Full Judgment Text
Neutral Citation Number:2023/DHC/001644
IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment delivered on: March 06, 2023
+ ARB.P. 95/2022
NEWTON ENGINEERING AND CHEMICALS LIMITED
..... Petitioner
Through: Mr. Akash Nagar, Adv. with
Ms. Ruchi Bhargarh Nagar,
Mr. Samarpit Chauhan &
Ms. Akanksha Chauhan, Advs.
versus
UEM INDIA PRIVATE LIMITED ..... Respondent
Through: Mr. Kirti Uppal, Sr. Adv. with
Mr. Debopriyo Maulik & Ms. Riya
Gulati, Advs.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
J U D G M E N T
V. KAMESWAR RAO, J
1. The present petition has been filed under Section 11 of the
Arbitration and Conciliation Act, 1996 (‘Act of 1996’), seeking
indulgence of this Court to appoint an Arbitrator for adjudication of
disputes which have arisen between the parties herein. Specifically, the
instant petition has been filed with the following prayers:-
“In light of the facts and circumstances of the case, it is most
humbly prayed that this Hon’ble Court may be pleased to:
a. Allow the present Petition.
b. Appoint an Arbitral Tribunal in the form of Sole
Arbitrator, in accordance with Section 11 (4) and 11 (8) of
the Arbitration and Conciliation Act, 1996 for reference
and adjudication of the claims of the Petitioner as against
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 1 of 19
Neutral Citation Number:2023/DHC/001644
the Respondent; and
c. Pass any other orders this Hon’ble Court may deem fit.”
2. It is stated in the petition that the petitioner is a private limited
company registered under the provisions of the Companies Act, 1956
and possesses extensive experience in the field of Project Management,
Detailed Engineering, Manufacture and Erection of Equipment,
Process Vessel, Tankages, Piping, Electrical and Instrumentation and
other similar areas of work. It has its registered office at 864/B-4,
G.I.D.C., Makarpura, Baroda-390010, Gujarat.
3. Whereas the respondent is also a private limited company
which specializes in Turnkey services in the water and effluent
collection, treatment and disposal and has requisite Manpower,
construction equipments and capability in construction Management,
Procurement and Detailed Engineering. It is also known as ‘Toshiba
Water Solutions Private Limited’.
4. It is stated that the petitioner had entered a Memorandum of
Understanding (‘MoU’) dated June 19, 2014 with the respondent for
the execution of the work under Tender No. UA5KC13001 (‘Tender’)
granted by the Oil and Natural Gas Corporation (‘ONGC’) to the
petitioner specifically for Modernization of ETP Plant at ONGC Uran
Plant.
5. It is stated that as per Clause 3 of the MoU, both the parties
had to cooperate in the execution of the Project in a manner that the
respondent had to act like a technical collaborator and provide Design
and Engineering Services, Supply Supervisory and Management
Services, Supply of Critical Equipment for the Project and also to
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 2 of 19
Neutral Citation Number:2023/DHC/001644
make available to the petitioner its expertise and technical know-how
in the field of execution of Water and Effluent Treatment projects. It is
further stated that the bid of the petitioner was accepted by the ONGC
and as a result, the afore-said MoU had come into force.
6. It is further stated that under Clauses 6 and 7 of the MoU, the
respondent had the obligation to render the afore-mentioned services
@2% of the contract value, excluding the operation and maintenance
costs. The agreed payment had to be disbursed by the petitioner to the
respondent in the following manner:
a) 0.50% had to be paid immediately upon receipt of advance
payment from the ONGC;
b) Balance 1.50% had to paid by way of three equal quarterly
installments, whereas first quarter period had to start from
the date of signing the contract.
7. It is stated that the said MoU also contains an Arbitration
Clause stipulated as Clause 10, which renders any dispute arising out
the said MoU arbitrable by a panel of three arbitrators. Clause 10 of
the MoU has been reproduced in the following manner:
“ 10. Dispute Resolution
In case of dispute between the Parties, The Parties shall
make all effort to resolve the dispute amicably.
However, in case the Parties could not resolved the
dispute amicably, the same can be referred for
arbitration to an Arbitration Panel of 3 arbitrators as
per provisions of the Arbitration and Conciliation Act,
1986. The seat of the Arbitration shall be located at
Delhi. The language of the arbitration will be English.”
8. It is further stated that as a result of the MoU coming into
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 3 of 19
Neutral Citation Number:2023/DHC/001644
force, the petitioner and the ONGC entered into a Contract, dated
May 11, 2015, bearing no. MR/URAN/MM/LSTK/ETP/14/2013-
14/UA5KC13001 (‘Contract’).
9. Subsequently, on June 09, 2015, the petitioner and the
respondent executed a Letter of Intent vide Letter No.
NECL/UEM/LOI/TCA/15 (‘LOI’) which was executed in reference to
the MoU. The LOI was for the purpose of declaring the
commencement of the operation of the project under the Tender
no.UA5KC13001 and to specify the payment- value of the Project to
the respondent.
10. As per the LOI, it was finalized that the respondent will be
paid 2% of the contract value which was ₹82,32,46,625/-. Therefore,
2% of the above mentioned value i.e., ₹1,64,64,933/- had to be paid by
the petitioner.
11. Thereafter, for the purpose of execution of the Project, the
petitioner initiated discussions through several emails, phone calls and
meetings were also held in the office of the respondent including one
‘Management Review Meeting’ (‘MRM’), which was organized by the
ONGC at its plant in Uran on November 29, 2016. It is stated that the
respondent kept delaying the execution of the work as it failed to
submit the proper documents for the execution of the Project. It is the
case of the petitioner that though the respondent was not carrying out
the execution of the Project but it was regularly asking the petitioner
for the payment for the execution of the Project.
12. Thus, as a result of the delay on the part of the respondent to
execute the Project, the ONGC issued a Notice bearing No. MR/
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 4 of 19
Neutral Citation Number:2023/DHC/001644
URAN/ MM/ LSTK/ ETP/ 14/ 2013-14/ UA5KC13001, dated May 09,
2017, wherein the petitioner was directed to complete certain tasks
mentioned in that Notice within the period of 30 days in order to
demonstrate improvement in the execution of the Project and also to
prove its capability to execute the Project.
13. It is the case of the petitioner that despite making enough
efforts, the respondent failed to execute the work as per the Contract.
As a result, the ONGC terminated the Contract vide a Notice of
Intimation of Termination of Contract (‘Notice of Termination’) dated
June 15, 2017.
14. It is the case of the petitioner and so contended by Mr. Akash
Nagar, learned counsel, appearing on behalf of the petitioner that the
payment of ₹84,34,849/- has already been made to the respondent for
the execution of the Project qua the Contract, dated May 11, 2015. It
has been submitted that the respondent is liable to pay the said amount
as well as the losses incurred by the petitioner and for which
arbitration proceeding is sought to be initiated by the petitioner as per
Clause 10 of the MoU.
15. It has been submitted that the petitioner had sent a Notice for
Invocation of Arbitration dated July 04, 2019 (‘Invocation Notice’),
wherein it recommended a panel of three arbitrators to the respondent.
16. It is his case that the respondent had failed to reply to the
Invocation Notice and thus, the petitioner was constrained to file a
petition under Section 11 of the Act of 1996 on December 09, 2019
bearing ARB.P. 831/2019, before this Court.
17. It is stated that to the aforesaid petition, the respondent filed
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 5 of 19
Neutral Citation Number:2023/DHC/001644
the objections dated December 17, 2019 and challenged the
maintainability of the same. It is the case of Mr. Nagar that the
respondent in the objections filed to that petition had curtailed its
scope of obligations under the MoU as being limited to ‘technical
collaboration and bidding for the aforesaid work’. It is further his case
that the respondent had failed to notice Clause 3 of the MoU, which
clearly stipulates that the obligations of the respondent will have to
remain in force throughout the subsistence of the work under the
Contract. It is also his case that the respondent should be estopped
from advancing such an argument since the respondent itself carried
out communications with the petitioner in relation to the execution of
the work and that fact is evident from the emails exchanged between
both the parties.
18. It has also been pointed out by Mr. Nagar that when the matter
was taken up in Arb.P. 831/2019, it was noted by this Court that there
exist an agreement containing the arbitration clause governing the
disputes between the parties herein. However, the Court directed the
petitioner herein to issue a fresh Notice of Invocation to the respondent
since the Court observed that the same was not in accordance with
the provisions laid down under the MoU and thus the said petition was
accordingly disposed of.
19. It is the case of Mr. Nagar that in conformity with the direction
of this Court, the petitioner issued a fresh ‘Notice of Invocation’ dated
April 20, 2020, reiterating clearly and specifically the detailed facts
pertaining to the nature and object of the MoU, details of the Contract
with ONGC, scope of work expected from the respondent and details
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 6 of 19
Neutral Citation Number:2023/DHC/001644
of payments already made to the respondent by the petitioner, the
details of the disputes and finally the losses incurred by the petitioner.
Moreover, the petitioner again suggested a panel of Arbitrators therein.
20. Whereas the respondent in the reply, dated May 04, 2020, filed
to the said Notice of Invocation, denied the existence of any disputes
between the petitioner and the respondent and thus did not give its
consent to refer the disputes to arbitration.
21. Thereafter the petitioner responded to the reply sent by the
respondent by sending a reminder Notice for invocation of arbitration
dated May 15, 2020 and this time recommended the name of a single
arbitrator instead of three. However, the respondent failed to respond
to the same.
22. It has been submitted by Mr. Nagar that the petitioner has
incurred heavy losses owing to the willful negligence of the
respondent towards its obligations contemplated in the MoU.
23. He further submitted that in view of the legislative mandate
contained under Section 11(6A) of the Act of 1996, the Court is now
required to only examine the existence of arbitration agreement
between the parties. He further submitted that in the instant case there
is an explicit admission towards an existence of the arbitration
agreement between the petitioner and the respondent by the respondent
which can be seen from the order dated February 13, 2020, passed by
this Court in the Arb. P. 831/2019.
24. Thus, aggrieved by the actions of the respondent, the petitioner
is constrained to file the instant petition.
25. On the other hand in the reply filed by the respondent, it is its
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 7 of 19
Neutral Citation Number:2023/DHC/001644
primary case and so contended by Mr. Kirti Uppal, learned Senior
Counsel appearing on behalf of the respondent that the MoU was only
entered for the purposes of submitting bids towards the Tender floated
by the ONGC and this is clear from the fact that the MoU contains a
Clause which limits the liability of the respondent and also waives
consequential damages causes to it.
26. He submitted that after the award of Contract to the petitioner
by the ONGC, the petitioner time and again issued multiple letters of
intent (‘LOIs’) / work orders, seeking services of the respondent qua
the Project. However, such LOIs, were independently issued by the
respondent and therefore should be construed as independent
agreements or contracts, devoid of any arbitration clause.
27. It is his submission that since the disputes which the petitioner
has sought to refer for arbitration are emanating from these LOIs and
not from the MoU, the disputes cannot be referred to arbitration as
there is no arbitration clause governing the same.
28. He submitted that mere perusal of the Notice dated July 04,
2019 issued by the petitioner would indicate that though the dispute
was essentially the same, the narration qua the dispute has undergone a
sea change in the Notice dated April 20, 2020. He further submitted
that the petitioner is misstating the facts to mislead this Court and to
substantiate the same, he has tabulated a comparison between the
description of the dispute in Notice dated July 4, 2019 and April 20,
2020, in the following manner:
| Notice dated 04.07.2019 | Notice dated 20.04.2020 |
|---|---|
| As per the discussion held at | As per the discussion held at your |
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 8 of 19
Neutral Citation Number:2023/DHC/001644
| your office on 17th and 18th May,<br>2017 a payment of Rs. 36 Lakhs<br>was demanded for initiation of<br>the work and signing of MOU.<br>Based on the demand made, my<br>client made a payment of Rs. 9<br>Lakhs which was made vide<br>cheque dated 18th May, 2017<br>and Rs. 20 Lakhs was paid on<br>23rd May, 2017 through RTGS.<br>A Post Dated Cheque dated 23rd<br>June, 2017 was issued to you<br>noticee for Rs. 7 Lakh towards<br>the balance payment. These<br>payments were made with a<br>bonafide belief that you will<br>cooperate with my client in<br>submission of drawings and sign<br>the MOU as required by ONGC<br>whose contract was to be<br>executed.<br>However, since you denied to<br>sign the MOU and neither<br>submitted any drawings as<br>desired, my Client has been put<br>to great troubles. The Subject<br>contract was terminated vide<br>letter dated May 09, 2017 on the<br>specific ground that My Client<br>has failed to resolve the dispute<br>with technical Collborator M/s.<br>UEM India Private Limited. The<br>same was communicated to your<br>office by my Client and vide its<br>email dated 21/06/2017,<br>intimated you that they do not | office on 17th and 18th May, 2017<br>a payment of Rs. 36 Lakhs was<br>demanded for start of the work as<br>required by ONGC.<br>Based on the demand made, a<br>payment of Rs. 9 Lakhs was made<br>vide cheque dated 18 May, 2017<br>and Rs. 20 Lakhs was paid on<br>23rd May, 2017 through RTGS. A<br>Post Dated Cheque dated 23rd<br>June, 2017 was issued to you for<br>Rs. 7 Lakh towards the balance<br>payment. These payments were<br>made with a trust that you noticee<br>will cooperate with my client in<br>submission of drawings and other<br>requirements of ONGO whose<br>contract was to be executed.<br>However, since you notice failed<br>to act in lines of discussion held in<br>meeting dated June 06, 2015, my<br>Client has been put to great<br>troubles. A termination notice for<br>the subject contract was issued by<br>ONGC vide letter dated May 09,<br>2017 on the specific ground that<br>my Client has failed to resolve the<br>dispute with its technical<br>Collaborator M/s. UEM India<br>Private Limited, i.e you noticee.<br>The same was communicated to<br>your office by my Client and vide<br>its email dated 21/06/2017,<br>intimating you that my client do<br>not intend to make the balance<br>payment to you in view of |
|---|
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 9 of 19
Neutral Citation Number:2023/DHC/001644
| intend to make the balance<br>payment to you in view of such<br>termination of the contract and<br>hence requested you to restrain<br>your office from depositing the<br>said cheque number 000982<br>drawn on Bank of Baroda for Rs.<br>7 Lakh. | termination of the contract by<br>ONGC vide its letter dated<br>15/06/2017 and hence requested<br>you to restrain your office from<br>depositing the said cheque<br>number 000982 drawn on Bank of<br>Baroda for Rs. 7 Lakh. |
|---|
29. He further submitted that from the perusal of the above table it
is abundantly clear that the petitioner has cosmetically changed the
narration of the description of the dispute in order to make it plausible
that the dispute is covered under the MoU.
30. It is his submission that the perusal of the order dated February
13, 2020 passed by this Court in Arb.P. 831/2019 indicates that the
petitioner had admitted that the description of the dispute in the
Invocation Notice was not in terms of the MoU which contains the
arbitration Clause. Therefore, as there has been no substantial change
in the description of the dispute in the Notice of Invocation, the
present dispute is not covered by Clause 10 of the MoU.
31. It is his primary submission that the genesis of the present
dispute does not arise out of the MoU wherein the Dispute resolution
Clause exists. However, the same pertains to one ‘unsigned MoU’
which was never executed between the parties. Thus, there does not
exist any arbitration clause which covers the dispute that the petitioner
intends to resolve by way of appointment of an arbitrator.
32. He submitted that the true reason for filing the instant petition
and resorting to Clause 10 of the MoU is to avoid and procrastinate the
proceedings initiated under Section 138 of the Negotiable Instruments
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 10 of 19
Neutral Citation Number:2023/DHC/001644
Act, 1881, by the respondent against the petitioner.
33. Whereas, in rejoinder submissions, Mr. Nagar had stated that
the scope of the MoU was never limited to mere respondent providing
technical collaboration and bidding for the work. It has been submitted
that the respondent has wrongfully narrowed down its obligations
under the MoU and is misleading this Court.
34. He reiterated and emphasized on the fact that under Clause 3
of the MoU, the respondent was to specifically participate in the
Project under the said Tender as a technical collaborator and provide
the following services: ‘Design and Engineering Services, Project
Supervisory and Management Services, Supply of Critical Equipment
for the Project and also to make available to the petitioner its expertise
and technical know-how in the field of execution of Water and
Effluent Treatment Projects’. He further submitted that the role of the
respondent under the MoU was not merely limited to submission of
bids by the petitioner but it was well beyond the same i.e., until the
completion of the work under the Contract awarded by the ONGC.
35. He submitted that the respondent should be estopped from
holding such a ground, as it has accepted several payments in
pursuance of the Project under the Tender and has also attended
several meetings which were not only confined to the bidding process.
36. It is his submission that the LOIs sent by the petitioner to the
respondent were never meant to be independent agreements/contracts.
He submitted that each of the LOIs was well knit and interlinked with
each other and also with the governing MoU. Moreover, the works
envisaged under each LOIs, forms an important part of the Scope of
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 11 of 19
Neutral Citation Number:2023/DHC/001644
work envisaged under the MoU. It has been submitted that the absence
of a dispute resolution Clause in the LOIs is irrelevant as each of such
LOIs was governed by the MoU and the LOI dated June 09, 2015
clearly contains a reference towards the MoU.
37. He submitted that there has not been a change in the facts of
Notice of Invocation dated April 20, 2020, with that of the Invocation
Notice, dated July 04, 2019. It has been submitted that the only change
in the facts of the said Notices is the correction of the typographical
error of the word ‘MoU’ which was supposed to be typed as ‘MOM’
i.e., the Minutes of Meeting, dated June 06, 2015. It is his case that no
such ‘MoU’ as stated under the facts narrated in Invocation Notice
dated July 04, 2019 exists and it was rather the ‘MoM’, of the meeting
held on June 06, 2015, between the representatives of the petitioner
and the respondent. He submitted that even now, the fact remains that
the ‘MoU’ covers each and every aspect of the present dispute under
its Clause 10 as the Governing document. Moreover, it his submission
that there does not exist any unsigned MoU as submitted by the
respondent and the existence of the same has not been proved by the
respondent by producing any iota of evidence.
38. Mr. Nagar has further submitted that in light of the termination
Notice dated May 09, 2017 sent by the ONGC to the petitioner, the
representatives of the petitioner and the respondent held multiple
meetings and one of such meeting was held on May 17, 2017 and
discussions of that meeting was summarized in the form of a MoM
dated May 30, 2017.
39. He submitted that under the said MoM, the obligations of both
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 12 of 19
Neutral Citation Number:2023/DHC/001644
the petitioner and the respondent were summarized, as discussed and
finalized in the meetings dated May 17, 2017 & May 18, 2017 and the
said obligations were pertaining to the aspects of Engineering,
Procurement, Payments to the respondent and the Success Fees.
40. It is his case that the aforesaid MoM was supposed to be
executed between the parties in accordance with Clauses 15.8 and 17
of the notice of the termination dated May 09, 2017, wherein ONGC
had required the petitioner and the respondent to resolve all the
technical and commercial issues between them.
41. He further submitted that the said MoM was drafted mutually
by the representatives of the petitioner as well as the respondent.
Moreover, time and again respondent was requested by the petitioner
to sign the said MoM, so that the same may be communicated to the
ONGC to avoid the termination of the Contract. However, it is his case
that the respondent never signed the said MoM and as a result, the
ONGC terminated the Contract.
42. He submitted that the petitioner has been using the word MoU
since the very inception. However, the same refers to the MoM, dated
May 30, 2017. It his submission that this fact is clear from the e-mail
dated May 31, 2017 sent by Mr. Amit Datarkar, representative of the
petitioner wherein he had specifically referred to the contents of that
MoM while stating that the respondent is expected to ‘ do detailed
engineering ’ and that the ‘ order for TTPRO is ready’ . It is his case that
the same typographical error in referring to that MoM crept in the
earlier Invocation Notice of July 04, 2019 under the heading dispute
description. He submitted that what was sought to be written and ought
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 13 of 19
Neutral Citation Number:2023/DHC/001644
to be written in the said Invocation Notice was that “Rs.36 lakhs were
demanded for initiation of the work and signing of MoM ” instead of
“ Rs.36 lakhs were demanded for initiation of the work and signing of
MoU ” .
43. So, on the basis of afore-said submissions, he seeks indulgence
of this Court to appoint an arbitrator for adjudication of the disputes
which have arisen between the parties.
44. It has additionally been submitted by Mr. Uppal that the copy
of the MoM dated May 30, 2017 has not been signed by the parties
and the respondent denies the execution of the same. He submitted that
it is a trite law that a contract only arises between the parties when
they absolutely and unequivocally agree to the same. Since the parties
to the said MoM have not executed the same, it cannot be said that it
will have any binding effect upon the parties. He reiterated and
emphasized that even the said MoM does not contain any arbitration
Clause, therefore, the same should not be relied upon to refer the
disputes for arbitration.
45. He submitted that the said MoM was only the subsequent
contract wherein additional work was allocated to the respondent on
fresh payment terms. He further submitted that in 2017, in a separate
MoU, it was made clear, that a separate work order will be issued by
the petitioner on the basis of a mutually agreed draft signed by both
the parties. However, as of now, no agreement to that effect has been
signed by the parties. So, it his submission that the reliance of the
petitioner on the MoM of the year 2017 is completely misplaced. He
submitted that the petitioner has particularly failed to show (i) how the
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 14 of 19
Neutral Citation Number:2023/DHC/001644
present description of the dispute is different and covered by the
arbitration clause stipulated in the MoU and (ii) how the said MoM has
given rise to the disputes between the parties.
46. He further submitted that the said MoM never finalized the
obligations pertaining to the aspects of Engineering, Procurement,
Payments made to the respondent and the Success Fees and it was only
a proposal and the same had never been accepted by the respondent.
47. So on the basis above-mentioned submissions, Mr. Uppal, is
seeking dismissal of the instant petition.
ANALYSIS
48. Having heard the learned counsels for the parties, the short
issue which arises for consideration is whether the petitioner is entitled
to the prayer made in the instant petition for appointment of an
Arbitrator.
49. There is no dispute that present petition is a second round of
litigation filed by the petitioner. The initial one being ARB.P.
831/2019 which was decided by this Court on February 13, 2020,
whereby this Court had passed the following order:
“Learned counsel for the respondent, at the outset, submits
that while there is an Agreement between the parties which has
an Arbitration Clause but the notice of invocation dated
04.07.2019 is not in terms of the Memorandum of
Understanding which contains the Arbitration Clause.
Learned counsel for the petitioner fairly submits that fresh
notice of invocation will be sent to the respondent in terms of
the Arbitration Agreement calling upon the respondent to
appoint an Arbitrator.
Learned counsel for the petitioner seeks leave to withdraw the
petition with liberty to take re-course to appropriate remedies
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 15 of 19
Neutral Citation Number:2023/DHC/001644
available to the petitioner in law.
Petition is disposed of with the liberty aforesaid. Needless to
state that petitioner is at liberty to approach the Court again
for appointment of an Arbitrator, in accordance with law.”
50. A perusal of the same would reveal that the afore-said petition
was disposed of, as the notice invoking the arbitration, which resulted
in the filing of the ARB.P. 831/2019, was not in conformity with the
terms of the MoU dated June 19, 2014. Thus, liberty was granted to
the petitioner to invoke Clause 10 as stipulated in the MoU, to file a
fresh petition, if in eventuality the dispute arises and it is pursuant
thereto that the instant petition has been filed.
51. The submission of the learned counsel for the petitioner is that
the instant petition is primarily filed by invoking the provisions of the
MoU wherein the parties had decided to enter into a relationship for
executing the Project which was awarded to the petitioner by the
ONGC. On the other hand, the only objection advanced by Mr.Uppal,
learned Senior counsel for the respondent, was primarily that the
dispute does not pertains to the MoU but several LoIs which have been
issued subsequently by the petitioner to the respondent and the said
LoIs do not contain any arbitration clause(s), which shall make the
present petition maintainable.
52. He had also tried to justify his submission by drawing a
comparison between the description of the disputes in Notices dated
July 4, 2019 and April 20, 2020 to contend that the attempt is being
made on behalf of the petitioner to misstate the facts by giving an
impression that the disputes are relatable to MoU dated June 19, 2014
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 16 of 19
Neutral Citation Number:2023/DHC/001644
and not the LoIs, which were subsequently issued by the petitioner to
the respondent.
53. At the outset, I may state that the Clause 10 of the MoU which
I have already reproduced in paragraph 7, is a part of the MoU. In the
order of this Court passed in the initial round of litigation, which I
have already reproduced in paragraph 49, the Court had directed the
petitioner to issue a fresh notice of invocation to the respondent as the
Court was of the view that the Invocation Notice dated July 04, 2019
was not in accordance with the provisions laid down under the MoU.
54. Subsequently, the Notice of Invocation dated April 20, 2020
was sent by the petitioner to the respondent, wherein reference has
been given to the Contract with ONGC and which reads as under:
“The work order was for a project which was as per ONGC
Tender No. UA5KC13001 for Modernization of ETP Plant at
ONGC Uran Plant only (UEM as a technical Collaborator).
ONGC awarded the contract for Modernization of ETP Plant
at ONGC Uran Plant on 11.05.2015 of an amount of Rs.
111,04,76,499/- inclusive all taxes, duties and levies and the
MOU was executed in furtherance of the same. The above-
mentioned work was assigned by my Client to your Company,
vide letter no. NECL/UEM/LOI/TCA/2015 dated June 09, 2015
as per the terms of the MOU as mentioned above, with the
contract value of Rs. 1,64,64,933.00/- (Rupees One Crore Sixty
four lakh sixty four thousand nine hundred thirty three only)
for UEM to make available to NECL, expertise and technical
know how in relation to carrying out work by NECL. Such
expertise and technical know how to be made available by
UEM to NECL included giving assistance, training and
practical experience/expert supervision in accordance with
good HSE practices to personnel employed by NECL, my
client. The arrangement was to remain in full force during the
term of the contract period with my Client.”
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 17 of 19
Neutral Citation Number:2023/DHC/001644
55. In any case, the issue, whether the disputes which have arisen
between the parties are in the terms of the MoU dated June 19, 2014 or
in terms of the LoIs issued by the petitioner or related to both (as
according to Mr. Nagar both the MoU and the LoIs are interrelated, as
LoIs were issued in furtherance of the MoU), can be looked into by the
Arbitrator as the Arbitrator can decide his own jurisdiction in terms of
Section 16 of the Act of 1996. It is not a case that no arbitration
Clause exists between the parties.
56. If the plea of Mr. Uppal that the disputes relate to the LoIs,
which do not contain the arbitration clause is not substantiated then the
dispute with regard to LoIs are necessarily to be decided through the
process of arbitration. It can be a position that MoU and LoIs are two
separate contracts, then also the arbitration Clause in MoU need to be
given effect to whatever is its effect.
57. So, it will be apt here to put reliance on the judgment of the
Supreme Court in the case of Sanjiv Prakash v. Seema Kukreja and
Ors. , MANU/SC/0238/2021 , wherein, the Court whilst delving into the
aspect of limited jurisdiction of the Court under Section 11 of the Act
of 1996, has in paragraph 9, held as under:-
“9. Judged by the aforesaid tests, it is obvious that whether the
MoU has been novated by the SHA dated 12.04.1996 requires
a detailed consideration of the clauses of the two Agreements,
together with the surrounding circumstances in which these
Agreements were entered into, and a full consideration of the
law on the subject. None of this can be done given the limited
jurisdiction of a court under Section 11 of the 1996 Act. As has
been held in paragraph 148 of Vidya Drolia (supra), detailed
arguments on whether an agreement which contains an
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 18 of 19
Neutral Citation Number:2023/DHC/001644
arbitration clause has or has not been novated cannot possibly
be decided in exercise of a limited prima facie review as to
whether an arbitration agreement exists between the parties.
Also, this case does not fall within the category of cases which
ousts arbitration altogether, such as matters which are in rem
proceedings or cases which, without doubt, concern minors,
lunatics or other persons incompetent to contract. There is
nothing vexatious or frivolous in the plea taken by the
Appellant. On the contrary, a Section 11 court would refer the
matter when contentions relating to non-arbitrability are
plainly arguable, or when facts are contested. The court
cannot, at this stage, enter into a mini trial or elaborate review
of the facts and law which would usurp the jurisdiction of the
arbitral tribunal.”.
58. Accordingly, this petition is disposed of by appointing Justice
R.K. Gauba, a former Judge of this Court as a learned Arbitrator, who
shall adjudicate the disputes between the parties, both through claims
and counter-claims, if any.
59. The fee of the learned Arbitrator shall be in terms of the
Schedule IV of the Act of 1996. The learned Arbitrator shall also give
his declaration in terms of Section 12 of the Act of 1996.
60. All the contentions of the parties, both on facts and in law are
left open for consideration of the learned Arbitrator.
61. This order must not be construed as an opinion of this Court on
the merits of the issues raised by the parties in this petition.
62. No costs.
V. KAMESWAR RAO, J
MARCH 06, 2023 /aky/jg
Signature Not Verified
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:07.03.2023
11:49:42
Arb.P.95/2022 Page 19 of 19