower rental for the tower
erected at Delhi and Chennai and monitoring charges in
respect of monitoring of technical compliances and
content are payable by the petitioner to respondent No. 1.
The said dealings are not under the Project Management
Agreements.
st
5. I state that upto 31 December, 2014 an amount of
Rs.2,45,98,008/- was payable by the petitioner towards
tower rental for the Towers at Delhi and Chennai for the
period 01.04.2008 to 31.03.2015 along with interest
thereon amounting to Rs. 1,25, 84,741/-. In addition, an
amount of Rs. 4,35,882/- was due from the petitioner
towards monitoring charges for 7 cities. The total amount
due from the petitioner upto 31.12.2014 was Rs.
3,76,18,631/-”
12. A perusal of the affidavit now filed by the respondent would show
as on December 31, 2014, the total amount due is Rs.2,45,98,008/- against
tower rentals for the towers at Delhi and Chennai for the period April 1,
2008 to March 31, 2015 and interest thereon of Rs.1,25,84,741/- and an
amount of Rs. 4,35,882/- towards monitoring charges for 7 cities, the total
OMP 280/2012 & connected petitions Page 12 of 50
of which, comes to Rs.3,76,18,631/-. No reply to the additional affidavit
has been filed.
OMP 287/2012:
13. It is the case of the petitioner in the petition that it had participated
in the auction of licences in respect of FM broadcasting stations by the
respondent No. 2, Ministry of Broadcasting (MIB) in Phase II of the
licensing policy and has been granted Letter of Intent and subsequently,
executed GOPA dated September 13, 2006, inter alia to set up and operate
7 Radio stations in Tamil Nadu and Puducherry. In terms of the FM Radio
policy, Phase II, the petitioner was required to co-locate transmission
facilities with the existing infrastructure of Prasar Bharti and the common
facilities had to be integrated by the respondent. In these circumstances,
the petitioner entered into a PMA dated April 16, 2006 for CTI at Avadi,
Chennai with the respondent No. 1. During oral discussions with the
officials of the BECIL, it raised concern with regard to the strength of
signals that would originate at Avadi since it is located at least 20
kilometers from Chennai. According to the petitioner, it had paid to the
MIB (GOI) an amount of Rs. 24.3 Crores as one time entry fee for the
operation of the FM broadcasting stations. It has also incurred capital
expenditure of approximately Rs.60 Crores besides having paid a sum of
Rs. 5.18 Crores to the respondent No. 1. It is also the case of the petitioner
OMP 280/2012 & connected petitions Page 13 of 50
being a successful bidder, the petitioner was also required to enter into an
agreement paying rent for the use of the tower as per the said policy. It has
also made an advance payment of Rs.1,08,00,000/- as 100% advance
towards the estimated share of capital cost on cost sharing basis towards
the building, installation, commissioning and completion of CTI to the
respondent. Besides that, the petitioner was required to pay land and tower
rentals. According to the petitioner, as per the FM Phase II policy at places
where a suitable tower for Prasar Bharti was not available, the broadcasters
were permitted to operationalise their transmission facilities out of interim
set up till permanent set up was completed. The petitioner, for the city of
Chennai created an interim set up at Doordarshan Centre, Chennai, and
started operations of its Radio station under the name Hello FM on
October 02, 2006 and the petitioner continues to use the said facility till
date in view of the problems with the CTI set up/created by the respondent
No. 1 at Avadi. The petitioner‟s case insofar as the facility at Avadi is
concerned; the signals are poor, noisy with very low clarity. According to
the petitioner, it is in receipt of letter dated March 31, 2009, wherein, the
respondent No. 1 has alleged that the petitioner, while operating from the
interim set up at Chennai is in violation of GOPA as well as the PMA. The
petitioner‟s stand is that it responded vide letter dated April 13, 2009,
providing a detailed account of the disadvantages for phase II, due to
OMP 280/2012 & connected petitions Page 14 of 50
technological deficiencies in services as well as signal interference at CTI
complex at Avadi. The petitioner also contested the demand made by the
respondent No. 1 vide its letter dated October 12, 2009 of an amount of
Rs.31,37,780/- along with security deposit of Rs. 13,93,776/-, by stating
that, the demand is unjustified as the petitioner had not commenced use of
the same in view of several deficiencies highlighted by it. The petitioner
has also stated that the grievance of the petitioner has not been addressed.
The petitioner also referred to the issuance of policy guidelines in the year
2011 by MIB for migration to FM Radio Phase III. The petitioner has also
stated that the respondent has agreed to adjust the monitoring charges from
the balance advanced capital with them and further agreed to provide,
interest on the balance capital, advance available with them, and with the
said understanding, and in acknowledgement/admission of the same, the
respondent has even provided the petitioner with TDS certificates,
however, the respondent is yet to make a refund of Rs.3,226,875/- and in
view of the fact that the respondent No. 1 has miserably failed and
neglected to comply with its obligations under the agreement, it is
constrained to invoke the arbitration clause to refer the disputes before the
Sole Arbitrator. It has also referred to the writ petition filed by it being
WP(C) No. 1257 of 2012 being Radio One Ltd. Vs. Union of India and
Anr., wherein, the Court has observed that the appropriate remedy in view
OMP 280/2012 & connected petitions Page 15 of 50
of the arbitration clause between the parties, is initiation of arbitration and
seeking interim directions therein.
14. As noted in the other petitions, the respondent No. 1 had also filed
its reply so also the respondent No. 2. That apart, the respondent No. 1 has
filed an additional affidavit on February 23, 2013, wherein, the respondent
No. 1 has taken the following stand:
“4. I state that there have been other dealings
between the parties in terms whereof tower rentals for
the tower erected at Chennai and monitoring charges in
respect of monitoring of technical compliances and
content are payable by the petitioner to respondent No.
1. The said dealings are not under the Project
Management Agreements.
st
5. I state that upto 31 December, 2014, an
amount of Rs.1,30,44,538/- was payable by the
petitioner towards tower rental for the Tower at
Chennai for the period 01.04.2008 to 31.03.2005 along
with interest thereon amounting to Rs.63,54,980/-. In
addition, an amount of Rs.38,91,906/- was due from the
petitioner towards monitoring charges for the 7 cities.
The total amount due from the petitioner upto
31.12.2014 was Rs.2,32,91,424”.
15. Suffice to state, it is the case of the respondent No. 1 that the total
amount due from the petitioner as on December 31, 2014 was
OMP 280/2012 & connected petitions Page 16 of 50
Rs.2,32,91,424/- towards tower rental for the tower at Chennai along with
interest thereon and monitoring charges for the 7 cities under GOPA. No
reply to the additional affidavit has been filed.
OMP 295/2012:
16. The case of the petitioner in this petition is that pursuant to an
auction of the licenses in respect of private FM broadcasting stations by
the MIB in Phase II of the licensing policy, Letters of Intent were granted
to the petitioner to set up and operate radio stations in Category B cities of
Agra and Varanasi, Category C cities of Bareily, Jalandhar, Gorakhpur and
Ranchi, and Category D cities of Hisar and Karnal. It had executed GOPA
on November 23, 2006. It had paid to the Govt. of India an amount of Rs.
7.88 Crores as one time entry fee and an amount of Rs. 25,10,505/-
towards fee for the first year in respect of the aforesaid 8 stations. It had
also incurred capital expenditure for an approximately sum of Rs.24 Crores
besides having paid a sum of Rs.5 Crores to the respondent No. 1 and a
sum of Rs. 1.20 Crores to Prasar Bharti. In terms of the Phase II policy,
successful bidder was required to co-locate the transmission facilities with
the existing infrastructure of Prasar Bharti and the common facilities had to
be integrated by the respondent No. 1. In entered into agreements in the
year 2006 with the Prasar Bharti for its existing infrastructure on payment
of licence fee for each of its 8 radio stations. It had also entered into a
OMP 280/2012 & connected petitions Page 17 of 50
Project Management Agreement for CTI on April 22, 2006 with respect to
FM radio station at Karnal. Similar agreements were executed in all the 8
cities. The petitioner, in consideration of the respondent No. 1, building,
installing, commissioning and completing the CTI agreed to pay to BECIL
its share of actual cost as also fee for providing project management
services equivalent to 10% of its share of actual net cost. An advance
payment of Rs. 5,02,00,000/- was paid to the respondent No. 2 on
22.04.2006 for all 8 stations. Further, as per GOPA, the petitioner was
required to pay its share of monitoring charges arrived at by equally
apportioning Rs. 25,000/- per month amongst all permission holders for
the city. It is the case of the petitioner, that, the BECIL vide letter dated
March 19, 2009 demanded the outstanding monitoring charges for the year
2007-08 and 2008-09 from the petitioner. It is the case of the petitioner,
pursuant to certain discussions, it was agreed that the monitoring charges
be adjusted from the balance capital advance already with BECIL on
account of common infrastructure set up. It is the case of the petitioner that
approximately, Rs.60 lakhs are available with the BECIL and called upon
the BECIL to square up the monitoring charges and for final reconciliation
duly audited at their end so that the payments, if any, may be made by the
petitioner. Surprisingly, it received a show-cause notice dated May 5,
2011 from the MIB for non payment of monitoring charges and stating that
OMP 280/2012 & connected petitions Page 18 of 50
the petitioner was in violation of the GOPA. The petitioner brought to the
notice of the MIB the understanding arrived at between the parties. It is
also its case that inspite of such unreasonable and arbitrary conduct of the
respondent, it had sent a cheque of Rs. 7,86,535/- to the BECIL, being
outstanding amount as per the petitioner‟s calculations. The petitioner
referred to the policy enunciated on July 25, 2011 for expansion of FM
radio broadcasting services to private agencies Phase III, wherein,
migration was permissible from Phase II to Phase III, subject to payment
of all dues and securing an NOC from the concerned authorities. The
petitioner also referred to a letter dated September 8, 2011 issued by MIB
to the petitioner, asking it to clear the dues of the respondent before
migration could take place. According to it, as per the respondent, vide its
letter dated October 7, 2011, it had sent a final statement of accounts with
regard to 8 Radio stations, whereby, it raised a demand of Rs. 84,07,047/-.
The respondent demanded Rs.58,24,172/- towards monitoring charges,
which according to the petitioner, is not payable. The petitioner‟s case is
that the statement also included an amount of Rs.5,77,628/- paid as TDS
by BECIL.
17. Suffice to state, the petitioner contested the statement of accounts
sent to it. The petitioner referred to a writ petition being WP (C)
8782/2011 wherein, it had prayed for a direction to permit it to migrate
OMP 280/2012 & connected petitions Page 19 of 50
without necessity of obtaining a certificate from the respondent. The Court
gave direction for invoking the arbitration. The writ petition was
withdrawn by the petitioner with liberty to initiate arbitration proceedings.
It is necessary to state here that the petitioner has invoked clause 17.1 of
the Project Management Agreements.
18. The respondent Nos. 1 and 2 have filed their replies to the petition. I
would not dilate much on the replies filed by the respondent Nos. 1 and 2
in view of the additional affidavit filed by the respondent No. 1 on
February 23, 2015, wherein, the following stand has been taken:
“4. I state that there have been other dealings
between the parties in terms whereof monitoring charges
in respect of monitoring of technical compliances and
content are payable by the petitioner to respondent No. 1.
The said dealings are not under the Project Management
Agreements.
st
5. I state that upto 31 December, 2014 an amount
of Rs.49,87,204/- was payable by the petitioner towards
monitoring charges in respect of the 8 cities for the period
starting from 2007 to 31.03.2011 and 01.04.2012 to
31.03.2013. In addition, an amount of Rs.25,82,875/- was
due from the petitioner towards CTI outstandings under
the Project Management Agreements. The total amount
due from the petitioner upto 31.12.2014 was
Rs.75,70,079”.
OMP 280/2012 & connected petitions Page 20 of 50
In response to the aforesaid affidavit, the petitioner has denied, that the
amount of Rs.75,70,079/- is due and payable.
19. During the hearing, Mr. Rajeev Sharma, learned counsel for the
BECIL, the respondent No. 1, submitted a due payment summary of the
petitioner, wherein, it is reflected that, the petitioner has to pay an amount
of Rs. 54,87,586/- in total, the break up of which is Rs. 44,35,360/-, against
monitoring charges and Rs.10,52,226/- against CTI charges.
OMP 291/2012:
20. The petitioner has filed the present petition with a stand that it had
participated in the auction of licences in respect of private FM
broadcasting stations by the MIB in Phase II of the licensing policy and
granted Letters of Intent to set up and operate 10 radio stations in the cities
of Shimla, Ahmednagar, Dhule, Jabalpur, Hisar, Jalgaon, Karnal, Patiala,
Mujjafarpur and Ranchi. In terms of the Phase II policy, the petitioner was
required to co-locate transmission facilities with the existing infrastructure
of the respondent Prasar Bharti and common facilities had to be integrated
by the Broadcasting Engineering and Consultants India Ltd. (BECIL). It
had entered into 10 agreements for availing the respondent‟s infrastructural
facilities i.e. tower aperture, open space, land, covered space, building and
other facilities. It had also entered into PMA for 10 cities for CTI with
BECIL. In terms of the agreement, the petitioner was required to pay to
OMP 280/2012 & connected petitions Page 21 of 50
the respondent the annual licence fee in advance for use of the
respondent‟s infrastructure. Apart from this, the petitioner was to pay to
the respondent in the first year an amount equal to one year‟s licence fee
by way of security deposit which was refundable to the petitioner on
termination of the agreement(s). Furthermore, as per the agreement(s), the
petitioner was to pay to the respondent 10% after every two years for the
open/covered space and the common facilities; 2.5% after every year for
the tower. According to the petitioner, it had paid an amount of
Rs.4,76,72,382/- towards licence fee in respect of all the 10 radio stations
till date. Furthermore, an amount of Rs. 68,94,331/- as security deposit
was paid to the respondent at the time of execution of the licence
agreements. The petitioner also referred to the new policy formulated by
the MIB on July, 2011, which stipulates migration to Phase III subject to
clearing the dues and obtaining NOC from the concerned authorities. It is
the case of the petitioner that a meeting was held with the Joint Secretary,
Broadcasting of MIB on the issue of higher interest being charged by the
respondent for use of its infrastructure. It was decided that the issue of high
rentals will be discussed with the respondent in a separate meeting. Despite
such an assurance, no meeting had been called for by the respondent. It is
the petitioner‟s case that the respondent has failed miserably and neglected
to comply with its obligation under the agreement(s) and is further making
OMP 280/2012 & connected petitions Page 22 of 50
unreasonable demand from the petitioner and had no other alternative, but,
to invoke clause 12 of the agreement(s), invoking arbitration for reference
of the disputes so arisen between the parties before the Sole Arbitrator.
21. The respondent Prasar Bharti filed its reply wherein, it has taken a
plea that the petitioner has not invoked any arbitration clause even though
the petition was filed as far back as on March 26, 2012.
22. It is the case of the respondent that the petitioner has defaulted in
making the payments and in such circumstances, it is not entitled to any
interim measure or protection. It would state that the agreements for the 10
locations were executed as far back as on March/April, 2006. The
agreements were arrived at voluntarily and the petitioner never objected to
the licence fees specified therein. The respondent has also stated that the
petitioner had paid licence fee without demur upto 2010-11. The
respondent would submit that the petitioner has no prima facie case nor
any balance of convenience in its favour. Admittedly, the petitioner,
utilizing the land of the respondent, despite using the land, the petitioner is
refusing to pay the rent which is not justified.
23. On March 03, 2015, when the matter was heard by this Court, the
learned counsel for the petitioner has stated that the petitioner has paid all
the dues to Prasar Bharti. According to him, the Prasar Bharti in advance
had raised an invoice for the year 2015-16 which has to be paid to the
OMP 280/2012 & connected petitions Page 23 of 50
petitioner and the same should not come in the way of for grant of NOC.
Despite opportunity, no affidavit was filed and at the request of the counsel
for the petitioner, the matter was adjourned to March 5, 2015. On March
5, 2015, the learned counsel for the petitioner has clarified that invoice
raised by the Prasar Bharti was for the year 2014-15 for the usage of
infrastructure like tower, open space and common facilities. He would
concede to the fact, the petitioner has not invoked the arbitration clause.
24. Mr.Rajeev Sharma, learned counsel for the respondent would state
that an amount of Rs.1,02,82,583/- is due from the petitioner as on October
2014 with interest. He would state that till such time, the amount is paid
by the petitioner, NOC cannot be granted. The learned counsel for the
petitioner would submit that the petitioner would pay 50% of the amount
to the respondent.
OMP 294/2012:
25. In this petition, the petitioner has inter alia sought an order of
injunction restraining the respondent No. 1 from raising a demand of Rs.
81,11,040/- apart from seeking an order of issuance of No due certificate
so as to enable the petitioner to sign GOPA for phase III. It is the case of
the petitioner that pursuant to the participation in the auction of licences,
an LOI was issued by Ministry of Information and Broadcasting to operate
Phase II FM broadcasting stations in 10 cities of Shimla, Ahmednagar,
OMP 280/2012 & connected petitions Page 24 of 50
Duley, Jabalpur, Hisar, Jalgaon, Karnal, Patiala, Muzafarpur and Ranchi.
It had entered into PMA with the respondent No. 1 with regard to the 10
cities. It had paid the respondent No. 1 an amount of Rs.6,03,00,000/- in
respect of all 10 radio stations. It had made a security deposit of Rs.
68,94,331/- to the respondent No. 2 in respect of each radio stations in
terms of GOPA and Rs.4,76,72,382/- towards licence fee for all 10
stations. It is the case of the petitioner that there was an issue of breach of
contractual obligation by the respondent No. 1 in respect of petitioner‟s
radio station at Shimla as the CTI facility which was to be handed over on
20.04.2007 could be handed over only on 08.10.2009. It is its case that it
had incurred huge costs on account of the delay. It had also denied its
liability to pay escalated costs as well as for delay in construction of CTI in
Shimla. It had asked the respondent No. 1 to refund an amount of
Rs.40,25,000/-. However, the respondent No. 1 has not refunded it till
date. Even a request for No-Objection Certificate has not been acceded to.
26. The respondent No. 1 demanded from the petitioner a payment of
Rs.35,51,536/- towards CTI and Rs.45,59,504/- towards monitoring
charges and interest on account of late payment of monitoring charges.
The respondent No. 1 had also demanded an amount of Rs.14,57,671
towards electricity consumption for the month of November 2011 to
January 2012 for the 10 radio stations of the petitioner. The petitioner
OMP 280/2012 & connected petitions Page 25 of 50
would refer to the policy regarding Phase III issued by MIB and would
refer to the clauses with regard to the issuance of NOC, subject to
clearance of all dues by the radio operators. The petitioner also referred to
the understanding arrived at between the petitioner and the respondent No.
1, adjusting the monitoring charges from the balance advance capital
available with the respondent No. 1. The petitioner would submit that the
refusal to give No-Objection Certificate is illegal.
27. The respondent has filed its reply, taking various objections.
28. During hearing, Mr.Rajeev Sharma, has said that the total amount
due from the petitioner is Rs. 77,86,632/- against monitoring charges under
clause 13.2 of GOPA, which payment has to be made to BECIL. Similarly,
he would state that a further amount of Rs.35,51,536 as on December 31,
2014 is due for the Common Transmission Infrastruture provided by the
BECIL. He would state, a total sum of Rs.1,13,38,168 is due.
29. Learned counsel for the petitioner would submit, an amount of Rs.
77 lakhs would be secured by way of a bank guarantee. He would dispute
the payment of Rs. 35,51,536/- as there was a delay on the part of the
BECIL to construct the CTI at Shimla. He would also state, the said
amount would also be secured by way of a bank guarantee. It is his case
that the petitioner is hard pressed for money in view of various investments
made by it.
OMP 280/2012 & connected petitions Page 26 of 50
SUBMISSIONS:
30. Mr.Sandeep Sethi, learned counsel appearing for the petitioner in
OMP No.280/2012 would submit that the petitioner operates, FM stations
in 45 cities in the country and in that regard paid to the MIB fees of Rs.160
crores as one time entry fee and an amount of Rs.33 crores to BECIL and
that apart making huge investments. The petitioner is not a fly by night
operator, who would not honour, any award even if comes against it. He
has drawn my attention to the e-mail dated February 4, 2015, received
from BECIL along with an attachment, a statement showing outstanding
payment of Rs.28,33,175/-, which has been paid by it. He would state,
unfortunately, in the affidavit filed by the Respondent No.1, it had for the
first time taken a plea that, the Tower rental, monitoring charges and
Studio Transmission Links charges are payable by the petitioners are not
under the PMA. Such an objection has been taken after 3 years, of the
filing of the petition. He refers to letter dated November 21, 2011, written
by the petitioner to BECIL to contend, that the, petitioner has genuine
issues for which immediate attention of BECIL was sought like
reconciliation of advances, interest, monitoring charges, CTI Chennai etc.
With regard to Chennai, he would state the Tower in the city of Chennai
was erected at Avadi, a small town in North West of Chennai, is
inadequate technically as the height of the Tower constructed is 130
OMP 280/2012 & connected petitions Page 27 of 50
meters, instead of 175, and thus, it is legitimate and prudent for the
Respondent No.1 to refund the entire advance amount paid to BECIL
under the agreement. It was his endeavour, to argue that, the Respondent
No.1 does not dispute the genuine issues raised by the petitioner and the
Court which considers an application under Section 9 of the Act, would
have a prima facie view to decide whether a direction to the petitioner to
pay is necessary. The amount now being claimed by BECIL is with regard
to tower rental for the Tower in Chennai, and interest on delayed payment
of tower rentals for the cities of Delhi , Chennai and Hyderabad, in
addition to interest on STL outstanding, cannot be said to be dues unless
adjudicated. He would refer to the agreement executed with Prasar Bharti
on June 20, 2006 to contend, that it was for usage of infrastructure of
Prasar Bharti to be collected by BECIL on behalf of Prasar Bharti with an
Arbitration clause. He would also refer to PMA between the petitioner and
BECIL and its various provisions. According to him, there is no dispute
with regard to Monitoring charges under GOPA. In the end, it is his
submission that the petitioner could not be called upon to discharge, a
claim where there is no dispute.
31. On the other hand, Mr.Rajeev Sharma, learned counsel for the
Respondent No.1 would state that the FM II Policy was framed in the year
2005, under which, out of 91 cities, in 84 cities, the operators could co-
OMP 280/2012 & connected petitions Page 28 of 50
locate with the infrastructure of Prasar Bharti and for 7 cities, referred to
above, new Towers were erected by the BECIL on behalf of MIB. The
BECIL was only a collecting agency. Till such time the towers did not
come up in these 7 cities, the operators were at liberty to have an
arrangement either independently or at AIR/DD (PB) station. According
to him, the agreement referred to by Mr.Sethi with Prasar Bharti was one
such arrangement which the petitioner had for Delhi. He would state that,
the Tower rental is payable and this aspect has been conceded by the
petitioner in its letter dated December 29, 2011, wherein in Para 7(a) the
petitioner had stated “it is submitted that out of the total amounts specified
towards rentals only Rs.1,00,42,640/- is due and payable”. According to
him, in fact, BECIL has constructed the Tower at Chennai, in terms of the
policy, the petitioner is bound to pay the rentals. Unfortunately, despite
construction they have not co-located. He would also state that Mr.Sethi
has not answered the objection taken by the Respondent No.1, with regard
to the arbitrability of the issues regarding Tower Rentals, and interest on
Tower Rentals for the cities of Delhi, Hyderabad and Chennai, as there is
no Arbitration agreement between the parties. According to him, the
petitioner has invoked the arbitration clause under PMA. The petition
under Section 9 is itself not maintainable. He has taken me through the
provisions of the PMA, to highlight, the scope of the agreement to submit
OMP 280/2012 & connected petitions Page 29 of 50
construction of tower and payment of tower rent does not find place in
PMA. He would state that towers does not fall under Common
Transmission Infrastructure. The petitioners were to execute an agreement
with regard to tower rental. Unfortunately, they have not come forward to
execute the same. He would refer to page 34 of the reply of respondent
No.1, which is a statement showing tower rental status. According to him,
vide letter dated April 08, 2009, the petitioner was called upon to pay the
tower rental charges. Unfortunately, the same has not been paid. The claim
of rent is not a recent development. NOC can be given only if the dues are
paid, which are to the tune of Rs.2,65,89,346/-.
32. Mr.K.Datta in rejoinder to the submissions made by Mr.Rajeev
Sharma would submit that the respondent No.1 had never taken the
objection regarding arbitrability of the disputes. He would state, rather a
statement was made on behalf of the respondent No.2 that MIB is willing
to appoint an Arbitrator. In that regard, he draws my attention to the order
dated June 01, 2012 and May 28, 2012 passed in the petition. In view of
such a statement, it is not correct on the part of respondent No.1 to contend
that the issues/disputes are not arbitrable in the absence of an
agreement/arbitration clause. He would reiterate the submission made by
Mr.Sethi regarding inadequacy of the tower in Chennai, being of a lower
height. So, the issue of inadequacy of infrastructure is an issue which falls
OMP 280/2012 & connected petitions Page 30 of 50
under the PMA and as such arbitrable. He referred to Annexure 1 of the
PMA. He would also state that as per Section 7(4)(c) of the Act, an
Arbitration Agreement is in writing, an exchange of statements of claim
and defence, in which the existence of the agreement is alleged by one
party and not denied by the other party. He refer to para 48-49 of the
petition and corresponding para in reply in this regard. He also refers to
the order of the Division Bench dated March 02, 2012 passed in W.P.(C)
1257/2012 filed by one of the petitioner in this batch of petitions i.e.
„Radio One Ltd‟. to contend that the Division Bench has said that remedy
for the petitioner is to initiate arbitration proceedings and seek interim
direction therein. He has referred to Clause 5.3 of the GOPA filed in OMP
No.295/2012 to contend that GOPA recognizes the construction of tower
through BECIL. In the last it is his submission that without prejudice, the
petitioner shall deposit the principal amount, excluding interest in this
Court, pending decision by the Arbitrator, the NOC must be given to
enable the petitioner to migrate; otherwise great hardship shall be caused to
the petitioner. Out of the 45 stations, the dispute is with regard to only one.
According to him, as the petitioner is operating at other places, there
cannot be an apprehension that the petitioner would not be able to
discharge the liability if established against the petitioner. He has filed
written submissions in OMP 273/2012.
OMP 280/2012 & connected petitions Page 31 of 50
33. Mr.Rajiv Nayyar, learned Senior Counsel who appeared for the
petitioner in OMP 273/2012 adopted the arguments advanced in OMP
280/2012 by Mr.Sandeep Sethi/Mr.K.Datta. That apart he would point out
the letter dated December 19, 2014 written by BECIL and January 19,
2015 written by the petitioner No.1, which provide justification for non
payment of the dues by the petitioner. He would state, insofar as
monitoring charges are concerned, the same shall be paid by the petitioner.
He would also state, for the last so many years, the respondent has assured
the petitioner during the hearings that the issue would be resolved or in the
alternatively the matter would be referred to arbitration, but at this point of
time to say that the issue with regard to tower rentals is not arbitrable is
unjustified. He says as per Section 7(4)(b) & (c), read with the statements
made and averments not denied by the respondent No.1, in its reply, the
existence of an arbitration clause is admitted and in that regard he has
drawn my attention to para Nos.48 & 49 of the reply. According to him,
without prejudice, the petitioner is ready to deposit the amount in the
Court. He would rely on the judgment of the Supreme Court in BSNL &
Ors. Vs. M/s. Subhas Chandra Kanchan and Anr., AIR 2006 SC 3335
34. Mr.Rajeev Sharma, learned counsel for the respondent No. 1 would
submit that the petitioner claim to have invoked clause 17.1 of the PMA
executed with BECIL. According to him, tower rental interest therein and
OMP 280/2012 & connected petitions Page 32 of 50
monitoring charges do not fall within the ambit of the PMA and therefore,
disputes are not covered under PMA. He would also state that, the reliance
placed on Section 7(4)(b) and (c) of the Act is not tenable. For
applicability of Section 7(4)(c), there has to be a specific averment which
has not been denied. A bare reading of paragraph 48 shows that there is no
specific averment regarding tower rental and monitoring charges . He
relied upon the judgment of the Supreme Court in S.N.Prasad Vs.Monnet
Finance Ltd. and Ors., AIR 2011 SC 442. On Section 7(4)(b) of the Act,
he would state, the letters must record the existence of an agreement.
According to him, no such letters have been pointed out. He would also
state that the tower/tower rentals are not part of PMA as is clear from
Annexure I and III, which lists out the CTI. According to him, any
jurisdictional issue needs to be pleaded by the petitioner and the Court also
needs to consider such an issue while exercising jurisdiction. On the
statement of the ASG, regarding willingness of the Govt. of India to
appoint an Arbitrator as a proof of existence of an Arbitration clause, it is
the submission, such submission needs to be rejected for the following
reasons;
(i) MIB only nominates the Arbitrator;
(ii) The Secretary does not even have to see whether Arbitration
Agreement exists and whether the disputes are within the ambit of
OMP 280/2012 & connected petitions Page 33 of 50
arbitration agreement;
(iii) The statement of ASG is not indicative of any consent by BECIL.
He would, on the judgment of the Division Bench, states that, the DB did
not go into the question as to what disputes are arbitrable and contains no
adjudication on the said issue. In the last, he states, once policy has been
upheld, it is not a case of an interim measure.
35. Mr. R.Gogna, learned CGSC for MIB states that even after the order
dated 28.05.2012 was passed, when statement of learned Additional
Solicitor General was recorded, the MIB has filed its reply in some of the
petitions wherein, it has been averred that since MIB is not a party to the
PMA, and since there is no arbitration agreement between the petitioner
and the answering respondent, the petition against MIB is not
maintainable.
36. Mr.K.Datta in OMP No. 295/2012, apart from relying on the
submissions made in other petitions would state that the petitioner would
deposit in Court the amount claimed by the respondent No. 1.
37. Mr.Rajeev Sharma has referred to para No.4 & 5 of the affidavit
which is already reproduced above to state , the petitioner is liable to pay
the dues, and till such time, NOC cannot be issued.
38. The learned counsel for the petitioner in OMP No.291/2012, which
OMP 280/2012 & connected petitions Page 34 of 50
is filed primarily against Prasar Bharti would submit that an invoice for the
year 2014-15 has been raised by the Prasar Bharti for the usage of
infrastructure i.e. tower, open space, common facilities. The petitioner is
ready to pay 50% of the amount to the Prasar Bharti.
39. Mr.Sharma on the other hand would submit that the petitioner is in
arrears of Rs.1,02,82,583/- and hardship is not a ground to not pay the
dues. Mr.Sharma also justifies, claim of Rs.1,13,38,168/- towards
monitoring charges and CTI charges against the petitioner in OMP No.
294/2012.
40. Having considered the submission made by the learned counsel for
the parties, the foremost question which arises for consideration at least in
OMP Nos. 280, 273 and 287 of 2012, is whether the petitions under
Section 9 of the Act per se are maintainable in view of the objection taken
by the learned counsel for respondent No.1 that the disputes regarding
tower rental and interest thereon, is not covered by the PMA, the
agreement which they invoked for the purpose of filing the petitions. From
the pleadings, it is clear that the petitioners in the aforesaid OMPs did rely
on the arbitration clause in PMA. It is to be seen whether PMA encompass
in itself the issue related to tower rental to attract the arbitration clause.
The clause 3.1 of the PMA stipulates, BECIL providing project
management services to build, install, commission and complete the
OMP 280/2012 & connected petitions Page 35 of 50
Common Transmission Infrastructure and clause 5.1 stipulates in
consideration the operator shall pay to BECIL its share of actual net costs
and fee @ 10% of its share of actual net costs. Suffice to state, as stated
above, the CTI does not include tower construction or the rental to be paid
for its usage. Rather I find, the petitioner in OMP No. 273/2012 in para 13
of the petition has admitted that the parties i.e. the operators and the
BECIL were also required to enter into agreement for use of tower aperture
and payment of rent. It has also come on record in OMP No. 273/2012, in
the reply of the respondent No.1, as per Annexure R3, which is a copy of
the minutes of meeting held between the officials of BECIL, AIR, Private
FM Broadcasting Companies under the Chairmanship of JS(B) MIB
wherein, in para 2.5 of the minutes, the following is recorded on
operational date for tower rent fixation:-
“2.5. Operational date for tower rent fixation
FM operators stated that they had signed agreements for
tower rental at certain price in 2006. As per agreements, the
tower rental is to escalate at certain rate per annum. The FM
operators started using the tower in 2008 even though they
signed the agreements in 2006. BECIL is charging them the
tower rental from 2006. However, the FM operators
requested that the tower rental should be charged from 2008,
from the date of actual use instead of 2006, the date of signing
the agreement”.
OMP 280/2012 & connected petitions Page 36 of 50
41. From the above, it is clear that without any doubt that the parties
were required to execute a separate tower agreement, which would have
governed the tower rentals. Mr.Rajeev Sharma may be right in his
submission that despite being called upon to execute the agreements, the
petitioners have not come forward. In any case, it is suffice to state that the
issue/dispute of tower rentals is not governed by PMA and the invocation
of PMA seeking relief under Section 9 is not tenable. To seek relief under
Section 9, an existence of an arbitration agreement is necessary and in that
regard Section 7 of the Act defines Arbitration Agreement to mean as
under:-
Judgment reserved on March 03, 2015
Judgment delivered on March 10, 2015
+ O.M.P. 280/2012
RELIANCE BROADCAST NETWORK LIMITED
..... Petitioner
Through: Mr.K. Datta, Advocate with
Mr.Ashish Verma and
Mr.Rahul Malhotra,
Advocates
Versus
BROADCAST ENGINEERING AND CONSULTANTS
INDIA LTD AND ANOTHER ..... Respondent
Through: Mr.Rajeev Sharma, Adv. &
Mr.R.Gogna, CGSC along
with Mr.Vipul,
Ms.L.Gangmei, Ms.Tanisha,
Advs. for Ministry of
Information & Broadcasting
(UOI)
+ O.M.P. 273/2012
RADIO ONE LIMITED ..... Petitioner
Through: Mr.Rajiv Nayar, Sr.
Advocate with Mr.Kirat
Singh Nagra and
Mr.Kartik Yadav, Advocates
Versus
BROADCAST ENGINEERING CONSULTANTS INDIA
LTD ..... Respondent
Through: Mr.Rajeev Sharma, Adv.
with Ms.Radha Lakhmi R.,
OMP 280/2012 & connected petitions Page 1 of 50
Adv. for R-1
Mr.R.Gogna, CGSC along
with Mr.Vipul,
Ms.L.Gangmei, Ms.Tanisha,
Advs. for Ministry of
Broadcasting (UOI)
+ O.M.P. 287/2012
MALAR PUBLICATIONS LTD ..... Petitioner
Through: Mr.Abhishek Malhotra,
Mr.Debashis Mukherjee,
Adv.
Versus
BROADCAST ENGINEERING AND CONSULTANTS
INDIA LIMITED & ANR ..... Respondent
Through: Mr.Rajeev Sharma, Adv. &
Mr.Vivek Goyal, CGSC with
Mr.M.Tapan Sharma, Adv.
for UOI/R2
+ O.M.P. 295/2012
PURAN MULTIMEDIA LTD ..... Petitioner
Through: Mr.K. Datta, Advocate with
Mr.Ashish Verma and
Mr.Rahul Malhotra,
Advocates
Versus
BROADCAST ENGINEERING AND CONSULTANTS &
ANR ..... Respondent
Through: Mr.Rajeev Sharma, Adv.
with Ms.Radha Lakshmi R.,
Adv. for respondent No.1
Mr.R.Gogna, CGSC along
with Mr.Vipul,
OMP 280/2012 & connected petitions Page 2 of 50
Ms.L.Gangmei, Ms.Tanisha,
Advs. for Ministry of
Information & Broadcasting
(UOI)
Judgment reserved on March 05, 2015
Judgment delivered on March 10, 2015
+ O.M.P. 291/2012
DHAMAAL 24 RADIO NETWORK LTD. ..... Petitioner
Through: Mr.Abhishek Malhotra, Adv. with
Mr.Nitin Bhatia, Adv.
Versus
PRASAR BHARTI ..... Respondent
Through: Mr.Rajeev Sharma, Adv.
+ O.M.P. 294/2012
DHAMAAL 24 RADIO NETWORK LTD. ..... Petitioner
Through: Mr.Abhishek Malhotra, Adv. with
Mr.Nitin Bhatia, Adv.
Versus
BROADCAST ENGINEERING AND CONSULTANTS INDIA
LTD. AND ANR ..... Respondent
Through: Mr.Rajeev Sharma, Adv.
CORAM:
HON'BLE MR. JUSTICE V.KAMESWAR RAO
V.KAMESWAR RAO, J.
1. This batch of petitions have been filed under Section 9 of the
Arbitration and Conciliation Act, 1996 (Act, in short), inter alia,
OMP 280/2012 & connected petitions Page 3 of 50
claiming a common interim measure in the nature of direction to the
Broadcasting Engineering and Consultants India Ltd. (BECIL, in
short)/Prasar Bharti to issue No-Objection Certificate to them, or a
direction for giving permission, to enable them to apply for migration to
Phase III in terms of FM Radio Policy dated July 25, 2011. Since the
issue(s) which arise(s) for consideration in this batch of petitions is
identical, they are being disposed of by this common order.
FACTS:
2. All the petitioners herein operate FM Radio Stations in different
cities of the country under FM Radio (Phase II) policy of Ministry of
Information and Broadcasting (MIB, in short) dated July 13, 2005.
Before Phase II policy was framed, there was a Phase I policy. Under
the Phase II policy, the case of a new entrant was also considered. The
policy stipulated a process of granting permission by issuance of a
Letter of Intent to enable the company to obtain frequency allocation,
SACFA clearance, achieve financial closure, and appoint all key
executives, enter into an agreement with DD/AIR/BECIL and deposit
the requisite amount towards land/tower lease rent, Common
Transmission Infrastructure (CTI, in short) etc. and comply with the
requisite conditions of eligibility for signing the “Grant of Permission
OMP 280/2012 & connected petitions Page 4 of 50
Agreement” (GOPA). The “grant of permission agreement” was
executed between the MIB and the petitioners herein on different dates.
The policy also contemplated mandatory for all Phase II operators to co-
locate transmission facilities in all the 91 cities on terms and conditions
to be prescribed separately. Out of 91 cities, in 84 cities, the facilities
had to be co-located on existing AIR/DD towers, while in remaining 7,
the policy contemplated new towers to be got constructed by the MIB
through BECIL. The new towers were to be constructed at Chennai,
Delhi, Kolkata, Mumbai, Bangalore, Hyderabad and Jaipur.
3. Pending creation of co-location, facility by BECIL, the successful
bidders in the 7 cities were permitted to operationalize their channels on
individual basis for a period of two years or till the co-location facility is
commissioned, whichever is later, at the end of which, they were to shift
their operations to new facilities. Permission to run individual channel
were to be granted to each successful bidder only after it had entered
into an agreement with BECIL and made full payment towards its share
in the common infrastructure. The BECIL acted as a system integrator
for providing a common transmission infrastructure to enable the
petitioners herein to obtain SACFA clearance and frequency allocation
etc. The petitioners herein entered into „project management
OMP 280/2012 & connected petitions Page 5 of 50
agreements‟ (PMA) with the BECIL on different dates, the details of
which shall be given in the judgment later.
4. The PMA was primarily to provide project management services,
to build, install, commission and completion of the common
transmission infrastructure. The PMA contemplated payment of fee to
BECIL for providing project management services. The common
transmission infrastructure in terms of Annexure I included the
following:
Antenna system; RF Feeder cable and accessories; combiners; Antenna
switch frame; power supply system for the total set up; building works
to house CTI as also the building for LOI holder; individual transmitters,
rigid lines and accessories, Air conditioning arrangements, earthing
system for CTI, fire fighting equipment for CTI, technical furniture at
CTI.
5. Suffice to state, the common transmission infrastructure did not
include the tower to be constructed by BECIL on behalf of MIB. Clause
17.1 stipulated a dispute resolution mechanism through the process of
arbitration by a Sole Arbitrator to be nominated by the Secretary, MIB.
6. None of the petitioners have signed agreements for tower rental.
On July 25, 2011, the MIB had issued an order in the nature of policy
OMP 280/2012 & connected petitions Page 6 of 50
guidelines in pursuance to a decision of Union Cabinet with a purpose to
expand the FM Radio Broadcasting Services through private agencies
called the FM Radio Phase III. The guidelines stipulates migration of the
existing permission holders i.e. the petitioners herein, to Phase III,
subject to the provisions contained therein, which includes payment of
all outstanding dues pertaining to the government, Prasar Bharti and
BECIL in relation to existing FM radio permission/operations; signing
of fresh „grant of permission agreement‟ (GOPA). In any case, if the
existing permission holder does not execute the fresh agreement within
the given time, it shall be construed to mean that he does not want to
migrate to the FM Phase III regime and therefore shall continue to be
governed by Phase II policy provisions. The counsels for the parties
state that the last date for getting NOC is March 9, 2015 and the
deadline to sign the GOPA has been extended till March 23, 2015. I
may only point here that this Court in the order dated July 3, 2014, has
recorded that the deadline to migrate has been extended till March 31,
2015.
PLEADINGS OF THE PARTIES:
OMP 280/2012
7. It is the case of the petitioner that, it operates FM radio stations at
OMP 280/2012 & connected petitions Page 7 of 50
45 cities in the country. For the said purpose, it had paid to the MIB a
fee of Rs. 160 Crores as a one time entry fee and an amount of Rs. 30
Crores towards licence fee till March 2011. It had on March 23, 2006
entered into a PMA for common transmission infrastructure for the FM
radio Phase II at Delhi and similar agreements were entered for all 45
cities, in which, it operates. It is the case of the petitioner that the
respondent No. 1 is falsely claiming from it monitoring charges, which
were payable as per clause 13.1 of the GOPA. According to the
petitioner, the respondent No. 1 has failed to provide monitoring as
contemplated in GOPA. It has charged arbitrary interest @ 19.5 percent
on the outstanding amount. The petitioner has also raised an issue of
failure on the part of the respondent No. 1 to set up a CTI structure at
Kolkata and the advance paid to the respondent No. 1, was Rs.
1,08,00,000/-. The petitioner also raised an issue with regard to CTI
tower at Chennai, stating that, the same is inadequate as its height is 130
meters instead of 175 meters, prescribed in clause 12.2 of GOPA. In
other words, it is the petitioner‟s case that there exist genuine
commercial disputes between the parties. It is noted, that the petitioner
has invoked clause 17.1 of the PMA, seeking settlement of disputes
through arbitration.
OMP 280/2012 & connected petitions Page 8 of 50
8. The respondent No. 1 has filed its reply. It may not be necessary
for this Court to go into the details of the averments made in the reply
by the said respondents in view of an additional affidavit filed by the
respondent No. 1 on February 23, 2015. In para 4 and 5 of the additional
affidavit, the respondent No. 1 has stated as under:
“4. I state that there have been other dealing
between the parties in terms whereof tower rental,
monitoring charges in respect of monitoring of technical
compliances and content and Studio Transmission Links
(STL) charges are payable by the petitioner to respondent
No. 1. The said dealings are not under the Project
Management Agreements.
st
5. I state that upto 31 December, 2014 an
amount of Rs. 1,30,44,538/- was payable by the petitioner
towards tower rental for the Tower at Chennai for the
period 01.04.2008 to 31.03.2015 along with interest on
delayed payments of Tower Rentals amounting to Rs.
1,32,81,909/-. In addition, an amount of Rs.2,62,901/-
was due from the petitioner towards interest on STL
outstandings. The total amount due from the petitioner
upto 31.12.2014 was Rs. 2,65,89,348/-”.
The petitioner, in response to the affidavit has denied the amount
claimed by the respondent No. 1.
OMP 273/2012:
OMP 280/2012 & connected petitions Page 9 of 50
9. The case of the petitioner in this petition is that it is a private FM
radio broadcaster in India and operates under the brand name “Radio
One” operating in 7 Indian cities namely Mumbai, Delhi, Kolkata,
Chennai, Bangalore, Pune and Ahmedabad. Under the Phase II scheme,
it entered into a separate PMA for the 7 cities on March 20, 2006 and
April 15, 2006 with the respondent for setting up of CTI. It is also
averred that the petitioner was also required to enter into agreements for
use of Tower Aperture on payment of rent as per the said policy.
Pursuant to the PMA, the petitioner has paid approximately Rs. 7.3
Crores to the respondent for setting up of Common Transmission
Infrastructure (CTI). It is the petitioner‟s case that the respondent
delayed the setting up of Common Transmission Infrastructure, and in
the case of Kolkata, had not even built the same, thus, breaching the
time frame specifically provided under the project agreements. Such
delay caused grave prejudice and loss to the petitioner. The petitioner‟s
case is that it has been taking up the issue of delay in handing over the
site by the respondent and thus, insofar as Kolkata is concerned, an
amount of Rs. 1,08,00,000/- need to be refunded back, which has not
been done till date. Insofar as the refusal to enter into rental agreements
OMP 280/2012 & connected petitions Page 10 of 50
for the use of tower aperture at the cities of Chennai and Delhi, it is the
case of the petitioner that they had not executed solely on account of the
respondent having illegally and wrongfully levied rentals on the CTI
sites, which are not contractually payable to the respondent. Suffice to
state, the petitioner has been disputing the invoices raised by the
respondent. It is their case, that even the consortium of broadcasters
including the petitioner made several representations in respect of
claims made by the respondent, which have not been addressed to. The
petitioner states that in view of the new policy, enunciated by the MIB,
the migration from Phase II to Phase III is possible if a No-Objection
certificate is granted by the Prasar Bharti/BECIL, which presupposes the
payment of all dues by the petitioner. In other words, the respondent is
insisting upon the dues by the petitioner otherwise the petitioner would
not be eligible for seeking migration to Phase III, and as such,
compelled it to file the present petition, seeking an order, directing the
respondent to issue the petitioner a No due certificate, without prejudice
to its rights and contentions, pending the outcome of the arbitration
proceedings. I note, that, the petitioner has filed an application under
Section 11(6) of the Act i.e. Arb. P. 88/2015, which stands adjourned.
10. The respondent–BECIL has filed its reply to the petition.
OMP 280/2012 & connected petitions Page 11 of 50
11. On February 23, 2015, the respondent filed an affidavit wherein, it
has taken the following stand:
“4. I state that there have been other dealings between
the parties in terms whereof tower rental for the tower
erected at Delhi and Chennai and monitoring charges in
respect of monitoring of technical compliances and
content are payable by the petitioner to respondent No. 1.
The said dealings are not under the Project Management
Agreements.
st
5. I state that upto 31 December, 2014 an amount of
Rs.2,45,98,008/- was payable by the petitioner towards
tower rental for the Towers at Delhi and Chennai for the
period 01.04.2008 to 31.03.2015 along with interest
thereon amounting to Rs. 1,25, 84,741/-. In addition, an
amount of Rs. 4,35,882/- was due from the petitioner
towards monitoring charges for 7 cities. The total amount
due from the petitioner upto 31.12.2014 was Rs.
3,76,18,631/-”
12. A perusal of the affidavit now filed by the respondent would show
as on December 31, 2014, the total amount due is Rs.2,45,98,008/- against
tower rentals for the towers at Delhi and Chennai for the period April 1,
2008 to March 31, 2015 and interest thereon of Rs.1,25,84,741/- and an
amount of Rs. 4,35,882/- towards monitoring charges for 7 cities, the total
OMP 280/2012 & connected petitions Page 12 of 50
of which, comes to Rs.3,76,18,631/-. No reply to the additional affidavit
has been filed.
OMP 287/2012:
13. It is the case of the petitioner in the petition that it had participated
in the auction of licences in respect of FM broadcasting stations by the
respondent No. 2, Ministry of Broadcasting (MIB) in Phase II of the
licensing policy and has been granted Letter of Intent and subsequently,
executed GOPA dated September 13, 2006, inter alia to set up and operate
7 Radio stations in Tamil Nadu and Puducherry. In terms of the FM Radio
policy, Phase II, the petitioner was required to co-locate transmission
facilities with the existing infrastructure of Prasar Bharti and the common
facilities had to be integrated by the respondent. In these circumstances,
the petitioner entered into a PMA dated April 16, 2006 for CTI at Avadi,
Chennai with the respondent No. 1. During oral discussions with the
officials of the BECIL, it raised concern with regard to the strength of
signals that would originate at Avadi since it is located at least 20
kilometers from Chennai. According to the petitioner, it had paid to the
MIB (GOI) an amount of Rs. 24.3 Crores as one time entry fee for the
operation of the FM broadcasting stations. It has also incurred capital
expenditure of approximately Rs.60 Crores besides having paid a sum of
Rs. 5.18 Crores to the respondent No. 1. It is also the case of the petitioner
OMP 280/2012 & connected petitions Page 13 of 50
being a successful bidder, the petitioner was also required to enter into an
agreement paying rent for the use of the tower as per the said policy. It has
also made an advance payment of Rs.1,08,00,000/- as 100% advance
towards the estimated share of capital cost on cost sharing basis towards
the building, installation, commissioning and completion of CTI to the
respondent. Besides that, the petitioner was required to pay land and tower
rentals. According to the petitioner, as per the FM Phase II policy at places
where a suitable tower for Prasar Bharti was not available, the broadcasters
were permitted to operationalise their transmission facilities out of interim
set up till permanent set up was completed. The petitioner, for the city of
Chennai created an interim set up at Doordarshan Centre, Chennai, and
started operations of its Radio station under the name Hello FM on
October 02, 2006 and the petitioner continues to use the said facility till
date in view of the problems with the CTI set up/created by the respondent
No. 1 at Avadi. The petitioner‟s case insofar as the facility at Avadi is
concerned; the signals are poor, noisy with very low clarity. According to
the petitioner, it is in receipt of letter dated March 31, 2009, wherein, the
respondent No. 1 has alleged that the petitioner, while operating from the
interim set up at Chennai is in violation of GOPA as well as the PMA. The
petitioner‟s stand is that it responded vide letter dated April 13, 2009,
providing a detailed account of the disadvantages for phase II, due to
OMP 280/2012 & connected petitions Page 14 of 50
technological deficiencies in services as well as signal interference at CTI
complex at Avadi. The petitioner also contested the demand made by the
respondent No. 1 vide its letter dated October 12, 2009 of an amount of
Rs.31,37,780/- along with security deposit of Rs. 13,93,776/-, by stating
that, the demand is unjustified as the petitioner had not commenced use of
the same in view of several deficiencies highlighted by it. The petitioner
has also stated that the grievance of the petitioner has not been addressed.
The petitioner also referred to the issuance of policy guidelines in the year
2011 by MIB for migration to FM Radio Phase III. The petitioner has also
stated that the respondent has agreed to adjust the monitoring charges from
the balance advanced capital with them and further agreed to provide,
interest on the balance capital, advance available with them, and with the
said understanding, and in acknowledgement/admission of the same, the
respondent has even provided the petitioner with TDS certificates,
however, the respondent is yet to make a refund of Rs.3,226,875/- and in
view of the fact that the respondent No. 1 has miserably failed and
neglected to comply with its obligations under the agreement, it is
constrained to invoke the arbitration clause to refer the disputes before the
Sole Arbitrator. It has also referred to the writ petition filed by it being
WP(C) No. 1257 of 2012 being Radio One Ltd. Vs. Union of India and
Anr., wherein, the Court has observed that the appropriate remedy in view
OMP 280/2012 & connected petitions Page 15 of 50
of the arbitration clause between the parties, is initiation of arbitration and
seeking interim directions therein.
14. As noted in the other petitions, the respondent No. 1 had also filed
its reply so also the respondent No. 2. That apart, the respondent No. 1 has
filed an additional affidavit on February 23, 2013, wherein, the respondent
No. 1 has taken the following stand:
“4. I state that there have been other dealings
between the parties in terms whereof tower rentals for
the tower erected at Chennai and monitoring charges in
respect of monitoring of technical compliances and
content are payable by the petitioner to respondent No.
1. The said dealings are not under the Project
Management Agreements.
st
5. I state that upto 31 December, 2014, an
amount of Rs.1,30,44,538/- was payable by the
petitioner towards tower rental for the Tower at
Chennai for the period 01.04.2008 to 31.03.2005 along
with interest thereon amounting to Rs.63,54,980/-. In
addition, an amount of Rs.38,91,906/- was due from the
petitioner towards monitoring charges for the 7 cities.
The total amount due from the petitioner upto
31.12.2014 was Rs.2,32,91,424”.
15. Suffice to state, it is the case of the respondent No. 1 that the total
amount due from the petitioner as on December 31, 2014 was
OMP 280/2012 & connected petitions Page 16 of 50
Rs.2,32,91,424/- towards tower rental for the tower at Chennai along with
interest thereon and monitoring charges for the 7 cities under GOPA. No
reply to the additional affidavit has been filed.
OMP 295/2012:
16. The case of the petitioner in this petition is that pursuant to an
auction of the licenses in respect of private FM broadcasting stations by
the MIB in Phase II of the licensing policy, Letters of Intent were granted
to the petitioner to set up and operate radio stations in Category B cities of
Agra and Varanasi, Category C cities of Bareily, Jalandhar, Gorakhpur and
Ranchi, and Category D cities of Hisar and Karnal. It had executed GOPA
on November 23, 2006. It had paid to the Govt. of India an amount of Rs.
7.88 Crores as one time entry fee and an amount of Rs. 25,10,505/-
towards fee for the first year in respect of the aforesaid 8 stations. It had
also incurred capital expenditure for an approximately sum of Rs.24 Crores
besides having paid a sum of Rs.5 Crores to the respondent No. 1 and a
sum of Rs. 1.20 Crores to Prasar Bharti. In terms of the Phase II policy,
successful bidder was required to co-locate the transmission facilities with
the existing infrastructure of Prasar Bharti and the common facilities had to
be integrated by the respondent No. 1. In entered into agreements in the
year 2006 with the Prasar Bharti for its existing infrastructure on payment
of licence fee for each of its 8 radio stations. It had also entered into a
OMP 280/2012 & connected petitions Page 17 of 50
Project Management Agreement for CTI on April 22, 2006 with respect to
FM radio station at Karnal. Similar agreements were executed in all the 8
cities. The petitioner, in consideration of the respondent No. 1, building,
installing, commissioning and completing the CTI agreed to pay to BECIL
its share of actual cost as also fee for providing project management
services equivalent to 10% of its share of actual net cost. An advance
payment of Rs. 5,02,00,000/- was paid to the respondent No. 2 on
22.04.2006 for all 8 stations. Further, as per GOPA, the petitioner was
required to pay its share of monitoring charges arrived at by equally
apportioning Rs. 25,000/- per month amongst all permission holders for
the city. It is the case of the petitioner, that, the BECIL vide letter dated
March 19, 2009 demanded the outstanding monitoring charges for the year
2007-08 and 2008-09 from the petitioner. It is the case of the petitioner,
pursuant to certain discussions, it was agreed that the monitoring charges
be adjusted from the balance capital advance already with BECIL on
account of common infrastructure set up. It is the case of the petitioner that
approximately, Rs.60 lakhs are available with the BECIL and called upon
the BECIL to square up the monitoring charges and for final reconciliation
duly audited at their end so that the payments, if any, may be made by the
petitioner. Surprisingly, it received a show-cause notice dated May 5,
2011 from the MIB for non payment of monitoring charges and stating that
OMP 280/2012 & connected petitions Page 18 of 50
the petitioner was in violation of the GOPA. The petitioner brought to the
notice of the MIB the understanding arrived at between the parties. It is
also its case that inspite of such unreasonable and arbitrary conduct of the
respondent, it had sent a cheque of Rs. 7,86,535/- to the BECIL, being
outstanding amount as per the petitioner‟s calculations. The petitioner
referred to the policy enunciated on July 25, 2011 for expansion of FM
radio broadcasting services to private agencies Phase III, wherein,
migration was permissible from Phase II to Phase III, subject to payment
of all dues and securing an NOC from the concerned authorities. The
petitioner also referred to a letter dated September 8, 2011 issued by MIB
to the petitioner, asking it to clear the dues of the respondent before
migration could take place. According to it, as per the respondent, vide its
letter dated October 7, 2011, it had sent a final statement of accounts with
regard to 8 Radio stations, whereby, it raised a demand of Rs. 84,07,047/-.
The respondent demanded Rs.58,24,172/- towards monitoring charges,
which according to the petitioner, is not payable. The petitioner‟s case is
that the statement also included an amount of Rs.5,77,628/- paid as TDS
by BECIL.
17. Suffice to state, the petitioner contested the statement of accounts
sent to it. The petitioner referred to a writ petition being WP (C)
8782/2011 wherein, it had prayed for a direction to permit it to migrate
OMP 280/2012 & connected petitions Page 19 of 50
without necessity of obtaining a certificate from the respondent. The Court
gave direction for invoking the arbitration. The writ petition was
withdrawn by the petitioner with liberty to initiate arbitration proceedings.
It is necessary to state here that the petitioner has invoked clause 17.1 of
the Project Management Agreements.
18. The respondent Nos. 1 and 2 have filed their replies to the petition. I
would not dilate much on the replies filed by the respondent Nos. 1 and 2
in view of the additional affidavit filed by the respondent No. 1 on
February 23, 2015, wherein, the following stand has been taken:
“4. I state that there have been other dealings
between the parties in terms whereof monitoring charges
in respect of monitoring of technical compliances and
content are payable by the petitioner to respondent No. 1.
The said dealings are not under the Project Management
Agreements.
st
5. I state that upto 31 December, 2014 an amount
of Rs.49,87,204/- was payable by the petitioner towards
monitoring charges in respect of the 8 cities for the period
starting from 2007 to 31.03.2011 and 01.04.2012 to
31.03.2013. In addition, an amount of Rs.25,82,875/- was
due from the petitioner towards CTI outstandings under
the Project Management Agreements. The total amount
due from the petitioner upto 31.12.2014 was
Rs.75,70,079”.
OMP 280/2012 & connected petitions Page 20 of 50
In response to the aforesaid affidavit, the petitioner has denied, that the
amount of Rs.75,70,079/- is due and payable.
19. During the hearing, Mr. Rajeev Sharma, learned counsel for the
BECIL, the respondent No. 1, submitted a due payment summary of the
petitioner, wherein, it is reflected that, the petitioner has to pay an amount
of Rs. 54,87,586/- in total, the break up of which is Rs. 44,35,360/-, against
monitoring charges and Rs.10,52,226/- against CTI charges.
OMP 291/2012:
20. The petitioner has filed the present petition with a stand that it had
participated in the auction of licences in respect of private FM
broadcasting stations by the MIB in Phase II of the licensing policy and
granted Letters of Intent to set up and operate 10 radio stations in the cities
of Shimla, Ahmednagar, Dhule, Jabalpur, Hisar, Jalgaon, Karnal, Patiala,
Mujjafarpur and Ranchi. In terms of the Phase II policy, the petitioner was
required to co-locate transmission facilities with the existing infrastructure
of the respondent Prasar Bharti and common facilities had to be integrated
by the Broadcasting Engineering and Consultants India Ltd. (BECIL). It
had entered into 10 agreements for availing the respondent‟s infrastructural
facilities i.e. tower aperture, open space, land, covered space, building and
other facilities. It had also entered into PMA for 10 cities for CTI with
BECIL. In terms of the agreement, the petitioner was required to pay to
OMP 280/2012 & connected petitions Page 21 of 50
the respondent the annual licence fee in advance for use of the
respondent‟s infrastructure. Apart from this, the petitioner was to pay to
the respondent in the first year an amount equal to one year‟s licence fee
by way of security deposit which was refundable to the petitioner on
termination of the agreement(s). Furthermore, as per the agreement(s), the
petitioner was to pay to the respondent 10% after every two years for the
open/covered space and the common facilities; 2.5% after every year for
the tower. According to the petitioner, it had paid an amount of
Rs.4,76,72,382/- towards licence fee in respect of all the 10 radio stations
till date. Furthermore, an amount of Rs. 68,94,331/- as security deposit
was paid to the respondent at the time of execution of the licence
agreements. The petitioner also referred to the new policy formulated by
the MIB on July, 2011, which stipulates migration to Phase III subject to
clearing the dues and obtaining NOC from the concerned authorities. It is
the case of the petitioner that a meeting was held with the Joint Secretary,
Broadcasting of MIB on the issue of higher interest being charged by the
respondent for use of its infrastructure. It was decided that the issue of high
rentals will be discussed with the respondent in a separate meeting. Despite
such an assurance, no meeting had been called for by the respondent. It is
the petitioner‟s case that the respondent has failed miserably and neglected
to comply with its obligation under the agreement(s) and is further making
OMP 280/2012 & connected petitions Page 22 of 50
unreasonable demand from the petitioner and had no other alternative, but,
to invoke clause 12 of the agreement(s), invoking arbitration for reference
of the disputes so arisen between the parties before the Sole Arbitrator.
21. The respondent Prasar Bharti filed its reply wherein, it has taken a
plea that the petitioner has not invoked any arbitration clause even though
the petition was filed as far back as on March 26, 2012.
22. It is the case of the respondent that the petitioner has defaulted in
making the payments and in such circumstances, it is not entitled to any
interim measure or protection. It would state that the agreements for the 10
locations were executed as far back as on March/April, 2006. The
agreements were arrived at voluntarily and the petitioner never objected to
the licence fees specified therein. The respondent has also stated that the
petitioner had paid licence fee without demur upto 2010-11. The
respondent would submit that the petitioner has no prima facie case nor
any balance of convenience in its favour. Admittedly, the petitioner,
utilizing the land of the respondent, despite using the land, the petitioner is
refusing to pay the rent which is not justified.
23. On March 03, 2015, when the matter was heard by this Court, the
learned counsel for the petitioner has stated that the petitioner has paid all
the dues to Prasar Bharti. According to him, the Prasar Bharti in advance
had raised an invoice for the year 2015-16 which has to be paid to the
OMP 280/2012 & connected petitions Page 23 of 50
petitioner and the same should not come in the way of for grant of NOC.
Despite opportunity, no affidavit was filed and at the request of the counsel
for the petitioner, the matter was adjourned to March 5, 2015. On March
5, 2015, the learned counsel for the petitioner has clarified that invoice
raised by the Prasar Bharti was for the year 2014-15 for the usage of
infrastructure like tower, open space and common facilities. He would
concede to the fact, the petitioner has not invoked the arbitration clause.
24. Mr.Rajeev Sharma, learned counsel for the respondent would state
that an amount of Rs.1,02,82,583/- is due from the petitioner as on October
2014 with interest. He would state that till such time, the amount is paid
by the petitioner, NOC cannot be granted. The learned counsel for the
petitioner would submit that the petitioner would pay 50% of the amount
to the respondent.
OMP 294/2012:
25. In this petition, the petitioner has inter alia sought an order of
injunction restraining the respondent No. 1 from raising a demand of Rs.
81,11,040/- apart from seeking an order of issuance of No due certificate
so as to enable the petitioner to sign GOPA for phase III. It is the case of
the petitioner that pursuant to the participation in the auction of licences,
an LOI was issued by Ministry of Information and Broadcasting to operate
Phase II FM broadcasting stations in 10 cities of Shimla, Ahmednagar,
OMP 280/2012 & connected petitions Page 24 of 50
Duley, Jabalpur, Hisar, Jalgaon, Karnal, Patiala, Muzafarpur and Ranchi.
It had entered into PMA with the respondent No. 1 with regard to the 10
cities. It had paid the respondent No. 1 an amount of Rs.6,03,00,000/- in
respect of all 10 radio stations. It had made a security deposit of Rs.
68,94,331/- to the respondent No. 2 in respect of each radio stations in
terms of GOPA and Rs.4,76,72,382/- towards licence fee for all 10
stations. It is the case of the petitioner that there was an issue of breach of
contractual obligation by the respondent No. 1 in respect of petitioner‟s
radio station at Shimla as the CTI facility which was to be handed over on
20.04.2007 could be handed over only on 08.10.2009. It is its case that it
had incurred huge costs on account of the delay. It had also denied its
liability to pay escalated costs as well as for delay in construction of CTI in
Shimla. It had asked the respondent No. 1 to refund an amount of
Rs.40,25,000/-. However, the respondent No. 1 has not refunded it till
date. Even a request for No-Objection Certificate has not been acceded to.
26. The respondent No. 1 demanded from the petitioner a payment of
Rs.35,51,536/- towards CTI and Rs.45,59,504/- towards monitoring
charges and interest on account of late payment of monitoring charges.
The respondent No. 1 had also demanded an amount of Rs.14,57,671
towards electricity consumption for the month of November 2011 to
January 2012 for the 10 radio stations of the petitioner. The petitioner
OMP 280/2012 & connected petitions Page 25 of 50
would refer to the policy regarding Phase III issued by MIB and would
refer to the clauses with regard to the issuance of NOC, subject to
clearance of all dues by the radio operators. The petitioner also referred to
the understanding arrived at between the petitioner and the respondent No.
1, adjusting the monitoring charges from the balance advance capital
available with the respondent No. 1. The petitioner would submit that the
refusal to give No-Objection Certificate is illegal.
27. The respondent has filed its reply, taking various objections.
28. During hearing, Mr.Rajeev Sharma, has said that the total amount
due from the petitioner is Rs. 77,86,632/- against monitoring charges under
clause 13.2 of GOPA, which payment has to be made to BECIL. Similarly,
he would state that a further amount of Rs.35,51,536 as on December 31,
2014 is due for the Common Transmission Infrastruture provided by the
BECIL. He would state, a total sum of Rs.1,13,38,168 is due.
29. Learned counsel for the petitioner would submit, an amount of Rs.
77 lakhs would be secured by way of a bank guarantee. He would dispute
the payment of Rs. 35,51,536/- as there was a delay on the part of the
BECIL to construct the CTI at Shimla. He would also state, the said
amount would also be secured by way of a bank guarantee. It is his case
that the petitioner is hard pressed for money in view of various investments
made by it.
OMP 280/2012 & connected petitions Page 26 of 50
SUBMISSIONS:
30. Mr.Sandeep Sethi, learned counsel appearing for the petitioner in
OMP No.280/2012 would submit that the petitioner operates, FM stations
in 45 cities in the country and in that regard paid to the MIB fees of Rs.160
crores as one time entry fee and an amount of Rs.33 crores to BECIL and
that apart making huge investments. The petitioner is not a fly by night
operator, who would not honour, any award even if comes against it. He
has drawn my attention to the e-mail dated February 4, 2015, received
from BECIL along with an attachment, a statement showing outstanding
payment of Rs.28,33,175/-, which has been paid by it. He would state,
unfortunately, in the affidavit filed by the Respondent No.1, it had for the
first time taken a plea that, the Tower rental, monitoring charges and
Studio Transmission Links charges are payable by the petitioners are not
under the PMA. Such an objection has been taken after 3 years, of the
filing of the petition. He refers to letter dated November 21, 2011, written
by the petitioner to BECIL to contend, that the, petitioner has genuine
issues for which immediate attention of BECIL was sought like
reconciliation of advances, interest, monitoring charges, CTI Chennai etc.
With regard to Chennai, he would state the Tower in the city of Chennai
was erected at Avadi, a small town in North West of Chennai, is
inadequate technically as the height of the Tower constructed is 130
OMP 280/2012 & connected petitions Page 27 of 50
meters, instead of 175, and thus, it is legitimate and prudent for the
Respondent No.1 to refund the entire advance amount paid to BECIL
under the agreement. It was his endeavour, to argue that, the Respondent
No.1 does not dispute the genuine issues raised by the petitioner and the
Court which considers an application under Section 9 of the Act, would
have a prima facie view to decide whether a direction to the petitioner to
pay is necessary. The amount now being claimed by BECIL is with regard
to tower rental for the Tower in Chennai, and interest on delayed payment
of tower rentals for the cities of Delhi , Chennai and Hyderabad, in
addition to interest on STL outstanding, cannot be said to be dues unless
adjudicated. He would refer to the agreement executed with Prasar Bharti
on June 20, 2006 to contend, that it was for usage of infrastructure of
Prasar Bharti to be collected by BECIL on behalf of Prasar Bharti with an
Arbitration clause. He would also refer to PMA between the petitioner and
BECIL and its various provisions. According to him, there is no dispute
with regard to Monitoring charges under GOPA. In the end, it is his
submission that the petitioner could not be called upon to discharge, a
claim where there is no dispute.
31. On the other hand, Mr.Rajeev Sharma, learned counsel for the
Respondent No.1 would state that the FM II Policy was framed in the year
2005, under which, out of 91 cities, in 84 cities, the operators could co-
OMP 280/2012 & connected petitions Page 28 of 50
locate with the infrastructure of Prasar Bharti and for 7 cities, referred to
above, new Towers were erected by the BECIL on behalf of MIB. The
BECIL was only a collecting agency. Till such time the towers did not
come up in these 7 cities, the operators were at liberty to have an
arrangement either independently or at AIR/DD (PB) station. According
to him, the agreement referred to by Mr.Sethi with Prasar Bharti was one
such arrangement which the petitioner had for Delhi. He would state that,
the Tower rental is payable and this aspect has been conceded by the
petitioner in its letter dated December 29, 2011, wherein in Para 7(a) the
petitioner had stated “it is submitted that out of the total amounts specified
towards rentals only Rs.1,00,42,640/- is due and payable”. According to
him, in fact, BECIL has constructed the Tower at Chennai, in terms of the
policy, the petitioner is bound to pay the rentals. Unfortunately, despite
construction they have not co-located. He would also state that Mr.Sethi
has not answered the objection taken by the Respondent No.1, with regard
to the arbitrability of the issues regarding Tower Rentals, and interest on
Tower Rentals for the cities of Delhi, Hyderabad and Chennai, as there is
no Arbitration agreement between the parties. According to him, the
petitioner has invoked the arbitration clause under PMA. The petition
under Section 9 is itself not maintainable. He has taken me through the
provisions of the PMA, to highlight, the scope of the agreement to submit
OMP 280/2012 & connected petitions Page 29 of 50
construction of tower and payment of tower rent does not find place in
PMA. He would state that towers does not fall under Common
Transmission Infrastructure. The petitioners were to execute an agreement
with regard to tower rental. Unfortunately, they have not come forward to
execute the same. He would refer to page 34 of the reply of respondent
No.1, which is a statement showing tower rental status. According to him,
vide letter dated April 08, 2009, the petitioner was called upon to pay the
tower rental charges. Unfortunately, the same has not been paid. The claim
of rent is not a recent development. NOC can be given only if the dues are
paid, which are to the tune of Rs.2,65,89,346/-.
32. Mr.K.Datta in rejoinder to the submissions made by Mr.Rajeev
Sharma would submit that the respondent No.1 had never taken the
objection regarding arbitrability of the disputes. He would state, rather a
statement was made on behalf of the respondent No.2 that MIB is willing
to appoint an Arbitrator. In that regard, he draws my attention to the order
dated June 01, 2012 and May 28, 2012 passed in the petition. In view of
such a statement, it is not correct on the part of respondent No.1 to contend
that the issues/disputes are not arbitrable in the absence of an
agreement/arbitration clause. He would reiterate the submission made by
Mr.Sethi regarding inadequacy of the tower in Chennai, being of a lower
height. So, the issue of inadequacy of infrastructure is an issue which falls
OMP 280/2012 & connected petitions Page 30 of 50
under the PMA and as such arbitrable. He referred to Annexure 1 of the
PMA. He would also state that as per Section 7(4)(c) of the Act, an
Arbitration Agreement is in writing, an exchange of statements of claim
and defence, in which the existence of the agreement is alleged by one
party and not denied by the other party. He refer to para 48-49 of the
petition and corresponding para in reply in this regard. He also refers to
the order of the Division Bench dated March 02, 2012 passed in W.P.(C)
1257/2012 filed by one of the petitioner in this batch of petitions i.e.
„Radio One Ltd‟. to contend that the Division Bench has said that remedy
for the petitioner is to initiate arbitration proceedings and seek interim
direction therein. He has referred to Clause 5.3 of the GOPA filed in OMP
No.295/2012 to contend that GOPA recognizes the construction of tower
through BECIL. In the last it is his submission that without prejudice, the
petitioner shall deposit the principal amount, excluding interest in this
Court, pending decision by the Arbitrator, the NOC must be given to
enable the petitioner to migrate; otherwise great hardship shall be caused to
the petitioner. Out of the 45 stations, the dispute is with regard to only one.
According to him, as the petitioner is operating at other places, there
cannot be an apprehension that the petitioner would not be able to
discharge the liability if established against the petitioner. He has filed
written submissions in OMP 273/2012.
OMP 280/2012 & connected petitions Page 31 of 50
33. Mr.Rajiv Nayyar, learned Senior Counsel who appeared for the
petitioner in OMP 273/2012 adopted the arguments advanced in OMP
280/2012 by Mr.Sandeep Sethi/Mr.K.Datta. That apart he would point out
the letter dated December 19, 2014 written by BECIL and January 19,
2015 written by the petitioner No.1, which provide justification for non
payment of the dues by the petitioner. He would state, insofar as
monitoring charges are concerned, the same shall be paid by the petitioner.
He would also state, for the last so many years, the respondent has assured
the petitioner during the hearings that the issue would be resolved or in the
alternatively the matter would be referred to arbitration, but at this point of
time to say that the issue with regard to tower rentals is not arbitrable is
unjustified. He says as per Section 7(4)(b) & (c), read with the statements
made and averments not denied by the respondent No.1, in its reply, the
existence of an arbitration clause is admitted and in that regard he has
drawn my attention to para Nos.48 & 49 of the reply. According to him,
without prejudice, the petitioner is ready to deposit the amount in the
Court. He would rely on the judgment of the Supreme Court in BSNL &
Ors. Vs. M/s. Subhas Chandra Kanchan and Anr., AIR 2006 SC 3335
34. Mr.Rajeev Sharma, learned counsel for the respondent No. 1 would
submit that the petitioner claim to have invoked clause 17.1 of the PMA
executed with BECIL. According to him, tower rental interest therein and
OMP 280/2012 & connected petitions Page 32 of 50
monitoring charges do not fall within the ambit of the PMA and therefore,
disputes are not covered under PMA. He would also state that, the reliance
placed on Section 7(4)(b) and (c) of the Act is not tenable. For
applicability of Section 7(4)(c), there has to be a specific averment which
has not been denied. A bare reading of paragraph 48 shows that there is no
specific averment regarding tower rental and monitoring charges . He
relied upon the judgment of the Supreme Court in S.N.Prasad Vs.Monnet
Finance Ltd. and Ors., AIR 2011 SC 442. On Section 7(4)(b) of the Act,
he would state, the letters must record the existence of an agreement.
According to him, no such letters have been pointed out. He would also
state that the tower/tower rentals are not part of PMA as is clear from
Annexure I and III, which lists out the CTI. According to him, any
jurisdictional issue needs to be pleaded by the petitioner and the Court also
needs to consider such an issue while exercising jurisdiction. On the
statement of the ASG, regarding willingness of the Govt. of India to
appoint an Arbitrator as a proof of existence of an Arbitration clause, it is
the submission, such submission needs to be rejected for the following
reasons;
(i) MIB only nominates the Arbitrator;
(ii) The Secretary does not even have to see whether Arbitration
Agreement exists and whether the disputes are within the ambit of
OMP 280/2012 & connected petitions Page 33 of 50
arbitration agreement;
(iii) The statement of ASG is not indicative of any consent by BECIL.
He would, on the judgment of the Division Bench, states that, the DB did
not go into the question as to what disputes are arbitrable and contains no
adjudication on the said issue. In the last, he states, once policy has been
upheld, it is not a case of an interim measure.
35. Mr. R.Gogna, learned CGSC for MIB states that even after the order
dated 28.05.2012 was passed, when statement of learned Additional
Solicitor General was recorded, the MIB has filed its reply in some of the
petitions wherein, it has been averred that since MIB is not a party to the
PMA, and since there is no arbitration agreement between the petitioner
and the answering respondent, the petition against MIB is not
maintainable.
36. Mr.K.Datta in OMP No. 295/2012, apart from relying on the
submissions made in other petitions would state that the petitioner would
deposit in Court the amount claimed by the respondent No. 1.
37. Mr.Rajeev Sharma has referred to para No.4 & 5 of the affidavit
which is already reproduced above to state , the petitioner is liable to pay
the dues, and till such time, NOC cannot be issued.
38. The learned counsel for the petitioner in OMP No.291/2012, which
OMP 280/2012 & connected petitions Page 34 of 50
is filed primarily against Prasar Bharti would submit that an invoice for the
year 2014-15 has been raised by the Prasar Bharti for the usage of
infrastructure i.e. tower, open space, common facilities. The petitioner is
ready to pay 50% of the amount to the Prasar Bharti.
39. Mr.Sharma on the other hand would submit that the petitioner is in
arrears of Rs.1,02,82,583/- and hardship is not a ground to not pay the
dues. Mr.Sharma also justifies, claim of Rs.1,13,38,168/- towards
monitoring charges and CTI charges against the petitioner in OMP No.
294/2012.
40. Having considered the submission made by the learned counsel for
the parties, the foremost question which arises for consideration at least in
OMP Nos. 280, 273 and 287 of 2012, is whether the petitions under
Section 9 of the Act per se are maintainable in view of the objection taken
by the learned counsel for respondent No.1 that the disputes regarding
tower rental and interest thereon, is not covered by the PMA, the
agreement which they invoked for the purpose of filing the petitions. From
the pleadings, it is clear that the petitioners in the aforesaid OMPs did rely
on the arbitration clause in PMA. It is to be seen whether PMA encompass
in itself the issue related to tower rental to attract the arbitration clause.
The clause 3.1 of the PMA stipulates, BECIL providing project
management services to build, install, commission and complete the
OMP 280/2012 & connected petitions Page 35 of 50
Common Transmission Infrastructure and clause 5.1 stipulates in
consideration the operator shall pay to BECIL its share of actual net costs
and fee @ 10% of its share of actual net costs. Suffice to state, as stated
above, the CTI does not include tower construction or the rental to be paid
for its usage. Rather I find, the petitioner in OMP No. 273/2012 in para 13
of the petition has admitted that the parties i.e. the operators and the
BECIL were also required to enter into agreement for use of tower aperture
and payment of rent. It has also come on record in OMP No. 273/2012, in
the reply of the respondent No.1, as per Annexure R3, which is a copy of
the minutes of meeting held between the officials of BECIL, AIR, Private
FM Broadcasting Companies under the Chairmanship of JS(B) MIB
wherein, in para 2.5 of the minutes, the following is recorded on
operational date for tower rent fixation:-
“2.5. Operational date for tower rent fixation
FM operators stated that they had signed agreements for
tower rental at certain price in 2006. As per agreements, the
tower rental is to escalate at certain rate per annum. The FM
operators started using the tower in 2008 even though they
signed the agreements in 2006. BECIL is charging them the
tower rental from 2006. However, the FM operators
requested that the tower rental should be charged from 2008,
from the date of actual use instead of 2006, the date of signing
the agreement”.
OMP 280/2012 & connected petitions Page 36 of 50
41. From the above, it is clear that without any doubt that the parties
were required to execute a separate tower agreement, which would have
governed the tower rentals. Mr.Rajeev Sharma may be right in his
submission that despite being called upon to execute the agreements, the
petitioners have not come forward. In any case, it is suffice to state that the
issue/dispute of tower rentals is not governed by PMA and the invocation
of PMA seeking relief under Section 9 is not tenable. To seek relief under
Section 9, an existence of an arbitration agreement is necessary and in that
regard Section 7 of the Act defines Arbitration Agreement to mean as
under:-
| 7. Arbitration agreement. — | |
|---|---|
| (1) In this Part, “arbitration agreement” means an | |
| agreement by the parties to submit to arbitration all or | |
| certain disputes which have arisen or which may arise | |
| between them in respect of a defined legal relationship, | |
| whether contractual or not. | |
| (2) An arbitration agreement may be in the form of an | |
| arbitration clause in a contract or in the form of a | |
| separate agreement. | |
| (3) An arbitration agreement shall be in writing. | |
| (4) An arbitration agreement is in writing if it is | |
| contained in— | |
| (a) a document signed by the parties; |
OMP 280/2012 & connected petitions Page 37 of 50
(b) an exchange of letters, telex, telegrams or other
means of telecommunication which provide a record of
the agreement; or
(c) an exchange of statements of claim and defence in
which the existence of the agreement is alleged by one
party and not denied by the other.
(5) The reference in a contract to a document
containing an arbitration clause constitutes an
arbitration agreement if the contract is in writing and
the reference is such as to make that arbitration clause
part of the contract.
42. Section 7 of the Act had come up for interpretation before the
Supreme Court in Travancore Devaswom Board Vs. Panchamy Pack (P)
Ltd., (2004) 13 SCC 510 wherein the Supreme Court has in paras 6,7 and
8 held as under:-
“6. We are unable to accede to any of the
three submissions made by the respondent. The
Arbitration Conciliation Act, 1996, clearly provides
that the arbitration agreement must be an agreement
which should be in writing (see Section 7(4)). In this
case, there was no agreement at all, quite apart from
the fact that there was no writing to this effect. The
High Court has not in the impugned order recorded
any consent as has been contended by the
OMP 280/2012 & connected petitions Page 38 of 50
respondent. We are not prepared to act on any basis
other than that expressed by the High Court itself.
7. The impugned order, therefore, cannot be
sustained. In the absence of any agreement the
Arbitrator could not have any jurisdiction. The
participation of the appellant in the preliminary
sittings before the Arbitrator would not make any
difference. It is to be noted that under Section 7 Sub-
section (2), the ground challenging jurisdiction of
the Arbitrator is required to be taken at the earliest
and not later than the filing of the defence but a
party shall not be precluded from raising such a
plea merely because it has appointed or participated
in the appointment of an Arbitrator. The language of
the Section, therefore, leaves no room for doubt that
mere participation in the proceedings would not
tantamount to an acceptance of the jurisdiction of
the Arbitrator to arbitrate disputes between the
parties.
8. The decision reported in Tamil Nadu Electricity
Board case (supra) is on all fours with the facts of
the present case. This Court has clearly said in
paragraph 2 of the decision:
"12. Since disputed questions of facts arose in the
present appeals the High Court should not have
entertained Writ Petitions under Article 226 of
OMP 280/2012 & connected petitions Page 39 of 50
Constitution and then referred the matter to
arbitration in violation of the provisions of the new
Act. There was no arbitration agreement within the
meaning of Section 7 of the new Act. Under the new
Act, award can be enforced as if it is a decree of a
Court and yet the High Court passed a decree in
terms of the award which is not warranted by the
provisions of the new Act. The appellant had also
raised the plea of bar of limitation as in many cases
if suits had been filed those would have been
dismissed as having been filed beyond the period of
limitation. In our opinion exercise of jurisdiction by
the High Court in entertaining the petitions was not
proper and the High Court in any case could not
have proceeded to have the matter adjudicated by an
arbitrator in violation of the provisions of the new
Act."
43. Similarly, in S.N.Prasad (supra), the Supreme Court held that there
can be a reference to arbitration only when there is an agreement between
the parties. If there is a dispute between a party, to an arbitration agreement
with other parties as also non parties, the reference can be only with
respect to the parties to the Arbitration agreement and not the non parties.
44. On the maintainability of Section 9 petition in the absence of an
arbitration agreement, this Court in Ashok Kumar and Anr. Vs. SBI
Officers Association and Anr. 2013 X AD (Delhi) 512 has held as under:-
OMP 280/2012 & connected petitions Page 40 of 50
“15. It is well settled principle of law that the court
seized of an application under Section 9 of the Act can
form a prima facie opinion on the preliminary aspects
relating to arbitrability of the dispute prior to granting or
refusing the interim measures under the said section. This
is due to the reason that the court would proceed to
consider the grant or non grant of the interim measures
only upon the satisfaction that there exists a valid
arbitration clause covering the dispute raised before the
court. The said preliminary enquiry relating to
arbitrability of the dispute is the jurisdictional fact which
enables the court to assume jurisdiction on the application
and proceed to consider the same on merit. If on the other
hand, the dispute itself does not fall within realm of the
arbitration, then the court may straightaway proceed to
reject the application as the court may not be able exercise
its powers under Section 9 of the Act.
16. The position in law has been aptly described by the
Supreme Court in the case of SBP & Co. v. Patel
Engineering Ltd. & Anr. [(2005) 8 SCC 618] wherein the
Apex Court has considered the powers of the court or
judicial authority at great length when faced with a
question as to whether the power to appoint the arbitrator
is a judicial power or administrative function. While
answering the said question, the Supreme Court also
proceeded to observe that the court seized of the
application under Section 9 has the power to examine the
OMP 280/2012 & connected petitions Page 41 of 50
validity of the arbitration agreement and also to arrive at
the finding whether the dispute is covered by the
arbitration clause or not. Upon satisfaction of the
preliminary jurisdictional facts, the court can proceed to
assume jurisdiction over the subject matter. In the words
of the Supreme Court speaking through Hon’ble
Balasubramaniyam for Majority (as his lordship then
was), it was observed thus:
“Similarly, Section 9 enables a Court, obviously, as
defined in the Act, when approached by a party before
the commencement of an arbitral proceeding, to grant
interim relief as contemplated by the Section. When a
party seeks an interim relief asserting that there was a
dispute liable to be arbitrated upon in terms of the
Act, and the opposite party disputes the existence of an
arbitration agreement as defined in the Act or raises a
plea that the dispute involved was not covered by the
arbitration clause, or that the Court which was
approached had no jurisdiction to pass any order in
terms of Section 9 of the Act, that Court has
necessarily to decide whether it has jurisdiction,
whether there is an arbitration agreement which is
valid in law and whether the dispute sought to be
raised is covered by that agreement. There is no
indication in the Act that the powers of the Court are
curtailed on these aspects. On the other hand, Section
9 insists that once approached in that behalf, "the
OMP 280/2012 & connected petitions Page 42 of 50
Court shall have the same power for making orders as
it has for the purpose of and in relation to any
proceeding before it". Surely, when a matter is
entrusted to a Civil Court in the ordinary hierarchy of
Courts without anything more, the procedure of that
Court would govern the adjudication.”
(Emphasis Supplied)
45. Now it is to be seen, what is the effect of the pleadings of the parties,
more specifically, in para 48 and 49 of OMP 273/2012 and also the
statement made by the learned ASG regarding appointment of an
Arbitrator, on the dispute regarding tower rental. Whether the dispute
regarding tower rental can at all be referred to arbitration.
46. I note, the petitioner in OMP 273/2012 in para 48 has stated “that
due to the inaction and/or failure and/or refusal by the respondent to act in
accordance with the agreements in releasing the payments to the petitioner
illegally withheld by it, releasing outstanding dues payable under the
PMAs; delaying any issuance of any clarifications on rentals and security
charges for sights at Delhi and Chennai.........XXXX” , to which, the reply
of the respondent BECIL is “it is denied that there is any inaction and/or
failure and/or refusal by respondent to act in accordance with the
agreements. It is denied that the respondent is liable to pay any amount to
the petitioner or there is any outstanding dues payable by it under the
OMP 280/2012 & connected petitions Page 43 of 50
project management agreement to the petitioner. It is denied that there is
any delay in issuance of clarifications on rentals and the security charges
for sites at Delhi and Chennai”.
47. To construe an averment made is an acceptance of a particular fact,
it is necessary, that such averment must be specific and unambiguous and
not by drawing an inference. To construe that the averments made above
relates to tower rentals, the petitioners should have pleaded; the agreement
in question (PMA) is in writing and deals with tower rentals and the said
agreement contains arbitration clause for settlement of disputes with regard
to tower rentals. In the absence of a specific and unambiguous stand in the
petition, it cannot be construed that the respondent has accepted the
existence of an arbitration agreement with regard to tower rentals.
Moreover, any claim by the petitioner with regard to existence of an
arbitration agreement qua tower rentals cannot be read in isolation
overlooking a specific stand of the petitioner in para 13 of the petition,
wherein, the petitioner has conceded that the parties were required to enter
into agreements towards the use of CTI tower aperture at the cities of
Chennai and Delhi and payment of rent. It cannot now, plead and contend
that the averments in para 48-49 must be read to mean that it had taken a
stand that the tower rentals are covered by PMA.
48. With regard to the statement made by the learned ASG during the
OMP 280/2012 & connected petitions Page 44 of 50
hearing on May 28, 2012, it is noted, the same has to be read in the context
that Union of India is willing to appoint an Arbitrator in terms of the
Arbitration clause (emphasis supplied). Suffice to state, with regard to
tower rentals, neither there was an agreement nor any arbitration clause.
The statement, can be read with regard to the disputes related to the
agreements executed between the parties i.e. PMA. It is also the case of
MIB during the submissions that after the hearing, dated May 28, 2012, it
has pleaded in its reply that in the absence of MIB being a party to the
arbitration agreement, the same is not binding on it.
49. Insofar as the judgment on which reliance was placed by Mr.Rajiv
Nayar, in the case of BSNL and Ors. (supra) is concerned, the Supreme
Court was considering a case wherein, existence of an arbitration
agreement is not disputed. Rather, clause 25 was an arbitration clause, in
terms of which, the Arbitrator was to be appointed by the Managing
Director of the appellant company. While hearing an application under
Section 11(6) of the Act, no objection was given by the counsel for the
appointment of Mr.B.C.Bhattarcharya as an Arbitrator. The said
statement was sought to be resiled from by the learned counsel for the
appellant, which was not agreed to by the High Court and in the said
background, the Supreme Court held, such a statement, cannot be resiled
OMP 280/2012 & connected petitions Page 45 of 50
from in view of the provisions of Order III Rule 1 of the Code of Civil
Procedure. The facts of the present case are different inasmuch as there
is no arbitration agreement in this case on tower rentals, the judgment
would not help the petitioner‟s case. Further, the order of the Division
Bench in W.P.(C) 1257/2012 dated March 2, 2012 would also not help
the case of the petitioners.
50. From the above, I note the disputes/differences between the
parties primarily are as below:
| Petition No. | Nature of dues | Payable under |
|---|---|---|
| OMP 280/2012 | (1) Tower rental; Chennai<br>(2) Interest on tower rental for<br>the city of Delhi, Hyderabad<br>And Chennai<br>(3) Interest on STL outstandings | No agreement for (1) and (2)<br>(3) GOPA |
| OMP 273/2012 | (1) Tower rental for the towers<br>at Chennai and Delhi with<br>interest<br>(2) Monitoring charges for 7 cities | (1)No agreement<br>(2) GOPA |
| OMP 287/2012 | (1) Tower rental at Chennai with<br>Interest<br>(2) Monitoring charges for 7<br>Cities | (1) No agreement<br>(2) GOPA |
| OMP 295/2012 | (1) Monitoring charges in<br>Respect of 8 cities<br>(2) CTI outstandings | (1) GOPA<br>(2) PMA |
| OMP 291/2012 | Tower, open space, common<br>Facilities | Agreement with Prasar Bharti |
| OMP 294/2012 | (1) Monitoring charges<br>(2) CTI charges | (1) GOPA<br>(2) PMA |
51. The petitioners in the present petitions have primarily invoked
PMA. The disputes under PMA are primarily CTI charges. In OMP
280/2012, OMP 273/2012 and OMP 287/2012, tower rentals have also
been claimed, for which, there is no agreement. In the absence of an
agreement for referring the disputes relating to tower rentals, a petition
OMP 280/2012 & connected petitions Page 46 of 50
under Section 9 of the Act would not be maintainable nor a direction as
sought for by the petitioners for issuance of NOC can be granted. These
petitions are accordingly dismissed.
52. Insofar as OMP Nos. 295/2012, 291/2012 and 294/2012, are
concerned, they primarily relate to monitoring charges, CTI charges,
charges for common facilities etc. under GOPA/PMA/agreement with
Prasar Bharti. In OMP 295/2012, the petitioner has only invoked clause
17.1 of the PMA and not the corresponding clause in GOPA. Insofar as
OMP Nos. 291/2012 and 294/2012 are concerned, the petitioner has not
invoked the relevant arbitration clause till date even though three years
have elapsed since the filing of the petitions. This itself can be a ground
to dismiss these petitions under Section 9 in view of the pronouncement
of the judgment of the Supreme Court in Sundaram Finance Ltd. Vs.
NEPC India Ltd., (1999 ) 2 SC 479 wherein, the Supreme Court has
stated, that, when an application under Section 9 of the Act is filed
before the commencement of the arbitral proceedings, there has to be a
manifest intention on the part of the applicant to take recourse to the
arbitral proceedings. Absence of invocation does not reveal the
manifest intention on the part of the petitioner to take recourse to the
arbitral proceedings. A possible argument of the petitioners on this
OMP 280/2012 & connected petitions Page 47 of 50
could be, it was under the bona fide belief of the matters getting settled.
53. It is true, as seen from the order sheets, the petitions also got
adjourned on the ground of settlement. It is also noted, that the last date
of migration to Phase III also got extended. Possibility of the petitioners
being under the bona fide belief that matters would be settled, and as
such, no steps were taken to invoke arbitration clauses, cannot be ruled
out, but, the larger question would be whether they have made out a
prima facie case, for grant of interim measure. The answer is in the
negative, for more than one reason; the amount sought to be recovered
by BECIL/Prasar Bharti has a contractual basis, in
GOPA/PMA/Agreement in the case of Prasar Bharti; the agreements
have been executed as per the policy enunciated by the MIB; the
demand made is not speculative. I note from the respective stand of the
parties, they are justifying/contesting the demand. The differences need
to be decided, through the process of arbitration contemplated under the
agreements, that cannot be a reason, not to pay the dues as demanded for
the purpose of NOC, in terms of the policy dated July 25, 2011, which
provision has been upheld by the Division Bench of this Court in
W.P.(C) 1257/2012. Even though, the petitioners have offered to give
bank guarantees as security/pay some of the amount, this Court is of the
OMP 280/2012 & connected petitions Page 48 of 50
view, the only order that can be passed, keeping in view the facts is that,
insofar as OMP No. 295/2012 is concerned, the petitioner shall deposit
the entire amount as claimed from it with BECIL within 10 days from
today. On deposit of the said amount, the BECIL, shall issue NOC to
the petitioner within two days. Simultaneously, the petitioner shall also
invoke the arbitration clause under GOPA. The BECIL shall keep the
amount so deposited by the petitioner in an interest bearing FDR(s) till
the culmination of the arbitration proceedings by the Arbitrator, to be
appointed by this Court in the petition filed by the petitioner under
Section 11(6) of the Act and pursuant to invocation of GOPA in terms
of this order, so that the interest amount is enured to the successful
party. Suffice to state, the deposit of the amount is subject to the orders
to be passed in Arbitral proceedings.
54. Similarly, insofar as OMP Nos. 291/2012 and 294/2012 are
concerned, the petitioner shall deposit the entire amount claimed from it
with BECIL/Prasar Bharti within 10 days. On deposit of the said
amount, the BECIL/Prasar Bharti shall issue NOC to the petitioner
within two days. Simultaneously, the petitioner shall also invoke the
arbitration clause for appointment of an Arbitrator within 10 days from
today. The BECIL/Prasar Bharti shall keep the amount so deposited by
OMP 280/2012 & connected petitions Page 49 of 50
the petitioner in an interest bearing FDR(s) till the culmination of the
arbitration proceedings by the Arbitrator(s), so that the interest is enured
to the successful party. Suffice to state, the deposit of the amount is
subject to the orders to be passed in arbitral proceedings.
55. The conclusion is, OMP Nos. 273/2012, 280/2012 and 287/2012
are dismissed.
56. OMP Nos. 291/2012, 294/2012 and 295/2012 are disposed of in
terms of the directions in para 53 & 54 of this judgment.
(V.KAMESWAR RAO)
JUDGE
MARCH 10, 2015
akb
OMP 280/2012 & connected petitions Page 50 of 50