Full Judgment Text
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO(S). 1401 OF 2019
K. L. SUNEJA & ANR. …APPELLANT(S)
VERSUS
DR. (MRS.) MANJEET KAUR MONGA (D)
THROUGH HER LR & ANR. …RESPONDENT(S)
WITH
CIVIL APPEAL NO(S). 4530 OF 2019
J U D G M E N T
S. RAVINDRA BHAT, J.
1. There are two appeals preferred against a common order of the National
Company Law Appellate Tribunal (hereinafter, “NCLAT”/“Tribunal”). The
first, by the original home buyer’s legal representative (hereinafter,
“complainant”) and the second by the builder / developer (hereinafter,
Signature Not Verified
Digitally signed by
NEETA SAPRA
Date: 2023.01.31
17:06:45 IST
Reason:
“developer”).
2
2. In 1989, one Smt. Gursharan Kaur had applied for a flat in a proposed
group housing scheme called ‘Siddharth Shila Apartments’, situated at Plot No.
24 in Vaishali Scheme, Ghaziabad, U.P. (hereinafter, “Scheme”). After
depositing three instalments towards the flat, she passed away, and was
succeeded by her daughter-in-law Dr (Mrs.) Manjeet Kaur Monga, who
deposited the fourth instalment. Thereafter, the developer issued an allotment
rd
letter dated 21.05.1992, earmarking Flat No. D-301 (3 floor) with a super built-
up area of 1375 sq. ft. in the Scheme. Dr Manjeet Kaur Monga deposited two
further instalments, with the sixth instalment deposited in September 1993.
Eight years later, i.e., in December 2001, a demand notice for payment of the
eighth and ninth instalments was issued to the complainant. She resisted this
notice, as there was no intimation about the progress of work and delivery of
possession of flat to her. The developer however, issued a letter thereafter,
th
cancelling the allotment of the complainant’s flat on 30 April 2005. The
th
complainant had deposited seven instalments up to 4 October 1993 totalling ₹
4,53,750/-. With the cancellation letter, the developer enclosed a Pay Order
th
dated 30 April 2005 for ₹ 4,53,750/- issued by Citibank towards full refund of
payments made by the complainant towards the flat.
th
3. Aggrieved, the complainant through her lawyer, issued a notice dated 7
September 2005 to the developer, stating that she was always ready and willing
to pay the instalments towards the flat, in tune with the allotment letter, but the
developer did not keep up its part of the bargain regarding timeliness of delivery
3
of possession and quality of construction. The notice alleged that even 40% of
the construction work had not been completed till the seventh instalment, though
the complainant had paid a cumulative of ₹ 4,53,750/-. She demanded
possession of the flat besides claiming ₹ 25,00,000/- as compensation. With the
notice, the complainant returned the Pay Order of ₹ 4,53,750/-. She also sent a
cheque of ₹1,00,000/- expressing willingness to pay the price of the flat. The
th
developer replied to the notice on 26 September 2005 denying the allegations
of delay in construction and accused the complainant of default in payment of
instalments. However, the developer did concede to slight delay in completion
of the project due to litigation with the Ghaziabad Development Authority.
4. Dr. Manjeet Kaur Monga filed a complaint under Section 36 of the (then)
Monopolies and Restrictive Trade Practices Act, 1969 (hereinafter, “MRTP
Act”) alleging unfair trade practice by the developer. The complaint claimed
physical possession of the flat or an alternative flat of the same size and
dimension. The complainant also applied under Section 12A of the MRTP Act
seeking to restrain the developer from alienating flat D-301 in Siddharth Shila
Apartments; she also filed C.A. No. 39/2009 for award of compensation of ₹
25,00,000/- under Section 12B of MRTP Act alleging to be a victim of unfair
trade practice at the hands of the developer. The MRTP Commission disposed
off the application filed under Section 12A of the MRTP Act restraining the
developer from creating third party interest with respect to the flat. The
developer also resisted the complaint and claimed that the complainant was
4
disentitled to any relief under the MRTP Act. It was further alleged that the
complainant had failed to deposit payments in accordance with the plan in the
nd
allotment letter and that she had, in terms of her letter dated 22 May 2002,
shown disinclination to take possession of the flat by alleging breach of
confidence on the part of the developer. The Notice of Enquiry issued by the
Commission was resisted on similar grounds.
5. Issues were framed for adjudication, which included whether the developer
had indulged in unfair trade practice, whether they were prejudicial to the
interest of the complainant and / or the public in general. The MRTP Act was
repealed by Section 66 of the Competition Act, 2002 which was brought into
st
force w.e.f. 1 September 2009. Chapter VIII-A introduced subsequently
provided for establishment of an Appellate Tribunal to hear appeals against
orders passed by the Competition Commission of India. The matters pending
before MRTP Commission were transferred to the (then) Competition Appellate
th
Tribunal (hereinafter, “COMPAT”). By order dated 29 July 2011, COMPAT
framed issues in the application filed under Section 12B of the MRTP Act. The
issues related to maintainability of the petition; whether unfair trade practice had
been proved; and if so, were they prejudicial to the public; and also, if the
complainant was entitled to any compensation.
1
6. Having regard to the evidence produced, COMPAT by its order concluded
that the developer had falsely represented to the general public (including the
1 rd
Dr (Mrs) Manjeet Kaur Monga vs. Mr K.L. Suneja, Civil Appeal No. 39/2009, dated 3 August 2015.
5
complainant) the time within which the project was to be completed, i.e., three
years, but did not complete the construction for more than a decade. The
COMPAT held the developer guilty of unfair trade practice under Section 36-A
(1) (i), (ii) & (ix) of the MRTP Act and also ruled that the complainant was
justified in not paying further instalments and the developer committed illegality
by cancelling the allotment. Noticing the law laid down by this court in
2
Ghaziabad Development Authority vs. Ved Prakash Agarwal, COMPAT held
that it and its predecessor (MRTP Commission) could not assume the powers of
a civil court to grant relief akin to specific performance. Hence, it declined the
relief of delivery of possession of the flat. The COMPAT however directed the
developer to pay compound interest @ 15% per annum to the legal
representatives of the complainant with interest calculated on each instalment
th
from the date of its deposit till 30 April 2005, i.e., the date on which the
allotment was cancelled. Besides, the respondents were directed to pay the
amount already invested by the complainant, i.e., ₹ 4,53,750/-, to the legal
representatives of the complainant.
7. COMPAT’s order was challenged by both the complainant and the
developer through separate appeals before this court, which by its order dated
th 3
18 July 2017, upheld the award of compensation to legal representatives of
2 th
Ghaziabad Development Authority vs. Ved Prakash Agarwal , C.A. No. 794/2001, dated 14 May 2008.
3
Dr (Mrs) Manjeet Kaur Monga (Thr. LH Karan Vir Singh Monga) vs. Mr K.L. Suneja, Civil Appeal No.
th
5032 / 2017, dated 18 July 2017.
6
the complainant in terms of the formula adopted by the COMPAT. This court
observed as follows:
“… Merely because a liquidated amount is not stipulated or determined
by the Tribunal, it cannot be said that it is not the compensation. Once
the interest, as ordered by the Tribunal, is calculated that will be the
amount of compensation referred to under section 12-B of the Act.”
8. This court also noticed the contentions of the developer that when it had
th
taken the Pay Order from Citibank on 30 April 2005, the amount of ₹
4,53,750/- covered by that instrument had been deducted from its current
account. It was not however received by the complainant payee. The account
holder / developer cancelled the Pay Order and requested for re-credit of the
nd
amount; which was done by Citibank on 22 June 2016. The court also noted
the contention of Citibank that the money deducted from current account of the
developer in April 2005, though not paid to the payee, was not enjoyed by the
bank as the Pay Order could have been presented at any moment. This court
observed that both these issues had not been considered by COMPAT,
apparently because these aspects were not addressed and Citibank was not a
party before the Tribunal. The court therefore disposed of the appeals by
remitting the matter to COMPAT with directions to implead Citibank as an
additional respondent. Additionally, the developer was directed to pay the
th
compensation worked at 15% compound interest up to 30 April 2005. The last
issue which COMPAT was to consider on remand was whether there should be
th
any compensation and if so, what should be the amount payable after 30 April
2005 and whether Citibank was liable to pay any interest to the account holder.
7
Impugned Order of the NCLAT
9. After remand, the complainant impleaded Citibank as a respondent. All
respondents were allowed to file their respective affidavits in regard to payment
st
of interest, if any, payable to the complainant from 1 May 2005 onwards. By
the impugned order, NCLAT noticed the facts leading to the order of this Court,
including that the complaint was filed in 2005 along with the original Pay Order,
issued at the behest of the developer by Citibank, which had been returned
initially by the complainant, but given back to the complainant. The NCLAT
also considered the affidavit and pleadings of the parties, including Citibank,
and noted that according to circulars, the amount of ₹ 4,53,750/- had been
deducted from the developer’s account and that Citibank too did not enjoy any
interest on that amount, during pendency of the complaint before COMPAT.
The impugned order noted that the legal representatives of the complainant did
rd
not get the refund of ₹ 4,53,750/- in terms of order dated 3 August 2015 by
th
COMPAT as funds were credited back to the account of the developer on 16
th
June 2016 and a fresh Pay Order (bearing No. 262910) dated 16 June 2016 was
issued by Citibank. Ultimately that amount was made over to the complainant
th th th
on 7 May 2016, in compliance with this court’s orders dated 8 and 26 April
2016. The NCLAT, by the impugned order, directed as follows:
“It is accordingly found that the direction of COMPAT in terms of order
dated 3rd August, 2015 in regard to payment of Principal amount of
Rs.4,53,750/- stood not complied with till 7th May, 2016. In view of the
same, the legal representatives of the Complainant would be entitled to
further compensation in the form of compound interest @ 15% per
annum on the principal amount of Rs.4,53,750/- w.e.f. 1st May, 2005
till 7th May, 2016 further entitled to pendente lite and future interest
8
till realization of the accumulated arrears from Respondents No. 1 and
2. (i.e., the developer)”
Contentions of the Complainant
10. The arguments on behalf of the complainant were common to both appeals.
It was urged that NCLAT fell into error as it failed to appreciate that since the
legal representatives of the complainant did not get the refund of the amount of
th
₹ 4,53,750/- from the developer until 7 May 2016, the interest on the said
th
principal amount ought to run from 4 October 1993 till the date of realization
th
of the amount i.e. 7 May 2016.
11. It was argued that once the Tribunal found that the developer was in the
wrong – a determination that was upheld by this court, which held that the
complainant was entitled to compensation, by way of compound interest – that
direction had to be taken to its logical end, which meant that interest on the sum
of ₹ 4,53,750/- was also payable from the date it was deposited with the
developer (in 1993) till the amount was realized. This was the only restitutionary
and equitable order, having regard to all circumstances of the case.
12. It was submitted that the developer’s argument that the amount had been
deducted from its account, and that it was not aware about the filing of the
original Pay Order, could not be countenanced. Learned counsel highlighted,
that moreover, the developer took full advantage of the amounts deposited by
the complainant, and after cancelling the allotment, had immediately allotted the
flat to another purchaser, for a considerably higher sum of ₹ 21 lakhs. This fact
was not disputed by the developer. Therefore, the complainant could not be
9
placed at a disadvantage, because the amounts deposited and lying with the
developer had multiplied manifold. The developer had the advantage (twice
over) of obtaining consideration from the new allottee / purchaser.
Contentions of the Developer
13. The developer urged, in response to the complainant’s appeal, as well in its
appeal, that no fault could be attached to it, and it could not be fastened with any
th
liability, once the Pay Order dated 30 April 2005 was received by the
complainant. It was urged by senior counsel for the developer that this court had
carefully restricted the remand to whether any liability arose due to any fault or
deficiency on its part, after April 2005, given that the Pay Order was not
encashed by the complainant. In this connection, it was submitted that Citibank
had categorically averred that the amount was deducted from the developer’s
account, when the Pay Order was issued. The bank also stated that the amount
did not earn any interest, and was kept separately, in accordance with
instructions and directives of the Reserve Bank of India (hereinafter, “RBI”).
The developer became aware that the Pay Order was part of the complaint filed
th
before the MRTP Commission for the first time on 29 April 2016, when a
statement was made by the complainant’s counsel.
14. It was submitted that this court recorded that the Pay Order was on the file
of the MRTP Commission, and consequently permitted its revalidation. It was
in these circumstances, that the developer approached the Commission,
10
resulting in revalidation and subsequent handing over of the instrument to the
complainant.
15. All these facts clearly established that the developer was not at fault; the
complainant in fact acknowledged having received the Pay Order, returned by
th
the developer, through letter dated 26 September 2005. Learned counsel relied
on the pleadings before the MRTP Commission, and pointed out that the index
to the complaint and the documents filed along with it, nowhere mentioned or
referred to the original Pay Order.
16. It was submitted that having returned the amount, through the medium of
the Pay Order, the developer had no further obligation to pay further interest
thereafter. It was submitted that the complainant would have been justified in
stating, if the facts were such that the amount was with the developer, or lying
in its account. However, once the amount was debited from its account, and the
Pay Order was made over to the complainant, who sought to return, it, but after
that, was handed back the Pay Order, the developer could not be held
responsible.
17. Counsel for the developer relied on Order XXI Rule 1(4) and (5) of the
Code of Civil Procedure, 1908 (hereinafter, “CPC”) to state that once the
amount in question was paid through the bank (i.e., through an instrument issued
by the bank, such as Demand Draft or Pay Order, as opposed to a cheque,
“ drawn on a bank ”) the liability would cease. Counsel for the developer relied
11
4
on the decisions in Hindustan Paper Corporation Ltd vs. Ananta Bhattacharjee
5
and in Gurpreet Singh vs. Union of India .
Analysis and Conclusion
18. For deciding this appeal, it is unnecessary to recount the entire spectrum of
facts and analyse the rival contentions, so far as they relate to the liability of the
th
developer for the period prior to 30 April 2005. The scope of the Tribunal’s
remit, in this case, was defined by this court's final order in the appeal decided
6
by it earlier. This court, after noticing that the developer had applied for
revalidation after the complainant had urged before the court that the Pay Order
had been deposited in the MRT Commission, further noted that the instrument
had been revalidated in 2016 and the amount was credited to the account of the
nd
developer on 22 May 2016. The court then proceeded to frame the scope of
the remand in the following terms:
“…To that limited extent, we propose to send back the matters to the
tribunal. Therefore, these appeals are disposed of as follows:
(1) Citibank NA represented by its manager, Jeevan Bharti building 124
Connaught Circus, New Delhi will stand impleaded as additional
respondent in the complaint before the Competition Appellate Tribunal,
New Delhi.
(2) the builder shall pay the compensation worked out at the rate of 15
percent compound interest up to 30-04-2005.
(3) whether there should be any compensation, and if so, what should
be the amount payable after 30-04-2005, and whether the Citibank's
liable to pay in interest to the account holder (sic)by the Tribunal.
To the above limited extent we remit the matters to the Competition
Appellate Tribunal, New Delhi.
It will be open to the parties to take all available contentions in respect
of the issues limited to, the Tribunal.”
4 th
Hindustan Paper Corporation Ltd vs. Ananta Bhattacharjee , (2004) 6 SCC 213, dated 28 April 2004.
5 th
Gurpreet Singh vs. Union of India , 2006 (8) SCC 457, dated 19 October 2006.
6
Supra note 3, para 9.
12
th
19. It is quite evident from the above that, with respect to the 30 April 2005
liability, this court had affirmed the findings of the COMPAT and also negatived
the contentions of the complainant’s legal heirs to the extent that separate
compensation other than compound interest was payable. The developer was
therefore directed to pay as a measure of compensation compound interest at
15% per annum for the entire period, i.e., 1993 to 2005. Since this court was
apprised of the fact that the complainant had deposited the Pay Order before the
MRTP Commission, it thought it appropriate to call for details from Citibank.
After considering the affidavit and the materials placed before it, this court
decided that the appropriate course would be to limit the matter to consider
whether for the duration after 2005, any liability could be attached to the
developer. That was the rationale for the limited scope of the remand.
20. The materials on record would disclose that in this case, after issuing
notice, the complainant returned the Pay Order received by her under cover of
th
letter dated 7 September 2005, however, the developer (in response to the
th
complainant’s notice), by letter dated 26 September 2005, denied the
allegations contained in the notice and also returned the Pay Order for ₹
th
4,53,750/- and the banker’s cheque for ₹ 1 lakh. It is also evident that on 7
October 2005, the complaint was filed. A copy of the complaint is on record.
Curiously, it contains no mention of the Pay Order, nor does it say that the
complainant filed the Pay Order in original along with the pleading. This is an
13
undeniable fact. Even the counter affidavit filed by the complainant in the
developer's appeal states that she:
“Bonafidely also deposited the Pay Orders dated 30-04-2005 in the
registry along with the complaint under protest in court.”
21. Since the pleadings in the complaint did not refer to the Pay Order, which
was attached in the original along with the complaint, the developer’s reply too
was silent on this aspect. This is evident from a bare reading of the reply to the
rd
complaint before the MRTP Commission filed by the developer on 3 February
2006. Likewise, the reply to the Notice of Enquiry, which was issued by the
MRTP Commission, and filed by the developer (supported by affidavit dated
th
25 January 2007) also does not allude to the Pay Order.
7
22. In the previous proceedings before this court, in the complainant’s appeal,
th
this court’s order, dated 29 April 2016 reads as follows:
“The learned counsel for the appellant submits that the Demand Drafts
furnished by the respondents have already been deposited before the
MRTP Commission. The respondents are free to move the Competition
commission for withdrawal of the amount.
We record the statement of the appellant that in case, such an attempt
is made by the respondents, the appellant shall not object the
withdrawal of the drafts/amounts”.
23. In terms of the leave granted by this court, through that order, the developer
moved an application before the COMPAT, which issued the following
th
directions on 18 May 2016:
“This is an application on behalf of respondent Nos. 1 and 2 for release
of Pay Order No. 885894 dated 30.04.2005 for Rs.4,53,750/- drawn in
favour of Dr. (Mrs.) Manjeet Kaur Monga for revalidation thereof in
the name of the legal representatives of Dr. (Mrs.) Manjeet Kaur
Monga.
7
Supra note 3.
14
Shri Aditya Narain, learned counsel for the applicants states that his
client will be satisfied if the pay order deposited in 2005 is returned to
his client for the purpose of renewal, if any, 1n accordance with. law.
Learned counsel for the representatives of the original complainant
says that she does not have any objection.
In view of the above, the application is allowed. The demand Draft No.
885894 dated 30.04.2005 lying in the registry of the Tribunal be
returned to the applicants.”
24. These developments were part of the record, and the court was aware of
th
them as a consequence of which the final order dated 18 July 2017, disposing
of the civil appeals, noted these facts:
“…During the course of hearing of the appeals another interesting
point came up for consideration. It has been brought to the notice of
this Court that when the builder company, the appellant in the appeals
arising out of SLP(C) Nos.10484-10485/2016, had taken the pay order
from the Citibank on 30.04.2005, the amount of Rs.4,53,750/- covered
by the pay order had actually been deducted from their current account.
But at the same time, the amount had not been paid/received by the
payee. In the instant case, the account bolder cancelled the pay order
and requested for re-credit of the amount and, accordingly, it is seen
that the Citibank has re-credited the amount to the account only on
22.06.2016. It is the contention of the account holder company that for
the period the money was with the Bank, the account holder is entitled
to interest and that can be the compensation if at all that can be paid to
the appellant in Civil Appeal Nos.5032-33/2016 for the period after the
cancellation of the allotment. We may, of course, take note of the
submission of the builder that in terms of the principles of restitution
under Section 144 C.P.C. and on the general principle of restitution,
the builder cannot be put to unmerited injustice and the appellant
should not take the undue advantage as held by this Court in Citibank
N.A. v. Hiten P. Dalal and Others, (2016) 1 SCC 411, as canvassed by
the learned counsel appearing for the builder.
7. Learned counsel appearing for Citibank, inviting our reference to the
additional affidavit contended that it is a fact that the money from the
current account of the builder has been deducted on 30. 04. 2005 and
it has not been paid to the payee. But, at the same time, it cannot be
said that the money was enjoyed by the Bank, since being a pay order,
at any moment the instrument is presented, the Bank was bound to
honour the same and, therefore, only for the lapse on the part of either
the payee or the account holder for encashing or cancelling the
instrument, the Bank cannot be saddled with any interest. It is also
submitted by the learned counsel appearing for the Bank that they are
governed by the instructions issued by the Reserve Bank of India in that
regard.
15
8. We find from the order of the Tribunal that both the issues have not
been gone into, apparently because these aspects have not been
canvassed and obviously because the Citibank was not before the
Tribunal.”
25. The counter affidavit filed by the complainant, to the developer’s appeal
presently before us, contains the following averments:
“It is reiterated that the said Pay Order was sent by the Appellant No.2
to Respondent No. 1 vide cancellation letter dated 30.04.2005.
Thereafter, the same was returned by Respondent No. l to the
Appellants vide legal notice dated 07.09.2005 following which the
Appellants once again returned the same back to Respondent No. l vide
their reply to the legal notice dated 26.09.2005. It is submitted that the
Respondent No. 1 then filed a Complaint under section 36 of the MRTP
Act before the Ld. MRTP Commission and deposited the said Pay Order
dated 30.04.2005 in protest before the Ld. MRTP Commission along
with the said Complaint.”
26. A consideration of the pleadings and other materials points to the fact that
the complainant did not state anywhere, before the MRTP Commission, that the
original Pay Order was attached with the pleadings . Interestingly, the index or
cover page to the complaint was made part of the additional written submissions
th
of the developer dated 12 February 2018 (before the NCLAT). This index to
the pleadings in the complaint did not refer to the Pay Order. It cannot be for a
moment disputed that the complainant was perhaps under a belief that filing
such an original Pay Order established that she was not interested in receiving
refund, but was interested only to secure possession of the flat. Nevertheless, it
was necessary for her to apply through counsel for an appropriate order to
ensure that the amount was deposited in an interest-bearing account . That step
unfortunately was not taken – perhaps she was not advised to do so. It was only
when for the first time when this was highlighted in the previous proceedings
th
on 29 April 2016, that the developer sought and obtained permission to apply
16
to the COMPAT for revalidation. The order facilitating that step was made on
th nd
18 May 2016, and eventually the Pay Order was revalidated on 22 June 2016.
27. From the impugned order, it is evident that the Tribunal accepted the
explanation of Citibank that since the Pay Order in question had become stale,
its proceeds / funds were moved to its ‘Unclaimed Sundry Account’, and did not
attract any interest in terms of the RBI directions. The bank had also deposed
that the Pay Order was cancelled on the request of the developer through its
th
letter dated 26 May 2016 and that the funds were credited back to the account
th
of the developer on 16 June 2016. It was further noticed that the amount for
issuing the Pay Order was deducted from the current account of the developer.
After noticing these facts, the Tribunal appears to have been swayed by the
circumstance that the developer was held liable for unfair trade practice, and
directed to pay compensation (in terms of the previous orders of the COMPAT)
affirmed by this court, i.e., 15% compound interest on ₹ 4,53,750/-.
28. In the opinion of this court, the impugned order has not rested its findings
on any principle of law, much less any statutory provision. The Tribunal appears
to have been completely swayed by the complainant's plight. In doing so, it did
not give due consideration to the fact that ₹ 4,53,750/- was debited from the
account of the developer. The complainant, for reasons best known to her, filed
the original Pay Order due to perhaps lack of proper advice or instruction.
Apparently, no order contemporaneously was sought from the MRTP
Commission, which would have protected the interests of the complainant with
17
respect to the money received even while ensuring that her contentions on the
merits with respect to entitlement towards the flat were preserved. Many
avenues / alternatives were available. Firstly , the complainant could have sought
for a deposit of the proceeds of the Pay Order in an account, to be maintained
by the Registrar of the Commission. Secondly , she could have sought for a
‘without prejudice’ order enabling her to encash the amount, and at the same
time ensure that her claim was not defeated on that score. Thirdly , equally, she
could have sought for appropriate orders that the amount be maintained by the
developer, who could, in the event it became necessary, be directed to pay the
principal along with such interest as the Commission or the Tribunal deemed
appropriate and in the interests of justice. Since none of these choices were opted
for, and also having regard to the fact that the amount in question was
undoubtedly debited from the developer's current account, there ought to have
been a discussion of what was the applicable legal provision which fastened any
liability upon the developer. This was more important because the Tribunal in
the present case has accepted Citibank’s explanation regarding interest (or
rather, its absence of liability, even though the amount was undoubtedly with
the bank for about 11 years).
29. This court, in Gurpreet Singh (supra), observed in the context of Order XXI
8
of CPC (which deals with modes of payment under decrees and also stipulates
when interest shall cease to “run” (i.e., not be payable)) as follows:
8
ORDER XXI Execution of Decrees and Orders Payment under Decree
18
“Thus, in cases of execution of money decrees or award decrees, or
rather, decrees other than mortgage decrees, interest ceases to run on
the amount deposited, to the extent of the deposit. It is true that if the
amount falls short, the decree holder may be entitled to apply the rule
of appropriation by appropriating the amount first towards the interest,
then towards the costs and then towards the principal amount due under
the decree. But the fact remains that to the extent of the deposit, no
further interest is payable thereon to the decree holder and there is no
question of the decree holder claiming a re-appropriation when it is
found that more amounts are due to him and the same is also deposited
by the judgment debtor. In other words, the scheme does not
contemplate a reopening of the satisfaction to the extent it has occurred
by the deposit. No further interest would run on the sum appropriated
towards the principal.
As an illustration, we can take the following situation. Suppose, a
decree is passed for a sum of Rs. 5,000/- by the trial court along with
interest and costs and the judgment debtor deposits the same and gives
notice to the decree holder either by approaching the executing court
under Order XXI Rule 2 of the Code or by making the deposit in the
execution taken out by the decree-holder under Order XXI Rule 1 of the
Code. The decree holder is not satisfied with the decree of the trial
court. He goes up in appeal and the appellate court enhances the decree
amount to Rs. 10,000/- with interest and costs. The rule in terms of
Order XXI Rule 1, as it now stands, in the background of Order XXIV
would clearly be, that the further obligation of the judgment debtor is
only to deposit the additional amount of Rs. 5,000/- decreed by the
1. Modes of paying money under decree.— (1) All money, payable under a decree shall be paid as follows,
namely:—
(a) by deposit into the court whose duty it is to execute the decree, or sent to that Court by postal money order
or through a bank; or
(b) out of Court, to the decree-holder by postal money order or through a bank or by any other mode wherein
payment is evidenced in writing; or
(c) otherwise, as the Court which made the decree, directs.
(2) Where any payments is made under clause (a) or clause (c) of sub-rule (1), the judgment-debtor shall give
notice thereof to the decree-holder either through the Court or directly to him by registered post,
acknowledgment due.
(3) Where money is paid by postal money order or through a bank under clause (a) or clause (b) of sub-rule
(1), the money order or payment through bank, as the case may be, shall accurately state the following
particulars, namely:—
(a) the number of the original suit;
(b) the names of the parties or where there are more than two plaintiffs or more than two defendants, as the
case may be, the names of the first two plaintiffs and the first two defendants;
(c) how the money remitted is to be adjusted, that is to say, whether it is towards the principal, interest or costs;
(d) the number of the execution case of the Court, where such case is pending; and
(e) the name and address of the payer.
(4) On any amount paid under clause (a) or clause (c) of sub-rule (1), interest, if any, shall cease to run from
the date of service of the notice referred to in sub-rule (2).
(5) On any amount paid under clause (b) of sub-rule (1), interest, if any, shall cease to run from the date of such
payment:
Provided that, where the decree-holder refuses to aceept the postal money order or payment through a bank,
interest shall cease to run from the date on which the money was tendered to him, or where he avoids acceptance
of the postal money order or payment through bank, interest shall cease to run from the date on which the money
would have been tendered to him in the ordinary course of business of the postal authorities or the bank, as the
case may be.”
19
appellate court with interest thereon from the date the interest is held
due and the costs of the appeal. The decree holder would not be entitled
to say that he can get further interest even on the sum of Rs. 5,000/-
decreed by the trial court and deposited by the judgment debtor even
before the enhancement of the amount by the appellate court or that he
can re-open the transaction and make a re-appropriation of interest
first on Rs. 10,000/-, costs and then the principal and claim interest on
the whole of the balance sum again. Certainly, at both stages, if there
is short-fall in deposit, the decree holder may be entitled to apply the
deposit first towards interest, then towards costs and the balance
towards the principal. But that is different from saying that in spite of
his deposit of the amounts decreed by the trial court, the judgment
debtor would still be liable for interest on the whole of the principal
amount in case the appellate court enhances the same and awards
interest on the enhanced amount.”
V. Kala Bharathi
30. The rule was explained in another decision of this court, in
9
& Ors. vs The Oriental Insurance Company Ltd:
“A bare perusal of the aforesaid provisions makes it amply clear that
the scope of Order XXI Rule 1 of the Code of Civil Procedure is that the
judgment debtor is required to pay the decretal amount in one of the
modes specified in Sub-rule (1) thereof. Sub-rule (2) of Rule 1 provides
that once payment is made Under Sub-rule (1), it is the duty of the
judgment debtor to give notice to the decree-holder through the Court
or directly to him by registered post acknowledgement due. Sub-rule (3)
of Rule 1 merely indicates that in case money is paid by postal money
order or through a bank under Clause (a) or Clause (b) of Sub-rule (1)
thereof, certain particulars are required to be accurately incorporated
while making such payment. Sub-rules (4) and (5) of Rule 1 states from
which date, interest shall cease to run-in case amount is paid under
Clause (a) or (c) of Sub-rule (1), interest shall cease to run from the
date of service of notice as indicated Under Sub-rule (2); while in case
of out of court payment to the decree-holder by way of any of the modes
mentioned under Clause (b) of Sub-rule (1), interest shall cease to run
from the date of such payment.”
31. The provisions of Order XXI are applicable to decrees of civil court.
However, they embody a sound policy principle, that if the amount is deposited,
or paid to the decree holder or person entitled to it, the person entitled to the
amount cannot later seek interest on it. This is a rule of prudence, inasmuch as
the debtor, or person required to pay or refund the amount, is under an obligation
9 st
V. Kala Bharathi & Ors. vs The Oriental Insurance Company Ltd ., 2014 (5) SCC 577, dated 1 April 1947.
20
to ensure that the amount payable is placed at the disposal of the person entitled
to receive it. Once that is complete (in the form of payment, through different
modes, including tendering a Banker’s Cheque, or Pay Order or Demand Draft,
all of which require the account holder / debtor to pay the bank, which would
then issue the instrument) the tender, or ‘payment’ is complete.
32. In the present case, the complainant was aware that the Pay Order had been
tendered by the developer to her; nevertheless she filed the original Pay Order
with her complaint, and did not seek any order from the MRTP Commission at
the relevant time. The pleadings in the complaint did not disclose that the Pay
Order was filed in the Commission, to enable the developer to respond
appropriately. In these circumstances, the developer’s argument that the rule
embodied in Order XXI, Rule 4 CPC, is applicable, is merited. The developer
cannot be fastened with any legal liability to pay interest on the sum of ₹
th
4,53,750/- after 30 April 2005.
33. This court is also of the opinion that the complainant’s argument that on
account of the omission of the developer, she was wronged, and was thus
entitled to receive interest, cannot prevail. The records nowhere disclose any
fault on the part of the developer; on the other hand, the complainant did not
take steps to protect her interests. It has been held by this court, in Sailen Krishna
10
Majumdar v Malik Labhu Masih that in such cases, even if equities are equal, the
court should not intervene:
10 st
Sailen Krishna Majumdar vs. Malik Labhu Masih, 1989 (1) SCR 817, dated 21 February 1989.
21
“Equity is being claimed by both the parties. Under the circumstances
we have no other alternative but to let the loss lie where it falls. As the
maxim is, 'in aequali jure melior est conditio possidentis'. Where the
equities are equal, the law should prevail. The respondent's right to
purchase must, therefore, prevail.”
In the present case too, the complainant cannot claim interest from the
developer, who had returned the Pay Order. As discussed, at the time of filing
of the complaint, she could have chosen one among the various options to ensure
that the amount presented to her was kept in an interest-bearing account, without
prejudice to her rights to claim interest later. In these circumstances, no equities
can be extended to her aid.
34. As regards the complainant’s appeal, the contention is that the impugned
order is in error, because the Tribunal ought to have directed that the developer
th
ought to have been directed to pay interest on the sum of ₹ 4,53,750/- from 4
th
October 1993 till the date of its realization i.e., 7 May 2016. This plea is plainly
untenable, because the interest payable for the past period was concluded in the
previous proceedings. The complainant did not point to any rule or binding legal
principle which obliged the developer to pay such interest, or justify the
direction in the impugned order, by showing how such liability arose in the facts
and circumstances of this case.
35. Before parting with this case, this court is of the opinion that all courts and
judicial forums should frame guidelines in cases where amounts are deposited
with the office / registry of the court / tribunal, that such amounts should
mandatorily be deposited in a bank or some financial institution , to ensure that
no loss is caused in the future. Such guidelines should also cover situations
22
where the concerned litigant merely files the instrument (Pay Order, Demand
Draft, Banker’s Cheque, etc.) without seeking any order , so as to avoid
situations like the present case. These guidelines should be embodied in the form
of appropriate rules, or regulations of each court, tribunal, commission,
authority, agency, etc. exercising adjudicatory power.
36. In view of the above discussion, the developer’s appeal, i.e., C.A. No. 1401
of 2019 is allowed. The impugned order is hereby set aside. The complainant’s
appeal, i.e., C.A. No. 4530 of 2019, is dismissed. There shall be no order on
costs.
...............................................J.
[ M.R. SHAH ]
| ..............................................J. | |
| [S. RAVINDRA BHAT] | |
| NEW DELHI, | |
| JANUARY 31, 2023. |