Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.8714 OF 2022
(Arising Out of SLP (CIVIL) NO.18607 OF 2004)
KARNATAKA POWER TRANSMISSION
CORPORATION LIMITED ...APPELLANT(S)
VERSUS
JSW ENERGY LIMITED
(EARLIER KNOWN AS JINDAL
THERMAL POWER COMPANY
LIMITED & JINDAL TRACTABEL
POWER COMPANY LIMITED) & ORS. ...RESPONDENT(S)
With
CIVIL APPEAL NO.8715 OF 2022
(Arising Out of SLP (CIVIL) NO.23793 OF 2004)
KARNATAKA ELECTRICITY REGULATORY
COMMISSION ...APPELLANT(S)
VERSUS
JINDAL THERMAL POWER COMPANY
LIMITED & OTHERS ...RESPONDENT(S)
J U D G M E N T
K.M. JOSEPH, J.
1. Leave granted. Being connected, the appeals are
Signature Not Verified
Digitally signed by
Jagdish Kumar
Date: 2022.11.22
16:16:07 IST
Reason:
being disposed of by a common judgment.
1
2. The appellant, in appeal arising out of SLP (C) No.
18607/04, is the Karnataka Power Transmission
Corporation Limited and hereinafter referred to as ‘the
appellant’.
3. By the impugned judgment, the High Court has
allowed Miscellaneous First Appeal No. 4795 of 2002
filed by the first respondent herein, viz ., JSW Energy
Ltd., earlier known as Jindal Thermal Power Company
Limited (hereinafter referred to as the first
respondent). The appeal was filed by first respondent
under Section 41 of the Karnataka Electricity Reforms
Act, 1999 (hereinafter referred to as the ‘Act’ for
brevity).
4. By the impugned order, the High Court has set aside
the order dated 22.05.2002 and the order dated
08.07.2002 which are orders passed by the Karnataka
Electricity Regulatory Commission (hereinafter
referred to as ‘Commission’ for brevity). The
Commission is the appellant in the other appeal. The
High Court has after setting aside the impugned orders
directed the appellant, to comply with the tariff rate
specified in the order of the Government of Karnataka
2
(hereinafter referred to as ‘GoK’ for brevity) dated
12.05.1999. The further direction given is as follows:
“(ii) as per the interim order passed by this
th
Court on 19 November, 2002, it is stated by
Dr. Singhvi that the appellant has paid 40%
of Rs. 62.5 crores computed by the KPTCL as
difference between the PPA rates and the rates
fixed by the Commission and, therefore, we
direct the KPTCL to repay the amounts
recovered from the appellant in pursuance of
th
the interim order dated 19 November, 2002
and also pay the adjustment arising out of
payments made by the appellant to KPTCL (i.e.,
the date between the respondent No. 2/PPA rate
and respondent No. 31 entered rate of this
Hon'ble Court; as the case may be) from 1st
August, 2000 up to November 2002 within a
period of one month from today;”
FACTS IN BRIEF
5. The first respondent was permitted by GoK during
March 1994 to set up a 2X130 MW cortex gas/ coal based
thermal power plant at Bellary. It was apparently
intended that Jindal Vijayanagar Steel Limited (JVSL)
would consume the power produced from the thermal plant
to be set up by the first respondent. The Central
Electricity Authority granted the required technical
economic clearance in March 1996. Originally, GoK gave
3
approval to set up the power plant by JTPCL for 300 MW.
It was initially reduced from 300 to 240 MW in March
1995 and finally, it was modified by order dated
13.02.1996 and reduced to 260 MW (130X2). There were to
be two units, that is Unit No.1 and Unit No.2. Karnataka
State Electricity Board (KEB for short) entered into a
heads of terms with JTPCL on 30.09.1995.
6. Clause 4 of the heads of terms reads as follows:
“4. SALE OF EXCESS ENERGY & CAPACITY TO KEB
If, at any stage, JTPC has excess firm
capacity and/or energy for sale to KEB, then
KEB may purchase the same from JTPC subject
to agreement on price and other terms to be
negotiated at the time of such sale.”
7. Heads of terms was essentially a memorandum prior
to the agreement, entered into in regard to wheeling
and banking in regard to sale to dedicated consumers by
the first respondent. It was followed up by a wheeling
and banking agreement between the KEB and JTPCL dated
23.01.1996.
8. In the said agreement also, the parties have
reiterated the Clause (Clause 2.4) relating to the sale
by first respondent to KEB in similar terms as in the
4
Heads of terms. Somewhere in 1998, the first respondent
invoked the clause in its bid to sell power to KEB.
9. On 20.10.1998, the first respondent wrote to KEB
as follows:
“ This has reference to your above referred
letter on the above subject. In this
connection kindly refer to our earlier letter
th
dated 28 September 1998, wherein we have
confirmed that our tariff is in accordance
th
with GOI notification dated 30 March 1992.
Further we have confirmed that we would offer
substantial rebate on the two-part tariff
calculated on the basis of GOI norms.
A statement giving details of Tariff
calculations at 85% PLF and 68.5% PLF and
68.5% PLF is enclosed. The statement also
gives details of cost under various sub-heads.
The tariff is subject to the following
assumptions:
1. Landed costs of imported coal assumed at
USD 50 per tone.
2. Any variation in coal price will be to
customer's account.
3. Exchange Rate assumed at USDI = Rs.42.
4. Repayment of Foreign Loan, ROE and
Depreciation will vary as per the applicable
exchange rate.
5. O&M Charges will vary as per Indian
Inflation Rate.
At your convenience, we can explain and
furnish any clarifications required on the
tariff calculations.
5
Hope the details furnished along with this
letter would enable you to consider our
proposal and hence request your to kindly
arrange for the approval of your board.
On 21.11.1998 again, there is a proposal put forth
10.
by the first respondent to the KEB. Therein it has
indicated that it has completed 100 per cent
construction, erection and testing facility of Unit
No.1.
11. After stating that they are scheduled to
synchronise Unit No.1, by December, 1998, it was
indicated that the commissioning of unit no.2 is
scheduled for July 1999. Thereafter, reference is made
to clause 2.4 of the Wheeling and Banking Agreement, as
already referred to. The respondent offered 50 MW from
the commissioning date of Unit No.1. Further offer of
100 MW was made (base load basis) from the commissioning
date of Unit No.2. It further offered upto maximum of
200 MW during the time when the steel plant JVSL and
JPOCL (another dedicated consumer of first respondent)
were under shut down (major breakdown) or during the
maintenance period. It further offered to pay penalty
if the supply was less than 75 MW from commissioning
6
date of Unit No.2. The rate was shown as 2.90/Kwh.
Payment was requested by irrevocable revolving L/C.
This offer, however, was exclusive of certain items and
it is indicated that the consideration of the same was
in line with Government of India and KEB Norms. We may
notice the following terms which are set out as the
elements to be excluded of the rate:
“1. Electricity Tax: The Organizations such as
KPCL, NTPC, NPC and MSEB who
are supplying power to KEB is
exempted from Electricity
Tax. Hence JTPC be exempted
from Electricity Tax.
2. Inflation: Each year the tariff will be
adjusted to inflation as per
the acceptable published
index.
3. Foreign Exchange: As an IPP, we have 85 MUS$
foreign exchange borrowing
from US. Exim Bank and SBI-
New York. For repayment of the
loan the exchange variation to
be incurred by JTPC to be
compensated in annual
revision of price.
4 Fuel escalation
Charges : We are using imported coal. In
case of an increase in the
coal price over and above the
base price declared to KEB it
is to be compensated.
7
5. Force majeure
Conditions : Due to grid failure or
transmission line failures if
we cannot supply power no
penalty should be levied on
minimum guaranteed power.
6. Maintenance of
Power Plant: During the scheduled
maintenance and shutdown
period penalty should not be
levied.
We propose to supply power on the basis outlined
in this letter for an initial period of five years
from the date of commissioning of second 130 MW
Unit. Since we are eligible for Income Tax
Exemption for the first five years, it is not
included in the proposed tariff.”
12. The promise was to supply for a period of five
years from the date of commissioning of the second
unit. It is stated that the first respondent is
available for any clarification and for further
negotiation. Under the head “Utilization of Power
During Stabilization Period” it is stated as follows:
“II. UTILISATION OF POWER DURING STABILISATION
PERIOD.
(from the date of synchronization to
commercial operation)
We have signed 'Wheeling and Banking'
agreement with KEB which allows us to bank
8
Power with KEB during the period from
synchronization to commercial operation.
During the above period we still be supplying
power to our sister company's i.e., JVSL and
JPIOCL who are located adjacent to Power Plant
and within a common's with yard (owned &
controlled by JTPC). During this period since
the power may not be available on 'FIRM' basis
we would like to draw power from our Banked
Power and supply to JVSL and JPOCL.
KEB has sanctioned power to JPOCL, JVSL and
JTPC to meet their star-up power requirements.
KEB has sanctioned demand for each unit
separately. All the three units are availing
KEB power for plant commissioning, start-up
purposes, trial operation and each unit is
paying demand and energy charges to KEB.
st
After synchronization of JTPCL's 1 130 MW
unit (December 98) we seek your kind consent
and approval for the following arrangements.
a. JTPCL will supply power to JPOCL and
JVSL.
b. JTPCL, JVSL, JPOCL will continue the
contract with KEB and continue to pay
contracted demand charges to KEB.
c. In exceptional cases when JTPC
generation is lower than the energy
requirement of JVSL and JPOCL, subject to
their individual contract demand with
KEB, JTPCL draws energy from KEB for a
limited period, or during the shutdown of
the unit.
d. Bank all excess power (without
limitation as per wheeling and banking
9
agreement) with KEB and take energy
credit for the Banked power, to utilize
as and when required.
e. In case, we draw power from KEB when
our bank is zero, we will also pay energy
charges to KEB as per the applicable
tariff.
Once the reliability tests are over and when
JTPC declares the commercial operation of
their unit, JVSL, JPOCL and JTPC will request
KEB to cancel (withdraw) their contract demand
with KEB and JTPC will meet both demand and
energy of these two units on regular basis.
Present metering system (Annexure -1)
INSTALLED by KEB in our complex is on
temporary basis and for adopting the above
modalities permanent metering system is
required to be established by KEB which is
detailed at Annexure- 2.
We request you to kindly accord your approval
for the above two proposals. Proposal 2
requires implementation of metering system
before synchronization of unit scheduled in
the last week of December 1998 and hence
approval may please be accorded at the
earliest.
Thanking you we remain
Yours faithfully
For JINDAL TRACTEBEL POWER CO. LTD.
Sd/-
S.S. Rao
Dy. MD & CEO”
13. The response of the KEB is found in communication
st
dated 1 December, 1998. It is stated as follows:
10
“The Board is in principle willing to purchase
surplus power from your plants as already
discussed. Your proposal regarding the tariff
is under evaluation by the Board”.
14. Next, it is relevant to notice the communication
dated 19.01.1999 made by KEB to GoK. It reads as under:
“KARNATAKA ELECTRICITY BOARD
K.P. SINGH, I.A.S. CAUVERY BHAVAN,
CHAIRMAN BANGALORE–560001
D.O.No./KEB/B2/B13/6306/93-94 Date: 19/1/1999
My dear Chaubey,
Sub: Purchase of power generated by the captive
power plant of M/s. Jindal Tractebel Power
Company at Hospet.
Government of Karnataka vide GO No. de 221 PPC 93
Bangalore dated 7-3-1994 had permitted M/s. Jindal
Tractebel Power Company to set up a 2xl20 MW power
plant at Hospet, which was subsequently enhanced
to 2xl30 MWs. This plant, which was set up as a
captive power plant was given an IPP status later
on vide Government letter No. DE 221 DPC 93 (P)
dated 1-2-1996 as the shareholders of the power
plant and steel plant were different. TEC for the
above project was issued by CEA vide their letter
dated 22-3-1996. As the company proposed to utilize
the power generated for their own use and to sell
to other industries in the State, after initial
round of discussions with the Company, only a
wheeling and banking agreement was proposed. In
January 1996, Board entered into a Wheeling and
Banking Agreement with the Company. In the Wheeling
and Banking Agreement, as per Clause 2.4, the
Company could sell excess capacity and/or energy
11
to KEB and KEB had an option to purchase the same
at a negotiated rate. The relevant clause is
reproduced below:
"'If at any stage, the Company offers excess
firm capacity and/or energy for sale to the
Board, then the Board may purchase the same
from the Company, subject to agreement on
price and other terms to be negotiated at the
time of such sale."
Jindal Tractebel Power Company is the first IPP
to have achieved Financial Closure. Subsequent to
achieving Financial Closure, the company took up
the work of construction of the plant and the first
unit of the plant has also been synchronised with
the KEB grid recently.
M/s. JTPC during discussion have stated that
due to downward trend in the Steel industry, the
requirement of the steel has reduced and
consequently progress of the Corex Plant has slowed
down. As a consequence of the above, the Company,
vide their letter No.4 JTPC/KEB dated 20-10-1998
have offered to sell 50 Mw after the first unit is
commissioned and 100 MW after the second unit is
commissioned to KEB on basis. Also, in case of shut
down of the JVSL Plant or its subsidiaries for
maintenance purposes, they have offered to sell
nearly 200 MWs to KEB.
Though KEB has signed PPAs with various IPPs,
the progress of these plants is not satisfactory.
As of today, only the 200 MW Barge Mounted Power
Plant being set up by M/s. Tanir Bavi Power Company
has neared financial closure. A table indicating
the first-year tariffs payable to various IPPs,
whose projects have been sanctioned under the bid
route is given below. The present rate of Rs.42.50
to a dollar has been taken for the purpose of
calculating the tariff.
12
| FIRST YEAR OF BID ROUTE PROJECTS | ||||||
|---|---|---|---|---|---|---|
| Name of<br>firm | Tariff<br>heat rate<br>Kcals.Kwh | Calorific<br>value of<br>fuel<br>Kcals/Kg | Price<br>of fuel<br>Rs./Kg. | Fixed<br>Charges | Variable<br>Charges | Total |
| Attria<br>Power | 1897.44 | 10800 | 8.40 | 1.3540 | 1.4758 | 2.8298 |
| Bharat<br>Forge | 1949.42 | 10800 | 8.40 | 1.2028 | 1.5162 | 2.7190 |
| Innox<br>Power | 2080.00 | 9900 | 6.80 | 1.6118 | 1.4287 | 3.0404 |
| Scintilla<br>Power | 1923.00 | 9900 | 6.80 | 1.6030 | 1.3208 | 2.9238 |
| Rayalseema | 2153.85 | 9900 | 6.80 | 1.0743 | 1.4794 | 2.5537 |
| Bhoruka | 2087.86 | 9900 | 6.80 | 1.3494 | 1.4341 | 2.7834 |
| DLF | 2153.85 | 9900 | 6.80 | 1.0743 | 1.4794 | 2.5537 |
| Tata | 2115.30 | 9900 | 6.80 | 1.3204 | 1.4529 | 2.7733 |
It is also to be stated that of the above mentioned
plants, some of the plants may not come up. The
doubtful plants are that of M/s. DLF, Scintilla
and lnnox Power. In case of M/s. Rayalseema, even
though the plant had intimated that they have
achieved financial closure nearly 8 months back,
they have requested for enhancement of capacity of
the plant to double its size to make it
economically viable. This issue is under
examination.
Because of the shortfall in generation in the State
and the steady demand for power, KEB is purchasing
power from MSEB in addition to that from Central
Generating Stations. The tariff we are paying for
power of MSEB is Rs.2.30/unit for power availed
during off peak hours and Rs.2.65 for power availed
during peak hours. We are at present purchasing
nearly 100 MWs during peak hours and upto 200 MWs
during off peak hours. MSEB has asked for revision
of prices from 1-1-1999 for the power supplied by
them. The revised rates are Rs.2.50 + FEC for off
peak power and Rs.3.00 + FEC for power supplied
during peak hours. Tamil Nadu is also purchasing
power from MSEB at Rs.2.65 /unit during peak hours
and Rs.2.30/unit during off peak hours. Tamil Nadu
Electricity Board is also purchasing power from
13
Eastern Grid at Rs.2.74/unit. KPCL is proposing to
synchronize their V and VI unit in the coming
months. Though the actual cost is yet to be
finalized, as the project cost is yet to be frozen,
it is indicated that the tariff for the power
generated by these plants vary between Rs.2.75 to
Rs.2.80. It has also been reported in the press
that for the power proposed to be generated from
the Kayamkulam Thermal power plant being set up by
M/s. NTPC, KSEB would have to pay nearly
Rs.3.90/unit and after the intervention of the
Prime Minister, the rate payable would be around
Rs.3.52/unit.
The project of M/s. JTPCL was under the Captive
route and it was contemplated that the entire power
generated would be used by JVSL and its
subsidiaries. Though a provision was there in the
wheeling and Banking agreement for KEB to purchase
any surplus power from this project at a later
date, it was clearly mentioned that the price at
which this power would be purchased would be at
negotiated rates. This was because, KEB did not
feel it necessary to go into the details of the
capital costs of this project as this project was
contemplated as a captive power plant and only
surplus power, if any, was to be sold to KEB, at a
later date. M/s. JTPCL vide their letter dated 20-
10-1998 had offered to sell power to KEB at
Rs.2.90/unit.
During internal meetings it was also decided that
as this project was meant as a captive power plant
and KEB did not go into the details of the project
cost earlier or anticipate in the meetings at CEA
before the TEC was issued, it would not be possible
to negotiate tariff based on two-part tariff
notification of GoI. Also, as we would be paying
only a fixed price per unit, it was felt that going
into the details such as the actual heat rate, the
O&M charges, the working capital, foreign exchange
14
protection to be provided, etc. should not be done
and only the cost per unit presently being offered
from other sources should be compared. Further, to
compensate for the variation in Rupee against the
dollar, the increase in Consumer Price Index,
interest rate on working capital etc., it was also
decided that some annual increase in the fixed
price should be allowed to take care of the above-
mentioned items as has been done in case of MOU
Route projects.
With this background, negotiations were held with
M/s. JTPCL. During discussions, it was stated that
the cost per unit will have to be split into two
parts, viz. Fixed Component and Variable charges.
The variable charges would be based on the actual
price of coal which JTPCL would buy. After detailed
discussions, it was decided that a price of
Rs.2.60/unit can be offered, comprising of Rs.l.70
as fixed charges and Rs.0.90 as variable charges.
To compensate for depreciation of rupee against
dollar, escalation of O&M charges due to increase
in cost of price index, working capital
requirements, etc. It was also decided that the
fixed charges should be escalated by 5% every year
beginning from the second year after we purchase
power from JTPC.
As regards the variable cost, which depends on the
cost of coal, the company will have to invite bids
from global markets and satisfy KEB about the
correctness of the procedure followed and the price
arrived at. These bids can be either of I year
duration or a longer period. Depending on the
actual cost of coal, the variable price will be
paid.
Regarding the term of the agreement, it is to be
stated that the major thermal power projects , i.e.
that of M/s Mangalore Power Company and M/s.
Nagrujuna Power Company may not be available for
the next five years. There is a case pending in
15
Supreme Court regarding Mangalore Power Company
and only after the judgment is known, Gol will
consider extending counter guarantee to this
project. After the counter guarantee is given, it
may take anything between 4 to 5 years for the
project to be issued. Again, it may take 4 to 5
years for the project to be put up, since the
company will have to achieve financial closure.
Hence it is considered prudent to limit the period
of the agreement to purchase power from Ms. JTPCL
to 5 years initially.
The cost per unit of power purchased from M/s
Jindal Tractebel during the five year period
keeping the variable cost constant would be as
follows:
Year Fixed Charge Variable Charge
Total
1 1.70 0.90 2.60
2 1.79 0.90 2.69
3 1.87 0.90 2.77
4 1.97 0.90 2.87
5 2.07 0.90 2.97
Even with the increase of Fixed Charges by 5% every
year, it is to be stated that in the 5th year, the
cost of power with the variable charges remaining
the same will be Rs.2.07 + Rs.0.90, i.e. Rs.2.97
per unit which is lower than the tariff now being
offered by MSEB during peak hours.
The company has offered to sell 100 MWs on a
guaranteed basis, it will be necessary to assure a
minimum level of offtake failing which Deemed
Generation Charges will have to be paid. As per
two part tariff notification the minimum assured
off-take should be 68.5% PLF. As this project is
essentially meant as a captive power plant, it is
suggested that the minimum off-take below which
16
deemed generation would be payable should be 50%
of the contracted/declared capacity, whichever is
lower. It is also suggested that a penalty be
levied on M/s. JTPCL if there is any shortfall in
power below 75% of the quantity assured by the
company.
Keeping all the above in mind, it is suggested that
we can purchase power from M/s JTPCL at
Rs.2.60/unit (FC Rs.1.70 + VC Rs.0.90) with the
fixed charge being escalated by 5% from the second
year with the conditions of penalty to be paid by
the firm for short supply of power and assured off-
take mentioned above.
For all IPPs, Government is giving guarantee for
the payments to be made by KEB for the power it
receives. Apart from this, irrevocable letter of
credit and escrow accounts are also being opened
by KEB as additional security for power supplied
by these companies. In case of JTPCL, as the
question of providing government guarantee does
not arise as the plant was essentially set up as a
captive power plant and majority of the power
generated is being sold to captive industries.
However, irrevocable revolving Letter of Credit
and backup escrow can be provided to the Company.
Approval of the Government is sought for the above
proposal. Subsequent to the approval, negotiations
will be held with M/s JTPCL for finalizing the
PPA.”
15. The GoK in its response by communication dated
05.03.1999 wrote as follows to the KEB:
“R.No.DE 18 FEB 99 Dated 05-03-1999
I invite your to your D.O. letter dated 19-1-
99 regarding your proposal to purchase power
17
from M/s Jindal Tractabel Power Company at
Rs.2.60/unit with a 5% escalation on fixed
charges.
The proposal has been examined in detail. The
efforts of the KEB to bridge the gap in power
availability by entering into a short -term
agreement with Jindal Tractebel Power Company
Limited (JTPCL) is well appreciated. Government
recognizes the fact that inspite of the best
efforts made by the State Government to augment
the power supply position there still continues
to be a big gap between demand and supply.
Government also note that presently KEB is
supplying more than 75 Million units per day
which is a record. The demand may further go up
in the coming months and the situation may not
change easily in the next few years on account
of the substantial delay in the starting up of
the Mega power projects in the State. Under
these circumstances there is a need to tie up
with IPP/other States/NTPC, for augmenting the
power supply within the State urgently. There
is no doubt all out efforts have to be made
within the short time to tide over the problems
of increased demand during the summer.
The present proposal of the KEB keeps the tariff
open ended and possible revision. The PP A being
for a period of 5 years, KEB is advised to
negotiate with the Jindal Tractebel for a fixed
tariff for the next 5 years.
This may kindly be got examined by KEB and the
revised proposal may be sent to the government.
Yours,
Sri K.P. Singh, IAS.”
18
16. On 31.03.1999 after referring to the proposal dated
21.11.1998 and a series of discussions and the further
meeting with the KEB officials on 26.03.1999, the first
respondent indicated that in the meeting, KEB officials
informed that it was willing to buy power from the first
respondent subject to the following terms and
conditions:
“1. The term of the agreement could be 5 years.
2. The tariff should be a single part tariff.
Escalation at a fixed percentage could be applied
on the total price on an annual basis. KEB will
not consider any request either for two-part tariff
based on CEA guidelines or for payment of fuel cost
at actuals.
3. KEB will open irrevocable revolving letter of
credit under which JTPC can get payments. It will
also be supported by Escrow mechanism.
4. There can be penalty clause both for short
supplies and short drawals.
5. The PPA should be a simple document.”
[Emphasis supplied]
17. Thereafter, it is stated that KEB asked for a
formal proposal within aforesaid parameters. Thereafter
in the communication, it is stated:
“1. JTPC offers 50 MW (Energy 36 MU per month)
of power from the commissioning date of Unit
19
1 and 100 MW (Energy 72 MU per Month) of
power from the commissioning date of Unit 2.
The first Unit of 130MW is expected to be
commissioned in June 1999 and the second unit
of 130 MW is expected to be commissioned in
August 1999.
2. JTPC would have an option to supply in excess
of 50MW (Energy 36 MU per month) after
commissioning of Unit 1 and 100 MW (Energy
72 MU per month) after commissioning of Unit
2, with KEB's approval, as and when JTPC has
surplus power available.
3. The tariff will be as follows:
I year (Upto 31" March 2000)Rs. 2.60 I kwhr.
II Year (Financial Year 2000-2001) Rs. 2.73 I kwhr.
III Year (Financial Year 2001-2002)Rs. 2.87 I kwhr.
IV Year (Financial Year 2002-2003) Rs. 3.01 l kwhr.
V Year (Financial Year 2003-2004) Rs. 3.16 I kwhr.
4. There will be no Wheeling charges or
Electricity Tax on supplies to KEB.
5. To maintain uniformity in penalty on either
side, JTPC proposes as follows as from COD
of Unit 2:
(a) JTPC guarantees minimum supply of the
Threshold Power Value after commissioning of
JTPC Unit 2. If the supply is less than the
Threshold Power Value, JTPC will pay penalty
at 10% of the tariff, for supplies below the
Threshold Power Value.
(b) KEB shall guarantee that it will consume
the Threshold Power Value. In case the
consumption is less than the Threshold Power
Value, KEB shall pay to JTPC the full value
of Threshold Power at the applicable tariff
as above.
20
(c) The Threshold Power Value is 75 MW
(Energy 54 MU per month).
6. The minimum supply and the minimum
consumption as per para 5(a) and 5(b) above
are applicable on a monthly basis.
7. If there is escalation in fuel cost beyond
5% at any time, JTPC reserves the right to
terminate the contract with 3 months' notice,
if KEB does not agree to compensate for such
escalation.
8. KEB shall open irrevocable revolving letter
of credit corresponding to 100 MW (Energy 72
MU per month) power sales under which JTPC
can get payment for its monthly bills. It
shall also be supported by Escrow mechanism.
9. The initial term of the agreement should be
5 years till March 31, 2004, with a provision
for renewal on terms mutually acceptable.
We request you to agree to the above terms and
conditions and convey your acceptance at the
earliest. We will approach our Board and the
lenders on getting your acceptance.
We also request you to let us have drafts of the
PP A, Escrow agreement and the Letter of Credit,
at the earliest. We propose to have one more
meeting with your officials, after studying these
drafts.”
18. It is next necessary to notice the communication
dated 23.04.1999 sent to the GoK by the Chairman of the
KEB.
21
“KARNATAKA ELECTRICITY BOARD
K.P. SINGH, I.A.S. CAUVERY BHAVAN,
CHAIRMAN BANGALORE–560001
Ref.No.83/99-2000 Date: 23 APR 1999
My dear Arvind,
Sub: Purchase of power generated by the captive
power plant of M/s. Jindal Tractebel Power at
Hospet.
Ref: 1. This office D.O.letter No.KEB/B28/B13/
6306/93-94 dated 19-1-1999
2. DO letter NO.DE 18 FEB 99 dated 5-3-1999
of Energy Secretary addressed to the
undersigned
Accordingly, M/s JTPCL were invited for negotiations
and discussions were held with them on 26th March
1999 to arrive at the rate they would sell power from
their plant to KEB. During the meeting, the position
of the Board/GoK was made known to the
representatives of M/s JTPC, i.e. the tariff should
be a single part tariff including variable charges
and should be fixed for each year with an annual
escalation by a fixed percentage. The firm was
requested to intimate the tariff at which it would
sell power to KEB.
The firm stated that from their calculations, they
will be taking a hit on fixed charges itself and this
will be mainly due to depreciation of Rupee against
the dollar and increase in O&M charges. Also in case
of variable charges, they stated that it is linked
to the cost of coal, which is imported and that this
will also increase due to the increase in cost of
coal, the freight charges and again due to the
depreciation of Rupee against the dollar in future
years. They requested that the earlier negotiated
22
position where the variable charges is a pass through
should be retained.
The stand of the Government of Karnataka that only a
fixed tariff per unit per year should be negotiated
was again made known to the firm. The firm stated
considering all aspects within the parameters fixed
by the Board, they would be able to sell power at
Rs.2.75 per unit with a cost escalation of 5% per
year, which was not ... acceptable to the Board. The
firm was requested to offer a revised figure. After
detailed negotiations, the firm, subject to
confirmation of their Board of Directors, offered to
sell power at a cost of Rs.2.60 per unit with an
annual escalation of 5%. They stated that this is the
minimum figure they could agree and any further
reduction of the same would affect the project as it
would be financially unviable.
Hence there are two options available, i.e. either
to retain the original proposal of the fixed charges
being escalated by 5% every year with the variable
charges being a pass through or the entire rate of
Rs.2.60 including variable charges being escalated
by 5% every year.
In case of the second option, the tariff payable by
KEB for each unit in different years will be as
follows:
With this the tariff payable during each year of
operation will be as follows:
Year Rs./Kwh
1 2.60
2 2.73
3 2.87
4 3.01
23
5 3.16
Considering the fact that rupee has been depreciating
heavily against the dollar the second proposal may
be advantageous to KEB.
The firm in its letter No.JTPC/KEB dated 31-3-1999
has confirmed that the tariff payable by KEB for
power purchased will be Rs.2.60/unit in the first
year with an annual escalation of 5% every year. They
have stated that they will be offering 50 MWs
(equivalent to 36 MU per month) from the date of
commissioning of the first unit and 100 MW
(equivalent to 72 MU per month) with the
commissioning of the second unit. The first unit is
expected to be commissioned in June 1999 and the
second unit in August 1999. They have also indicated
that in case they have any surplus power beyond 50
MWs and 100 MWs after commissioning of unit I and
unit 2, with the approval of KEB, they will sell
power in excess of 50 MW s and 100 MW s.
The firm has also proposed the following after
commissioning of Unit 2:
1. They will supply power with a threshold value of
75 MWs equivalent to 54 MU per month.
2. If supply is less than the threshold power value,
then JTPC will pay penalty of 10% of the tariff for
supplies below the threshold power value.
3. KEB shall guarantee that it will consume the
threshold power value. In case the consumption is
less than the threshold value, KEB shall pay to JTPC
the full value of threshold at the applicable tariff
as above.
4. The minimum supply and minimum consumption as
above are on monthly basis.
5. If there is an escalation in fuel cost beyond 5%
at any time, JTPC reserves the right to terminate the
contract with 3 months notice, if KEB does not agree
to compensate for such escalation.
24
6. KEB shall open irrevocable revolving letter of
credit corresponding to 100 MW (energy 72 MU per
month) power sales under which JTPC can get payment
for its monthly bills. It shall also be supported by
Escrow mechanism.
7. The initial term of the Agreement should be 5
years till March 31, 2004 with a provision for
renewal on terms mutually acceptable.
These are issues to be negotiated with the firm
while finalising the PP A and will be taken up later
on.
This is for information of the government and it
is requested that orders may please be obtained and
communicated to us.
With regasrds,
Yours sincerely,
Sd/-
(K.P. SINGH)
Shri Arvind Jadav,
Secretary to Government,
Department of Energy,
Government of Karnataka
Bangalore”
19. Finally, on 12.05.1999, we find the following
proceedings. It reads interalia as follows:
“After detailed examination GOVT. ORDER NO. DE 18
FEB 99, BAN GALORE DATED 12TH MAY 1999
1. KEB is permitted to finalize a Power Purchase
Agreement with M/s Jindal Tractebel Power Company
Limited (JTPCL) for the purchase of surplus power and
submit the same to the Government for approval.
25
2. The rate per unit being Rs. 2.60 including
variable charges with an annual increase of 5% every
year.
3. The term of the PPA shall be for a period of five
years.
4. To adopt the same principle of negotiated tariff
for captive generating power project who intend to
sell power to KEB.”
20. The Act came into force with effect from
01.06.1999. The significance of this is that under
Section 27 of the Act, unless there was a ‘concluded
contract’ as on 01.06.1999, the Commission was to
regulate the tariff. Thereafter we may notice the
following correspondence as well. On 04.01.2000, the
superintending Engineer of the KEB wrote to JPPCL. The
correspondence would show as follows:
“This refers to the tariff of 2.60 per KWhr
negotiated for purchase by KPTCL of the
electricity generated by the subject power
project. You are requested to furnish details
of the break-up of the tariff so as to enable
us to take further action.”
21. On 06.04.2000, the first respondent wrote to the
Chairman of the appellant (KPTCL). It reads as follows:
26
“JINDAL TRACTEBEL POWER COMPANY LIMITED
Ref: JTPC/KPTCL/1545 April 6, 2000
To,
The Chairman
Karnataka Power Transmission Corporation Ltd.,
Bangalore
Dear Sir,
Sub:Purchase of Power from Jindal Tractebel
Power Company Limited (JTPCL) by Karnataka
Power Transmission Corporation Limited
(KPTCL)
Ref: 1. Government Order No.DE 18 EEB 99
th
Bangalore dated 12 May 1999
2. Government Order No.DE 120 EEE 99
th
Bangalore dated 7 July 1999
We are happy to inform you that both the
units (2 x 130 MW) of our Power Plant are
operating continuously. As per JVSL's agreement
with KPTCL, JVSL was to return 215.810 MU to
KPTCL. As on 6'h Apri12000 JVSL has returned
199.802 MU to KPTCL and the balance left over
is only 16.008 MU, which will be completed by
12'h April 2000.
As per the Government Order (Ref. l), the
Government of Karnataka has permitted KPTCL to
purchase power from JTPCL at the rate of Rs.
2.60 per unit including variable charges with
an annual escalation of 5% every year. The said
order has also permitted KPTCL to finalize the
PPA with JTPC. Accordingly, JTPC has finalized
PPA with KPTCL and the final draft as accepted
27
between JTPC and KPTCL has been submitted to
KPTCL in September / October 1999.
SI. No.8 of the Government Order (Ref. 2)
directs KPTCL to operate the PPA with JTPC as
Per Government Order NO. DE 18 EEB 99 Bangalore
dated 12th May 1999 (Ref. I) only after
complying with the obligations under the
th
Government of Karnataka Order issued on 7
July 1999 (Ref. 2). SI. No.9 of the Government
th
of Karnataka Order dated 7 July 1999 (Ref.2)
also directed KPTCL to honour the obligations
under Wheeling, Banking and Grid Supporting
Agreement between KPTCL and JTPCL only after
fulfilment of obligations under the Government
th
of Karnataka Order dated 7 July 1999 (Ref. 2)
Since the submission of final draft PPA to KPTCL
in September I October 1999, JTPC is
continuously pursuing KPTCL and Government of
Karnataka for signing of the PPA. During this
period, whatever clarifications were sought by
KPTCL were submitted by JTPC & KTPCL. Inspite
of our best efforts, so far, the PPA has not
been signed by KPTCL thought the tariff and
other conditions are already covered in the
Government Order.
After returning of the power by JVSL to
KPTCL which is expected to happen by 11th April
2000, JTPC will be supplying power to KPTCL as
per the Government of Karnataka Order dated 18'h
May 1999 (Ref. 1). Even though PPA is not yet
signed and is pending with KPTCL, the absence
of PP A should not come in the way of supplying
of power by JTPC to KPTCL from 12'h April 2000
as the formal Government of Karnataka Order
dated 12m May 1999 along with the details of
tariff (Ref. 1) does exist. Hence, pending
finalization and signing of PP A between JTPC
and KPTCL, we request you to kindly accept the
power dispatched by JTPC to KPTCL from 12m April
28
2000. JTPC will be submitting the invoices as
per the Government of Karnataka Order dated 12m
May 1999 (Ref. 1) subject to any changes
required to be done subsequently as per the
terms and conditions of the PPA to be agreed
and signed between JTPC and KPTCL.”
22. In response to letter dated 06.04.2000, the
appellant corporation wrote to the first respondent on
12.04.2000. It reads as under:
“With reference to the above, I am directed to
communicate approval of the Corporation to continue
to supply energy to the grid from the 2x130 MW Power
Plant of your Company pending finalization of PPA
under the following conditions.
1. The Grid support charges envisaged in the
Wheeling & Banking and Grid support Agreement
i.e., Rs. 1.73 Crores Annum will be
provisionally deducted from the tariff
invoices when the amount is paid. This will be
subject to change and has to be paid as per
the terms of PP A to be signed.
2. The 115% energy imported will be deducted from
the energy exported, provisionally pending
finalization.
3. The energy will be accounted only after
signing of PPA.
4. The energy banked prior to signing of PP A
will be treated as energy banked with the
Corporation and will be accounted as per the
Corporations rules.
5. This orders is only for facilitating continued
operations of the Power Plant and Corporation
29
makes no commitments with respect to terms of
PPA which is being finalized separately.
6. The metering arrangements should be as per the
Article No. 4 of the Wheeling, Banking
Agreement and Grid Support Agreement already
signed copy of the same is enclosed.”
23. We may still further notice the communication dated
24.05.2000 addressed by the appellant to its Chief
Engineer Electricity which reads as under:
“With reference to the above, I am directed to
convey approval of the Corporation to make payments
to M/s. JTPCL for the energy supplied to the grid
from 15-4-2000 and onwards at Rs. 2.52 per unit
pending signing of PPA. Under following terms.
1. The procedure for payments should be as per
the standard procedure followed in case of IPP
Projects.
2. 115% of imported energy should be deducted
form the exported energy and payments will be
made for net exported energy so arrived.
3. The metering should be as per the terms of
Wheeling & Banking Grid support Agreement
between KEB and JTPCL signed on 23-1-96, till
such time PP A is finalized.
4. The firm has to submit an undertaking that the
terms and conditions of PP A between KPTCL and
JTPCL will be applicable for the payments made
by KPTCL for the energy supplied by JTPCL from
the date as approved by government till the PP
A is signed.
30
5. This is only an order to facilitate payment of
energy charges to M/s. JTPCL and Corporation
makes no commitments in this regard and the
terms of PPS will be finalized separately.
6. The energy transaction prior to 15-4-2000 will
be finalized separately.”
24. Finally, we notice the proceedings of the
Government of Karnataka dated 17.07.2000. It reads as
under:
PREAMBLE:
ln Government Order No. DE 18 EEB 99 dated:
12.5.99 KEB was permitted to finalize a power
purchase agreement with M/s. JTPCL for purchase
of surplus power from generating units at the
rate of Rs. 2.60 per unit with an annual
increase of 5% every year for a period of 5
years. Further the rate per unit has been
reduced from Rs. 2.60 to Rs. 2.52 vide
Government Corrigendum dated 8.5.2000. It is in
this context the request made by the JTPCUJVSL
has been examined and it is found that
continuing with the earlier rate of Rs. 2.60
per unit would result in honoring the commitment
of the Government. Besides it has the advantage
of procuring a better price every year for
KTPCL. It would ensure that power is purchased
at Rs. 2.60 instead of Rs. 2.63 per unit in the
first year, Rs. 2. 73 instead of Rs. 2.77 per
unit on the second year, Rs. 2.87 instead of
Rs. 2.92 per unit in the third year and Rs. 3.01
instead of Rs. 3.05 in the fourth year.
Honoring the earlier Government Order would
also ensure that there is no litigation on this
subject in a court of law.
31
The KPTCL vide it's letter dated 22.5.2000 read
at Sl. No. Shad also requested the Government
to review the effective date for purchase of
power from the said company and communicate the
Government decision. The matter has been
examined at Government level in consultation
with KPTCL and in the interest of the Company.
After examining the requested made by the
Company, Government are pleased to Order as
follows:
GOVERNMENT ORDER NO. DE 18 EEB 99. BANGALORE
DIST: 17.7.2000
In the circumstances explained above,
Government are pleased to permit Karnataka
Power Transmission Corporation Limited to
purchase power from M/s. Jindal Tranctebel
Power Company Limited at the rate of 2.60 per
unit with an annual increase of 5 every year as
indicated in the Preamble to this Order. The
implementation of this Order will commence from
the date of the issue.
The other conditions of the Government Order of
even no. 6 dated 12.5.1999 remains unaltered.”
25. A draft power purchase agreement came to be made
on 07.11.2000 between the appellant and the first
respondent. There are elaborate details contained
therein. Suffice at this juncture to notice further,
that a letter was sent to the Commission on 17.11.2000.
This letter was treated as an application by the
appellant (KTPCL) for entering into a power purchase
32
agreement under Section 25 (3) of the Act read with
Section 17(1) of the Act. Based on a public notice,
objections were filed by five objectors. More
importantly, the stand taken by the first respondent
was that the Commission was bereft of jurisdiction to
examine the PPA on the ground that it merely represented
a contract which was concluded with it prior to the
commencement of the Act, and therefore, the case fell
within the four walls of the proviso to sub-section 2
of Section 27 of the Act. The Commission thereafter
proceeded to enter the following findings, inter alia :
The entire negotiation, correspondence and
acceptance of an offer must be absolute. The offer
of the first respondent was subject to further
approval, that is, the approval of the Board of the
Company and the lenders to the company. The Deputy
Managing Director and CEO of the company was not
delegated the authority to bind the company. The
offer was not one to be converted into a contract.
After referring to order of the GoK dated
12.05.1999, it is found that out of the 9 issues
containing the proposal of JTPCL, Government has
33
indicated its intention to agree only to two issues,
namely the rate of Rs 2.60/- per KW hr. and the
period of five years that is the term of the
agreement. The GoK, it is noted, directed KEB to
negotiate the PPA and to submit the same for
approval.
The provision for an escrow facility to guarantee
payment to JTPCL and payment for full charges for
deemed generation did not find reflection. These
conditions were central to any PPA.
As on 12.05.1999, the parties did not intend the
agreement to be binding. By the GO dated
12.05.1999, Government reserved its right to vary
the tariff. There is no acceptance of the
proposal as far as GOK is concerned. Government
order dated 12.05.1999 only served to provide
broad guidelines to negotiate with the first
respondent for a mutually agreed term.
(1) The PPA cannot be restricted to the aspect of
rates only. The mutual rights and obligations
have to be stipulated specifically even after the
rate is agreed. There is no concluded contract.
34
(2) Government of India notification dated
30.03.1992 was to be considered only as a ceiling
and it is perfectly open to the Electricity Board
and generating companies to negotiate and arrive
at a lower tariff. Reference is made to the
omission of sub-section (2) of Section 43A of the
Electricity (Supply) Act, 1948 in the State of
Karnataka with effect from 14.09.2000.
26. After an elaborate study of documents, it was
found, that the power proposed to be supplied to the
appellant (KPTCL) was surplus power and the grant of
IPP status by communication dated 01.02.1996 would not
avail the first respondent.
We may next notice the following discussion:
“60. Simply because, plant is making use of
common infrastructures for coal hand long and
water supply it cannot be said that the plant
of the appellant is a CPP. It is common
knowledge that a number of generating projects
are set up to take advantage of the existing
infrastructures of other projects and it can
never be said that merely because
infrastructure is shared, the consumption of
power is captive. The infrastructure facilities
are shared between the projects only with a view
to minimise the project costs. The power plant
is designed to fire either corex gas or coal as
35
fuel, which confirms that the appellant's power
plant is not a captive plant and that it was
intended to supply power to KPTCL even with the
steel plant is not working and not producing
corex gas. It also needs to be noticed that
appellant and JVSL are distinct Corporate
entities and the appellant has obtained
financial assistance, project approvals from
various statutory authorities, Gol and GoK on a
stand alone' basis.
61. It was, however, contended on behalf of the
respondents that power was supplied to KEB only
after JVSL's commitment was fulfilled and since
the entire capacity of 240 MW has been
underwritten by JVSL, the appellant is a CPP to
the JVSL. It is also contended on behalf of the
respondents that determination of IPP/CPP is
irrelevant as the Commission has allowed KPTCL
to pay fixed charges to the appellant.”
27. Thereafter, the Commission arrived at a probable
tariff and finally directed the appellant to negotiate
with the first respondent based on the calculation made
and to come up with a fresh proposal. The first
respondent did not negotiate. It is this which led to
the Commission passing the second impugned order. In
the light of the same, Commission proceeded to approve
a draft PPA, submitted on 17.11.2000 with the following
modifications:
36
a) The tariff charges for the first tariff period
shall be Rs.2.36 Unit instead of Rs.2.60/unit
upto 657 MU (page 17 of the Draft PPA).
b) The tariff for the entire energy in excess of
657 MU in, the first tariff period will be Rs.
1.88/unit instead of Rs.2.20/unit (page 17 of
the draft PPA)
c) Grid support charges per month as per the
following formula:
GSC = Fl Load in MW x 1000 x DC
PF
Where:
Fl Load in MW is the fluctuating load in MW
(l3.55 mw)
DC- Applicable Demand Charges
PF- Power Factor
d) the yearly escalation is 2.50% instead of 5%
(Page 17 of the Draft PPA)
e) Regarding the penalty for non-generation, it is
directed that a penalty of 20% of the tariff
shall be levied.
14. The PPA as approved by the Commission will
come into effect from 1.8.2000 and shall be valid
for a period of five years as per the proposal of
KPTCL.
15. In their letter No. JTPCL/AUTCH/2358 dated
20th June 2002. JTPCL has expressed their
willingness to enter into long term PPA on two-
part basis. The Commission advises KPTCL to
negotiate with M/s. JTPCL a long term PPA
depending upon the need for power. On approval of
such a PPA by the Commission, the present PPA
will get terminated.”
37
28. It is these orders which came to be challenged by
the first respondent before the High Court under
Section 41 of the Karnataka Electricity Reforms Act,
1999. The High Court formulated the following points
for decision.
| “19. After hearing the learned Counsel for the | |
|---|---|
| parties, following points arise for decision: | |
| (I) Whether the Karnataka Electricity | |
| Regulatory Commission-Respondent No. 3 can be | |
| added as a party respondent to the appeal and | |
| whether it is entitled to defend the impugned | |
| order on merits? | |
| (II) Whether there existed a binding contract | |
| between the appellant and the KPTCL on the | |
| tariff prior to commencement of Karnataka | |
| Electricity Reform Act, 1999 with effect from | |
| 01.06.1999, in terms of Explanation to Section | |
| 19 and proviso to Section 27(2) of the Act? if | |
| the answer is in the positive, whether the | |
| Commission has jurisdiction to review the | |
| tariff particularly when the proviso to sub- | |
| section (2) of Section 27 is restricted to | |
| tariff determination and does not require a PPA | |
| to establish a concluded contract? | |
| (III) Whether the status of the appellant is | |
| that of an IPP or CPP? | |
| (IV) Whether the impugned orders are perverse, | |
| arbitrary and passed without application of | |
| mind? | |
38
| (V) Whether the Commission has failed to | |
|---|---|
| appreciate the appellant's rights grounded on | |
| the principles of promissory estoppel and | |
| legitimate expectation?” | |
Commission was performing as a quasi-judicial body. It
was further found that when validity of the order of a
quasi-judicial body is assailed in a court of law, it
is healthy and fair that such authority (the
commission) should not take sides. The High court did
not find justification for the Commission to file its
own extensive pleadings, engage a senior counsel and
show abnormal interest. The contesting parties were
capable of taking care. The question was also posed as
to the position of the Commission if a case is remanded
back to it when it has been impleaded as a party and
takes an unambiguous and inelastic view. It was finally
found that the Commission was not a proper party having
regard to the questions that arose for decision in the
appeal. The High court took care that it should not be
understood as meaning that the Commission cannot be a
necessary and proper party if an appeal is preferred
under Section 41 against its order regardless of the
39
question which arose. Answering point No.2, that is
whether there is a concluded contract, the Court went
on to find that there was a concluded contract within
the meaning of the explanation to Section 19 and proviso
to Section 27(2) of the Act. This view was formed on
the basis of the conspectus of the correspondence
beginning with the Government order dated 07.03.1994
and the communications which we have already indicated
and culminating in the GO dated 12.05.1999 of GoK. Thus,
it was found that all essential terms and conditions,
that is, the tariff rate, escalation, quantity and
tenure for purchase and sale of power were agreed
between the parties before 01.06.1999 (the date on
which the Act came into force). The order dated
12.05.1999 was preceded by several rounds of
negotiation. It was no doubt found that there were
several rounds even after the Act came into force
between the parties, and they discussed and finalised
the terms and conditions of the PPA except tariff as
the tariff was agreed upon as evident from GO dated
12.05.1999. The PPA dated 10.11.2000 incorporated all
the agreed terms. After signing the PPA, the appellant
40
took steps to open letter of credit for securing payment
based on the tariff of Rs.2.60 per unit plus 5 per cent
escalation per annum without obtaining approval of the
Commission. The letters dated 04.01.2000, 12.04.2000
and 24.05.2000 according to the High court reflected
the intention of the parties to treat GO dated
12.05.1999 as the binding contract as far as the tariff
was concerned. The High Court discussed case law and
found inter alia that there was a concluded contract.
Interpreting the proviso to Section 27 (2) of the Act,
it was found that the proviso was only for the purpose
of Section 27(2), that is, factors relating to tariff
determination. The proviso could not deal with other
fields, the Section itself did not deal with. The
correct interpretation, according to the High Court,
was as far as ‘contract concluded’ is concerned the
proviso is referable to the tariff which is agreed
between the parties before the Commission came into
existence. There is no form for the concluded contract
in the Act. No penalty is imposed for not entering into
the PPA. This shows that PPA is not an essential
requirement under the Act. The appellant purchases
41
power from other utilities without PPA. The fact that
the learned counsel for the Commission entertained this
view, was recorded. It is found that when an offer is
made and acceptance does not extend to all the terms,
on the terms accepted, a contract is concluded. The
order dated 12.05.1999 was for all purposes treated as
contract for sale of power. Parties were ad idem. All
terms and conditions agreed upon in the GoK order dated
12.05.1999 were incorporated in the PPA without any
variation. GoK has given its consent to the first
respondent in terms of Section 43A of the Act, prior to
the commencement of the Act. Since approval was already
given under Section 43A of the Electricity (Supply)
Act, 1948, approval under Section 17(1) was not
necessary. It is recorded in the judgment that the
appellant agreed with the first respondent that Section
27(2) of the Act did not require a contract in writing
or any formal document or that it prescribed any
particular form. The appellant contended that there was
no concluded contract for certain reasons. They are as
follows.
42
(1) It is reflected as the contention of the
appellant that the offer of first respondent
itself was “subject to” the approval of the Board
and its lenders. These approvals constituted
conditions precedent for formation of the
contract.
(2) There was no acceptance or communication of
acceptance by the appellant (KTPCL).
(3) Essential clauses such as Escrow, deemed
generation, auxiliary consumption etc. required
for a PPA were not agreed upon.
(4) The order dated 12.05.1999 was merely an internal
approval and not in exercise of any statutory
provision.
(5) The tariff of Rs.2.60 was an indicative figure.
There was no basis to arrive at the figure of
Rs.2.60.
(6) There was no record to show that appellant
participated before the CEA (Central Electricity
Authority).
30. The High Court proceeded to find that as regards
the condition in the proposal that the offer that was
43
made was subject to approval by the Board of Directors
and lenders that, neither of the parties insisted on
the satisfaction of the conditions before supplying
power. The principle of waiver was employed also. The
order dated 12.5.1999 did not employ the word “subject
to”. The terms such as ‘deemed generation’ were not
considered essential by the parties. The fact that the
party continued to perform for almost 3 years would
show by ‘conduct’ that they cannot be termed as
essential. It is not necessary that KPTCL should
communicate acceptance to the respondent. It is further
found that a contract which is concluded by acceptance
by the ‘Gok’ is protected by proviso to Section 27(2).
GoK found that the single part tariff is more
advantageous to the appellant. The tariff rate is
arrived at on the basis of two-part tariff rate. The
break up of tariff for 20 years was submitted to the
appellant after detailed negotiation and examination.
The tariff of Rs.2.60 per unit was approved. The court
concluded that there was a concluded contract.
Answering point No.3, it was found that the status of
the power plant was of the IPP and not of a CPP. In
44
regard to point No.4, namely, whether order of the
Commission was perverse, arbitrary and passed without
application of mind, noticing certain errors, it is
found that the Commission having opined that the fixed
charges should be paid for 657 MUs, it calculated the
fixed charges for 487 MUs while fixing the tariff.
Incentive payment charges was found by Commission to be
Rs.0.952 in arriving at the tariff rate, but the
incentive payment charges are taken as Rs.0.924 per
unit. These errors were not disputed. Having agreed to
a negotiated single part tariff, it was found the
Commission could not have unilaterally ignored well
established parameters, and applied norms which were
relevant for the calculation of two-part tariff. The
tariff proposed was on the basis of single part tariff.
The tariff of the first respondent is one of the
cheapest as it was based on the least cost tariff basis,
whereas other companies pay higher charges either on
the basis of a two-part tariff or a fixed negotiated
tariff. This was not seriously disputed. The appellant
(KPTCL) has fixed heat rate at 2400 Kcal/Kwh
disregarding the norms of the Ministry of Power as per
45
which the heat rate should be 2500 Kcal/Kwh or the
actual heat rate whichever is lower. The commission
took the plant load factor at 77% disregarding norms
under the Electricity Supply Act as per which the plant
load factor would be 68.5% or at a rate negotiated
between the parties. The escalation was reduced from 5%
to 2.5% per annum. The two-part tariff provides for
escalation for inflation and exchange fluctuation and
complete reimbursement of fuel cost. The Commission
arrived at 1637 MUs at 77% PLF and disproportionately
loaded fixed charges on to the first respondent. The
Commission ignored the fact that 1150 MUs are arrived
on the basis that the appellant is supplying the energy
to the steel plant at 85% PLF and this disproportionate
loading was found tantamounting to cross subsidising
contrary to the observations in the decision of this
Court in West Bengal Electricity Regulatory Commission
1
v. CESC Ltd. . The Commission was found at fault in
reducing the assured supply level to 487 MUs in its
calculation whereas more than 900 MUs have been
supplied by the first respondent to the appellant for
1
(2002) 8 SCC 715
46
the years 2001 and 2002. In view of the wheeling and
banking agreement in 1996 under which Grid Support
Charges payable were agreed upon, the finding of the
commission was found flawed in reviewing the charges
without any basis. It was found ultra vires the Act.
The objections of the first respondent filed before the
first impugned order were rejected by the Commission
but reasons have not been given. The court went on to
answer point No.5 which was whether the case of the
first respondent based on principles of promissory
estoppel has not been considered by the commission and
therefore impugned order required interference. The
court after referring to case law on promissory
estoppel and doctrine of legitimate expectation found
it unnecessary to dilate on this aspect, but finding
merit in the contention of the respondent that the
Commission failed to appreciate the rights of the
respondent in the light of the, ‘said principles’.
Thereafter the High Court went on to allow the appeal
in the manner which we have already explained.
47
SUBMISSIONS OF THE APPELLANT
31. Shri S.S. Naganand, learned Senior Counsel appeared
along with Shri Raghavendra S. Srivastava. Shri
Raghavendra S. Srivastava, learned Counsel appearing
for the appellant would make the following submissions.
There is no concluded contract within the meaning
of the proviso to Section 27 of the Act with the aid of
the correspondence and the facts established otherwise.
He would complain that the High Court has not
appreciated factual and the legal position. It is his
case that it is clear that the parties intended that
there should be a PPA. This is not a case of mere desire
that there should be a written document encompassing
the agreement between the parties. On the contrary, he
would contend that the parties contemplated that there
be a PPA whereupon alone a concluded contract would
emerge. He would submit that Government G.O. dated
12.05.1999 relied upon by first respondent as the
fountain head for the claim there is a concluded
contract cannot for many reasons be treated as such.
48
32. Attacking the findings of the High Court that the
concluded contract under Section 19 and Section 27 of
the Act need not be in writing or in any particular
form, it is contended as follows:
While there may not be any statutory requirement
that there must be a PPA in writing, the
correspondence and the conduct of the parties make it
clear that they intended to have a formal document
binding them on all material terms. Correspondence
shows that KEB was willing to buy power on certain
terms and conditions one of which was that there
should be a PPA. The first respondent had also called
upon the appellant to confirm the terms, for placing
them before its own Board and sought draft of the PPA
to be executed. The Order dated 12.05.1999 cannot be
treated as acceptance of the offer. It was merely the
permission granted by the GoK to enter into an
agreement on certain terms and conditions. Since, KEB
and the first respondent were not ad idem on any other
term, no agreement was reached. Relying upon Clause
2.4 of the Wheeling and Banking Agreement, it is
contended that agreement was contemplated not merely
49
on price but other terms which were to be negotiated.
Being a statutory corporation, there was no scope for
an implied contract. It is contended that a perusal
of letter dated 23.04.1999 would show that even as
regards the tariff rate proposed by the first
respondent, it was subject to the confirmation by the
Board of Directors. Reinforcement, in this regard, is
sourced in letter dated 04.01.2000, wherein the first
respondent was requested for the quote of the tariff
for ‘further action’. Further reliance is placed on
the contents of letter dated 06.11.2000. Support is
sought to be drawn from the Judgement reported in
2
India Thermal Power Ltd. v. State of M.P. and others .
The High Court erred in assuming that the first
respondent waived its rights under the draft PPA.
Reliance is placed on the Judgment of this Court in
All India Power Engineer Federation and others v.
3
Sasan Power Ltd. and others to contend that whenever
waiver is pleaded, particularly, in contracts having
public interest, the party must show an agreement
2
(2000) 3 SCC 379
3
(2017) 1 SCC 487
50
waiving the right, which has not been done in this
case. The proviso to Section 27(2) cannot be read in
isolation but it must be harmonised with the other
relevant provisions. Bearing in mind the mandate of
Section 17, the contract must be in the manner
approved by the Commission under Section 17 and it
must include all material terms. The first respondent
was insisting that a PPA must be executed by the
appellant. In its communication dated 20.06.2002, the
first respondent admitted that the tariff was not
acceptable but it would be willing to negotiate on the
basis of two-part tariff if the PPA was made valid
for 10 to 15 years. The first respondent again has
admitted that tariff and several other aspects were
pending discussion and negotiation with the appellant.
GoK Order dated 12.05.1999 was amended vide
Corrigendum dated 08.05.2000 by revising the tariff
to Rs.2.52/unit. Later, vide Order dated 17.07.2000,
on request by the first respondent, the tariff was
restored to Rs.2.60/unit. This establishes that the
GoK Order dated 12.05.1999 was not final. Even the
rate was confirmed only after 01.06.1999. There is no
51
approval granted by GoK under Section 43A of the
Electricity (Supply) Act, 1948. Therefore, approval
of the Commission was mandatory under Section 17 of
the Act. The Order dated 12.05.1999 was not an
approval under Section 43A but it was in the nature
of permission given to KEB to negotiate and enter into
the contract. There was no contract with the KEB.
There could not have been any contract with the
appellant (KPTCL) as the appellant was constituted
only under the Act, which came into effect from
01.06.1999. The following findings of the High Court
are placed under focus:
“It is not necessary that only the KPTCL
should communicate acceptance to the
appellant. A contract which is concluded by
acceptance by the GOK is protected by the
proviso to Section 27(2) of the Act.
In our considered opinion the combined
reading and consideration of the following
documents and circumstances and the reasons
we presently state would lead us to conclude
that there existed a “concluded contract”
between the appellant, KPTCL and GoK well
before 01.06.1999.”
33. In other words, the Court has even proceeded as if
there was a contract between the GoK and the first
52
respondent. If that were the case, apart from other
contentions, Article 299 and requirements thereunder,
are pressed into service. Drawing upon the Judgment in
4
K.P. Chowdhary v. State of Madhya Pradesh and others ,
it was contended that State Government cannot be bound
by an implied contract. It is next contended that the
first respondent cannot be treated as an Independent
Power Producer (IPP). The operation of the first
respondent and the sister steel plant (JVSL) are
intertwined and interdependent. They share common
infrastructure for coal handling, water supply and the
coal for the first respondent is purchased by JVSL, for
which, it raises an invoice on the first respondent.
The first respondent is to be treated as the CPP, as it
was supplying power to the steel plant. The capacity
was reduced at the request of the first respondent. The
contents of the G.O. dated 12.05.1999, which also
indicates that the same principle of negotiated tariff
for captive generating power plant that intends to sell
power to the KEB was applicable to the first respondent
are pressed into service. Reliance is also placed on
4
(1966) 3 SCR 919
53
the agreement dated 14.10.1999. Though first respondent
was granted the status of IPP by the GoK, it was
recognised by KEB/the appellant as a captive plant. The
Commission found that the energy supplied under the PPA
was only the surplus energy, after meeting the
requirements of its dedicated consumers. When an IPP is
desirous of contracting power supply with the appellant
on two-part tariff basis, the KEB/appellant would be
involved in every stage of project formation,
finalisation of capital costs and technical parameters.
KEB/the appellant would be represented before the
Central Electricity Authority for according Techno
Economic Clearance as well as for coal supply
agreements, but none of these formalities were carried
out. It is also pointed out that the first respondent
availed of concession in the matter of electricity tax
by contending that it was the CPP, which was accepted
by a Quasi-Judicial Body by Order dated 21.11.2000.
34. It is next contended that the findings arrived at
by the High Court in regard to the facts, was
unsustainable. In this regard, it is contended that the
jurisdiction of the High Court in an Appeal under
54
Section 41 of the Act, is a limited one. The limitation
arose from the requirement that the appeal is
maintainable only, when there is a question of law.
This legislative cribbing of the appellate power of the
High Court is to be viewed in the context of the fact
that the appeal is directed against the findings of an
Expert Body like the Commission. Legislature,
therefore, wished to clothe High Court not with the
ordinary untrammelled power of an Appellate Court. In
the instant case, even though the point raised is,
whether there was any perversity in the findings of the
Commission, without finding any perversity, as such,
the High Court has proceeded to make a foray into
factual findings rendered by the Expert Body. The
findings of the Expert Body were premised on adequate
reasoning and material. It is without carefully
appreciating and analysing the findings, that various
observations have been made. It is lastly also
contended that pursuant to the Interim Order passed by
this Court, the appellant had to deposit a sum of Rs.100
crores, which the first respondent was permitted to
withdraw on furnishing bank guarantee. The learned
55
Counsel would submit that, if the appellant succeeds,
the amount paid by the appellant, must be ordered to be
restored by the first respondent.
SUBMISSIONS OF RESPONDENT NO. 1
35. Dr A.M. Singhvi, learned Senior Counsel appeared
along with Shri Gopal Jain, learned Senior Counsel, for
the first respondent. Dr. Singhvi appearing would
contend that prior to the issue of GO dated 12.05.1999,
parties were agreed about the essential terms, viz .,
price/tariff, quantum and tenure. These terms were
incorporated in the PPA without any change or
amendment. The conditions, seven in number, enumerated
in letter dated 23.04.1999, were incidental matters,
which were not necessary or a pre-requisite for the
formation of the contract. A PPA was not a pre-
condition. From 15.04.2000, the first respondent
supplied power to the appellant and the tariff was paid
at the rate of Rs.2.60/unit. With reference to GO dated
12.05.1999, it is contended that though it contemplated
submission of the PPA to the Government of Karnataka
(GOK), the interpretation has to be necessarily that
56
the draft PPA terms, apart from the terms in GO dated
12.05.1999, as and when finalised, had to be submitted
to the GoK. The seven conditions mentioned in letter
dated 23.04.1999 remaining in the realm of negotiation
as on 01.06.1999 did not detract from a concluded
contract based on the GO dated 12.05.1999. The Act does
not prescribe a format for a concluded contract. No
penalty or consequence is contemplated for not entering
into a PPA. A signed PPA is not condition precedent.
The language in Section 18(6) of the Act, which
contemplates a PPA, is contrasted with the term
‘concluded contract’, employed in Section 17 of the
Act. The concluded contract on tariff is also evident
from the conduct of the parties as power was being
supplied at Rs.2.60 per unit without waiting for
approval by Commission. The stand of the Commission
that a PPA may not be necessary, found recorded in the
impugned Judgment is highlighted. It is contended that
this is not a case where there is a counter proposal
from the appellant. This is a case where the final
proposal of Rs.2.60 per unit, made by JTPCL during the
meeting held on 26.03.1999, was formalised by it in the
57
letter dated 31.03.1999. The appellant sought approval
from the GoK. The approval was granted by GO dated
12.05.1999. It resulted in a concluded contract between
the GOK/KEB with JTPCL. The GO dated 17.07.2000,
restoring the tariff of Rs.2.60, reversing its
corrigendum on 08.05.2000, by which, tariff was sought
to be reduced to Rs.2.52 per unit, indicates that
Rs.2.60 emerged as a sacrosanct figure, which had to be
honoured. This again probabilised the case of the first
respondent that there was a concluded contract. The
expression ‘concluded contract’ employed in Section
27(2) of the Act, must be given the interpretation
apposite to the context provided by Section 27, which
deals with factors/guidelines for determination of the
tariff by the Commission. In other words, similar words
to be found in Sections 14(7), 18(6) and 19, where the
words used are ‘concluded contract’ or ‘contract
concluded’, may not be suitably used. Reliance is
placed on the Judgment of this Court in Ram Narain Sons
5
Ltd. v. Asstt. Commissioner of Sales Tax and others ,
5
AIR 1955 SC 765
58
6
Dwarka Prasad v. Dwarka Das Saraf and Mackinnon
7
Mackenzie & Co. Ltd. v. Audrey D'Costa and another . In
other words, the contention appears to be that the
proviso to Section 27(2) of the Act, must be interpreted
in the context, which is that a Law-Giver wanted to
give relief against retrospectivity, by protecting
tariffs, which were subject matter of agreements
between the parties arrived at prior to the
commencement of the Act. It is further contended that
it is nobody’s case that the contracts entered into by
the KEB were not transferred to the appellant. As per
Section 14(7) of the Act, all contracts entered into,
with or for the KEB, are deemed to have been transferred
to KPTCL (the appellant).
36. Considerable support is drawn from the Judgment of
the House of Lords reported in Alexander Brogden and
others and the Directors, & c., of the Metropolitan
8
Railway Company and Kollipara Sriramulu (Dead) by His
Legal Representative v. T. Aswatha Narayana (Dead) by
6
AIR 1975 SC 1758
7
(1987) 2 SCC 469
8
[L.R.] 2 App. Cas. 666 / HL(E) 1877 Vol.2 666
59
9
His Legal Representatives and others . Reliance is
placed on these decisions to contend that even if the
parties did contemplate the signing of an agreement, it
would not prevent formation of a contract, even dehors
the formal document.
37. He further contended that the appellant made
admissions before the High court about the existence of
a concluded contract qua tariff, quantum and tenure. As
regards the confirmation of the offer by the first
respondent’s Board, it is merely a procedural internal
requirement, an aspect of the doctrine of indoor
management. The recommendation made by the KEB of the
rate is relied upon. The contention based on the
appellant coming into existence after 1.6.1999 is
brushed aside as a matter of no moment as it is the
successor of KEB, therefore bound by the contract.
Merely because the first respondent was pressing for
the execution of the PPA, it would not detract from
there being a concluded contract qua tariff, quantum
and tenure. Otherwise, the appellant would not have
purchased power from 15.04.2000. The appellant is
9
AIR 1968 SC 1028
60
unjustified in contending that even qua tariff, there
is no agreement. The submission of the appellant that
there is a model PPA is erroneous. The model PPA was
issued only in 2005 by the Government of India after
the issue of guidelines for tariff determination by
competitive bidding under the provisions of the
Electricity Act, 2003. The contention that there was no
approval granted under Section 43A of the Electricity
(Supply) Act, 1948 and therefore, the approval of the
commission is mandatory under Section 17 is
deliberately made knowing it to be erroneous. GoK Order
dated 02.03.1996 expressly establishes the consent
given by the GoK under Section 43A(1)(c) of the
Electricity (Supply) Act, 1948. Section 17 does not
speak about tariff determination powers of the
commission. The tariff determination is exclusively
dealt with by Section 27. It is pointed out that the
terms and conditions which were left to be negotiated
in letter dated 23.4.1999 have been incorporated as
terms and conditions in the draft PPA. Instances of
perversity in the commission’s orders are pressed
before the Court. The first respondent also contended
61
that for various reasons it is entitled to be treated
as IPP.
38. The first respondent does not lay store by the
finding on promissory estoppel & legitimate
expectation. However, learned Counsel, indeed, supports
the other finding interfering with the Order of the
Commission, viz., that the first respondent was to be
treated as an independent power producer and that the
Orders of the Commission were afflicted with
arbitrariness and error apparent.
ANALYSIS
THE ACT – THE KARNATAKA ELECTRICITY REFORM ACT,
1999.
39. Section 1(3) provides that the Act shall be deemed
to have come into force w.e.f. the First Day of June
1999. Section 13 provided for the incorporation of the
appellant/company. The principal object was to engage
in the business of purchase, transmission, sale and
supply of electrical energy. Section 13(4) contemplates
that the appellant was to undertake the functions in
Section 13 and other functions, as may be assigned to
62
it under the licence to be granted by the Commission
under the Act. Section 13(5) reads as follows:
“13(5) Upon the grant of license to the KPTC
under chapter VII, the KPTC shall discharge
such powers, duties and functions of the Board
including those under the Indian Electricity
Act, 1910 and the Electricity (Supply) Act,
1948 or the rules framed thereunder, as may
be specified in the license and it shall be
the obligation of the KPTC to undertake and
duly discharge the powers, duties and
functions so assigned.”
40. Section 14 of the Act reads as follows:
“14. Reorganisation of the Karnataka
Electricity Board.- (1) On and with effect
from the date on which a transfer scheme
prepared by the State Government to give
effect to the object and purposes of this Act
is published or such further date as may be
prescribed (hereinafter referred to as the
effective date of the first transfer), any
property, interest in property, rights and
liabilities which immediately before the
effective date of first transfer belong to the
Board shall vest in the State Government on
such terms as may be agreed between the State
Government and the Board.
(2) Any property, interest in property, rights
and liabilities vested in the State Government
under sub-section (1) or part thereof may be
revested by the State Government in the KPTC
or any generating company or companies in
accordance with the transfer scheme published
under subsection (1) along with such other
property, rights and liabilities of the State
Government as may be specified in such scheme,
on such terms and conditions as may be agreed
63
between the State Government and the KPTC or
any generating company or companies, as the
case may be.
(3) From the effective date of first transfer
of properties etc., to the KPTC, the Board
shall stand dissolved. The Chairman and
Members of the Board shall be deemed to have
vacated their office. Such of the functions,
duties, rights and powers exercisable by the
Board under the Indian Electricity Act, 1910
or Electricity (Supply) Act, 1948 or any rule
framed thereunder as the State Government may
by notification specify shall be exercisable
by the KPTC or any generating company or
companies, as the case may be, from the
effective date of first transfer.
(4) Notwithstanding anything in this section,
where,- (a) the transfer scheme involves the
transfer of any property or rights to any
person or undertaking not wholly owned by the
State Government, the scheme shall give effect
to the transfer only for fair value to be paid
by the transferee to the State Government; and
(b) a transaction of any description is
effected in pursuance of a transfer scheme,
it shall be binding on all persons including
third parties.
(5) The State Government may, after consulting
the KPTC [or a licensee as the case may be],
KPTC require the 1 [or a licensee as the case
may be]1 to draw up a transfer scheme to vest
in a further licensee (the “transferee
licensee”), any of the function including a
distribution function, any property, interest
in property, rights and liabilities which have
been vested in the KPTC [or a licensee as the
case may be] under this section and publish
the same as the scheme of transfer under this
Act. The transfer scheme to be notified under
this sub section shall have the same effect
as the transfer scheme under sub section (2)
64
and shall be effective from the date specified
(effective date of second transfer).
(6) A transfer scheme under this section may,
amongst others,.-
(a) define the property, interest in
property, rights and liabilities to be
allocated,-
(i) by specifying or describing the
property, rights and liabilities in
question;
(ii) by referring to all the property,
interest in property, rights and
liabilities comprised in a specified part
of the transferor’s undertaking; or
(iii) partly in the one way and partly in
the other;
(b) provide that any rights or liabilities
specified or described in the scheme shall
be enforceable by or against the transferor,
or the transferee, as the case may be;
(c) impose on KPTC or any licensee, an
obligation to enter into such written
agreements with, or execute such other
instruments in favour of, any person as may
be specified in the scheme;
(d) impose on any transferee licensee the
obligations to comply with the power
procurement and purchase arrangements with
KPTC; and
(e) make such supplemental, incidental and
consequential provisions as transferor
licensee considers appropriate including
provision specifying the order in which any
transfer or transaction is to be regarded as
taking effect.
65
(7) All debts and obligations incurred, all
contracts entered into and all matters and
things engaged to be done by, with or for the
Board, or the KPTC or generating company or
companies before a transfer scheme becomes
effective shall, to the extent specified in
the relevant transfer scheme, be deemed to
have been incurred, entered into or done by
the Board, with the Board or for the State
Government or the KPTC or the transferee, and
all suits or other legal proceedings
instituted by or against the Board or
transferor, as the case may be, may be
continued or instituted by or against the
State Government or the concerned transferee,
as the case may be.
(8) If pursuant to a transfer scheme framed
by the State Government, the KPTC 1 [or a
licensee as the case may be]1 is required to
vest any part of its undertaking in another
company or body corporate or person, the
Commission shall amend the licence granted to
enable the transferee to carry out the
functions and activities assigned to the
transferee.”
41. Section 17 which is the opening section in part
VII, inter alia provided as follows: -
“17. Regulation of generating companies and
stations- (1) A licensee or a bulk purchaser
or any other person may enter into a contract
with a generating company for purchase of
electricity in the manner approved by the
Commission and such approval granted by the
Commission shall have the effect of the
consent given by the State Government in terms
of section 43A of the Electricity (Supply) Act
66
1948: Provided that the approval granted by
the Commission under this sub-section shall
not in any manner affect the requirements to
obtain approvals and sanctions of the State
Government or any other authority under any
other law, rule or regulations.”
42. Section 18, which falls in Part VII, deals with the
requirements of a license. It, inter alia , reads as
follows:
“18. Requirement of licence.- (1) No person,
other than those authorised to do so by license
or by virtue of exemption under this Act or
authorised to or exempted by any other
Authority under the Electricity (Supply) Act,
1948, shall engage in the State in the business
of,- (a) transmitting electricity; or (b)
supplying electricity, including bulk supply.
XXX XXX XXX
(6) All licenses issued under the provisions
of Indian Electricity Act, 1910, by the State
Government or any competent authority shall be
deemed to be a provisional licence and shall
be subject to the conditions provided under
sub-sections (4) and (5). All power purchase
agreements, transmission services agreements
and other contracts entered into shall continue
in full force and effect and will be
transferred to the successor entities.”
(Emphasis supplied)
43. Section 19 of the Act, deals with grant of licenses
by the Commission. Section 19(1) reads as follows:
67
“19. Grant of licenses by the Commission. -
(1) The Commission may on an application
made in such form and on payment of such fee
as may be specified by regulations, grant a
license authorising any person to, - (a)
transmit electricity in a specified area of
transmission; and/or (b) supply electricity
in a specified area of supply or supply in
bulk to the licensees or any person.”
44. Section 19(4)(j) reads, inter alia , as follows:
“(4) Without prejudice to the generality of
sub-section (3), the conditions included in
a license by virtue of that sub-section may
require the licensee to,-
(a) to (i) xxx xxx xxx
(j) purchase power in an economical manner
and under a transparent power purchase
procurement process; Explanation. - The
contracts concluded by the State Government
or the Board with generating companies and
transmission companies prior to the date of
commencement of the Act shall stand assigned
to the KPTC in terms of section 14 and the
KPTC may continue the purchase or
transmission of power under such contracts
for effecting bulk sales, distribution and
supply to other licensees;”
45. Section 20 provides for exemption from the
requirement of license. It contemplates that the
regulation by the Commission to grant exemption from
the requirement to have a supply license subject to
conditions to be specified. The other provisions of
68
Part VII deals with amendment of licenses and revoking
of licenses apart from the general restrictions on the
licensee.
46. Section 27, which contains the proviso which is at
the heart of the controversy, inter alia, reads as
follows:
“27. Tariffs.- (1) The holder of each licence
granted under this Act shall observe the
methodologies and procedures specified by the
Commission from time to time, in calculating
the expected revenue from charges which it is
permitted to recover pursuant to the terms of
its licence and in designing tariffs to
collect such revenues.
(2) The Commission shall, subject to sub-
section (3), have the power to lay down
methodology and the terms and conditions for
determination of revenue of the licensee under
sub section (1) of this section and the
determination of tariff, in such other manner
as the Commission considers appropriate and
for doing so, the Commission shall be guided
by the following factors, namely:-
(a) the financial principles and their
applications provided in sections 7 and 57-A
of the Electricity (Supply) Act, 1948 (54 of
1948) and in the sixth schedule thereto;
(b) in the case of the Board or its successor
entities, the principles under section 59 of
the Electricity (Supply) Act, 1948;
(c) that the tariff progressively reflects the
cost of supply of electricity at an adequate
and improving level of efficiency;
69
(d) the factors which would encourage
efficiency, economical use of the resources,
good performance and optimum investments and
other matters which the Commission considers
appropriate for the purpose of this Act ; and
(e) the interest of the consumers are
safeguarded and at the same time, the
consumers pay for the use of electricity in a
reasonable manner based on the average cost
of supply of energy;
(f) the electricity generation, transmission,
distribution and supply are conducted on
commercial principles
(g) national and state power plans formulated
by the Central or State Government, as the
case may be :
Provided that the contracts concluded by the
Government of Karnataka and/or the Board with
generation and transmission companies prior
to commencement of the Act shall be deemed to
have been approved by the Commission under the
provisions of this Act and shall be given
effect by the Commission.
(3) Where the Commission departs from factors
specified in the sixth schedule to the
Electricity (Supply) Act, 1948 (Central Act
54 of 1948) while determining revenue of the
licensee and tariffs, it shall record the
reasons therefor in writing.
(4) Any methodology or procedure specified by
the Commission under sub-sections (1), (2) (3)
above shall be to ensure that the objectives
and purposes of the Act are duly achieved.
(5) Any tariff implemented under this Act,-
(a) shall not show undue preference to any
consumer of electricity, but may
70
differentiate according to the consumer’s
load factor, power factor, and total
consumption of energy during any specified
period or the time at which supply is
required, or the geographical position of any
area , the nature of the supply and the
purpose for which the supply is required; or
paying capacity of category of consumers and
need for cross subsidisation; and
(b) shall be just and reasonable and be such
as to promote economic efficiency in the
supply and consumption of electricity; and
(c) shall satisfy all other relevant
provisions of the Act, regulations and
conditions of the license.
(6) The Commission also shall endeavour to fix
tariff in such a manner that, as far as
possible, similarly placed consumers in
different areas pay similar tariff.”
(Emphasis supplied)
47. Section 5(1) of the Act declares that Members of
the Commission shall be persons of ability, integrity
and standing, who have adequate knowledge and
experience of and have demonstrated capacity in dealing
with law or administration. Section 5 further declares
that, at all times, one Member shall be a graduate
Electrical Engineer with at least 25 years of
experience of either generation, transmission or
distribution of electricity and have worked in a senior
position in the said field. There must always be two
71
Members, who have qualification in the field of law,
finance, economics, commerce or administration, with at
least 25 years of working experience. Such person
should have worked in a senior position in the said
field. There are other aspects, which need not detain
us. Under Section 10 of the Act, the Commission is
endowed with certain powers of a Civil Court. It can
enforce attendance of witnesses. It can call for
information. It can consult to the extent, it considers
appropriate, such persons or group of persons, who may
be affected or likely to be affected by its decisions.
Section 11 deals with the functions of the Commission.
An array of functions vests with it which includes
regulating the purchase, distribution and supply and
utilisation of electricity, the quality of service, the
tariff and charges payable, keeping in view the
interest of the consumer as well as the consideration
that the charges are adequately levied and duly
collected. There are various other functions. It is to
function as an independent Statutory Body Corporate.
The Commission has the power to act as an Arbitrator or
to nominate Arbitrators to decide disputes between the
72
licensees. The Commission is tasked with the power to
grant licences under Section 19 of the Act. More
pertinently, the Commission is empowered under Section
27(2), to lay down the methodology and the terms and
conditions for determination of the tariff, inter alia .
Section 27(2)(a) to (g) provide for the factors, which
are to guide the Commission.
48. On a conspectus of the provisions of the Act, it
is self-evident that in keeping with the very name of
the Act, viz. , Karnataka Electricity Reforms Act, 1999,
the Legislature intended to depart from the earlier
regime, under which, the State Electricity Boards, in
conjunction with the Government, enjoyed a free run in
the matter of fixation of tariff. The Act put in place
a mechanism, by which, an independent Body, a
Commission, consisting of the Experts, as we saw, were
to proceed in the matter, in an independent manner, to
determine, inter alia , the tariff. The determination
of the tariff was to be done, bearing in mind, the
interest of the consumer. At the same time, the
Commission was not to be oblivious to the need to arrive
at charges for the service of purchase, distribution
73
and supply of electricity, in such a manner that the
tariff is adequate in that the charges for the
electricity supply, was duly collected, being adequate,
for maintaining the supply and distribution of
electricity.
49. Section 14(7) provides, inter alia , that all
contracts, entered into with or for the Board or the
appellant or the generating company or companies,
before a transfer scheme becomes effective, is to be
deemed to have been entered into or done by the Board,
with the Board or for the State Government or the
appellant or the transferee. Section 17 provides that
a licensee or the bulk purchaser or any other person,
may enter into a contract, with a generating company,
for purchase of electricity, in the manner approved by
the Commission. Such approval, is accorded the status
of a consent given by the State Government under Section
43A of the Electricity (Supply) Act, 1948. Section 18,
dealing with the requirement of a licence for
transmitting electricity and for supplying electricity,
including bulk supply, inter alia , provides in Section
18(6) that all power purchase agreements, transmission
74
services agreements and other contracts, entered into,
shall continue, in full force and have effect and will
be transferred to the successor entities. Section 19
deals with actual power to grant licence. The power is
vested with the Commission. Section 19(3) provides that
the duration, extent to which and the terms and
conditions, under which, transmission or supply of
energy is to be made, are to be specified in the
licence. The licence is also to contain such other
conditions as the Commission may consider appropriate
for achieving the purpose of the Act. It is thereafter
that Section 19(4) provides that without detracting
from the generality of the power with the Commission to
impose conditions mentioned in Sub-Section (3), the
conditions enumerated expressly in Sub-Section (4), may
be imposed. The Explanation relevant to the case, is
found sandwiched between Section 19(4)(j) and (k).
Section 19(4)(j), the Explanation, which follows
thereafter and Section 19(4)(k) read as follows:
“(j) Purchase power in an economical manner and
under a transparent power purchase procurement
process;
75
Explanation: The process concluded by the
State Government or the Board with generating
companies and transmission companies prior to
the date of commencement of the Act shall
stand assigned to KPTC in terms of section 14
under such contracts for effecting bulk sales,
distribution and supply to other licensees;
(k) the purchase of power from KPTC to the
extent necessary to enable the KOPTC to
perform its obligations under the contracts
concluded by the State Government or the Board
referred to in a clause.”
50. Moving on to Section 27, the proviso to Section
27(2), brings up the rear to the said sub-Section.
Section 27 deals with the duty of the holder of every
licence, to observe the methodologies and procedure to
be specified by the Commission from time-to-time, in
calculating the expected revenue from what it charges.
Section 27 uses the expression ‘design’. It only means
that the Commission is to fix the tariff, which would
be a medium to raise revenue. It is thereafter that
Section 27(2) clothes the Commission with the power to
actually lay down the methodology and the terms and
conditions for determination of the revenue and the
determination of the tariff. The factors to guide the
Commission in this regard are explicitly set-out in
Clauses (a) to (g) under Section 27(2). Since sub-
76
Section (2) limits the power, with reference to sub-
Section (3), we may only notice that Section 27(3)
obliges the Commission to record reasons, when it
departs from the factors specified in the Sixth
Schedule to the Electricity (Supply) Act, 1948 in
determining the revenue and the tariffs. Section 27(4)
declares that the Commission, in formulating the
methodology or procedure, is to ensure that the
objectives or purpose of the Act, are duly achieved.
Section 27(5) further ordains that the tariff is not to
reflect any undue preference to any consumer but may
discriminate on the basis of the load factor, power
factor, inter alia . The paying capacity of the category
of the consumers and the need for cross-subsidisation,
can form the premise for differentiation. Every
licensee is to provide to the Commission, full details
of its calculations for the ensuing financial year, of
the expected aggregate charges, which it believes to
have been permitted to recover, pursuant to the terms
of its licence and such further information, as the
Commission may reasonably require, to access such
calculation [See Section 27(7)]. Section 27(7) further
77
provided that within 90 days of the receipt of all the
information by the licensee that the Commission is to
notify either its acceptance or its refusal of the
licensee’s revenue calculation and tariff proposals. It
is obliged to issue a notice, giving reasons, as to why
it does not consider the tariff proposals as compliant
with the extant methodology or that it is incorrect. It
was to propose a modification or an alternative
calculation of the expected revenue from charges, which
a licensee was to accept. Section 27 defined ‘expected
revenue from charges’ in the Explanation (a) under
Section 27(12) as meaning, ‘the total revenue which the
appellant or the licensees are expected to recover from
charges for the level of forecast supply used in the
determination under sub-Section (7) in any financial
year in respect of goods or services supplied to
customers’ . Explanation (b) defined ‘tariffs’ as ‘ a
schedule of standard prices or charges for specified
services which are applicable to all such specified
services provided to the type of customers specified in
the tariff published ’.
78
51. On a conspectus of the Act, the Law-Giver has
intended that the holder of every licence granted under
the Act, is bound by the regime of regulation of the
tariff by the Commission. The appellant was
incorporated under Section 13 of the Act. The Act came
into force with effect from 01.06.1999. The appellant,
in other words, was not in existence prior to
01.06.1999. No doubt it succeeded to KEB. In an answer
to a query, it is pointed out that initially, the
appellant was the holder of a distribution and supply
licence. Subsequently, there has been an unbundling. At
present, appellant is engaged in supply of electricity.
It is further not in dispute that the appellant is a
licensee under the Act. It would, therefore, be clear
that being a holder of a licence, the appellant was to
follow the procedure under Section 27. It came under
the embrace of the jurisdiction and power of the
Commission in regard to the regulation of the tariff.
The power and jurisdiction of the Commission is to be
exercised to ensure that the objectives and the purpose
of the Act, are duly achieved. In the Statement of
Objects of the Act, it is, inter alia , recited that the
79
law was made to ensure the development and management
of the electricity industry in the State in an
efficient, economic and competitive manner to provide
reliable quality power and to protect the interest of
the consumer, including, vesting in the Commission, the
power to regulate the power sector. The sublime
legislative object is further reflected in Section 11A,
viz ., the declaration of the functions of the
Commission is, inter alia , to protect the interest of
the consumer, apart from promoting efficiency, economy,
safety, in the use of electricity. This is, of course,
besides ensuring that the charges for electricity are
adequately levied and duly collected. As noticed by us,
the Act signalled the demise of the old system,
whereunder, fixation of tariff was afflicted with
caprice, unilateralism and a tendency to unduly
subsidise the State Electricity Boards, thereby
preventing a natural free play of market forces, which
also did not conduce towards the promotion of the
production of electricity in the country. Section
27(2)(e) specifically contemplates that the Commission
is to be guided by the interests of the consumers, but
80
at the same time, providing for the return, by ensuring
that the consumer pays for the use of electricity in a
reasonable manner, based on average cost of supply of
energy. Section 27 marked a paradigm shift. An
independent Body was to exercise fairly drastic power
in the matter of regulating revenue and designing
tariff by the licensees. The proviso in Section 27(2)
was, indeed, intended to protect cases, where contracts
were concluded by either the Government of Karnataka
and/or the KEB with generation and transmission company
prior to the commencement of the Act. The proviso freed
parties to such contracts, which were concluded from
the regulatory regime. If such contracts were
concluded, the Law-Giver has made it clear that they
would be deemed to have been approved under the
provisions of the Act. Furthermore, the Commission is
charged with the duty to give effect to such contracts
which are concluded before the commencement of the Act.
It is, undoubtedly, true that the proviso to Section
27(2) does not use the words ‘power purchase
agreement’. It is equally true that Section 18(6),
falling under Part VII and dealing with licensing of
81
transmission and supply, employs, inter alia , the words
‘power purchase agreement’. Section 18(6), in fact,
uses also the words ‘transmission service agreements
and other contracts’. The attempt of the first
respondent is to highlight the fact that the proviso to
Section 27(2) does not use the words ‘power purchase
agreement’. The Law-Giver was aware and has used the
expression ‘power purchase agreement’ in Section 18(6).
In a later provision of the same Act, the same Law-
Giver has, by omitting the words ‘power purchase
agreement’ in the proviso to Section 27(2), evinced its
intention to be that a contract can be concluded for
the purpose of the proviso to Section 27(2) even without
there being a power purchase agreement.
52. The further argument is, that the proviso to
Section 27(2) must be understood with reference to
Section 27 and not based on a roving expedition,
involving survey of other provisions of the Act, which
may use similar words such as, Section 14(7) and
Sections 18 and 19. The principle that a proviso must
receive meaning with reference to the main provision to
which it is a proviso, is pressed into service.
82
53. The first respondent relied upon the decision of
10
this Court in Dwarka Prasad v. Dwarka Das Saraf . This
Court held, interpreting the proviso in question in the
said case as follows:
“18. We may mention in fairness to Counsel
that the following, among other decisions,
were cited at the Bar bearing on the uses of
provisos in statutes: CIT v. Indo-Mercantile
Bank Ltd, [AIR 1959 SC 713 : 1959 Supp (2) SCR
256, 266 : (1959) 36 ITR 1] ; Ram Narain Sons
Ltd. v. Asstt. CST [AIR 1955 SC 765 : (1955)
2 SCR 483, 493 : (1955) 6 STC 627]
; Thompson v. Dibdin [(1912) AC 533, 541 : 81
LJKB 918 : 28 TLR 490] ; Rex v. Dibdin [1910
Pro Div 57, 119, 125] and Tahsildar
Singh v. State of U.P. [AIR 1959 SC 1012 :
1959 Supp (2) SCR 875, 893 : 1959 Cri LJ 1231]
. The law is trite. A proviso must be limited
to the subject-matter of the enacting clause.
It is a settled rule of construction that a
proviso must prima facie be read and
considered in relation to the principal matter
to which it is a proviso. It is not a separate
or independent enactment. “Words are
dependent on the principal enacting words to
which they are tacked as a proviso. They
cannot be read as divorced from their context”
( Thompson v. Dibdin , 1912 AC 533). If the rule
of construction is that prima facie a proviso
should be limited in its operation to the
subject-matter of the enacting clause, the
stand we have taken is sound. To expand the
enacting clause, inflated by the proviso, sins
against the fundamental rule of construction
that a proviso must be considered in relation
to the principal matter to which it stands as
a proviso. A proviso ordinarily is but a
10
(1976) 1 SCC 128
83
proviso, although the golden rule is to read
the whole section, inclusive of the proviso,
in such manner that they mutually throw light
on each other and result in a harmonious
construction.
“The proper course is to apply the broad
general Rule of construction which is that a
section or enactment must be construed as a
whole, each portion throwing light if need be
on the rest.
The true principle undoubtedly is, that the
sound interpretation and meaning of the
statute, on a view of the enacting clause,
saving clause, and proviso, taken and
construed together is to prevail. ( Maxwell on
Interpretation of Statutes , 10th Edn., p.
162)””
54. In other words, since Section 27 is a provision,
which appears to deal with the revenue and tariff, which
a licensee can garner/charge, it suffices, if there is
a contract, which is concluded, which has, for its
subject matter, the most indispensable element, viz .,
the tariff. It is pointed out that in this case, the
three essential components of a contract for the
purposes of Section 27, have been concluded well before
01.06.1999. Correspondence and negotiation culminating
in the issue of the G.O. dated 12.05.1999 by the GoK,
by which, the Government of Karnataka, gave its
84
approval for the tariff at Rs.2.60 per unit, for the
tenure of five years, and what is more, the quantum to
be supplied by the first respondent, was also agreed
upon cements the case of the first respondent that there
was a concluded contract for the purpose of Section
27(2).
55. Shri Gopal Jain, learned Senior Counsel, would
persuade the Court to take a pragmatic and fair view.
The Government of Karnataka/KEB was, indeed, faced with
the shortage of power. The proposal of the first
respondent was most reasonable. If the parties were
agreed on the essential terms, which, in terms of the
proviso to Section 27(2), consisted, primarily of the
tariff, and a PPA is conspicuous by its absence in the
proviso , as an indispensable requirement, to constitute
a concluded contract, then, nothing more is required to
support the impugned Judgment, it is contended.
THE LAW RELATING TO CONTRACT
56. Section 2 of the Indian Contract Act, 1872 provides
for the interpretation clause. We may set out our
understanding of Section 2, so far as it is relevant,
to be as follows:
85
It begins with a proposal made by a promisor. A
proposal is an offer to do something or an offer to
abstain from doing something. The offer must be made
with a view to obtaining the agreement to it from the
party to whom it is made. When the person to whom the
proposal, as defined, is made, who is treated as the
promisee, conveys his unqualified consent, the
proposal is treated as having been accepted. The
proposal, when it is accepted, becomes a promise. An
agreement is every promise and every set of promises
forming the consideration for each other. As to what
is consideration, we need not be detained. A contract
is an agreement enforceable by law. Section 3 of the
Contract Act deals with communication, acceptance and
revocation of proposals. The acceptance of a proposal,
inter alia , takes place by any act or omission of the
party accepting. It must be an act or omission by
which he either intends to communicate his acceptance
or which has the effect of communicating his
acceptance. These are matters of fact to be decided
on the facts of each case. Section 10 of the Contract
Act reads as follows:
86
| “10. What agreements are contracts. —All | |
|---|---|
| agreements are contracts if they are made by the | |
| free consent of parties competent to contract, | |
| for a lawful consideration and with a lawful | |
| object, and are not hereby expressly declared | |
| to be void. |
Nothing herein contained shall affect any law
in force in India and not hereby expressly
repealed by which any contract is required
to be made in writing1 or in the presence of
witnesses, or any law relating to the
registration of documents.”
Thus, from the second part of Section 10 of the
Contract Act, it is self-evident that it is not
essential to form a contract, that it should be in
writing. The second part of Section 10, illustrated by
Section 19 of the Copyright Act, 1957 applies where a
law stipulates that a contract be in writing in which
case a contract must be reduced to writing.
THE CORRESPONDENCE AND CONDUCT OF THE PARTIES
57. It is apposite to refer to order dated 7.3.1994
where it all began. It reads as follows:
“PROCEEDINGS OF THE GOVERNMENT OF KARNATAKA
Sub: Proposal of M/s. Jindal Iron & Steel
Company Limited to set-up a 300 MW .
Power plant in two stages of 150 Mw Each
near Bellary-Hospet.
87
Consequent on the amendments made by the
Government of India to the India Electricity
Act 1990, and the Electricity (Supply)
sector participation in power generation and
to sign MOUs with private or foreign
companies to set up Thermal Power Plants at
Mysore, Hospet, Raichur, Mangalore and
Bangalore and a Hyde! Power Station at
Shivasemudram.
1. M/s. Jindal Iron & Steel Company Limited
are setting up a combined gas cycle plant
of 300 MW (2XI50 MW) power plant at Bellary-
Hospet within the site allotted for a Steel
Plant of 1.25 million ton capacity per
annum, for which the Government of Karnataka
has already accorded approval.
2. The estimated cost of the power plant is
approximately Rs.900 Crores. The debt equity
ratio shall be 2.1. The equity of around
Rs.225/- crores will be met 50% each by '
.. the participants - M/s. JISCO and M/s.
TRACT ABEL. The loans shall be arranged both
from Indian financial institutions and
foreign banka for which discussions are
under progress.
3. The advantage in setting up of the power
plant at Bellary-Hospet is that the excess
power generated will be fed to the KEB grid
which will make the system more stable and
can supply power to other industrial units
in and around the Bellary-Hospet region.
Besides. it would also help to generate
additional employment. The fact that the
Lingapur 220 KV Sub-station is nearer to the
site of the proposed Thermal Power Plant,
will help in inter-connection with the Sub-
station.
4. The Karnataka Electricity Board has
agreed to the proposal of M/s. Jindal
88
Tractebel Power Company for setting up of
the generating plant at Bellary - Hospet
subject to the toll owing conditions:
1. The above firm should send a detailed
project report duly indicating the cost
of the project with all relevant details
like, mode of execution fixation of
tariff etc;
2. For evacuation of power from the
above, the present KEB transmission and
distribution system may have to be
strengthened thus necessitating
substantial funds for the above. Board
is examining the possibility of
obtaining funds from various
organizations either from Government or
other sources;
3. The sale of power should be
exclusively to KEB and not to any other
entrepreneurs. In case power is
contemplated to be sold to third parties
directly, the sales shall be at the
rates to be fixed by Government of
Karnataka/KEB and with the prior
approval of Government of
Karnataka/KEB;
4. The firm has to enter into power
purchase agreement with KEB and the rate
at which power is to be purchased by KEB
is to be separately worked out;
5. The firm has to indicate the cost of
the generation to take a definite
decision for I purchase of power from
them.
TH
ORDER NO. DE 221 PPC 93 BANGALORE. DATED 7
MARCH 1994.
89
After examining the matter in detail
Government are pleased to accord; approval
to the proposal of M/s. Jindal Iron & Steel
Company Limited a follows:
[1] Ms. Jindal Tractabel Power Company
(JTPCL) is permitted to set up this
plant in two phases of 300 MW (each
phase consisting of !50 MW each) subject
to obtaining the approval of the
Government of India in respect of
foreign investment by M/s. Tractabel,
Belgium in Karnataka and also subject
to obtaining other statutory clearances
under the relevant Acts;
[2] M/s. JTPCL is permitted to sell
power directly to industrial units of
the area at the mutually negotiated
rates between M/s. JTPCL and the
industrial Units, subject to approval
by the State Government
[3] To permit KEB to evacuate power
produced by M/s. JTPCL through its grid
system subject to the capacity of the
grid system and subject to payment of
Wheeling and Banking charges payable to
KEB by M/s. JTPCL after evacuating power
produced by KPCL;
[4] The company has to sell the balance
power to KEB at a tariff to be fixed
according to the norms laid down by the
Government of India vide Notification
dated 31.3 .1992;
[5] KEB will make wheeling and banking
arrangements for M/s. JTPCL on payment
of wheeling charges;
[6] KEB is permitted to enter into an
agreement with M/s. JTPCL regarding
power purchase subject to approval by
the State Government.”
90
58. A perusal of proceeding dated 07.03.1994 would
reveal that though the KEB put forth the condition,
inter alia , that the power to be generated by the
thermal plant sought to be set up by JISCL, was to be
sold exclusively to KEB and not to any other
entrepreneur and that the firm has to enter into a power
purchase agreement with KEB, and the rate at which power
to be purchased by the KEB, is to be separately worked
out, in the Order, the GoK permitted the first
respondent to sell power directly to industrial units
of the area at mutually negotiated rates between the
first respondent and the industrial units subject to
approval by the State Government. Further, it was
decided, inter alia , that the first respondent had to
sell the balance power to KEB at a tariff fixed
according to the norms laid down by the Government of
India vide Notification dated 31.03.1992.
59. Finally, KEB was permitted to enter into an
agreement with the first respondent regarding power
purchase, subject to approval by the State Government.
What is noteworthy is that the KEB took the stand that
the first respondent would have to enter into a power
91
purchase agreement with the KEB, and the rate at which
power was to be purchased, was to be separately worked
out. In keeping with the decision, apparently, that the
first respondent was to sell the balance power to the
KEB, the Clause relating to sale of excess power to KEB
was first indicated in the Heads of Terms and later on
in the Wheeling Banking and Grid Support Agreement. It
will be noticed that in the clause, what was agreed
upon, was that there was to be agreement as regards
price and other terms which were to be negotiated at
the time of sale. This may be contrasted with the terms
of the proceedings dated 07.03.1994, which contemplated
sale according to norms dated 31.03.1992. On
20.10.1998, referring to an earlier letter dated
28.09.1998, the first respondent wrote to the KEB that
tariff at which they would sell power was in accordance
with the Government of India Notification dated
30.03.1992. A statement was forwarded, containing the
tariff calculation and also indicating certain
assumptions. On 21.11.1998, the first respondent wrote
to the KEB and we need notice the following:
92
First respondent claimed that it has completed
100% construction, erection and testing activities of
Unit No.1 (130 MW). It was scheduled to synchronise
the Unit No.1 by last week of December 1998. For Unit
No.2, the first respondent claimed, it had completed
100% construction, 90% erection of equipment, the
boiler light up was scheduled in January 1999 and the
commissioning was scheduled in July 1999. Thereafter,
first respondent refers to the PPA signed with JVSL
and JPOSCL. It was further stated that by proceeding
dated 02.03.1996, Government of Karnataka had given
approval for the same. The first respondent further
makes reference to Clause 2.4 of the Wheeling and
Banking Agreement for sale of power to KEB at mutually
agreed rates. The communication reveals that
thereafter, the first respondent proceeded to make an
offer to KEB for sale of power. It offered 50MW from
the commissioning date of Unit No.1. Further, it
offered 100 MW (base load basis of commissioning date
of Unit No.2). A further offer was made of maximum of
200 MW during the period when JVSL, JPOCL, which were
the dedicated consumers were under shut down (major
93
break down or during their maintenance period).
Penalty was offered if supply was less than 75 MW from
the commissioning date of Unit No.2. The price offered
was Rs.2.90/KWHR. It is thereafter that it was
indicated that the price was to be exclusive of the
electricity tax, adjustment towards inflation,
compensation towards foreign exchange variations,
provision for fuel escalation charges, maintenance of
power plant, for force majeure conditions. The
proposal was to supply power for an initial period of
five years from the date of commissioning of the
second 130 MW Unit. There is reference made to
utilisation of power during the stabilisation period
and we are not referring to the contents of the same
except to point out that this represented the second
proposal. Finally, the letter ended with a request to
the KEB to accord approval for the above two
proposals. The KEB, in response, pointed out that the
Board was, in principle, willing to purchase power
from the first respondents and the proposal of the
first respondent, regarding tariff, was stated to be
under evaluation by the Board. It can be safely
94
concluded that as on 15.12.1998, quite clearly, apart
from the KEB indicating that it was, agreeable in
principle, to purchase surplus power from the first
respondent, there is no other effect in law produced.
60. Under the proviso to Section 27 of the Act relied
upon by the respondent, a contract could be concluded
with the Government or with the Electricity Board. In
either case undoubtedly the regime under section 27
would cease to apply and the Commission would not have
any power.
61. In the notes submitted by first respondent, it was
seen contended that the contract was concluded between
the first respondent and GoK/KEB. To proceed with
clarity, the court specifically asked whether the case
of the first respondent was that the contract was
concluded between the GoK and the first respondent or
with KEB with the first respondent. The submission
which was made by the first respondent was that the
contract was concluded between the KEB and the first
respondent. Therefore, we must proceed on the basis
that contention of the first respondent is that the
contract was concluded between the first respondent and
95
the KEB. The significance of this finding is that it
obviates any adjudication as to whether the contract in
question complies with the mandate of Article 299 of
the Constitution. The appellant asserts that there can
be no implied contract with the Government under
Article 299 and enlists support of case laws in this
regard. In view of the stand of the first respondent
which we have indicated it would be an unnecessary
digression to explore the contours of Article 299.
62. The main question which arises for consideration
is whether there is contract concluded between the
first respondent and the KEB and if so, whether such a
contract was concluded before 01.06.1999? 01.06.1999
admittedly marks the commencement of the Act. If as on
01.06.1999, no contract was concluded between the KEB
and the first respondent within the meaning of proviso
to Section 27(2), and such a contract was concluded
thereafter, it will not advance the case of the first
respondent.
63. We must at this juncture deal with an appeal made
by the learned Senior Counsel for the first respondent.
It is contended that this Court may adopt a pragmatic
96
view. The first respondent had excess power. The KEB
stood in dire need of power. Thereafter, negotiations
ensued based on Clause 2.4 of the wheeling and Banking
and Grid Agreement. Apart from oral negotiation,
correspondence evidence the respective positions
adopted by the parties. The KEB took up the matter with
the GoK and GoK finally gave approval on 12.05.1999.
The terms approved by the GoK stand incorporated in the
subsequent PPA though the PPA was executed after
01.06.1999 but the significance of all this is that as
regards the essential terms, the parties were agreed.
A practical view is therefore pressed upon as a just
view also, namely, substantially for all practical
purposes the parties were ad idem. Repeatedly our
attention is alerted to the fact that acting upon the
GO dated 12.05.1999 and making it the sheet anchor,
first respondent even supplied power. Though there was
some prevarication as regards the rate being 2.60 per
KWH, the GoK sought to honour the contract as embodied
in the G.O. dated 12.05.1999 by issuing G.O. dated
17.07.2000.
97
64. We are dealing with a statutory dictate. What is
required to be established is that the contract stood
concluded and furthermore it was so done before
01.06.1999. Dr. Abhishek Manu Singhvi and Shri Gopal
Jain, learned Senior Counsels are right in pointing out
that the purport of proviso is to provide against
retrospectivity of the law. In other words, the
lawgiver contemplated that when a contract stands
concluded between the Government or the KEB and a party
before the Act came into force, the regulatory regime
should not be allowed to unsettle a solemn contract.
65. In this regard, we must bear in mind that the Act
envisages the setting up of an independent Commission.
The Commission stood endowed with various functions.
One of the important functions is to fix the tariff.
One of the vital objects of the Act is to protect the
interest of the consumer. The Electricity Board which
was set up under the Electricity (Supply) Act, 1948 was
clothed with the power for fixing the rate. The
undesirable results it produced and the need for
locating the power in an independent body which would
98
fairly and on preordained principles which involves
striking a balance between the interest of the consumer
and at the same time promoting efficiency in the power
sector leading to enhancement in power generation led
to the new regime. While a reasonable view must indeed
be taken it cannot be half baked or a legally untenable
approach. Flying on the wings of pragmatism, the Court
cannot gloss over a statutory injunction. We would
think that the first respondent must anchor its case on
surer foundations.
66. In this case, we proceed on the basis that it all
began with the communication dated 20.10.1998 sent by
the first respondent. However, for reasons which will
be clear, we need not harp upon its contents in greater
detail. On 21.11.1998, after referring to the fact that
the first respondent was recognised as an independent
power producer and it has achieved financial closure
and further that it was the only company in Karnataka
which could be set up as an independent power producer
and still further having completed 100% construction,
erection and testing ability in regard to Unit I, it
was stated that the synchronising of Unit I will take
99
place by the last week of December 1998. Regarding Unit
II, commissioning was projected in July, 1999.
Thereafter, the formal offer was made for sale of power.
The rate was Rs.2.90/Kwhr. Even the said rate was to
exclude electricity tax, inflation, foreign exchange,
fuel escalation charges, maintenance of power plant.
The rate was also to be exclusive of force majeure.
This meant that if there is grid failure or transmission
line failure leading to no supply, there would be no
penalty on the minimum guaranteed power. There is also
another aspect in the offer under the caption
“utilisation of power during stabilizing period” that
is from the date of synchronisation till commercial
operation. There are certain details thereunder and the
letter concluded by the first respondent requesting
approval to the two proposals at the earliest. By
communication dated 15.12.1998, the Board conveyed that
the proposal of the first respondent is under
evaluation. The Board (KEB) also expressed its
willingness to purchase power as already discussed. On
19.01.1998, the KEB wrote to the GOK. Therein, it is,
inter alia , stated that the plant of the first
100
respondent which was set up as a captive power plant
was given IPP status later on by GO dated 01.02.1996 as
the shareholders of the power plant (the first
respondent) and the steel plant (the sister concern of
the first respondent) were different. After referring
to the wheeling and Banking agreement, it is, inter
alia, stated that the first respondent during
discussion revealed that there was a decline in the
demand for power due to the reduction in the demand of
the steel, leading to the proposal by first respondent,
KEB further wrote about PPAs entered into with various
IPPs and the fact that the progress under the said
agreements was not satisfactory. Some other plants may
not come up was a concern voiced by the KEB. Other
issues relating to them find reflection. Shortfall in
generation in the state and the steady demand for power
are seen articulated. KEB was purchasing power from
Maharashtra State Electricity Board in addition to
central generating stations. After dealing with
Wheeling and Banking agreement and clause 2.4 which
contemplated sale of excess power to the KEB, it was
stated that the clause, however, contemplated purchase
101
at a negotiated rate. This, it is further stated was
because at that stage details regarding the capital
cost were not looked into as the project was
contemplated as a captive power plant. It is also for
the same reason stated that it would not be possible to
negotiate tariff based on two-part tariff notification
of the Government of India. After providing certain
other details including the variation in the exchange
rate qua the US $ and the decrease in consumer price
index, interest rate and the need for annual increase
in the fixed price, negotiations were undertaken it is
mentioned. After detailed discussion, it was decided
that a price of Rs.2.60 per unit could be offered. This
comprised of Rs.1.70 as fixed charge and Rs.0.90 as
variable charge. Variable cost was to depend on the
cost of coal. Its cost would determine the variable
price. Suffice it to further notice that the KEB
suggested that “We” can purchase power from the first
respondent at Rs.2.60 per unit (FC Rs.1.70) plus (VC
Rs.0.70). The fixed charge was to be escalated from the
second year with the conditions of penalty to be paid
by the firm for short supply of power and assured off
102
take which has been referred in the letter earlier. We
may finally notice the final paragraph of the said
communication “Approval of the government is sought to
the above proposal. Subsequent to the approval,
negotiations will be held with M/s JTPCL for finalizing
the PPA.”
67. The GOK wrote to the KEB. It is stated inter alia
that the proposal was examined in detail. The efforts
of KEB to bridge the gap on power availability by
entering into short term agreement with the first
respondent was appreciated. The wide gap between demand
and supply was noted. The prospect of the demand going
up further was echoed. It is finally stated as follows:
“The present proposal of the KEB keeps the
tariff open ended and possible revision.
The PPA being for a period of 5 years, KEB
is advised to negotiate with the Jindal
Tractebel for a fixed tariff for the next
5 years.
This may kindly be got examined by KEB and
the revised proposal may be sent to the
government”
68. We must not be led astray by the use of the word
“the present proposal of the KEB” as meaning that the
proposal is one made by the KEB. In law, it would be
103
the first respondent which has made the proposal as
contained in its communication dated 21.11.1998 and
thereafter following negotiations, the first respondent
came up with the price of Rs.2.60. It is this proposal
of the first respondent which was suggested by the KEB.
The GoK found that the said suggestion about the
proposal made by the first respondent kept the tariff
open ended with possible revision. The GoK contemplated
a PPA being entered into limited to a period of 5 years.
Therefore, the GoK wanted KEB to further negotiate a
fixed rate for the next 5 years. A revised proposal was
to be sent to the Government. It is not the case of the
either party that a concluded contract emerged at this
stage. Without the parties apparently being aware, the
next communication brought them even more perilously
close to the date of the commencement of the Act. On
31.03.1999, the first respondent wrote about its first
proposal on 21.11.1998. The fact that the discussions
followed is further mentioned. Specifically, there is
reference to meeting held on 26.03.1999. The readiness
of the KEB to purchase power was made subject to the
following terms and conditions:
104
1. The term of the agreement could be 5
years.
2. The tariff should be a single part
tariff. Escalation at a fixed percentage
could be applied on the total price on an
annual basis. KEB will not consider any
request either for two-part tariff based on
CEA guidelines or for payment of fuel cost
at actuals.
3. KEB will open irrevocable revolving
letter of credit under which JTPC can get
payments. It will also be supported by
Escrow mechanism.
4. There can be penalty clause both for
short supplies and short drawals.
5. The PPA should be a simple document.”
69. A formal proposal being demanded by the KEB subject
to the approval of the Board of Directors and also the
approval of its lender, the first respondent made the
proposal.
“Accordingly, subject to approval of our Board
and also subject to approval of our lenders,
we make the following proposal for sale of
power to KEB.
1. JTPC offers 50 MW (Energy 36 MU per month)
of power from the commissioning date of Unit 1
and 100 MW (Energy 72 MU per Month)of power
from the commissioning date of Unit 2. The
first Unit of 130MW is expected to be
commissioned in June 1999 and the second unit
of 130 MW is expected to be commissioned in
August 1999.
105
2. JTPC would have an option to supply in
excess of SOMW (Energy 36 MU per month) after
commissioning of Unit 1 and 100 MW (Energy 72
MU per month) after commissioning of Unit 2,
with KEB's approval, as and when JTPC has
surplus power available.
3. The tariff will be as follows:
I year (Upto 31" March 2000) Rs.2.60/kwhr.
II Year (Financial Year 2000-2001) Rs.2.73/kwhr.
III Year (Financial Year 2001-2002) Rs.2.87/kwhr.
IV Year (Financial Yea; 2002-2003) Rs.3.01/kwhr.
V Year (Financial Year 2003-2004) Rs.3.16/kwhr.
4. There will be no Wheeling charges or
Electricity Tax on supplies to KEB.
5. To maintain uniformity in penalty on either
side, JTPC proposes as follows as from COD of
Unit 2:
(a) JTPC guarantees minimum supply of the
Threshold Power Value after commissioning of
JTPC Unit 2. If the supply is less than the
Threshold Power Value, JTPC will pay penalty
at l0% of the tariff, for supplies below the
Threshold Power Value.
(b) KEB shall guarantee that it will consume
the Threshold Power Value. In case the
consumption is less than the Threshold Pow~r
Value, KEB shall pay to JTPC the full value of
Threshold Power at the applicable tariff as
above.
(c) The Threshold Power Value is 75 MW (Energy
54 MU per month).
6. The minimum supply and the minimum
consumption as per para 5(a) and 5(b) above are
applicable on a monthly basis.
106
7. If there is escalation in fuel cost beyond
5% at any time, JTPC reserves the right to
terminate the contract with 3 months' notice,
if KEB does not agree to compensate for such
escalation.
8. KEB shall open irrevocable revolving letter
of credit corresponding to 100 MW (Energy 72
MU per month) power sales under which JTPC can
get payment for its monthly bills. It shall
also be supported by Escrow mechanism.
9. The initial term of the agreement should be
5 years till March 31, 2004, with a provision
for renewal on terms mutually acceptable.
We request you to agree to the above terms and
conditions and convey your acceptance at the
earliest. We will approach our Board and the
lenders on getting your acceptance.
We also request you to let us have drafts of
the PPA, Escrow agreement and the Letter of
Credit at the earliest. We propose to have one
more meeting with your officials, after
studying these drafts.
Looking forward for your early favorable
response,
Thanking you,
Yours faithfully
For JINDAL TRACTEBEL POWER CO., LTD.
Sd/-
S.S. Rao
Dy, Managing Director & CEO
CC: Superintending Engineer El. Projects. KEB”
107
70. 23.04.1999 is the next milestone. After referring
to the previous development leading up to the proposal
dated 31.03.1999, KEB wrote that there were two options
available. The fall in the rupee was noted. Thereafter,
it is stated as under:
“The firm in its letter No.JTPC/KEB dated 31-
3-1999 has confirmed that the tariff payable
by KEB for power purchased will be Rs.2.60/unit
in the first year with an annual escalation of
5% every year. They have stated that they will
be offering 50 MWs (equivalent to 36 MU per
month) from the date of commissioning of the
first unit and 100 MW (equivalent to 72 MU per
month) with the commissioning of the second
unit The first unit is expected to be
commissioned in June 1999 and the second unit
in August 1999. They have also indicated that
in case they have any surplus power beyond 50
MWs and 100 MWs after commissioning of unit I
and unit 2, with the approval of KEB, they will
sell power in excess of 50 MWs and 100 MWs.
The firm has also proposed the following after
commissioning of Unit 2:
1. They will supply power with a threshold
value of 75 MWs equivalent to 54 MU per month.
2. If supply is less than the threshold power
value, then JTPC will pay penalty of 10% of
the tariff for supplies below the threshold
power value.
3. KEB shall guarantee that it will consume the
threshold power value. In case the consumption
is less than the threshold value, KEB shall pay
to JTPC the full value of threshold at the
applicable tariff as above.
108
4. The minimum supply and minimum consumption
as above are on monthly basis.
5. If there is a escalation in fuel cost beyond
5% at any time, JTPC reserves the right to
terminate the contract with 3 months notice,
if KEB does not agree to compensate for such
escalation.
6. KEB shall open irrevocable revolving letter
of credit corresponding to 100 MW (energy 72
MU per month) power sales under which JTPC can
get payment for its monthly bills. It shall
also be supported by Escrow mechanism.
7. The initial term of the Agreement should be
5 years till March 31, 2004 with a provision
for renewal on terms mutually acceptable.
These are issues to be negotiated with the firm
while finalising the PPA and will be taken up
later on.
This is for information of the government and
it is requested that orders may please be
obtained and communicated to us.
With regards,
Yours sincerely,
Sd/-
(K.P. SINGH)
Shri Arvind Jadav,
Secretary to Government,
Department of Energy,
Government of Karnataka,
Bangalore.”
71. Thereafter, on 12.05.1999 emerges the Government
Order which reads as under:
109
1. KEB is permitted to finalize a Power
Purchase Agreement with M/s Jindal Tractebel
Power Company Limited (JTPCL) for the purchase
of surplus power and submit the same to the
Government for approval.
2. The rate per unit being Rs. 2.60 including
variable charges with an annual increase of 5%
every year.
3. The term of the PPA shall be for a period
of five years.
4. To adopt the same principle of negotiated
tariff for captive generating power project who
intend to sell power to KEB.
By Order and in the name of the Governor of
Karnataka
(K.T. VUAYARAJ URS)
Under Secretary to Government
Energy Department”
DEVELOPMENTS POST 01.06.1999
72. Nearly, six months after 01.06.1999, i.e., on
04.01.2000, the Superintending Engineer of KEB wrote to
the first respondent stating that the communication
related to the tariff of Rs.2.60 per kw/hr negotiated
for purchase by the appellant. The first respondent was
requested to furnish details of the break-up of the
tariff so as to enable KEB to take further action in
the matter. It may at once be noticed that appellant
110
could not have negotiated prior to 01.06.1999. This is
for the reason that the appellant was only an offspring
of the Act, which came into force with effect from
01.06.1999. The first respondent wrote letter dated
06.04.2000 to the chairman of the appellant. It refers
to the agreement between the first respondent and the
appellant and that thereunder first respondent was to
return 215.810 MU to the appellant. It is indicated
that as on 06.04.2000, the first respondent had
returned 199.80 MU to the appellant. Referring to order
dated 12.05.1999, it was stated that it permitted the
appellant to purchase power from it at Rs. 2.60 inter
alia. It was also stated that it permitted appellant to
finalise the PPA with the first respondent. It was also
stated that the first respondent had finalised the PPA
with the appellant and the final draft as accepted was
submitted to the appellant in September-October, 1999.
73. It may be noticed that the aforesaid statement
indicates that the final draft which was accepted
between the parties was submitted only in
September/October 1999. This is significant as it
111
fortifies us in our view that the parties did
contemplate the PPA and the relevant terms were to be
embodied in the PPA. The final draft was clearly ready
only after 01.06.1999. Thereafter, referring to G.O.
th
dated 7 July 1999, the first respondent goes on to
state that the said order directs the appellant to
operate the PPA as per the order dated 12.05.1999 only
after complying with the obligations of GoK under order
dated 07.07.1999. This is with reference to serial no.8
th
of order dated 7 July 1999. The first respondent goes
on to state in the letter dated 06.04.2000 that it was
continuously pursuing the appellant and GoK for signing
of the PPA. It is further stated that even though the
PPA was not yet signed, being pending with appellant,
the absence of the PPA should not come in the way of
supplying power by the first respondent to the
appellant from 12.04.2000 as the order dated 12.05.1999
along with the details of the tariff does exist.
Significantly thereafter, the first respondent
indicated that pending finalisation and signing of the
PPA between the parties, appellant was requested to
accept power despatched by the first respondent from
112
12.04.2000. Invoices would be generated by the first
respondent in terms of letter dated 12.05.1999. It was
indicated by the first respondent that it was to be
again subject to any changes required to be done
subsequently as per the terms and conditions of the
PPA, to be agreed and signed between the parties. The
contents of the communication have been emphasised by
Shri Raghavendra S. Srivatsa, learned counsel for the
appellant as clearly indicating that matters were in a
state of flux and uncertainty and still furthermore
articulation was to await the finalisation of the PPA.
On 12.04.2000 the appellant responded to the
communication dated 06.04.2000. The appellant
communicated its approval for the continued supply
pending finalisation of the PPA but subject to certain
conditions. We may notice those conditions:
1. The Grid support charges envisaged in the
Wheeling & Banking and Grid support Agreement
i.e., Rs. 1.73 Crores Annum will be
provisionally deducted from the tariff
invoices when the amount is paid. This will be
subject to change and has to be paid as per
the terms of PPA to be signed.
113
2. The 115% energy imported will be deducted
from the energy exported, provisionally
pending finalization.
3. The energy will be accounted only after
signing of PPA.
4. The energy banked prior to signing of PPA
will be treated as energy banked with the
Corporation and will be accounted as per the
Corporations rules.
5. This order is only for facilitating
continued operations of the Power Plant and
Corporation makes no commitments with respect
to terms of PPA which is being finalized
separately.
6. The metering arrangements should be as per
the Article No. 4 of the Wheeling, Banking
Agreement and Grid Support Agreement already
signed copy of the same is enclosed.
[Emphasis supplied]
74. Pertinently, it is noteworthy that the appellant
appointed a professional body CRISIL to re-examine the
matter relating to tariff. CRISIL submitted report to
the appellant that the rate should be Rs. 2.10 per KWH
in the first year. The appellant found the figure
indicative and recommended that Rs. 2.45 per KWH should
not be exceeded. GoK issued corrigendum dated
114
08.05.2000 fixing the rate at Rs. 2.52 per KWH. A
perusal of the letter dated 24.05.2000 sent by the
Additional secretary of the appellant to the Chief
Engineer Electricity, KTPCL indicates that Corporation
gave its approval for the energy supplied to the Grid
from 15.04.2000 onwards at Rs.2.52 per unit pending
signing of PPA. It also contains certain terms. They
are as follows:
1. The procedure for payments should be as per
the standard procedure followed in case of IPP
Projects.
2. 115% of imported energy should be deducted
form the exported energy and payments will be
made for net exported energy so arrived.
3. The metering should be as per the terms of
Wheeling & Banking Grid support Agreement
between KEB and JTPCL signed on 23-01-96, till
such time PPA is finalized.
4. The firm has to submit an undertaking that
the terms and conditions of PPA between KPTCL
and JTPCL will be applicable for the payments
made by KPTCL for the energy supplied by JTPCL
from the date as approved by government till
the PPA is signed.
5. This is only an order to facilitate payment
of energy charges to M/s. JTPCL and Corporation
115
makes no commitments in this regard and the
terms of PPS will be finalized separately.
6. The energy transaction prior to 15-04-2000
will be finalized separately.”
(Emphasis supplied)
75. Therefore, the said communication would not
indicate conduct which matches action in accordance
with the concluded contract allegedly under the GO
dated 12.05.1999, as the rate stood reduced from
Rs.2.60 to Rs.2.52. Various conditions as noticed by us
are incorporated. Importantly, condition no.5 indicates
that it is only an order to facilitate payments. It was
unambiguously indicated that the appellant did not make
any commitment in this regard and clinchingly it was
indicated that the terms of the PPA will be finalised
separately.
76. The last communication after 1.6.1999, to bear in
mind, is the Order dated 17.07.2000. Therein, in the
Preamble, it is, inter alia , stated that KEB was
permitted to finalise the PPA for purchase of the
surplus power, as provided therein. Reference is made
further to the Government Corrigendum dated 08.05.2000,
whereunder, the rate was reduced to Rs.2.52 per unit.
116
Next, it is stated that, on examination, it was found
that, continuing with earlier rate of Rs.2.60 per unit,
would result in honouring the commitment of the
Government. There would be advantage of procuring the
better price every year. The formal Order was passed by
the GoK, permitting the appellant to purchase power at
the rate of Rs.2.60, with an annual increase of five
percent every year, as indicated in the Preamble to the
Order. The Order was to be implemented from the date of
issue of the Order. The other conditions of the
Government Order dated 12.05.1999 were to remain
unaltered. It is thereafter that the draft PPA was
prepared dated 07.11.2000. We may observe, that as far
as the rate is concerned, the rate indicated in G.O.
dated 12.05.1999, being restored and bearing in mind
the contents of G.O. dated 07.07.2000, it could be
found, that the ‘rate’ as such was concluded under G.O.
dated 12.05.1999.
77. However, a golden thread, which runs through the
correspondence is that, both the KEB, GoK and the
appellant and the first respondent, did contemplate the
execution of the PPA. The correspondence after
117
01.06.2000 also, unerringly, points to the fact that
parties did not view the PPA as a mere desire. They
have clearly proceeded on the footing that the terms of
the agreement must be evidenced in writing. Quite
clearly, the High Court has erred in not bearing in
mind the contents of the communications and their true
purport.
78. It is true that there is no express provision in
the proviso to Section 27(2) of the Act within the
meaning of second part of Section 10 of the Indian
Contract Act, that the contract, which is concluded,
must be in writing. However, the question would arise,
as to whether there is a contract, which was concluded
within the meaning of proviso to Section 27(2). It is
further true that Section 27(2) does not use the words
‘Power Purchase Agreement’. Section 19(4)(j) of the Act
refers to ‘contracts concluded’. Placing the said words
side-by-side with the words used in the proviso to
Section 27(2), we find that they are identical. The
said words, viz ., ‘contracts concluded’ must bear the
same meaning, both in Section 19 and in Section 27. It
is true that there is no format prescribed for a PPA.
118
The format came in 2005. Section 27(2) and Section
19(4)(j), do not expressly refer to a PPA. However, the
search must continue to ascertain the purport of the
words ‘contracts concluded’. In order that there must
be a contract concluded, undoubtedly, there must be a
proposal made, which must be accepted. There must be
consideration for the promise. The proposal must be
accepted, which must be communicated, as already
explained. The acceptance must be unqualified. This is
an over simplification of a complex process. We say
this, as the parties can be said to have entered into
a contract or a contract would be said to be concluded
only when they are ad idem on all the essential terms
of the contract. In other words, if the proposals
containing the essential terms have been accepted, and
the acceptance is communicated and, if the other
conditions in Section 2 of the Indian Contract Act are
complied with, viz ., that is there is consideration and
the contract is enforceable in law, within the meaning
of Section 10 of the Act, it would lead to the creation
of a concluded contract. Here, as we have noticed, the
119
KEB, the GoK and, what is more, the first respondent,
clearly contemplated that there should be a PPA.
79. We may further notice that there was a Banking,
wheeling and grid agreement, executed in the year 1996
between the KEB and the first respondent. It is with
the execution of the draft PPA, that it was decided
that the earlier agreement of 1996, was to remain in
abeyance during the period of the PPA. In the proposal
dated 21.11.1998, the rate was initially shown as
Rs.2.90/KWH but even this rate was exclusive of certain
six elements, which meant that the rate would be even
more. Thereafter, communication dated 19.01.1999,
addressed by KEB to the GoK would indicate that
negotiations were held, and what is more, detailed
discussions were held, whereunder, it was decided that
a price of Rs.2.60 per unit can be offered, comprising
of Rs.1.70 as fixed charges and Rs.0.90 as variable
charges. Fixed charges were to be escalated by five per
cent every year beginning from the second year.
Conditions of penalty to be paid by the firm for short
supply of power and assured offtake was also indicated.
The KEB sought approval from GoK. The GoK responded to
120
this recommendation by KEB by letter dated 05.03.1999.
It was indicated that the present proposal kept the
tariff open-ended and possible revision. The PPA being
for a period five years, KEB was advised to negotiate
with the first respondent for fixed tariff for five
years. Revised proposal was called for, which led to
further discussions. In the said communication, KEB
expressed its willingness to buy power subject to
certain terms and conditions. They included a penalty
clause, both for short supply and short drawal and that
the PPA was to be a simple document. A two-part tariff
was ruled out. Equally, was payment of fuel cost, at
actual. Therefore, on 31.03.1999, it is that, what has
been described as the proposal, as such, was made by
the first respondent. KEB was asked to convey its
acceptance at the earliest. This is as first respondent
was to approach its Board and its lenders on getting
its acceptance. We will proceed on the basis that it
was a matter of internal arrangement. On 23.04.1999,
KEB wrote to the GoK. KEB mentioned about two options.
Further, the KEB also, indicated it must be noted that
the first respondent had made an offer as detailed in
121
letter after the commissioning of Unit 2. They are seven
aspects. They included obligation to supply power with
a threshold value of 75MW equivalent to 54MU per month,
penalty to be paid by the first respondent in case of
supply being less than threshold value, payment by KEB
of full value of threshold in case consumption is less
than the threshold value and minimum supply and minimum
consumption being on monthly basis, right of first
respondent to terminate the contract, if there is
escalation in fuel cost beyond five per cent at any
time unless KEB agreed to compensate for such
escalation. What is most important is, with regard to
these matters, it was expressly indicated in the letter
dated 23.04.1999 that ‘these are issues’ to be
negotiated with the firm while finalising the PPA and
will be taken up later on. These issues were not
negotiated between the KEB and the first respondent
before 01.06.1999. There is no dispute about this
aspect. The fact that the appellant did not mention in
communication after 01.06.1999 about the need for
approval by the Commission is clearly insufficient to
oust the jurisdiction of the Commission. The Commission
122
cannot be prevented from exercising the power based on
the conduct of the appellant in this regard which
included preparation of the draft PPA.
Equally, the act of the GoK in issuing corrigendum dated
08.05.2000 or the order dated 07.07.2000, cannot also
detract from the power of Commission or lead us to hold
that there was a concluded contract under Section
27(2). The fact that issues in letter dated 23.04.1999
have been included in terms of the PPA is clearly
besides the point as the question is whether the parties
were agreed on them as on 01.06.1999. They were clearly
not. In this regard we may notice the sheet anchor of
the first respondent, viz ., the G.O. dated 12.05.1999.
GoK in the said G.O., undoubtedly, agreed for the rate
per unit to be Rs. 2.60, including variable charges. It
also agreed for an annual increase of five per cent
every year. The term of the PPA was to be five years.
The other two aspects must, however, are not be lost
sight of. By G.O. dated 12.05.1999, actually KEB was
permitted to ‘finalise a Power Purchase Agreement’ and
to submit the same to the Government for approval. What
could be said to be approved by the Government was the
123
rate, as indicated, and the term. The G.O. clearly
indicated that all the parties, including the GoK
contemplated a PPA with the execution of which alone,
they were to be bound. The Principle of Negotiated
Tariff for captive generating power project, who intend
to sell power to KEB, was to be adopted. Several matters
remained unsettled. It is not in the region of dispute
that the issues, which KEB, in its letter dated
23.04.1999, had indicated, as issues to be negotiated
while finalising the PPA and to be taken up later on,
never came to be negotiated pursuant to the GO dated
12.05.1999 before 01.06.1999. This is crucially fatal
to the case of the first respondent. We conclude that
the parties contemplated a written PPA containing
various details apart from the tariff rate and the
tenure. There was no concluded contract with respect to
several aspects, at least, as on 01.06.1999, which is
the date on which the Act came into force. The fact
that power was supplied after the Act came into force,
must be understood in the context of the
correspondence, which we have elaborately referred to.
Even here, we may notice that there were doubts about
124
the rates itself. An Expert Body was appointed. It
recommended Rs.2.10 per KWH. The appellant, which, in
the meantime, came upon the scene, as a result of the
Act, and succeeded to the KEB, recommended that supply
of power may be made by the first respondent subject to
the finalisation of the PPA at a rate not exceeding
Rs.2.45 per unit. GoK issued a Corrigendum providing
for the rate of Rs.2.52 per unit. Supply was made and
payments made at Rs.2.52 per unit. Government issued
Order dated 07.07.2000 reinstating the rate of Rs.2.60
per unit. There may be merit in the contention of the
first respondent that as far as the rate is concerned,
there is consistency in that, GoK restored the rate at
Rs.2.60 by way of honouring its contractual commitment.
It is here that we must unravel the true scope of the
words ‘contracts concluded’ in Section 27(2) of the
Act. The proviso when it uses the words ‘contracts
concluded’, does not use the words ‘contracts concluded
as regards tariffs’. A contract of the nature, we are
concerned with, cannot be said to consist only of a
rate and the term or even the quantum included. In a
contract of this nature, there are obviously various
125
other aspects about which the parties must be ad idem .
The rate, the term and quantum are integrally
interconnected with other terms. There cannot be
concluded contract without parties being ad idem about
those terms. We found that the parties were not ad idem
as regards the issues which were expressly left open
for negotiations in the communication dated 23.04.1999.
GoK also contemplated ‘finalising’ a PPA. The word
‘finalising’ and the word ‘PPA’, both of which did not
take place before 01.06.1999, in our view, has resulted
in a situation where a contract could not be said to be
concluded even within the meaning of the proviso to
Section 27(2) of the Act. In other words, even
proceeding on the basis that even in a given case, a
contract could be concluded within the meaning of the
proviso, even in absence of a written PPA, bearing in
mind also the absence of the word ‘PPA’ in the said
provision and contrasting it with Section 18 where the
same Law-Giver has used the word ‘PPA’, if the parties
were not ad idem about the necessary terms and if the
parties equally contemplated a PPA to bring it into
existence a contract within the meaning of Section
126
27(2), then, clearly a PPA would be indispensable to
attract the proviso to Section 27(2). This is not even
a case where, in other words, parties were ad idem on
all the essential aspects, which go into the formation
of a complex contract as is involved in the facts of
this case. Therefore, the supply of power, in our view,
by the first respondent, after 01.06.1999, cannot be
relied upon, in view of the facts revealed by the
correspondence, which itself makes it a stop gap
arrangement, and what is more subject to conditions
which included execution of a PPA, to conclude that the
subsequent conduct, unerringly pointed to the fact that
a contract within the meaning of Section 27(2) stood
concluded before 01.06.1999.
80. In Alexander Brogden (supra), from which
considerable support is sought to be drawn by
Dr. Abhishek Singhvi, learned Senior Counsel, the
appellants who were defendants claimed that there was
no binding contract between them and the plaintiffs.
The appellants had supplied coal for some time to the
plaintiffs. The appellants suggested after some time
that there should be a contract entered into between
127
the parties. After the agents met, the terms of the
agreement came to be drawn up by the agent of the
plaintiff and sent to the defendants. The defendants
filled up certain parts which had been left in blank,
and what is more, the name of a person was shown as an
arbitrator. The word ‘approved’ was written at the end
of the paper. The chief partner in the defendant’s firm
signed. Though the usual form of the signature of the
partnership was “B & Sons”, it was the chief partner
who signed. The defendant sent the paper to the agent
of the plaintiff who put it in his desk. Nothing towards
the execution of the formal agreement took place. Both
parties acted upon the same. Coals were supplied.
Payments were made. In fact, when there were some
complaints in regard to the correctness of the supply
in accordance with the paper containing the approval of
the appellant through its chief partner, explanation
and excuses were given, ‘the contract’ came to be
alluded to in the correspondence. Further supplies
resumed. However thereafter arose disputes. The
appellants refused to honour the agreement to supply.
In much of the correspondence which followed again the
128
word ‘contract’ made its appearance. The plaintiff
brought an action for damages for breach of contract.
It was on these facts that Lord Hatherley inter alia
held:
“Now, my Lords, I apprehend that if it had
stopped here, this is a course of action from
which the inference would fairly be drawn
which becomes quite conclusive afterwards. Up
to the present stage to which I have brought
it the case stands thus: Agreement proposed
first of all by the coal company, sent as a
proposition to the railway company, converted
by the railway company into a definite
agreement with some very slight alterations,
sent back again with these few alterations
and then adopted and approved by the coal
company with only one important farther
alteration, namely, the insertion of Mr.
Armstrong's name as the arbitrator — a letter
written with it by the person engaged in the
whole negotiation on the one side, saying
that he could not see the person who was
negotiating on the other side until the time
when the agreement was to come into effect —
that immediately followed by an order for
coals to the extent of 250 tons — an inquiry
sent by telegram, and an anxious inquiry by
letter also saying:— “Let us know whether we
can rely upon your supplying us with 220 tons
of coal per week, because, upon your answer
whether you can or cannot supply us with that
quantity will depend the arrangements I am
to make with other coal companies in the
North.
It was said that this was inconsistent with
the Plaintiffs having an agreement by which
the Defendants had bound themselves to supply
that quantity of coal. I do not see any such
inconsistency whatever. It might possibly
129
bear on the question of whether the agreement
was actually clenched at that moment or not.
It might indicate this: If you cannot answer
definitely that you can supply us with the
250 tons of coal, we may feel ourselves at
liberty then to deal with the other coal
companies — that might possibly be the true
view of it, in which case it struck me it
might be said that it was not eo instanti
that the agreement was clenched. However,
what followed did clench it most distinctly,
because there not only comes the answer,…
XXX XXX XXX
My Lords, I will not go through the whole of
these transactions, If you ask me, when in
my judgment the agreement was complete, I
answer that the agreement was complete when
the first coals, the 300 tons of coal
supplied in January, were invoiced at the
differing price, and when that differing
price was accepted and paid. I think that did
bring the case up to what Mr. Herschell very
fairly admitted, as he was bound to admit it,
would be a sufficient case to make out on the
part of the Plaintiffs. It does establish a
course of action on the part of the
Plaintiffs of such a character as necessarily
to lead to the inference on the part of the
Defendants that the agreement had been
accepted on the part of the Plaintiffs, and
was to be acted upon by them; and they did
act upon it accordingly.”
81. We have noticed the facts. It was a contract for
sale of coal. There was a long course of dealing between
the parties. The defendant wanted, however, to have a
written contract. The agents met. The terms of the draft
130
agreement were prepared by the agent of the buyer and
sent to the seller. The chief partner of the Seller
firm, in fact, filled up certain parts of the terms
which had been left in blank. What is more, the name of
the arbitrator to decide in the case of a dispute was
also written. Most importantly, the word ‘approved’ was
written. It was signed by the chief partner. It was
sent to the agent of the buyer. Though the matter did
not culminate in the drawing up of a formal written
agreement as such, the evidence revealed that the coal
was supplied and paid for. It is pertinent to notice
the context in which the question arose. It did not
involve the aspect about a statute like the Act in
question, with its ramifications both qua the alleged
contracting parties and the impact on the object of the
Act bearing in mind the interests of the consumers as
well. At any rate, the view taken in the said case
cannot be safely applied even otherwise to the facts of
the case before us. It is not a case where the parties
were not ad idem on all the essential terms of the
contract. It is not a case where the correspondence
revealed that a concluded contract did not exist. The
131
conduct of the parties in the supply of the goods in
question, and the acceptance of the same and the payment
made therefor and the not infrequent reference to the
terms of ‘the contract’ as approved by the chief partner
of the Seller firm “as contract” fortified the Court in
the facts in concluding that there was a concluded
contract. On the other hand, the correspondence in this
case establish a completely different factual matrix.
Both before 01.06.1999 and thereafter, the parties
clearly contemplated the execution of the PPA. They
were not ‘ ad idem ’ on seven matters which are expressely
left open for negotiations as indicated in letter dated
23.04.1999. We are unable to brush aside these as not
constituting essential terms. To conflate ‘concluded
contract’ even in the context of the proviso to Section
27, as one merely agreeing to the tariff, tenure and
the quantum overlooks the complex nature of the working
of such a contract. We cannot be oblivious to the impact
of provisions relating to penalty, threshold value,
consumption and other terms. Before 01.06.1999, it is
not in dispute that no negotiation as was contemplated
in regard to the same took place. Even negotiations
132
after 01.06.1999, and the preparation of a draft PPA on
07.11.2000, cannot clearly suffice. This is a case of
a contract involving a public body. This is also a case
where the implications of the contract are not confined
to the parties alone. The contract impinges on interest
such as interest of the consumer and other relevant
aspects. We, therefore, are of the view that we cannot
permit the first respondent to draw support from the
said judgment.
82. In Kollipara Sriramulu (Dead) by His Legal
Representative (supra), the Court was dealing with a
question, whether there was an oral agreement for the
sale of shares by the partners of the firm. One of the
contentions of the appellant therein was that there was
no contract because the sale was conditional upon a
regular agreement being executed and there was none. It
is apposite that we notice the following discussion:
“3. … We do not accept this argument as
correct. It is well established that a mere
reference to a future formal contract will
not prevent a binding bargain between the
parties. The fact that the parties refer to
the preparation of an agreement by which
the terms agreed upon are to be put in a
more formal shape does not prevent the
133
existence of a binding contract. There are,
however, cases where the reference to a
future contract is made in such terms as to
show that the parties did not intend to be
bound until a formal contract is signed.
The question depends upon the intention of
the parties and the special circumstances
of each particular case. As observed by the
Lord Chancellor (Lord Cranworth) in Ridgwa
y v. Wharton [6 HLC 238, 63], the fact of a
subsequent agreement being prepared may be
evidence that the previous negotiations did
not amount to a concluded
agreement, but the mere fact that persons
wish to have a formal agreement drawn up
does not establish the proposition that
they cannot be bound by a previous
agreement. In Von Hatzfeldt-Wildenburg v. A
lexander [(1912) 1 CH 284, 288] it was
stated by Parker, J. as follows:
“It appears to be well settled by the
authorities that if the
documents or letters relied on as
constituting a contract
contemplate the execution of a further
contract between the parties, it is a
question of construction whether the
execution of the further contact is a
condition or term of the bargain or
whether it is a mere expression of the
desire of the parties as to the manner
in which the transaction already
agreed to will in fact go through. In
the former case there is no
enforceable contract either because
the condition is unfulfilled or
because the law does not recognize a
contract to enter into a contract. In
134
the latter case there is a binding
contract and the reference to the more
formal document may be ignored.”
4. In other words, there may be a case
where the signing of a further formal
agreement is made a condition or term of
the bargain, and if the formal agreement is
not approved and signed there is no
concluded contract. In Rossiter v. Miller [
3 AC 1124] Lord Cairns said:
“If you find not an unqualified
acceptance subject to the condition th
at an agreement is to be prepared and
agreed upon between the parties, and
until that condition is fulfilled no
contract is to arise then you cannot
find a concluded contract.”
In Currimbhoy and Company Ltd. v. Creet [60
IA 297] the Judicial Committee expressed
the view that the principle of the English
law which is summarised in the judgment of
Parker, J. In Von Hatzfeldt-Wildenburg v.
Alexander [(1912) 1 CH 284, 288] was
applicable in India. The question in the
present appeals is whether the execution of
a formal agreement was intended to
be a condition of the bargain dated July 6,
1952 or whether it was a mere expression of
the desire of the parties for a formal
agreement which can be ignored. The
evidence adduced on behalf of Respondent 1
does not show that the drawing up of a
written agreement was a pre-requisite to
the coming into effect of the oral
agreement. It is therefore not possible to
accept the contention of the appellant that
135
the oral agreement was ineffective in law
because there is no execution of any formal
written document. As regards the other
point, it is true that there is no specific
agreement with regard to the mode of
payment but this does not necessarily make
the agreement ineffective. The mere
omission to settle the mode of payment does
not affect the completeness of the contract
because the vital terms of the contract
like the price and area of the land and the
time for completion of the sale were all
fixed. We accordingly hold that Mr Gokhale
is unable to make good his argument on this
aspect of the case.”
The principle is unexceptionable. But we are of the
view that the facts are distinguishable and, on the
facts, herein, there was no concluded contract and what
is more, a PPA was not a mere desire but an
indispensable requirement to conclude the terms.
83. It is clear as day light that all through the
parties undoubtedly contemplated entering into a power
purchase agreement. The subject matter of the contract,
the position of the parties, the implications of the
working of the contract and more importantly, the
intention of the parties do not persuade us to safely
gather that there was a concluded contract upon
136
negotiations and correspondence, culminating in the
Government Order 12.05.1999. It is clear that even the
GO dated 12.05.1999 expressly contemplated only a
permission by the Gok to the KEB to finalise “a PPA”
for the purchase of surplus power. The word “finalise”
in the context of the PPA cannot be played down in the
context of the previous correspondence at any rate. It
was, in fact, also contemplated that the PPA which was
to be finalised must after finalisation be submitted
again to the government. GoK was thereafter to grant
its approval. This cannot be overlooked.
C.A. @ S.L.P. (C) NO. 23793 OF 2004
84. The contention of the appellant-Commission is that
it was not a party originally in the appeal. The Court,
on 17.08.2002, directed the Commission to be ready with
the written submission on the question of interim
relief. On 19.11.2002, the High Court directed the
appellant in the other case to add the Commission as a
party. On this basis, it is contended that the findings
in the impugned Order, that at no stage, the High Court
137
had directed the Commission to be impleaded, is not
correct.
85. Next, it is contended that the finding that
Commission filed extensive pleadings and contested the
appeal, exhibiting an abnormal interest, is not
correct. The Order dated 17.08.2002, hereinbefore
referred to, is relied upon. The finding, therefore,
that the Commission exhibited an abnormal interest in
contesting the appeal or filed extensive pleadings, is
impugned. As regards the decision of the Court to not
allow the impleadment of the Commission, it is
contended that the appellant does not seek to challenge
the same. All that the learned Counsel submits is that
the observations made against the appellant-Commission
may be set aside.
86. Shri Gopal Jain, learned Senior Counsel for the
first respondent has no objection to the same.
Therefore, the appeal filed by the Commission is to be
disposed of, setting aside the observations made
against it and the appeal is to be allowed on the said
basis.
138
THE CONTOURS OF SECTION 41 OF THE ACT
87. Section 41 of the Act reads as follows:
“41. Appeals against the order of the
Commission. - Any person aggrieved by any
decision or order of the Commission passed
under this Act may file an appeal to the
High Court of Karnataka within sixty days
from the date of communication of the
decision or order of the Commission to him,
on questions of law arising out of such
order:
Provided that the High Court may, if it is
satisfied that the appellant was prevented
by sufficient cause from filing the appeal
within the said period, allow it to be
filed within a further period not
exceeding thirty days.”
(Emphasis supplied)
88. A Right of Appeal is a creature of a Statute. The
right can be qualified or conditioned. The ambit of the
appellate power is to be discerned from the terms of
the Statute. A ‘question of law’ is not the same as a
‘substantial question of law’. However, when the
Statute insists on a ‘question of law’ to maintain an
appeal, the Appellate Body stands constrained to that
extent.
89. Interpreting Section 15Z of the Securities and
Exchange Board of India Act, 1992, which also
139
conditions the Right of Appeal, ‘on any question
arising out of such Order’, this Court, speaking
through P.S. Narasimha J., in Securities and Exchange
11
Board of India v. Mega Corporation Limited held, inter
alia , as follows:
“14. On a ‘textual’ interpretation, the
expression ‘question of law’ is defined in
the Black’s Law Dictionary as follows:
“1. An issue to be decided by the judge,
concerning the application or interpretation
of the law;
2. A question that the law itself has
authoritatively answered, so that the Court
may not answer it as a matter of discretion;
3. An issue about what the law is on a
particular point; an issue in which parties
argue about, and the court must decide what
the true rule of law is;
4. An issue that, although it may turn on a
factual point, is reserved for the court and
excluded from the jury; an issue that is
exclusively within the province of the judge
and not the jury”
17. The jurisdiction of the Supreme Court
under Section 15Z to consider any question
of law arising from the orders of the
Tribunal should therefore be seen in the
‘context’ of the powers and jurisdiction of
the Tribunal under Sections 15K, 15L, 15M,
15T, 15U and 15Y of the Act. It is in the
functioning of the Tribunal to re-examine
11
MANU/SC/0362/2022
140
all questions of fact at the appellate stage
while exercising jurisdiction under Section
15T of the Act. In Clariant18 and National
Securities Depository19, this Court had an
occasion to examine the jurisdiction of the
Tribunal and explain that the Tribunal has
wide powers. Being a permanent body, apart
from acting as an appellate Tribunal on
fact, the Tribunal routinely interprets the
Act, Rules and Regulations made thereunder
and evolves a legal regime, systematically
developed over a period of time. The
advantage and benefit of this process is
consistency and structural evolution of the
sectorial laws.
19. It is in this very context that the UK
Supreme Court in the case of Jones v. First
Tier Tribunal,20 formulated certain
principles for appellate courts to interfere
against the orders of Tribunals on the
ground of existence of questions of law. The
Court held as under:
“16 … It is primarily for the tribunals, not
the appellate courts, to develop a
consistent approach to these issues [of law
and fact], bearing in mind that they are
peculiarly well fitted to determine them. A
pragmatic approach should be taken to the
dividing line between law and fact, so that
the expertise of tribunals at the first tier
and that of the Upper Tribunal can be used
to best effect. An appeal court should not
venture too readily into this area by
classifying issues as issues of law which
are really best left for determination by
the specialist appellate tribunals.”
20. The scope of appeal under Section 15Z
may be formulated as under:
141
20.1 The Supreme Court will exercise
jurisdiction only when there is a question
of law arising for consideration from the
decision of the Tribunal. A question of law
may arise when there is an erroneous
construction of the legal provisions of the
statute or the general principles of law. In
such cases, the Supreme Court in exercise of
its jurisdiction of Section 15Z may
substitute its decision on any question of
law that it considers appropriate.
20.2 However, not every interpretation of
the law would amount to a question of law
warranting exercise of jurisdiction under
Section 15Z. The Tribunal while exercising
jurisdiction under Section 15T, apart from
acting as an appellate authority on fact,
also interprets the Act, Rules and
Regulations made thereunder and
systematically evolves a legal regime. These
very principles are applied consistently for
structural evolution of the sectorial laws.
This freedom to evolve and interpret laws
must belong to the Tribunal to subserve the
Regulatory regime for clarity and
consistency. These are policy and functional
considerations which the Supreme Court will
keep in mind while exercising its
jurisdiction under Section 15Z.”
The Commission is an Expert Body. Interference with
its findings cannot be sustained, to begin with, if it
is bereft of reasons. Findings of such a body must
receive due deference. Perversity in the sense of
findings, which are wholly without basis or material or
which no person with the professed skills would arrive
142
at, may merit interference. A finding, which ill
squares with a clear statutory injunction, would leave
the door ajar for overturning the finding.
THE OTHER FINDINGS OF THE HIGH COURT
90. We must deal with the three other findings. The
High Court has found that there is merit in the argument
based on principles of promissory estoppel and
legitimate expectation. We would have explored the
matter and rendered our findings qua the approach of
the High Court in regard to this matter which at least
at first blush looks ‘wholly untenable’ but since the
first respondent has taken the stand before this Court
that it may not seek to draw support from the said
principles and rightfully so, we desist from further
enquiry.
WHETHER THE FINDINGS OF THE COMMISSION ARE
PERVERSE, ARBITRARY AND WITHOUT APPLICATION OF
MIND (POINT NO.4)?
91. As regards the finding by the High Court answering
point no. 4, namely, whether the impugned orders are
perverse, arbitrary and passed without application of
143
mind, our attention is drawn by the appellant to the
limited nature of jurisdiction exercised by the High
Court under Section 41 of the Act.
92. It has been the endeavour of the appellant to point
out that contrary to the point which was raised, namely,
whether the orders were perverse, arbitrary and passed
without application of mind at any rate, the point has
been answered in a manner which cannot be sustained.
The High Court opens the discussion under point no. 4
by referring to the contention of the first respondent
that the impugned order suffers from certain errors
apparent on its face. Reliance is placed on a decision
of this Court dealing with power of this court under
Article 136 of the Constitution.
93. The High Court has proceeded to find that patent
errors have been committed by the Commission. It is
found that the Commission has wrongly calculated the
fixed charges for 487MUs while fixing the tariff. This
is after finding that the fixed charges should be for
657Mus. The second error, it is found, lay in the
Commission finding that the incentive payment charges
should be Rs.0.952, in arriving at the tariff rate
144
whereas incentive payment charges were taken as
Rs.0.924 per unit. The tariff would stand raised to
Rs.2.54 per unit, if the aforesaid errors were
corrected. Next, it is observed that these errors were
not disputed by the appellants in the pleadings before
the High Court or in the course of argument. The learned
Senior Counsel for the appellant Shri S.S. Naganand,
who submits that he had appeared in the High Court,
pointed out that, in the first place, being a Statutory
Appeal, there is no provision for pleadings, as such,
in the High Court. Further, the Commission has given a
basis for what it has done. A detailed note is also
made available, in this regard, to this Court. The
learned Counsel has further said that the matter was
argued threadbare before the Court. We find that the
High Court has not given any independent reasoning
except as we have referred to. Next, the High Court has
found that, having agreed to a negotiated single part
tariff, the Commission could not have unilaterally
ignored the well-established parameters and applied
norms, which were, undoubtedly, valid for a two-part
tariff and super impose the same in calculating tariff
145
on a single part tariff basis. The two-part tariff
applied uniformly, it is found would have resulted in
a tariff rate of Rs.3.16 per unit, which was much higher
than Rs.2.60 under the draft PPA. Here again, these
findings appear to be based on there being a concluded
contract and, secondly, are bereft of any reasons and
material. The High Court proceeds to note the case of
the first respondent that tariff of the first
respondent was one of the cheapest as it was based on
least cost tariff basis unlike other companies. No
attempt is made to deal with the findings of the
Commission or the power and duty of the Commission.
This part of the finding is summed-up by finding that
there is ‘some substance’ in the contention of the first
respondent that it was at the receiving end of
‘invidious discrimination and arbitrariness’. We take
exception to this approach by the High Court in a
Statutory Appeal conditioned by the requirement that a
question of law must arise. A finding that there is
‘some substance’ cannot be the approach, when it is
finally disposing of an appeal and finding fault with
the Order of an Expert Body, in particular. Equally, we
146
are mystified by the invocation of the Doctrine of
Invidious Discrimination and Arbitrariness in the facts
of the case.
94. Next, the High Court proceeded to find fault with
the fixing of the heat rate disregarding the norms laid
down by the Ministry of Power/CEA or whichever is lower.
The High Court has been critical of the Commission
fixing of the plant load factor disregarding the norms
under the Electricity Supply Act or the negotiated
plant load factor. There are no reasons forthcoming to
support this finding. High Court next found fault with
the Commission for doubling the penalty. There is no
rationale. There is no appreciation within the limits
of its qualified jurisdiction. Reduction of escalation
by the Commission from five per cent to two and a half
per cent per annum, is apparently with reference to
what transpired during the negotiations and, therefore,
proceeding on the basis that the matter was a concluded
contract, as it was, indeed, the finding of the High
Court. It is without considering the ambit of the power
of the Commission and the objects of the Act. There are
similar findings with respect to fixed costs,
147
disproportionate loading, tantamounting to cross
subsidisation being contrary to the Judgement of this
Court in West Bengal Electricity Regulatory Commission
12
v. CESC Ltd. . Again, there is no discussion and the
High Court has purported to proceed as if it is itself
an Expert Body. At least, the reasons have not been
furnished for justifying the Commission being arraigned
in the manner done. Likewise, there is impugning of the
findings of the Commission in regard to grid support
charges being unjustified and ultra vires the Act. It
is also stated that objections filed by the first
respondent were not considered by the Commission.
Lastly, it was found that the Commission has not given
reasons.
95. We are of the view that the High Court has
apparently proceeded on the basis that there existed a
concluded contract within the meaning of proviso to
Section 27(2). We have found that it is unsustainable.
We are of the view that findings which have been
rendered under Point No. 4, have been considerably
influenced by the finding relating to there being
12
(2002) 8 SCC 715
148
negotiations and the emergence of the concluded
contract. We are of the view that, at any rate,
particularly bearing in mind, the limited nature of the
jurisdiction of the High Court under Section 41 of the
Act, the approach and the findings of the High Court
under Point No. 4, may not be sustainable. But, at the
same time, we are of the view that, being an assessment
of the findings of an Expert Body, the High Court must
reconsider the matter. To the said extent, the matter
must be remitted back to the High Court in regard to
Point No.4.
CPP V. IPP (POINT NO.3)
96. The last question which remains relates to point
no.3 that is, whether the first respondent was a CPP or
an IPP.
97. Under point no.3, the High Court has relied upon
the orders of GoI dated 09.10.1995, 31.01.1996,
06.11.1996 and 09.01.1997. The High Court has found
that under these orders there is a distinction between
the IPP and CPP and the first respondent has complied
with the requirement under the Supply Act for
establishing a generating company with reference to
149
Sections 29 to 31 for sale, pursuant to Section 43A,
making it an IPP. It is found that CPP would have to
get clearance under Section 44 of the Electricity
(Supply) Act, whereas an IPP would require to process
the matter under Sections 29 to 31 of the Electricity
(Supply) Act, 1948. Reliance was placed on the fact
that the first respondent was granted techno-economic
clearance by order dated 22.03.1996.
98. It is further found with reference to the G.O.
dated 07.03.1994, which we have referred to that GoK
gave approval so that continuous power could be
supplied to the grid making it more stable. Reliance is
also placed on letter dated 01.03.1995 allegedly issued
by the appellant (whereas it is actually issued by the
KEB) confirming to the CEA, that the first respondent
was an IPP. It is next found that under the Wheeling
th
and Banking Agreement dated 26 January, 1996 sale of
firm capacity to the appellant was provided for. GoK
also confirmed to the CEA that the first respondent was
an IPP under Section 43A of the Supply Act. GoK order
nd
dated 2 March, 1996 providing for consent for sale of
power under Section 43A of the Supply Act is referred
150
to. The techno economic clearance granted by the CEA
nd
dated 22 March, 1996 is adverted to and it is further
found that such a clearance was unnecessary if the first
respondent was a CPP. The appellant is alleged to have,
th
by letter dated 29 March, 1996, supported the project
cost and forwarded the same for the approval of GoI.
The appellant is also alleged to have participated in
the discussion with the CEA for approval of the project
and started the transmission system as availed by all
IPPs. It was further found that the procedure for
payment of charges for supply of electricity was to be
a standard procedure followed in case of IPP projects.
Next, the High Court reasons that if the first
respondent was a CPP, it would have set up a 140 MW
plant to meet the requirements of JVSL and not 260 MW
plant. 260 MW plant was contemplated to provide firm
capacity to the appellant as evident from the order
th
dated 7 March, 1994. The detailed project report
provided that the requirement of steel plant was only
150 MW and rest 110 MW will be supplied to KEB to reduce
the power deficit in the State. If the first respondent
was a CPP, it could not have dedicated firm capacity to
151
the appellant and guaranteed continuous supply of
power. The Commission itself, having recognised the
fact that the status of IPP was granted, it could not
treat it as CPP for determining the tariff. The mere
use of common infrastructure for coal handling and
water supply could not render the first respondent a
CPP. The power plant was designed to fire either corex
gas or coal as fuel which confirmed that the first
respondent plant was not a captive plant and it was
intended to supply power to the appellant even with the
Steel plant not working and not producing corex gas.
The first respondent and JVSL were distinct corporate
entities having obtained financial assistance and
project approval on stand-alone basis. The fact that
the capacity of 240 MW was underwritten by JVSL was
also found not germane to conclude that the first
respondent was a CPP. The Commission, it was found,
erred in arriving at 1637 MUs at 77 per cent PLF and
fixed charges at 1150 MUs supplied to appellant
ignoring that the first respondent was supplying energy
to JVSL at 85 per cent PLF. Such direction was based on
the wrong conclusion that the first respondent was CPP.
152
The High Court concluded that the power plant of the
first respondent was having the status of IPP and not
CPP.
99. According to the appellant, the operation of first
respondent and JVSL was intertwined and interdependent.
It is contended by the appellant that they share common
infrastructure for coal handling, water supply and the
coal is purchased for the first respondent by its sister
company, JVSL, and JVSL raised invoices on the first
respondent. Therefore, the first respondent is to be
treated as a CPP as it is supplying power to JVSL.
Reliance is placed on the Wheeling, Banking and Grid
Support Agreement dated 23.01.1996. The priority of the
sales was to begin with sales being made to its
dedicated customers firstly. Secondly, power was to be
wheeled to third party exclusive customers, and only if
excess power is available, it was to be supplied to the
KEB on negotiated terms. The Government Order dated
12.05.1999 itself makes it clear that the first
respondent was selling surplus power to the appellant
and indicates that the same principle of negotiated
tariff for CPP would be applicable to the first
153
respondent. The agreement dated 14.10.1999 entered into
between KEB and the first respondent for supply of power
from KEB to JVSL on barter basis makes it clear that
the entire net capacity is underwritten by JVSL and it
has permitted the first respondent to enter into a
Wheeling and Banking Agreement as well as PPA with KEB
for sale of excess power. It is further pointed out
that the Government of Karnataka has extended
concessions for payment of electricity taxes by
treating it as a captive unit by Government Order dated
21.12.2000. The power proposed to be supplied by the
first respondent to the appellant was surplus power and
the grant of status of IPP by GoK would make no
difference. The appellant has a case that the grant of
status of IPP was also based on the difference in the
shareholding of the companies but that cannot overlook
the other aspects about the transactions from which it
could be concluded that the first respondent was a CPP,
it is contended.
100. The first respondent would support the findings of
the High Court. Reliance is undoubtedly placed on the
Government of India policies stressing the distinction
154
between the IPP and CPP. Having obtained consent under
Sections 29 to 31 of the Supply Act, 1948, it is
contended that it is an IPP. Prior to the Electricity
Act, 2003, there was no definition of a CPP nor were
their requirements set out. Such requirements evolved
only with the Electricity Rules of 2005. The first
respondent has been recognised by the KEB and the GoK
as an IPP. Reliance is placed on GoK order dated
07.03.1994, KEB letter dated 01.03.1995 confirmation by
GoK of the IPP status, GoK Order dated 02.03.1996, CEA
letter dated 22.03.1996, granting techno-economic
clearance, and GoK letter dated 22.03.1996, supporting
project cost. G.O. dated 02.03.1996, according the
exemption to the first respondent from electricity tax
only on the power supplied to JVSL, its sister concern.
The alleged CPP status was only qua power sold to the
sister concern to benefit it and not the first
respondent and it is not as projected. The
establishment of the plant of 260 MW can be explained
not with it being CPP, in which latter case, it would
have sufficed to set up a plant of 140 MW. The letter
dated 01.03.1995 sent by KEB confirmed that the first
155
respondent was an IPP. An affidavit of the appellant
dated 18.10.2001 admitted that the first respondent was
an IPP. The DPR contemplated the need to supply power
to the grid and the appellant and GoK approved the
project cost as an IPP and it was forwarded to the CEA
for approval.
101. The guaranteed minimum supply of threshold power
is compatible with the first respondent being an IPP.
Penalties for failure to sell the firm capacity or
rather for short supplies is relied upon. Payment of
charges for supply of electricity was based on
procedure in IPP projects. The tariff order of the
commission for the years 2000, 2002 and 2003 shows that
the first respondent was an IPP. Sharing of common
infrastructure did not necessarily imply that the power
plant of the first respondent was a CPP. There were
other projects taking advantage of such infrastructure.
It was intended only to optimise the project cost.
FINDINGS
102. It is not in dispute that it is with the Electricity
Rules of 2005 that the requirements of a captive
generating plant were laid down. It is the admitted
156
position that at the relevant time there was no
definition of a CPP in existence. The requirements of
a captive generating plant was, according to the first
respondent, not available.
103. It would appear that the private power policy of
the GoI was announced in the year 1991. GoI letter dated
09.10.1995 would show that there were a number of
proposals through IPP route. It was found however that
it would have a long gestation period. Captive power
plants provided an alternative. GoI decided that
captive power plants of industries could be allowed to
sell the surplus power, if any, to the grid on a
remunerative tariff as per mutually agreed terms. This
would add to the generating capacity in the country.
There is mention of co-generation as also small power
production. It was therefore suggested to all Chief
Secretaries of the states that they may create an
institutional mechanism which may allow captive power
units an easy automatic entry into power sector by
quickly clearing such applications by the state
governments by giving them rational tariff for purchase
of surplus power by the grid and the third-party access
157
for direct sale of power to other industrial units. We
may notice that this communication is after GoK order
dated 07.03.1994 by which the first respondent was
permitted to be set up. Moreover, what is contemplated
under captive power plant was that it could sell surplus
power, if any, to the grid as per mutually agreed terms.
Therefore, in the case of the captive power plant,
primarily, the industries could satisfy their power
requirements from the captive units.
104. On 01.03.1995 the KEB responding to the request
from the Director of the CEA to clarify whether the
generating plant set up by the first respondent was
captive plant under Section 44 of the Supply Act, 1948
or a generating plant, stated that it was an independent
generating plant. The copy of the approval granted by
the GoK for setting up the generating plant was
enclosed. This would take us to G.O. dated 07.03.1994
which we have already adverted to. What is stated
therein is that the first respondent’s sister company
namely Jindal Iron and Steel Company was setting up a
combined gas cycle plant of 300 MW x 150 MW within the
site allotted for a steel plant for which GoK had
158
already given approval. There is reference to the
financial aspects. Thereafter, it is recited that the
advantage of setting up the power plant at Bellary-
Hospet was that the excess power generated will be fed
to the KEB grid and can sell to other industrial units
in the area, besides generation of additional
employment. The KEB was found seeking a detailed
project report indicating the cost of the project inter
alia. It is thereafter that the first respondent was
permitted to set up the plant in two phases of 300 MW
of 150 MW each. This was subject to approval of the GoI
in respect of the foreign investment. It was also
subject to obtaining statutory clearances under the
relevant Acts. The first respondent was permitted to
sell power directly to industrial units in the area at
mutually negotiated rates again subject to approval of
the state government. The first respondent had to sell
the balance power to KEB at tariff to be determined as
per norms dated 31.03.1992. We may get the prima facie
impression that the said terms would appear to be in
tune with the concept of a captive unit, as contemplated
in GoI letter dated 09.10.1995.
159
105. It would appear it is not in dispute that the
capacity has been reduced from 300 MW to 260 MW. The
circumstances in which it stood reduced is not borne
out by any order produced before us. The next
development in chronological order, we notice, is the
Wheeling and Banking Agreement dated 23.01.1996. The
agreement is entered into between the first respondent
and the KEB. The agreement refers to the company or the
first respondent as a generating company and that it
proposed to set up a 2x120MW dual fire which is to be
understood with reference to the statement that it is
fired, namely, with corex gas with coal firing to
supplement it. Next it is stated that the first
respondent intended to sell the ‘majority’ of the power
to dedicated or third-party exclusive customers as
defined. Dedicated customers has been defined in the
agreement as those consumers of power supplied solely
by the first respondent through transmission lines set
up by it and it was to include the sister concern, JVSL.
Third party exclusive customer was defined to mean the
consumer who had contracted for its entire demand and
energy requirements from the first respondent. However,
160
the power was to be supplied through the KEB’s
transmission system. It is as we have already noted
provided in Clause 2.4 that ‘if at any stage’ the first
respondent offered ‘excess’ firm capacity for sale to
the board (KEB), then, the Board ‘may purchase’ the
same from the first respondent. Such purchase was to be
based on agreement on price and other terms to be
negotiated at the time of such sale. Therefore, it would
appear that what was contemplated was the sale of the
majority or most of the power generated to its dedicated
customers which included the JVSL and to other third
party exclusive customers. Clause 2.4 appears to
provide that if at any stage it was found that there
was excess power which could be firmly offered to KEB,
KEB may purchase such power. The order dated 30.01.1996
is not seen produced. It is one of the letters of the
GoI which has been referred to by the High Court and
the first respondent.
106. On 02.03.1996 GoK after referring to the G.O. dated
07.03.1994 and the request by the first respondent for
support in various matters offered certain concessions.
GoK gave its consent under Section 43A(1)(c) and
161
paragraph-3.2 of the GoI Tariff Notification dated
13.03.1992 as amended for sale of power by the first
respondent directly to any customer at rates to be
mutually negotiated by the first respondent. It is also
provided that the consent was also to be deemed as
previous sanction under Section 28 of the Indian
Electricity Act, 1910. Still further exemption was
granted under Section 3 of the Karnataka Tax on
Consumption of Electricity Act, 1959 on the consumption
of electricity generated by it for five years from the
date on which the power plant of the first respondent
went into commercial operation. Likewise, the consumer
was exempted. Certain other concessions were promised.
107. Section 43A(1)(c) of the Supply Act, 1948 provided
inter alia that a generating company could enter into
a contract for sale of electricity generated by it with
any other person with the consent of the competent
government or governments. The Order, thus, must be
viewed in the said perspective. This is apart from it
operating as consent for sale within the meaning of
Section 28 of the Electricity Act, 1910.
162
108. On 22.03.1996, we may notice that the ‘scheme’ for
establishment of a 2x130 MW corex/ coal based thermal
power station was accorded techno economic clearance by
the CEA subject to certain conditions which are
indicated therein.
109. Next in chronological order is the communication
dated 06.11.1996 issued by the GoI. The heading in fact
of the said communication is promotion of co-generation
power plants. In the said communication after noticing
the energy shortage and referring to letter dated
09.10.1995 it was indicated that by the subsequent
th
communication dated 30 January, 1996 (a communication
which we are not provided with) regarding clearance
process of captive power that the captive power plants
of any other persons including the juristic persons and
excepting generating companies was not subject to
Section 29(2) of the Supply Act. It is further indicated
that the Electricity Board [KEB] was to send to the
Authority under Section 44(2)(A) if the capacity of a
new generation station, inter alia , exceeded
25 MW. Thus, in terms of Section 44 of the Act captive
power/ co-generation plants required the approval of
163
the board only. The Board were to refer the proposal
for consultation with the CEA where the capacity
exceeded 25 MW under Section 44 (2A). Thereafter, the
order went on to deal with co-generational units which
were understood as units which simultaneously produce
two or more forms of energy.
110. The last communication is dated 09.01.1997.
th
Therein, reference is made to the order dated 30
January, 1996 and that it was therein clarified that
proposals for setting up captive power plants under
Section 44 would not come under the purview of Sections
29 to 31 of the Supply Act, 1948, which related to the
CEA’s detailed scrutiny and techno economic clearance.
It was added that the intention was that in view of the
large demand supply gap existing industries should be
encouraged to set up their own captive power plants to
add quick captive capacity in the electricity supply
th
industry. The letter dated 9 January, 1997, further
noticed that there were suggestions from some States
that some of the industries found it difficult to set
up power plants through the existing companies and they
favoured setting up of power plants by an independent
164
entity (IPP) with total dedication of power generated
to the existing industry/group of industries but
without any sale of power to the State Grid. In the
letter dated 01.01.1997, it is further observed
pertinently that however these would be generating
companies by definition and reference is made to GoI
instructions dated 18.01.1995, which required that
selection of IPP be through competitive bidding by the
government or electricity board. The industries
preferred to have the choice of negotiations with
parties on a bilateral basis instead of the IPP being
selected through competitive bidding. GoI decided to
facilitate setting up of ‘generating stations’ by ‘IPP’
exclusively for ‘the captive use’ of an industry or a
group of industries without involving any sale to the
State Grid. The selection of such IPP through
competitive bidding was no longer required. Thus,
th
letter dated 9 January, 1997, appears to indicate that
IPP generating stations could be set up exclusively for
the ‘captive use’ of the industry or a group of
industries without any sale to the State Grid.
Secondly, such IPPs could be selected without
165
competitive bidding. We do not have the letter dated
th
18.01.1995, which is referred to in letter dated 9
January, 1997. We do not also have the order dated
21.12.2000 which appears to have been relied upon by
the Commission and which is relied upon by the appellant
before us, as per which the first respondent availed
concessions from payment of electricity taxes holding
out to be a CPP. We further notice that the High Court
in the impugned judgment does not appear to have dealt
with order dated 21.12.2000. There is a case for the
appellant that when IPP desires to contract for power
with the appellant on two-part tariff basis, KEB/ the
appellant must be involved in every stage of project
formation, finalisation of capital costs. According to
appellant, KEB/ KPTCL would be involved during the
discussions stage to accord techno economic clearance
as well as for whole supply agreement to ensure the
least cost and these formalities have not been complied
with. In this case the High court has referred to the
th
appellant (KEB) vide its letter dated 29 March, 1996,
supporting the project cost and forwarding the same for
approval to the GoI. It is also further stated that the
166
appellant participated in discussion with the CEA for
approval of the project and supported the transmission
th
system. We are unable to locate the letter dated 29
March, 1996. No doubt, the appellant must be understood
as its predecessor the KEB. But there is no
th
communication dated 29 March, 1996 indicating that the
KEB supported the project cost. It would appear that a
copy of such a letter (29.03.1996) was annexed as
Annexure 14A before the High Court. Further, in the
appeal memorandum, in paragraph 9 thereof, it would
appear that what was contended by the first respondent
was that the appellant and GoK approved the project
cost and DPR and letter dated 29.03.1996 was produced.
Appellant is stated to have participated in the
discussion before the CEA and the second respondent
(GoK) actively supported the project by granting
approval and various benefits. The High Court has apart
from finding that the appellant participated also
stated that appellant supported the transmission system
as availed by all IPPs. Prima facie , we would think
also that what was contemplated in the Wheeling and
Banking Agreement dated 23.01.1996 was that, if there
167
was any excess which meant after fulfilling its
obligations to the dedicated and third-party customers,
it would be offered to KEB.
111. The appellant has a case that what in ‘substance’
was agreed to be sold to the appellant was only surplus
available power. The status of IPP being established
also would not by itself be relevant in the
determination of the cost, it is contended. We would
think that the interest of justice require that taking
note of also the fact that first respondent had
allegedly specifically claiming to be a CPP availed
benefits and this has also not been considered by the
High Court, the matter must be reconsidered by the High
Court. The findings therefore, that the first
respondent was CPP will stand set aside and High Court
will undertake a consideration of the matter based on
a study of the documents and also taking note of the
proceedings by which, the first respondent allegedly
claimed as CPP and availed benefits. The High Court
will also consider the argument of the appellant that
even treating the first respondent as IPP, in the
context of the contention of the appellant that the
168
sale contemplated to the appellant was only of ‘surplus
power’, only after the demand of the first two
categories were fulfilled on the aspect of fixation of
tariff.
112. The upshot of the above discussion is that the
appellant is entitled to succeed in the manner we shall
hereinafter immediately indicate. The appeal is partly
allowed. The finding that there was a concluded
contract within the meaning of the proviso to Section
27(2) of the Act will stand set aside. The findings
which have been rendered under point no. 4 about
perversity, arbitrariness in the findings of the
Commission are set aside. The finding relating to the
first respondent being an IPP is also set aside. The
matter will now stand remitted back to the High Court.
It will proceed on the basis that there was no concluded
contract within the meaning of the proviso to Section
27(2) of the Act. It will proceed, however, to deal
with the appeal under Section 41 of the Act in regard
to point no.3 and 4, namely, whether the findings of
the Commission are such that they are required to be
interfered under the jurisdiction available under
169
Section 41 of the Act including the question whether
the first respondent is a CPP or an IPP.
113. We must also deal with the request made by the
learned Counsel for the appellant that as Rs.100 crores
has been received by the first respondent on the
strength of a bank guarantee based on the impugned
judgment, under the interim Order passed by this Court,
if the appeal is allowed, the first respondent is duty
bound to pay the aforesaid amount to the appellant.
This was countered by the first respondent by pointing
out in the ‘unlikely event’ of the appeal being allowed
only on the point that there was no concluded contract
and if the other two aspects are to be reconsidered by
the High Court, then the first respondent cannot till
these matters are reconsidered be directed to repay the
amount. It is also the contention of the first
respondent that there will be undue enrichment as the
appellant would have shifted the burden to the end
customer.
114. This line of argument is sought to be met by the
learned counsel for the appellant by pointing out that
the appellant is a public authority, and more
170
importantly, the appellant being erroneously compelled
to pay under the orders of the court, has witnessed a
deprivation of valuable funds from the appellant, which
would otherwise have been available to it. Furthermore,
what is more important is, if the appellant succeeds in
regard to the point canvassed, namely, that there was
no concluded contract within the meaning of proviso to
Section 27 of the Act and if the amount is ordered to
be given to the appellant, then, it would have a bearing
on the interest of the consumers. This is for the reason
that in working out the rate to be charged from
consumers, even now this amount if it is brought into
the coffers of the appellant, it would result in a
corresponding reduction in the burden which the
consumer would have to bear.
115. We have considered this aspect of the matter. We
are remitting the matter back after finding that the
High Court was clearly in error in finding that there
was a concluded contract. We have also interfered with
the other findings. However, at the same time we may
not overlook the fact that we are not allowing the
appeal entirely. The validity and correctness of the
171
order of the Commission must be decided with reference
to the boundaries of the jurisdiction of High Court
under Section 41 in regard to the matter. We would at
the same time find that the appellant has succeeded in
a substantial manner. We would think that the equities
must be balanced.
116. We would think that the interest of justice would
be met if the first respondent be directed to pay a sum
of Rs.50 crores from out of Rs.100 crores which has
been paid. The payment of the amount is to be made
within a period of 8 weeks from today.
117. Disbursement of further amounts as also the fate
of the payment of Rs.50 crores by the first respondent
will await the final decision of the High Court in
regard to the determination for which we remit the
matter.
118. The appeal filed by Karnataka Power Transmission
Corporation Limited is partly allowed and the impugned
Judgment shall stand set aside. We find that there was
no contract concluded within the meaning of Section
27(2) of the Act. We remand the case back to the High
Court for reconsidering the points ‘3’ and ‘4’
172
formulated by the High Court. The first respondent
shall pay to the appellant a sum of Rs.50 crores (fifty
crores) within eight weeks. As regards further
liability to pay, it will await and depend upon the
decision of the High Court. So also, the payment of
Rs.50 crores (fifty crores) by the first respondent,
under this Judgment, will be subject to the
determination to be made by the High Court.
119. The appeal filed by Karnataka Electricity
Regulatory Commission will stand allowed to the extent
that the remarks made against it in the impugned
judgment shall stand set aside as indicated
hereinbefore. Parties will bear their respective costs.
………………………………………………………J.
[K.M. JOSEPH]
………………………………………………………J.
[ANIRUDDHA BOSE]
………………………………………………………J.
[HRISHIKESH ROY]
NEW DELHI;
DATED; NOVEMBER 22, 2022.
173