Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 17
CASE NO.:
Appeal (civil) 5610 of 2006
PETITIONER:
Ramchandra Murarilal Bhattad & Ors.
RESPONDENT:
State of Maharashtra & Ors.
DATE OF JUDGMENT: 05/12/2006
BENCH:
S.B. Sinha & Dalveer Bhandari
JUDGMENT:
J U G D M E N T
(Arising out of S.L.P. (C) No.5900 of 2004)
WITH
CIVIL APPEAL NO. 5611/2006
(Arising out of S.L.P. (C) No.23665 of 2004)
S.B. Sinha, J.
Leave granted.
The Mumbai Metropolitan Region Development Authority (for short,
’the Authority’) was created under the Mumbai Metropolitan Region
Development Authority Act, 1974 (’the Act’). It conceptualized the idea of
establishing a Convention and Exhibition Centre (’C&EC). Pursuant thereto
and in furtherance thereof it called for "Expression of Interest for
development of C&EC" in Bandra Kurla Complex. An advertisement was
issued inviting ’Expression of Interest for development of C&EC’.
Appellant No.1, pursuant whereto and in furtherance whereof, entered into a
Memorandum of Understanding (MoU) with M/s. Larsen & Toubro Ltd.
(L&T) for setting up such a complex. It also conducted conference of
investors therefor. It submitted its tender on 7.4.2003, highlighting :
a) Entire ground of 75,000 sq.m. would be required for international
standard C&EC.
b) They have formed a consortium for bidding for the said project and
giving the names of the members of the consortium as including
L&T and IMAG (Germany).
c) Letters of acceptance from L&T was also annexed to show its
participation.
d) The Authority was offered equity participation to the extent of 5%
of the total equity base.
Several other companies also submitted their tenders.
The tenders were to be considered at three stages and thus, three
different covers were to be submitted along with tenders. The first cover
contained compliance with minimum eligibility criteria, the second cover
contained financial bid and the third one contained technical and business
proposals. The technical bid was opened on 7.5.2003. The financial bid was
thereafter opened which was contained in second cover, on 8.5.2003.
Appellant was the highest bidder having offered 91.514 crores. M/s.
Reliance Capitals Ltd. was said to be the lowest bidder therein. The offer of
the bidders thereof are as under :
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 17
1. M/s. Shapurji Pallonji & Co. Ltd. Rs.50.005 Crores.
2. M/s. Reliance Capitals Ltd. Rs.13.032 Crores.
3. M/s. R.M. Bhuther & Co. Ltd. and
its Associate companies in consor-
tium with L&T Ltd. Rs. 91.514 Crores.
3rd Cover thereof was opened thereafter and the Authority, on
26.6.2003 informed Appellants that it had decided to arrange a presentation
on the business proposal by them on 3.7.2003. Pursuant thereto they made a
presentation on 4.7.2003.
Appellants, by a letter dated 29.8.2003, informed the Authority that :
a) reputed concerns like L&T and IMAG were associated in the
project.
b) A presentation was made on 4th July, 2003, a copy whereof was
enclosed.
c) Thereafter it did not receive any query from the Authority.
d) List of business partners shown with details of Convention
projects of L&T and business of IMAG.
e) Role of IMAG was also set out.
The Authority, however, took a decision to reject all the bids on
1.9.2003, which was said to have been communicated to Appellants by a fax
message on 22.10.2003.
Allegedly, the news item appeared in the ’Economic Times’ on
2.10.2003, wherein, inter alia, it was reported that :
a) The Authority is close to finalizing the much talked about
Convention centre in Bandra Kurla Complex.
b) An official of the Authority had stated that they were trying to
get private participation and three bidders had been finalized
and in a few days the plans for the Centre would be finalized in
an area of 5.5 hectares.
Appellant issued a letter to the Chairman of the Authority, in terms
whereof he was, inter alia, informed that the project would start getting
yield only after 12 years from the date of commencement thereof. It was
furthermore informed that its consortium members included L&T and
IMAG.
It was contended :
i) The company has offered highest bid price for the land at BKC
for a reserved plot for C&EC since the company is interested in bringing up
an international standard Exhibition Centre, a long over-due infrastructure
asset for a city like Mumbai inspite of reserved plot (restricted utility) area
with high gestation period and longest break even which is almost about 7
years. In all, the project starts getting yield only after 12 years from date of
commencement of construction.
(ii) It has also been the contention of the company to relocate the
asset base of the company on account of core competency of the company in
the field for more than 50 years and intending to continue to command on
industry.
iii) As per the press release for a commercial block bidding invited
by the Authority, it was awarded at Rs.25,000/- per square metre in spite of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 17
having a total flexibility to exploit the commercial aspect vis-‘-vis an offer
given by the company for the reserved plot for convention centre at the rate
of Rs.14,642/- per square metre.
iv) Company also expressed that the projects of such type are
always being given land at very concessional rate. Statistics indicates that
world over such exhibition centres are either funded by way of concessional
land price or absolute government contribution by way of land to make the
project to early break even.
The expertise of L&T and IMAG in setting up Exhibition Centres was
again highlighted by a letter dated 20.10.2002, therein it was alleged :
a) The Authority had informed in the presence of other bidders
that the consortium led by the appellants were the successful bidders.
(b) Some committee members informed that the matter had not
been decided on 1.9.2003 and the matter was deferred till the next meeting
to be held on 27.10.2003.
(c) The detailed history was set out including the fact that Reliance
Capital had quoted Rs.13.032 crores against Rs.91.514 crores quoted by
Appellants.
d) L&T and IMAG were the consortium members and the decision
would have an international impact.
A writ petition was filed before the Bombay High Court by
Appellants, inter alia, questioning :
a) the validity of clause 2.4 of the Request for Proposal in which
the Authority reserved the right to reject at any stage all or any of the bids
without assigning any reason.
b) the power of the Authority to cancel or reject the bids.
c) the cancellation of the bid by the decision purported to have
been made on 1.9.2003.
The contentions of Respondents before the High Court were :
a) the decision to reject all bids is in pursuance of the power was
conferred by the terms of the contract.
b) the authorities acted reasonably and fairly and have now
reached a decision to set up the convention centre on their own without any
private participation.
c) By virtue of sections 12(1)(b)(d) and (h) and the power to issue
directions under S.14 of the Act, it could, at any stage, review any decision
including the decision of the executive committee and direct either rejection
of all bids or issuance of fresh bids.
The writ petition filed by Appellants was dismissed by the High Court
holding :
A. the Executive Committee is not the sole judge in matters of
approval or rejection of tenders for projects and schemes of the authorities.
B. In view of sections 12, 13, 14 and other provisions of the
Chapter, the power of the Authority cannot be whittled down or restricted.
C. It being the authority entitled to acquire, hold and dispose of the
property it cannot be said that its power in such mattes will not include the
power to reject a tender or bid which is invited for projects and schemes
framed by it.
D. In exercise of the powers under Article 226 it could not act as
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 17
an Appellate Authority to review of supervise the functions of authorities
like the Mumbai Metropolitan Region Development Authority.
E. Considering the material on record it cannot be held that the
Authority acted unreasonably unfairly or in an unjust manner.
F. The Authority consisting of people possessing expertise and
skill in the field its decision to develop the property as a C&EC by itself
cannot be faulted with.
G. It is not a case where Article 14 can be said to have been
infringed.
H. It cannot be said the facts which are pleaded are not based on
evidence or materials which are not annexed to the counter affidavit.
I. Reasons in such matters can be gathered from files/records
maintained by the authorities.
A review petition filed thereagainst was dismissed.
Appellants filed the special leave petition on 29.10.2004 against the
order dated 20.1.2004 as also against the order dated 11.10.2004 dismissing
the review petition.
In its counter affidavit filed before this Court the Authority, inter alia,
disclosed that the rate of premium for the commercial properties was
increased from Rs.25,000/- per square metre to Rs.42,500/- per square
metre. It was further disclosed that the Authority called for fresh tenders for
development of 5.5 hectares as C&EC and 2.0 hectares for a commercial
complex, in terms whereof the bidders were required to quote separately for
C&EC and Real Estate Components. Whereas the rate for C&EC was fixed
at 130 crores (Rs.20,000/- per square metre); for the Real Estate Component
the bidder was required to quote higher than 350 crores (i.e. higher than
Rs.70,000/- per square metre). It was further stipulated that the successful
bidder was required to pay 50% of the compensation amount within one
month of acceptance thereof and the rest 50% within three months thereof.
The other terms and conditions and procedure for evaluating bids, however,
remained the same. A supplementary affidavit was filed by Respondents on
20th February, 2006, wherein it was brought to this Court’s notice that in
response to the tender floated in 2005, Reliance Industries Ltd. had bid
Rs.974,00,00,111/- for the commercial portion and the fixed price of Rs.130
crores for the C&EC. Reliance Industries Limited thereafter was directed to
be impleaded as a party by an order dated 24.4.2006, wherein this Court
recorded :
"These matters pertain to the construction of a
Convention-cum-Exhibition Centre and commercial
complex at Bandra Kurla, Mumbai. The petitioner
before us is the unsuccessful bidder who has challenged
the action of the Mumbai Metropolitan Region
Development Authority (MMRDA) cancelling all the
bids at an earlier stage. Despite the application made by
the petitioner, we declined to grant injunction in the
matter. As a result, MMRDA re-tendered and we are
informed that the highest bid was by Reliance Industries
Limited, which is said to have been granted the contract
and paid a sum of Rs.552 crores.
The petitioner desires to demonstrate to this Court
(a) that the bid was cancelled by the MMRDA, which
had no jurisdiction to do so under the Act; and (b) that
there was mala fides in cancelling all the bids as it was
intended to engineer the re-tendering process to favour
the party who has now succeeded. To demonstrate his
bona fides, the petitioner’s counsel states that the
petitioner would not only match the bid of the presently
successful party only for the Convention Centre, but that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 17
he would also pay the amount at one go instead of paying
it over a period of time.
We are informed that there is another party who is
involved. Mr. R.F. Nariman, the learned senior counsel,
states that the petitioner would move an application to
implead that other party (Reliance Industries Limited)."
The Reliance Industries Limited was impleaded as a party to this
appeal thereafter.
Mr. R.F. Nariman, learned Senior Counsel appearing on behalf of
Appellant in support of this appeal would contend that \026
i) the purported major shift in the policy by the Authority was
impermissible in law;
ii) rejection of the bid offered by the Authority was wholly illegal
as the Executive Committee alone was the sole judge in relation thereto;
iii) in accepting the bid of Reliance Industries Ltd., the offer of the
appellants that they would pay @2=% per year from the annual turnover
from the 21st year had not been considered;
iv) in rejecting the tender of the appellant, the Executive
Committee/Mumbai Metropolitan Region Development Authority was
required to assign sufficient and valid reason; and the same having not been
done, the order impugned in the writ petition was vitiated in law.
Mr. Harish N. Salve, learned Senior Counsel appearing on behalf of
the Reliance Industries Ltd., on the other hand, would submit that \026
i) the Executive Committee could not have taken a decision in
regard to the change of policy;
ii) when the second tender was floated, Appellant did not take part
therein;
iii) procedural lapses, if any, cannot be a ground for judicial
review.
Contentions of Mr. Shekhar Naphade, learned Senior Counsel
appearing on behalf of the Authority were \026
i) judicial review is not maintainable as Appellant has not
disclosed infringement of any constitutional or statutory right;
ii) the Authority was entitled to reject the tender on appreciation of
professional competence and capacity of Appellant to run the centre
profitably, as well as the fact that prices offered by them were competitively
low; and
iii) the policy being in relation to a mega project and the judgment
of the authority being objective criterion, no interference is called for by this
Court.
The Act was enacted for forming Brihan Mumbai and certain areas
round about into a Mumbai Metropolitan Region. Section 4 thereof deals
with the composition of the Authority. Section 4A provides for powers and
functions, inter alia, of its Chairman and Metropolitan Commissioner.
Section 7 provides for constitution and powers of Executive Committee.
Clause (iii) of Sub-Section (3) of Section 7 reads as under :
"7. (3)(iii) approval or rejection of tenders for
projects and schemes of the Authority;"
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 17
Section 12 of the Act provides for powers and functions of the
Authority. Clause (b) of Sub-Section (1) of Section 12 deals with the power
of reviewing any project or scheme for development which may be proposed
or may be in the course of execution or may be completed in the
Metropolitan Region. Clause (d) thereof refers to execution of projects and
schemes and Clause (h) provides for co-ordination in execution of the
project or schemes for the development of the Metropolitan Region.
Pursuant to or in furtherance of its regulation making power contained in
Section 50 of the Act, regulations were framed by the Authority, known as
the Mumbai Metropolitan Region Development Authority (Disposal of
Land) Regulations, 1977 (Regulations). Regulations 7 and 9 of the
Regulations are as under :
"7. Disposal of land by offers to Government,
Local Authority or Public Sector Undertaking
Where the Authority determines to dispose of land
by making offers to the Government, Local Authority or
Public Sector Undertaking, the offers shall be made by
the Metropolitan Commissioner in such form as he may
decide, incorporating the terms and conditions of offers
determined by the Authority which shall include the
condition that the offer shall remain open and valid for
acceptance for a period of 30 days and shall lapse if it
remains unaccepted by the expiry of this period; provided
that it shall be lawful for the Metropolitan Commissioner
to renew any lapsed offer on an additional condition that
the Government, Local Authority or Public Sector
Undertaking, as the case may be, shall pay interest at the
rate of 18% per annum over the premium specified in the
lapsed offer with effect from the date on which the lapsed
offer was made; provided further that nothing contained
herein shall authorize the Metropolitan Commissioner to
renew any lapsed offer after three months of its lapse."
Regulation 9 provides for the mode and manner of payment of
premium.
Sub-Regulation (ii) of Regulation 9 reads as under :
"9(ii) Notwithstanding anything contained in the
foregoing Clause to contrary, if there shall a scheme
formulated and sanctioned by the Authority to erect or to
finance erection of a building or buildings on land agreed
to be leased to the Government, a Local Authority or a
Public Sector Undertaking to subserve the development
of the Metropolitan Region or any part thereof and to
grant in lease such building or buildings to the concerned
government, Local Authority or Public Sector
Undertaking it shall be lawful to agree with the
concerned Government local authority or Public Sector
Undertaking to recover the premium agreed to be paid in
consideration of the lease of such building or buildings in
yearly installments, not exceeding ten in number."
We may also notice some of the provisions of "Request for Proposal
for Grant of Lease of Land for developing and operating a Convention and
Exhibition Centre". Clause 3.15 defines "successful bidder" to mean the
bidder selected according to the evaluation criteria as detailed in Section 7
for grant of lease of land. The concept of Convention and Exhibition Centre
is contained in Clause 4.3 thereof. Clause 5 provides for specification of
C&EC. Clause 5.1 reads as under :
"5.1 The C&EC facility for Phase I is estimated to
require approximately 35,750 sq.m. of built up area
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 17
which will be reckoned as 44,525 sq.m. for computation
of FSI after allowing for height in excess of 4.20 m. for
exhibitions areas. In Phase II there is a provision of a
further 10,650 sq.m. of built up area (which will be
reckoned as 15,975 sq.m. for computation of FSI for
Exhibition areas having height in excess of 4.20 m) that
is to be used for further expansion of exhibition areas
having at least 2 additional exhibition halls having an
area of 5000 sq.m. each."
The total built-up area comes to about 60,500 sq.m.
Provision of Convention Auditorium was made in Clause 5.3. Clause
7 provides for submission and evaluation of bids stating that interested
parties shall submit their bids in three separate sealed covers : (1) Cover 1
should contain compliance in regard to minimum eligibility criteria.
Evaluation of minimum eligibility criteria is contained in clause 7.15 in the
following terms :
"7.15 The objective of the minimum eligibility criteria is
to short list Bidders who have :
? The financial strengths necessary to contribute
and/or arrange the funds required to execute the
Project in the desired time frame.
? The technical skills necessary to design,
construct, operate and maintain the Facility as
per the Principles of Good Industry Practice.
? The commercial skills necessary to market the
Facility and successfully develop business.
Clause 7.17 provides for the eligibility criteria being :
? "Tangible Net worth not less than Rs. 750 Million
as per the latest audited financial statement.
? Annual turnover not less than Rs.500 Million as
per the latest audited financial statement.
? Net Profit not less than Rs. 50 Million as per the
latest audited financial statement or Average
annual net profit of the last three financial years
not less than Rs.50 Million."
Category "I", related to field of activity defined as Convention &
Exhibition Centres, Hotels, Restaurants and Banquet Halls.
Clause 7.22 provides for Category "II" to include an indirectly related
field of activity defined as shopping centers, commercial complexes,
housing or office complexes, retail stores, entertainment centres and
amusement parks. Clause 7.23 provides for the eligibility criteria to show
that the bidding company must have developed during last five years at least
one Project having Capital Cost not less than Rs.1,000 Million. Clauses
7.24 and 7.25 thereof read as under :
"7.24 The turnover of the Bidding Company or the
combined turnover of the Financially Significant
Members of the Bidding Consortium from the
directly related field of activities shall not be less
than Rs.500 million.
7.25 Format for Cover I \026 compliance to minimum
eligibility criteria
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 17
Bidders are required to organize "Cover I \026
Companies with Minimum Eligibility Criteria"
according to the following checklist :
Cover 1
Compliance to Minimum Eligibility
Criteria
Section 1
\005\005\005\005\005\005.
Section 2
a) \005\005\005\005
b) \005\005\005\005
c) Letters of Acceptance, as per the
format specified in Exhibit 4, from each
of the Consortium Members in case of a
Bidding Consortium.
Section 3
a) \005\005\005\005..
b) Letters of Commitment as per the
format specified in Exhibit 3, from each of
the entities which are Financially
Significant Consortium Member, the
strengths of which is to be considered for
the purpose of evaluation.
Clause 7.26 reads as under :
"7.26 MMRDA on demand will return unopened
Financial Bids and Technical Bids (Covers 2 and
3) of the Bidders who do not comply with the
minimum eligibility criteria."
Step 2 (Cover 2) provides for financial bid. Clause 7.30 provides for
methodology for evaluation of bids.
Clause 7.30 deals with the manner in which the bids would be dealt
with.
Clause 7.34 provides for technical and business proposal evaluation
criteria. Clauses 7.38 and 7.39 are as under :
"7.38 In evaluating the Business Proposal, MMRDA
reserves the right to seek clarifications from the
Bidders. The Bidders shall be required to furnish
such clarifications.
7.39 The Technical and Business Proposal of only the
Rank 1 bidder will be opened. He may also be
requested to make a presentation at his own cost,
for clarifications and additional information on
bidder’s capability, concept plan and the business
proposal in this regard to the evaluation committee
appointed by the Metropolitan Commissioner,
MMRDA. The Committee may seek further
clarifications and make suggestions in respect of
the proposal, within the permitted built-up area,
which will not include any change in the premium
or the manner in which it is to be paid. These
suggestions will have to be incorporated by the
bidder."
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 17
The Bidding Companies/Bidding Consortium of Appellants included :
1. M/s. R.M. Bhuther & Co. Ltd.
2. M/s. Larsen & Toubro Ltd.
3. M/s. R.M. Bhuther & Co.
4. M/s. M.B. Development Corporation
5. M/s. M.B. Constructions
6. M/s. Bhattad Bros.
7. M/s. Alusett System (India) Pvt. Ltd.
The principal question which arises for consideration is as to whether
the Authority had any jurisdiction to cancel the bid.
The Executive Committee is a statutory functionary. The powers and
functions of the authority and the respective committees concededly are
governed by the provisions of the statute, but, then the jurisdiction of the
Executive Committee is limited. It was confined to rejection or acceptance
of the tender. The Authority exercises a larger power. For the said purpose
we would assume that the Authority had no incidental or ancillary power,
but there cannot be any doubt or dispute that the Executive Committee could
not cancel the entire tender. It could not have caused any change in the
entire scheme or policy. It could not make alterations in the methodology of
tender. It could not have gone into the working of the project. It also could
not have gone into the question as to whether the project would be
financially viable if the method of calculation is changed.
Strong reliance has been placed by Mr. Nariman on Marathwada
University v. Seshrao Balwant Rao Chavan [(1989) 3 SCC 132 : AIR
1989 SC 1582] to contend that as therein the power of the Vice Chancellor
and the Executive Council was different, the former’s power could not have
been exercised by the latter.
We do not dispute the proposition of law laid down therein.
We would assume that the power of the Executive Committee and the
Authority under the Act are different and the latter for all intent and purport
could not usurp the functions of the former. But in this case, it has not been
so done.
Jurisdiction of the Authority being larger, and the power to cancel the
tender being not vested in the Executive Committee, the action on the part of
the former was neither illegal nor without jurisdiction.
This Court rejected the contention that the power of the Vice
Chancellor to regulate work also included the power to initiate disciplinary
action, stating :
"This takes us to the second contention urged for
the appellants. The contention relates to the legal effect
of ratification done by the Executive Council in its
meeting held on December 26/27, 1985. The decision
taken by the Executive Council is in the form of a
resolution and it reads as follows :
"Considering the issues, the Executive Council
resolved as follows :
1. The Executive Council at its meeting held on
22-3-1979, had by a resolution given full authority to
the Vice-Chancellor for taking further proceedings
and decision in both the cases of the defaulting
officers.
2. In exercise of above authority, the Vice-
Chancellor appointed an Inquiry Officer and as
suggested by the Inquiry Officer issued show-cause
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 17
notices, obtained replies from the officers and lastly
issued orders for terminating their services;
*
It was further resolved that\027
(i) There has been no inadequacy in the
proceedings against both the officers;
(ii) The punishment ordered against both the
officers is commensurate with the defaults and
allegations proved against both the officers; and
(iii) The Executive Council, therefore, wholly,
endorses the actions taken by the then Vice-Chancellor
against both the officers."
By this resolution, we are told that the Executive
Council has ratified the action taken by the Vice-
Chancellor. Ratification is generally an act of principal
with regard to a contract or an act done by his agent. In
Friedman’s Law of Agency (5th edn.) Chapter 5 at p. 73,
the principle of ratification has been explained :
"What the ’agent’ does on behalf of the
’principal’ is done at a time when the relation of
principal and agent does not exist: (hence the use
in this sentence, but not in subsequent ones, of
inverted commas). The agent, in fact, has no
authority to do what he does at the time he does it.
Subsequently, however, the principal, on whose
behalf, though without whose authority, the agent
has acted, accepts the agent’s act, and adopts it,
just as if there had been a prior authorisation by the
principal to do exactly what the agent has done."
As noticed hereinbefore, we have proceeded on the basis that the
powers of the Executive Committee and the Authority are separate and
distinct and we have pointed out that the powers vested in the Executive
Committee being limited, the decision taken by the Authority cannot be said
to be illegal.
It was furthermore contended that the Executive Committee had a
special power which would prevail over general power vested in the
Authority. In J.K. Cotton Spinning & Weaving Mills Co., Ltd. vs. The
State of Uttar Pradesh & Ors. [(1961) 3 SCR 185], this Court applied the
rule of construction that general provisions yield to special provisions, but,
the said rule has no application in the facts and circumstances of the present
case. Executive Committee does not exercise any special power. The
jurisdictions of both the authorities are separate and distinct.
Dr. A.M. Singhvi, learned Senior Counsel appearing for Appellants in
the connected appeal relied upon Bhavnagar University vs. Palitana Sugar
Mill Pvt. Ltd. & Ors. [(2003) 2 SCC 111], wherein it was held :
"It is the basic principle of construction of statute
that the same should be read as a whole then chapter by
chapter, section by section and words by words.
Recourse to construction or interpretation of statute is
necessary when there is ambiguity, obscurity, or
inconsistency therein and not otherwise. An effort must
be made to give effect to all parts of statute and unless
absolutely necessary, no part thereof shall be rendered
surplusage or redundant."
We fail to understand as to how the principle laid down therein can be
said to have been violated.
Reliance has also been placed on State of Uttar Pradesh vs.
Singhara singh & Ors. [AIR 1964 SC 358 : (1964) 4 SCR 485], wherein
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 17
this Court quoted with approval the decision in Taylor v. Taylor [([1875] 1
Ch. D. 426, 431] for the proposition that where a power is given to do a
certain thing in a certain way, the thing must be done in that way or not at all
and that other methods of performance are necessarily forbidden. There is
again no quarrel over the aforementioned proposition of law. Here the
Authority has not exercised any power forbidden by law. The Authority has
also not exercised its power in the manner which is not in accordance with
law.
On merit of the matter, Mr. Nariman has pointed out, the distinction
between 2002 and 2005 tenders to show that such a policy decision as laid
down in the 2005 tender was not in pari materia with 2002 tender. The
comparison of methodology for evaluation of bids is as under :
2005 TENDER
2002 TENDER
METHODOLOGY FOR
EVALUATION OF BIDS
7.30 The bidder will have to quote
separately for the Convention &
Exhibition Centre and the
Commercial Complex. The built-up
area (considered for FSI computa-
tion) of the Convention & Exhibi-
tion Centre shall be considered as
65,000 sq.m. irrespective of the
reduction that may be possible on
finalization of detailed architectural
designs. Similarly the floor space
considered for FSI computation for
the commercial Complex will be
50,000 sq.m. The bidder will have
to quote a fixed rate of Rs.20,000
per sq.m. of built up area for total
built-up area 65,000 sq.m. for
Convention & Exhibition Centre.
The amount will be Rs.130 crores.
The bidder will also have to quote a
rate of premium higher than
Rs.70,000 per sq.m. of built-up area
for 50,000 sq.m. of total built-up
area for Commercial Complex. The
premium amount will be higher than
Rs.350 crores. The total minimum
amount of lease premium to be
quoted by the bidder will be higher
than Rs.480 crores of the total
amount of lease premium that will
be payable to MMRDA 50% will
have to be paid within one month
and the balance will have to be paid
within two months i.e. within three
months from the time the bid is
accepted. The lease period is of 80
years as is indicated in the
MMRDA (Disposal of land)
Regulation 1977.
METHODOLOGY FOR
EVALUATION OF BIDS
7.30 The bidder will have to quote
separately for the C&EC and the
Real Estate component. The built-
up area (considered for FSI
computation) of C&EC shall be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 17
considered as 60,500 sq.m. (Phase I
and II) irrespective of the reduction
that may be possible on finalization
of detailed architectural designs.
Similarly the floor space considered
in FSI computation for the Real
Estate component shall be 15,000
sq.m. The bidder has the option of
bidding only for the C&EC without
the Real Estate component. The
bidder has to quote a rate of
premium in terms of Rs. per sq.m.
of FSI and the total premium,
separately for the C&EC and the
Real Estate component subject to
the condition that the rate quoted for
the Real Estate component shall be
greater than that quoted for the
C&EC.
The Authority is a statutory authority. It consists of not only
politicians but also various other responsible officers. It, while exercising its
power under the Act, must necessarily take policy decisions. Whereas under
the 2002 tender the bidder had to quote the rate of premium in terms of
rupees per square meter of FSI and the total premium separately for C&EC
and the Real Estate component subject to the condition that the rate quoted
for the Real Estate component should be greater than that quoted for the
C&EC, upon having come to know that the value of the land would be much
more, the Authority in the 2005 tender decided that the bidders should be
required to quote a fixed rate of 20,000 per sq.m. of built-up area for total
built-up area 65,000 sq.m. for Convention & Exhibition Centre. Economic
viability of the entire project component, taking into consideration two
different components for C&EC and the Commercial Complex, could have
been taken differently. The premium amount was to be quoted higher than
Rs. 350 crores for the Commercial Complex. While exercising its
jurisdiction of judicial review, the Court is required to decide the cases
before it, keeping the well known principles therefor in mind and having
regard to the fact situation obtaining therein. No hard and fast rule can be
laid down therefor. Recently, in Noble Resources Ltd. vs. State of Orissa
and Anr. [2006 (9) SCALE 181] this Court has noticed the power of
judicial review vis-‘-vis contractual disputes, opining :
"Although terms of the invitation to tender may
not be open to judicial scrutiny, but the courts can
scrutinize the award of contract by the Government or its
agencies in exercise of their power of judicial review to
prevent arbitrariness or favouritism. [See Directorate of
Education and Ors. v. Educomp Datamatics Ltd. and Ors.
2004 (4) SCC 19]. However, the court may refuse to
exercise its jurisdiction, if it does not involve any public
interest.
Although the scope of judicial review or the
development of law in this field has been noticed
hereinbefore particularly in the light of the decision of
this Court in ABL International Ltd. (supra), each case,
however, must be decided on its own facts. Public
interest as noticed hereinbefore, may be one of the
factors to exercise power of judicial review. In a case
where a public law element is involved, judicial review
may be permissible."
Noticing some of the areas where judicial review would be
permissible, this Court opined that ordinarily, this Court would not enforce
specific performance of contract where damages would be adequate remedy.
It was also held that conduct of the parties would also play an important role.
The expansive role of Courts in exercising its power of judicial review
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 17
is not in dispute. But as indicated hereinbefore, each case must be decided
on its own facts.
Dr. Singhvi placed reliance upon Star Enterprises & Ors. vs. City
and Industrial Development Corporation of Maharashtra & Ors.
[(1990) 3 SCC 280], wherein Ranganath Misra, J., as His Lordship then was,
opined :
"In recent times, judicial review of administrative
action has become expansive and is becoming wider day
by day. The traditional limitations have been vanishing
and the sphere of judicial scrutiny is being expanded.
State activity too is becoming fast pervasive. As the State
has descended into the commercial field and giant public
sector undertakings have grown up, the stake of the
public exchequer is also large justifying larger social
audit, judicial control and review by opening of the
public gaze; these necessitate recording of reasons for
executive actions including cases of rejection of highest
offers. That very often involves long stakes and
availability of reasons for action on the record assures
credibility to the action; disciplines public conduct and
improves the culture of accountability. Looking for
reasons in support of such action provides an opportunity
for an objective review in appropriate cases both by the
administrative superior and by the judicial process. The
submission of Mr. Dwivedi, therefore, commends itself
to our acceptance, namely, that when highest offers of the
type in question are rejected reasons sufficient to indicate
the stand of the appropriate authority should be made
available and ordinarily the same should be
communicated to the concerned parties unless there be
any specific justification not to do so."
In this case, highest offer has not been rejected. A new policy
decision has been taken. Question as noticed herein is not as to whether the
offer of the Appellants should have been rejected but is as to whether the
Authority in law could have altered its policy in regard to disposal of its
properties. ’Public Trust Doctrine’ was also sought to be invoked by Mr.
Nariman against the Authority and in this behalf reliance has been placed on
Bangalore Medical Trust Vs. B.S. Muddappa & Ors. [(1991) 4 SCC 54].
This Court therein was dealing with a master plan in the light of justifiability
of exercise of discretionary jurisdiction under the Town Planning Act.
Having regard to the provisions contained in Sub-Section (4) of Section 19
of the Bangalore Development Authority Act, 1976 as also the fact that the
discretionary jurisdiction had been arbitrarily exercised, this Court invoked
the ’public trust doctrine’ saying that although the State is required to keep a
vigil on the local body, but, thereby the power thereunder cannot be
stretched so as to entitle the Government to alter any scheme and convert
any site or power specifically reserved in the statute in the Authority.
By floating a tender in furtherance of a public project, the Authority
was not truly concerned with the enforcement of its master plan. No such
argument was advanced before the High Court. Such an argument has been
advanced for the first time before us. We would consider the efficacy of
said contention a little later.
The next question which arises for consideration is as to whether any
reason was required to be assigned. A power to deal with a contractual
matter and a power of a statutory authority to exercise its statutory power in
determining the rights and liabilities of the parties are distinct and different.
Whereas reasons are required to be assigned in a case where civil or evil
consequences may ensue, the same may not be necessary where it is
contractual in nature, save and except in some cases, e.g., Star Enterprises
(supra).
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 17
Whether assignment of reasons forms third pillar of principle of
natural justice, is not free from doubt. There is a diversity of opinion as has
been noticed by this Court in Rajesh Kumar & Ors. vs. D.C.I.T. & Ors.
[2006 (11) SCALE 409].
Reliance has also been placed by Mr. Nariman on Commissioner of
Police, Bombay vs. Gordhardas Bhanji [1952 (1) SCR 135] and Union of
India & Ors. vs. Dinesh Enginering Corporation & Anr. etc. [(2001) 8
SCC 491]. In Commissioner of Police (supra) the Court was concerned
with a situation where a statutory authority had acted on dictation of an
Appellate Authority, which was found to be illegal. In Dinesh Enginering
(supra), this Court opined that the Railways have no arbitrary power to reject
the bid offered by a party merely because it has that power, particularly,
when the same can be exercised only on the existence of certain conditions
which in the opinion of the Railways are not in the interest of the Railways
to accept the offer.
We have noticed hereinbefore that power has not been exercised by
the Executive Committee in rejecting the tender. The power has been
exercised by the Authority in canceling the tenders so as to enable it to have
a re-look of the entire project.
Some reasons may be required to be assigned for rejecting the bid, but
in the instant case, in our opinion, no reason was required to be assigned as
there has been a change in the policy decision.
The news item appearing in the Economic Times is not of much
significance. No affidavit has been affirmed as regards the correctness or
otherwise of the said news item.
It may be true that the Authorities at one point of time, as was
disclosed in the Counter Affidavit, had thought of setting up a Convention
Centre of their own and without any private participation, but only because
there has been a deviation from the said stand would not, in our considered
opinion, render the entire policy decision vitiated in law.
It had set up its Evaluation Committee. The decision presumably has
been reached by experts.
The reasons as regards purported unsatisfactory performance of
Appellants, take a back seat once having a re-look to the entire situation was
thought of.
It is not a case where the Court is called upon to exercise its equity
jurisdiction. It is also not a case where ex facie the policy decision can be
held to be contrary to any statute or against a public policy. A policy
decision may be subjected to change from time to time. Only because a
change is effected, the same by itself does not render a policy decision to be
illegal or otherwise vitiated in law.
In Harminder Singh Arora vs. Union of India & Ors. [(1986) 3
SCC 247], whereupon Dr. Singhvi relied upon, the tender was arbitrarily
rejected. Therein the writ petition was dismissed in limine only on the
premise that the question involved therein related to contractual obligations
and the policy decision could not be termed as unfair or arbitrary. It was
opined that therein no question of policy decision arose and as such contract
was to be given to the lowest bidder in terms of the tender notice and the
contract should have been awarded to the appellant therein, especially when
he had been doing the job for many years. As to how the said decision is
applicable to the facts of the present case, we fail to understand. For the
self-same reasons we are unable to appreciate the contention that only
because a change has been effected in computation of total price under the
new tender, the same was invalid in law.
In New Horizons Ltd. & Anr. vs. Union of India & Ors. [(1995) 1
SCC 478], this Court opined that in the matter of grant of tender the State
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 17
cannot act as a private person having regard to Article 14 of the Constitution
of India. It was categorically opined that departing from the narrow
legalistic view the Courts have taken note of the realities of the situation
which, by no stretch of imagination, would mean that the Court would
substitute itself in the place of a statutory authority. The Court in a case of
this nature must exercise judicial restraint. It may be one thing to say that
having regard to the public interest, the Court may itself invite bids so as to
verify the justification of accepting a palpably lower bid as was done in
Ram and Shyam Company vs. State of Haryana and Ors. [(1985) 3 SCC
267], but it is another thing to say the Court would under all circumstances
not allow a play in joint in favour of the employer.
However, if the Court in a given situation is not in a position to allow
a bid to take place before, it may not still venture to strike down an Act in
the name of public interest, although, no such public interest exists.
Appellant stated before us that he is ready and willing to take a part of
the contract, viz., construction of the C&EC and pay the same amount as has
been done by Reliance Industries Ltd. and in addition it would pay 2.5% of
its annual turnover from the Convention Centre from the 21st year, as was
initially offered.
Appellant did not participate in the second bid. The tender process is
complete. Before us only a higher bid has been given. We do not intend to
enter into the intricacies of the question. Appellants could have submitted
its bids pursuant to the new tender and new conditions, even without
prejudice to its rights and contentions in this appeal. The stipulations made
in 2002 tender could have been repeated by it so as to demonstrate before
the experts comprising members of the Executive Committee that its bid was
the highest. If, in view of the change in the policy decision, the Authority
does not intend to become a partner in the profit making and opt for having
the entire bid amount at one go instead of waiting for 20 years, we do not
find any fault therewith.
Before us comparative bids of the bidders have been placed on the
second tender, which are as follows :
SR.No.
Name of the Bidder
Bid Amount
Rs.
Rate per sq.
m.
(approx.)
Rs.
1.
Reliance Industries Ltd.
11,04,00,00,111
96000
2.
DLF
1050 crores
91304
3.
Reliance Communications &
Infrastructure Ltd.
1011.12 crores
87913
4.
Gammon India
1011 crores
87913
5.
EMAR
911.07 crores
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 17
79217
The comparative statistics reads as under :
1.
Rate offered by the Petitioners Rs.
91.514 crores (divided by)
75,500 sq.mtrs.
Rs.12,121 per sq.
mtrs.
2.
Rate expected by MMRDA
Rs. 25,000 per
sq.mtrs.
3.
Amount for 75,500 sq. mtrs @ Rs.25,000/-
per sq.mtrs. (This should have been the
minimum bid in 2003)
Rs.188.75 crores
4.
Amount for 1,15,000 sq.mtrs @ Rs.25,000/-
per sq.mtrs. (This would have been the
reserve price at old rate in 2005)
Rs.287.50 crores
5.
Reserve Bid of MMRDA in 2005
(Minimum price revised as below)
Rs.480 crores
6.
Rate per sq. mtrs in the Reserve bid
Rs.480 crores (divided by)
1,15,000 sq.mtrs.
Rs.41,739/- per sq.
mtrs.
7.
Bid by Reliance Industries Ltd.
Rs.1104,00,00,111/-
8.
Rate per sq.mtrs of RIL Bid
Rs.11,04,00,00,111/- (divided by)
1,15,000 sq. mtrs.
Rs.96,000/- per sq.
mtrs.
Appellant complains that whereas the bid of Sister concern of
Reliance Industries Ltd. was very low, now it has offered a bid of
Rs.1104,00,00,111/-. From the chart placed before us it would appear that
there had been a stiff computation. The Reliance Industries Ltd. has become
the highest bidder. Its competitors had taken part in the earlier contracts.
No mala fide in accepting the tender has been alleged nor do we find any.
We, therefore, in the facts and circumstances of this case and having
regard to the subsequent events, are of the opinion that it is not a case where
we should interfere with the judgment of the High Court.
It, however, would not mean that the Authority or the Executive
Committee would not be entitled to take note of the offer of Appellant. It
may do so. It would not further mean that if the terms of new tender are
violative of the provisions of the master plan, the same would not be suitably
dealt with. We merely place on record that we have not gone into the said
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 17
questions, although raised before us by the learned counsel for the appellant,
simply on the ground that no such plea had been taken before the High
Court. In the absence of any plea that the policy decision adopted by the
Authority would be violative of the provisions of the Act or any master plan,
the same cannot be entertained. The question, however, is left open.
For the reasons aforementioned, there is no merit in these appeals,
which are accordingly dismissed. There shall, however, be no order as to
costs.