Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
PETITIONER:
UNION OF INDIA.
Vs.
RESPONDENT:
M/S. G.S. ATWAL & CO.(ASANSOLE)
DATE OF JUDGMENT: 22/02/1996
BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
G.B. PATTANAIK (J)
CITATION:
1996 SCC (3) 568 JT 1996 (2) 607
1996 SCALE (2)447
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
K. RAMASWAMY. J.
This appeal by special leave arises from the judgment
and order dated February 12, 1992 of the Division Bench of
the Calcutta High Court in F.M.A.T. No. 1990 of 1991. The
respondent had entered into an agreement in 1968-69 for
excavation of feeder canal from RD.68.00 to RD.97.00. During
the course of the execution of the work certain disputes had
arisen between the respondent and the appellant. The
disputes were referred from time to time to arbitration.
This is the 5th arbitration the instalment. Details of
previous four arbitrations are as under:
S. Name of the Award Interest Amount
No. Arbitrator Rs. Rs. Rs.
--- ----------- ----------- ------------ -------------
1. R.P. Ahuja 4,70.000.00 78,129.45 5,48,129.45
2. O.P. Gupta 7,00,974.00 7,604.96 7,08,578.96
3. T. Rajaram 23,78,100.00 23,34,501.00 47,12,601.60
4. Brig.D.R.
Kathuria 78,90,570.00 38,40.653.88 1,17,31,223.00
------------------------------------------------------------
The dispute as regards hire charges of equipment load
by Farakka Barage Project was referred to Goyal Committee
for rationalization. On submission of its report and in
furtherance thereof the respondent by letter dated August 8,
1984 had claimed for reference to the arbitration thus:
"And whereas M/s. Tarapore & Co.
having long back been refunded the
excess hire charges recovered
earlier, but having became
refundable on the basis of said
Goyal Committee Report, in our case
the excess recovered amount and now
refunded to us despite repeated,
written as well as oral requests
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
and demands in this respect."
[emphasis supplied]
In furtherance thereof, by proceedings dated November
18, 1984, the General Manager, Farakka Barrage Project
appointed T. Raja Ram as the sole arbitrator to settle the
disputes. After entering into the reference on December 12,
1984, admittedly the respondent laid claim for the refund of
hire charges which was disputed by counter-statement by the
appellant. Later the respondent laid further claims on March
6, 1985 for Rs.1,68,000/- towards repairs on departmental
equipments; Rs.1,38,600/- towards refund of expenses on
security watch and ward; Rs.28,12,085.33 towards final bill
of the firm; Rs. 95,60,653.10 towards part interest and the
amount of claim in addition to the refund of hire charges
was Rs.32,45,538.27. The appellant in its statement had
objected to unilateral enlargement of the reference. The
arbitrator awarded by a non-speaking award dated August 18,
1987, a sum of Rs.35,72,550/- with interest at 15% per annum
from July 1, 1976 or the date of the payment of decree
whichever was earlier.
The appellant fixed Misc. Case No.95/87 on April 8,
1988 under Section 30(c) of the Arbitration Act, 1940 [for
short, the ’Act’], questioned the award contending that the
claim was barred by limitation; the arbitrator had no power
to enlarge the scope of the arbitration and he had no power
to award interest at higher rate without any claim before
it. The Assistant District Judge, Murshidabad by his order
dated January 19, 1991 set aside the award upholding these
contentions. On appeal, in the inpugned order the High Court
set aside the order of the civil Court holding that there
was no error apparent on the face of the award warranting
setting aside of the award. It directed the civil Court to
take steps for passing a decree in terms of the award as
expeditiously as possible not later than four months. Thus
this appeal by special leave.
Since Shri Goswamy, learned senior counsel appearing
for the appellant has not pressed the bar of limitation for
our consideration, it is unnecessary for us to go into that
question. Only two questions have been canvassed, viz., the
power of the arbitrator to unilaterally enlarge the scope of
the reference and the power to award the amount in a non-
speaking award and the rate of interest. The question
therefore, is: whether the arbitrator has jurisdiction and
power to unilaterally enlarge the reference? As extracted
above, the specific demand and acceptance by the Manager of
Farakka Barage Project was to refer the dispute of refund of
hire charges pursuant to the report of the Goyal Committee.
That was acceded to and reference to T. Raja Ram was made
for arbitration on November 18, 1984 and claim in that
behalf was duly made. On March 6, 1985 claims were laid by
the respondent for arbitration. They were objected to by
the respondent. The question emerges: whether the arbitrator
has power to unilaterally enlarge the reference and
adjudicate the claims? It is seen that impugned award is a
non-speaking award. Shri Soli J. Sorabjee, learned senior
counsel for the respondent contended that the appellant
having participated before the arbitrator and had an award
unfavorable to them, could not question invalidity
thereafter. The appellant had participated in the
proceedings before the arbitrator with full knowledge of
these facts. The conduct on the part of the appellant
amounts to acquiescence to the power and jurisdiction of the
arbitrator to make the award. Thereby the plea of lack of
jurisdiction cannot be permitted to be raised by the
unsuccessful party to the arbitration. In support thereof he
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
placed strong reliance in N.Chillappam v. Secretary, Kerala
State Electricity Board and Anr.[(1975) 1 SCC 289]; M/S.
Neelkanthan Construction v. Superintending Engineer,
National Highways, Salem and Ors. [(1988) 4 SCC 462]; Russel
on Arbitration, 17th Edition, page 215; 33, Chowdhri Murtaza
Hossein v. Mussumat Bibi Bechunnisa [L.R. (IA) Vol.III 209];
Champsey Bhara & Company v. Jivraj Balloo Spinning and
Weaving Company, Ltd. [L.R. (IA)Vol.I 324]; Champsey Bhara
Company v. The Jivraj Ballo Spinning and Weaving Company
Ltd. [AIR 1923 P.C. 66] and Firm Madanlal Roshan Lal Mahajan
v. Hukumchand Mills Lrd., Indore [(1967) 1 SCR 105 ].
To constitute an arbitration agreement, there must be
an agreement that is to say the parties must be ad idem.
Arbitrability of a claim depends upon the dispute between
the parties and the reference to the arbitrator. On
appointment, he enters upon that dispute for adjudication.
The finding of the arbitrator on the arbitrability of the
claim is not conclusive, as under Section 33 ultimately it
is the court that decides the controversy. In U.P. Rajkiya
Nirman Nigam Ltd. v. Indure Pvt.Ltd. & Ors. decided on
February 9, 1996, a three-Judge Bench of this Court [to
which one of us, K. Ramaswamy, J., was a member was to
consider the question whether the arbitrator had
jurisdiction to decide the arbitrability of the claim
itself. In that context, the question arose: whether there
was an arbitration agreement for reference to the
arbitrator? It was held that the arbitrability of the
controversy of the claim being a jurisdictional issue, the
arbitrator cannot cloth himself with jurisdiction to
conclusively decide, whether or not he had power to decide
his own jurisdiction. Relying upon the passage in "Russel on
Arbitration" [19th Edn.] at page 99, this Court had held
that it can hardly be within the arbitrator’s jurisdiction
to decide whether or not a condition precedent to his
jurisdiction has been fulfilled. The arbitrator had no power
cide his own jurisdiction. The arbitrator is always entitled
to inquire whether or not he has jurisdiction to decide the
dispute. He can refuse to deal with the matter at all and
leave the parties to go to the court if he comes to the
conclusion that he has no power to deal with the matter; or
he can consider the matter and if he forms the view that the
contract upon which the claimant is relying on and from
which, if established, he alone has jurisdiction, he can
proceed to decide the dispute accordingly. Whether or not
the arbitrator has jurisdiction and whether the matter is
referred to or is within the ambit of clause for reference
of any difference or dispute which may arise between the
martis, it is for the Court to decide it. The arbitrator by
a wrong decision cannot enlarge the scope of the submission.
It is for the court to decide finally the arbitrability of
the claim in dispute or any clause or a matter or a thing
contained therein or the construction thereof. It was,
therefore, held that "arbitrators cannot cloth themselves
with jurisdiction to decide conclusively the arbitrability
of the dispute." It si for the court under Section 33 or on
appeal thereon to decide it finally". There is no estoppel
to challenge the action and to seek a declaration under
Section 33. It was further held that "mere acceptance or
acquiescence to the jurisdiction of the arbitrator for
adjudication of the dispute as to the extent of the
arbitration agreement or arbitrabity of the dispute does not
disentitle the appellant to have the remedy under Section 33
through the court." The remedy under Section 33 is "the only
right royal way for deciding the controversy."
In Law of Arbitration by Justice Bachawat [2nd (1987)
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
Ed.] at page 90 it is stated that jurisdiction of the
arbitrator is solely derived from the arbitration agreement.
The arbitrator has jurisdiction to deal only with matters
which on a fair construction of the terms of the
contract,the parties agreed to refer to him. Whether or not
the arbitrator acts within the jurisdiction depends solely
upon the clause of reference. The court may grant a
declaration that the party appointed by the defendants as
the arbitrator has no jurisdiction. The submission furnishes
the source and prescribes the limit of the arbitrator’s
authority. The arbitrator take upon himself an authority
which the submission does not confer on him. The award must
in substance and form conform to the submission, It must
comply in point of form to the directions contained in the
submission. If the award determines any matter not referred
to arbitration and such matter cannot be separated without
affecting the determination of the matters preferred, the
award is invalid. It may be remitted to the arbitrator for
reconsideration under Section 16 and if the arbitrator acts
in excess of authority, the award should be set aside.
In N. Chellappan v. Secretary, Kerala State Electricity
Board and Anr. [(1975) 1 SCC 289], the facts therein were
that the arbitrators nominated an umpire. The arbitrators
did not make the award within the time limit which
ultimately expired. Thereupon the appellant had invoked the
jurisdiction of the civil Court to revoke the authority of
the arbitrator under Sections 5 and 11 of the Act. An
application was made to appoint ’K’ to enter upon the
reference as an umpire and to proceed with the arbitration.
Another application was made to appoint ’K’ as the sole
arbitrator in place of two arbitrators. The court revoked
the authority of the arbitrators and directed the umpire to
enter upon the dispute in his capacity as an umpire and
allowed the application of the appellant to appoint ’K’ as
the sole arbitrator. The umpire entered upon the reference
in his capacity as an umpire. The party submitted to his
jurisdiction, conducted the proceedings and when the award
went against the respondent-Board umpire’s jurisdiction was
challenged. On those facts a three-Judge Bench of this Court
had held that when the respondent Board acquiesced to the
jurisdiction of the umpire as the sole arbitrator, the Board
was, by acquiescence, precluded from challenging the
jurisdiction of the umpire. When the party consented to the
appointment and took part in the proceedings with full
knowledge of the relevant fact of appointment as the sole
arbitrator it amounted to acquiescence. Same is the ratio in
M/s. Neelankantan & Bros. Construction v. Superintending
Engineer, National Highway, Salem & Ors. [(1986) 4 SCC 462]
wherein a two-Judge Bench of this Court held that if the
parties to the reference either agree beforehand to the
method of appointment, or afterwards acquiesce in the
appointment made, with full knowledge of all the
circumstances, they will be precluded from objecting to such
appointment as invalidating subsequent proceedings.
Attending and taking part in the proceedings with full
knowledge of the relevant fact will amount to such
acquiescence. The rest of the decisions are not directly on
the point. Therefore, it is not necessary to burden the
judgment with reference to those cases.
It would thus be seen that appointment of an arbitrator
is founded upon the agreement between the parties, Once on
his appointment either by consensus or by an order of the
court, the parties put forth their claim and participate in
the proceedings, the parties acquiesce to the appointment of
the arbitrator and the award made thereon binds the parties.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
The party who has suffered the award is precluded from
questioning the power and jurisdiction of the arbitrator to
make the award. The reason being that the parties have by
contract consented to the forum to adjudicate their dispute
and to-give a decision, by a non-speaking or speaking award
in terms of the agreement. This principle is inapplicable to
the jurisdiction of the arbitrator to unilaterally enlarge
his own power to arbitrate any of the disputes. It is seen
that by express agreement between the parties, arbitrability
of the claim for refund of the hire charges was referred to
arbitration and T. Raja Ram came to be appointed as
arbitrator and entered upon that reference. But when claim
was made, he enlarged the dispute unilaterally without there
being any agreement by the appellant. In fact they objected
to the enlargement of the Scope of the arbitration. Since
arbitrator went on adjudicating the disputes, they were left
with no option but to participate in the proceedings as the
claims were pressed for and parties submitted to the
jurisdiction of the arbitrator. Therefore, it did not amount
to acquiescence. The jurisdiction of the arbitrator is
founded upon the agreement between the parties. To the
extent of the agreement, the parties are bound by the
decision of the arbitrator. But the arbitrator cannot
enlarge the scope of his arbitration and make in a non
speaking award, a lump sum amount of all claims, after
enlarging his jurisdiction on non-accepted or objected
claims. In Champsey Bhara Company case [supra] Lord Dunedin,
speaking for the Privy Council had held that "(t)he question
of whether an arbitrator acts within his jurisdiction is, of
course, for the Court to decide but whether the arbitrator
acts within his jurisdiction or not depends solely upon the
clause of the reference. It is, therefore, for the Court to
decide... whether the dispute which has arisen is a dispute
covered by Cl. 13 of the Articles". In Gobardhan Das v.
Lachmi Ram and Ors. [AIR 1954 SC 689], this Court held that
so long as the arbitrator acts within the scope of his
authority there is no doubt that the decision must be
accepted as valid and binding on the parties. In that case,
the agreement entered into between the parties read as
under:
"that the arbitrators should sit
together, take down the statements
of the parties, hear and consider
the arguments brought forward by
the parties, inspect the documents
of all descriptions and take other
evidence and evidence of witnesses
and whatever award they shall give,
is and shall be, acceptable to the
parties and whatever award the
arbitrators may give unanimously or
by majority of votes shall be
treated as true and correct and
valid in every court and shall be
binding upon all of us executants
parties."
The arbitrators went out of their way to declare that
whatever amount in addition to Rs.3,500/- was found due from
respondent No.1 upon the bahikhata account was remitted
having regard to his labour and poverty and the whole
unspecified amount found due against respondent No.2 was
remitted in full in view of his labour and poverty. It was
contended that the award was decided outside the authority
of the arbitrators. It was held that the arbitrators had
clearty misdirected themselves and had exceeded the scope of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
their authority and the award was, therefore set aside.
Thereby, the arbitrator had misdirected himself and
committed legal misconduct in making the award vitiating the
entire award itself. It is difficult to decide as to what
extent each of the claims was accepted or rejected. In that
view, it is not necessary to go into the second question of
the power of the arbitrator to award interest or excess
rate of interest.
The appeal is accordingly allowed. The order and
judgment of the High Court is set aside and that of the
trial Court is restored, but in the circumstances, parties
are directed to bear their own costs.