Full Judgment Text
Neutral Citation Number-2023/DHC/000888
$~4
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Decision: 07.02.2023
+ ARB.P. 26/2023
M/S KBG ENGINEERS ..... Petitioner
Through: Mr. Avinash Trivedi, Advocate.
versus
DELHI STATE INDUSTRIAL AND INFRASTRUCTURE
DEVELOPMENT CORPORATION LTD ..... Respondents
Through: Mr. Sonal Anand and Ms.
Surbhi Singh, Advocates.
CORAM:
HON’BLE MR. JUSTICE PRATEEK JALAN
PRATEEK JALAN, J. (ORAL)
%
1. The petitioner has approached this Court under Section 11 of
the Arbitration and Conciliation Act, 1996 [“the Act”], for
appointment of an arbitrator to adjudicate disputes between the parties
under a contract for construction of roads and SW drains at Qutub
Vihar, Phase-1, Najafgarh, Matiala. The contract was awarded to it by
the respondent-Delhi State Industrial and Infrastructure Development
Corporation Limited [“DSIIDC”] vide letter of acceptance dated
14.02.2012, pursuant to a tender issued by the respondent.
2. Notice of this petition was issued on 11.01.2023, and the
respondent was granted time to file a reply. Although DSIIDC’s reply
Signature Not Verified
Digitally Signed
By:SHITU NAGPAL
Signing Date:09.02.2023
11:53:20
ARB.P.26/2023 Page 1 of 8
Neutral Citation Number-2023/DHC/000888
has not come on record, a copy has been handed up in Court and is
taken on record.
3. The contract incorporates Clause 25 of the General Conditions
of Contract [“GCC”], which provides for settlement of disputes and
arbitration. The relevant parts of the said clause are reproduced
below:-
“ Settlement of Disputes & Arbitration
Except where otherwise provided in the Contract all questions and
disputes relating to the meaning of the specifications, design,
drawings and instructions herein before mentioned and as to the
quality of workmanship or materials used on the work or as to any
other question, claim, right, matter or thing whatsoever in any way
arising out of or relating to the Contract, designs, drawings,
specifications, estimates, instructions, orders or these conditions or
otherwise concerning the works or the execution or failure to
execute the same whether arising during the progress of the work or
after the cancellation, termination, completion or abandonment
thereof shall be dealt with as mentioned hereinafter:
3) If the Contractor considers any work demanded of him to be
outside the requirements of the Contract, or disputes and drawings,
record or decision given in writing by the Engineer on any matter in
connection with or arising out of the Contract or carrying out of the
work, to be unacceptable, he shall promptly within 15 days request
the superintending engineer shall give his written instructions or
decision within a period of one month from the receipt of the
Contractor’s letter.
If the superintending engineer fails to give his instructions or
decision in writing within the aforesaid period or if the Contractor is
dissatisfied with the instructions or decision of the superintending
engineer, the Contractor may, within 15 days of the receipt of the
superintending engineer decision, appeal to the chief engineer who
shall afford an opportunity to the Contractor to be heard, if the latter
so desires, and to offer evidence in support of his appeal. The Chief
Engineer shall give his decision within 30 days of receipt of
contractor’s appeal. If the Contractor is dissatisfied with this
decision of the Chief Engineer, the contractor may within 30 days
from the receipt of the Chief Engineer decision, appeal before the
Signature Not Verified
Digitally Signed
By:SHITU NAGPAL
Signing Date:09.02.2023
11:53:20
ARB.P.26/2023 Page 2 of 8
Neutral Citation Number-2023/DHC/000888
Dispute Redressal Committee (DRC) along with a list of disputes
with amounts claimed in respect of each such dispute and giving
reference to the rejection of his disputes by the Chief Engineer.
The Dispute Redressal Committee (DRC) shall give his decision
within a period of 90 days from the receipt of Contractor’s appeal.
The constitution of Dispute Redressal Committee (DRC) shall be
as indicated in Schedule ‘F \ If the Dispute Redressal Committee
(DRC) fails to give his decision within the aforesaid period or any
party is dissatisfied with the decision of Dispute Redressal
Committee (DRC), then either party may within a period of 30 days
from the receipt of the decision of Dispute Redressal Committee
(DRC), give notice to the Chief Engineer for appointment of
arbitrator on prescribed proforma as per appendix XV, failing which
the said decision shall be final binding and conclusive and not
referable to adjudication by the arbitrator.
It is the term of contract that each party invoking arbitration must
exhaust the aforesaid mechanism of settlement of claims/disputes
prior to invoking arbitration.
4) Except where the decision has become final, binding and
conclusive in terms of Sub Para (1) above, disputes or difference
shall be referred for adjudication through arbitrator by a sole
arbitrator appointed by the chief engineer, CPWD, in charge of the
work there be no chief engineer, the additional director general, the
director general of the concerned regional work CPWD or if there
be no additional director general, the director of general of work,
CPWD, if the arbitrator so appointed is unable or unwilling to act or
resigns his appointment vacates his office due to any reason
whatsoever, another sole arbitrator shall be appoint in the manner
aforesaid. Such person shall be entitled to proceed with the
reference from the stage at which it was left by his predecessor.
It is a term of this Contract that the party invoking arbitration shall
give a list of disputes with amount claimed in respect of each such
dispute along with the notice for appointment of arbitrator and
giving reference to the rejection by the chief engineer of the appeal.
It is also a term of this Contract that no person other than a person
appointed by such Accepting Authority as aforesaid should act as
arbitrator and if for any reason that is not possible, the matter shall
not be referred to arbitration at all.
It is also a term of this Contract that if the Contractor does not make
any demand for appointment of arbitrator in respect of any claims in
writing as aforesaid within 120 days of receiving the intimation from
Signature Not Verified
Digitally Signed
By:SHITU NAGPAL
Signing Date:09.02.2023
11:53:20
ARB.P.26/2023 Page 3 of 8
Neutral Citation Number-2023/DHC/000888
the Engineer-in-Charge that the final bill is ready for payment, the
claim of the Contractor shall be deemed to have been waived and
absolutely barred and the Employer shall be discharged and
released of all liabilities under the Contract in respect of these
1
claims….”
4. The petitioner claims that the payments due to it under the
contract were not paid by the respondent. There was considerable
correspondence between the parties with regard to the petitioner’s
claims, including the following:-
a. The petitioner addressed a letter dated 01.01.2020 to the
respondent, requesting it to “act in terms of clause 25 of an
2
agreement” and to release the payments claimed by it.
b. By a further letter dated 07.06.2020, the petitioner asserted that
it had invoked the arbitration clause and requested the
respondent to appoint an arbitrator in terms of the arbitration
agreement within 30 days.
c. The petitioner sent a letter dated 07.08.2020 stating that it had
invoked the arbitration clause and also approached the office of
the Chief Engineer. It reiterated its request to the respondent to
appoint an arbitrator.
d. The respondent, vide letter dated 26.02.2021, notified that the
petitioner had not submitted the final bill and the account of
work had not been finally closed. The petitioner was, therefore,
directed to submit the final bill within 15 days.
1
Emphasis in original.
2
Document-7 of petitioner’s list of documents.
Signature Not Verified
Digitally Signed
By:SHITU NAGPAL
Signing Date:09.02.2023
11:53:20
ARB.P.26/2023 Page 4 of 8
Neutral Citation Number-2023/DHC/000888
e. Although the petitioner disputed the respondent’s assertion, it
addressed a letter dated 10.08.2021 to the respondent, noting
that it had approached the Superintending Engineer and the
Chief Engineer for resolution of disputes, but to no avail. In this
communication, the petitioner suggested dispensing with the
Dispute Redressal Committee [“DRC”] and proposed names of
five persons for appointment as the arbitrators. It also enclosed
the required pro forma for this purpose.
f. The petitioner addressed a further communication dated
25.10.2021 to the respondent, making a grievance that its letter
dated 10.08.2021 had not elicited a response. It was further
requested that the appointment of an arbitrator may be accepted.
However, the petitioner also conceded that “in case department
think DRC can resolve our disputes then the same may be
3
constituted under clause-25 at the earliest”.
g. Alongwith the reply, DSIIDC has relied upon a communication
dated 17.03.2022, by which the respondent replied to the
aforesaid letter dated 25.10.2021. In the said letter, several
short-comings on part of the petitioner have been alleged, but
there is no suggestion that the DRC is being constituted.
h. Several further letters have also been placed on record by
learned counsel for the parties, including the petitioner’s
reminders for appointment of an arbitrator and the respondent’s
3
Document-13 of petitioner’s list of documents.
Signature Not Verified
Digitally Signed
By:SHITU NAGPAL
Signing Date:09.02.2023
11:53:20
ARB.P.26/2023 Page 5 of 8
Neutral Citation Number-2023/DHC/000888
communications with regard to the petitioner’s claims and
required documentation.
5. I have heard Mr. Avinash Trivedi, learned counsel for the
petitioner, and Mr. Sonal Anand, learned counsel for respondent.
6. Mr. Anand principally raises two objections to the appointment
of an arbitrator. His first submission is that the claims sought to be
raised by the petitioner are barred by limitation. The second ground is
that the petitioner has not exhausted the procedure of Clause 25 of the
GCC. Mr. Anand submits that respondent is even now ready to
constitute a DRC.
7. As far as the issue of limitation is concerned, I am of the view
that in the facts and circumstances, it is appropriate to leave the issue
for consideration by the arbitrator. Although the judgments of the
Supreme Court inter alia in BSNL and Anr. vs. Nortel Networks India
4
Pvt. Ltd. , make it clear that the Court may decline a reference to
arbitration in case the claims are ex facie time barred, such a course is
to be adopted only in a very limited category of cases “where there is
5
not even vestige of doubt that the claim is ex facie time barred”.
8. Mr. Anand submits that in the present case, the petitioner’s
cause of action, even according to the averments made in the petition
itself, arose in the year 2015 whereas the arbitration clause was first
invoked on 01.01.2020. Mr. Trivedi, on the other hand, points out that
there are several acknowledgements and part-payments by the
4
(2021) 5 SCC 738.
5
Paragraph 47.
Signature Not Verified
Digitally Signed
By:SHITU NAGPAL
Signing Date:09.02.2023
11:53:20
ARB.P.26/2023 Page 6 of 8
Neutral Citation Number-2023/DHC/000888
respondent, which according to him, serve to give rise to fresh periods
of limitation under Sections 18 and 19 of the Limitation Act, 1963.
9. Having regard to the clear mandate of the Supreme Court that,
in proceedings under Section 11 of the Act, the Court is to be guided
6
by the principle, “when in doubt, do refer”, I am of the view that
proper course in the present case is to reserve the question of
limitation for a decision by the arbitrator.
10. As far as the second ground, with regard to compliance with the
procedure for DRC under Clause 25 is concerned, suffice it to say that
the petitioner expressly sought reference to the DRC in its
communication dated 25.10.2021, which was not addressed at all in
the respondent’s reply dated 17.03.2022. Clause 25 itself provides a
period of 90 days from the receipt of the contractor’s appeal for the
DRC to make its decision, failing which any party is entitled to
approach the arbitrator. While this position has already been triggered
in the present case, Mr. Trivedi submits that the petitioner is agreeable
to an attempt at resolution of disputes by the DRC within a period of
90 days from today, failing which the disputes may be resolved
through arbitration.
11. Having regard to the aforesaid, the petition is disposed of with
the following directions:-
a. The respondent will constitute a DRC and inform the petitioner
as well as Mr. Trivedi of the constitution of the DRC so that the
6
Vidya Drolia v. Durga Trading Corpn., (2021) 2 SCC 1, paragraph 238.
Signature Not Verified
Digitally Signed
By:SHITU NAGPAL
Signing Date:09.02.2023
11:53:20
ARB.P.26/2023 Page 7 of 8
Neutral Citation Number-2023/DHC/000888
petitioner may submit its representation within one week
thereafter.
b. The DRC will dispose of the matter within a period of 90 days
from today. In the event the DRC does not give a decision
within 90 days, or either party is dissatisfied with the decision
of the DRC, disputes under the contract will be referred to the
arbitration of Ms. Padma Priya, Advocate [Tel:- 9910531145].
c. Either party may approach the learned arbitrator after 90 days
from today, with a request to enter into the reference forthwith.
d. The learned arbitrator is requested to furnish a declaration under
Section 12 of the Act, prior to entering upon the reference.
e. The renumeration of the learned arbitrator will be computed in
accordance with the Fourth Schedule to the Act.
12. It is made clear that all rights and contentions of the parties,
including on limitation, are left open for adjudication before the
learned arbitrator.
13. The petition is disposed of in terms of the aforesaid directions.
PRATEEK JALAN, J
February 07, 2023/ ‘vp’/
Signature Not Verified
Digitally Signed
By:SHITU NAGPAL
Signing Date:09.02.2023
11:53:20
ARB.P.26/2023 Page 8 of 8