2024 INSC 458
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6458 OF 2024
(@ PETITION FOR SPECIAL LEAVE TO APPEAL (CIVIL) NO. 29970 OF 2017)
SUBODH SINGH PETITIONER
VERSUS
UNION OF INDIA AND OTHERS RESPONDENTS
O R D E R
1. Leave granted.
| The present appeal is directed against the order dated 31 | st | August, 2017, |
|---|
passed by the Division Bench of the High Court of Judicature at Allahabad whereby, the
| Writ Petition filed by the appellant herein praying | inter alia | for issuing directions to the |
|---|
respondents to pay additional compensation for the entire land area, subject matter of
| the Notification dated 12 | th | December, 2008, issued under Section 20(E)(1) of the Indian |
|---|
| Railways Act | 1 | , 1989, at the rate higher than 5% per month and further pay interest @ |
|---|
| 18% per annum for delay in payment from 30 | th | March, 2011, i.e. the date on which this |
|---|
| Court had passed an order in Civil Appeal No. 2794 of 2011 | 2 | titled “ | Dedicated Freight |
|---|
Signature Not Verified
| Corridor Corporation of India Vs. Subodh Singh | ”, till the actual date of payment |
|---|
Digitally signed by
Nirmala Negi
Date: 2024.06.12
12:02:31 IST
Reason:
1 For short the ‘Act’
2 (2011) 11 SCC 100
1
| in respect of the award dated 08 | th | February, 2010. |
|---|
3. It is submitted on behalf of the appellant that the respondents had acquired
| land in Village Kakrahi, Tehsil and District Auriya, Uttar Pradesh | vide | Notifications |
|---|
| dated 10 | th | June, 2008 and 16 | th | December, 2008 issued under Section 20(E)(1) of the |
|---|
| Act. An award was declared on 08 | th | February, 2010 only in respect of the land that |
|---|
the respondents required. As a result, a parcel of land admeasuring 0.0624 Hectare
| was left out. Aggrieved by the said action, the appellant filed a Writ Petition | 3 | before |
|---|
| the High Court for quashing the award dated 08 | th | February, 2010, which was allowed |
|---|
| vide | order dated 12 | th | May, 2010. Challenging the said order, the respondents filed a |
|---|
| Petition for Special Leave to Appeal | 4 | before this Court, which was allowed | vide |
|---|
| judgment dated 30 | th | March, 2011 holding | inter alia | that the acquisition in question had |
|---|
not lapsed and having regard to the second proviso to section 20F(2) of the Act, the
land owners would be entitled to an additional compensation for the delay in making
| the payment in terms of the award dated 08 | th | February, 2010, at a rate not less than |
|---|
5% of the value of the award for each month of delay.
4. Pursuant to the aforesaid order, the respondent no.2 issued a certificate in
| respect of the entire parcel of land in terms of the Notification dated 12th | December, |
|---|
2008, again leaving an area of 0.0624 Hectare as free from acquisition proceedings.
| Being aggrieved by the said decision, the appellant filed another petition | 5 before the |
|---|
Writ C. No. 14945/2010
3
4 SLP(Civil) No. 26410 of 2010 (i.e. Civil Appeal No. 2794/2011)
5 Writ C. No. 63467/2011
2
| High Court, which was allowed | vide | order dated 20 | th | September, 2016 and the |
|---|
respondents were directed to provide compensation to the appellant for 0.0624
Hectare of land along with additional compensation within a period of two months.
| On 19 | th | November, 2016, the respondents prepared a bank draft for a sum of |
|---|
| ₹ | 2,74,56,000/- (Rupees Two Crores Seventy Four Lakh Fifty Six Thousand) stating |
|---|
that the same was in respect of the compensation payable to the appellant in terms of
| the order passed by the High Court on 20 | th | September, 2016. While calculating the |
|---|
additional compensation, the respondent no.2 confined the same to a period of two
months for the delayed period.
6. Aggrieved by the compensation offered by the respondents limiting the delay
to only two months, the appellant approached the High Court by filing yet another
| petition | 6 | claiming that he was entitled to compensation for a period of 84 months, |
|---|
which would come to Rs.10,23,28,000/- (Rupees Ten Crores Twenty Three Lakh and
| Twenty Eight Thousand), on which the impugned order dated 31 | st | August, 2017, has |
|---|
been passed observing that the appellant ought to approach the Arbitrator for
determining the additional compensation, by invoking Section 20F (1) of the Act.
7. It is submitted on behalf of the appellant that the respondents have adopted a
pick and choose policy in the instant case. While they have paid additional
compensation for a period of delay of 66 months to one Smt. Kamla Devi & Ors., who
were similarly situated persons like the appellant and their land was also acquired
6 Writ C No. 39875/2017
3
under the very same award, in the case of the appellant the respondents have
arbitrarily confined the payment towards the delay only to two months, instead of 84
months.
8. We have perused the record and heard the arguments advanced by learned
counsel for the parties.
| At the outset, we may note that the order dated 18 | th | September, 2017, passed |
|---|
| by the Competent Authority refers to an order dated 19 | th | July, 2017, passed by the |
|---|
| High Court in a Writ Petition | 7 | filed by Kamla Devi and others and goes on to record |
|---|
that after completion of formalities of publication, some portion of the land
admeasuring 0.0890 Hectare had been left out, as the same was not required for the
| subject project. Subsequently, another award | 8 | was declared in respect of the left out |
|---|
area and additional compensation was paid to the land owners @ 5% per month of
| the award for a period of 66 months, i.e. from 19 | th | April, 2012 to 12 | th | September, 2017. |
|---|
In the light of the above, the appellant herein is justified in arguing that he cannot be
treated differently and in his case, the respondents ought not to have confined the
delayed payment on the awarded amount for the left out portion of land to only two
months.
10. The aforesaid submission is disputed by learned counsel for the respondents
on a plea that no such direction was issued either by this Court or the High Court
permitting compensation for the delayed period beyond two months, for which
| Award No. 1/2011-12, dated 19 | th | April, 2012 |
|---|
4
| reliance is sought to be placed on the order dated 20 | th | September, 2016 passed by |
|---|
the High Court.
11. The aforesaid submission is taken note of only to be turned down. The period
| of two months referred to by the High Court in its order dated 20 | th | September, 2016 |
|---|
was only for making payment of the amount. Not that any direction was issued to the
respondents to confine the payment of additional compensation only to a period of
| two months. In fact, the order passed by this Court on 30 | th | March, 2011 is crystal |
|---|
clear and needs no interpretation. Highlighting certain anomalies noticed in Chapter
IV A of the Act, particularly Section 20F, this Court referred to the proviso to Section
20F (2) and observed as follows:
“12. (iii) The second proviso to section 20F (2) requires payment of additional
compensation for the delay in making of the award, at the rate of not less
than five percent of the value of award, for each month of delay. This vests
unguided discretion in the competent authority or the Arbitrator to award
additional compensation at any higher rate and gives room for unnecessary
litigation at the instance of “entitled persons” claiming higher percentages as
additional compensation. It is necessary to consider whether specifying a
fixed monthly rate of increase would serve the ends of justice better instead
of indicating a minimum rate per month.
xxxx xxxx xxxx
“13. In view of our finding that the acquisition has not lapsed, we allow this
appeal, set aside the judgment of the High Court, and dismiss the challenge
to the acquisition. It is however made clear that in view of the delay in making
the award beyond one year, the first respondent shall be entitled to additional
compensation as provided under the second proviso to section 20F (2) of the
Act. Parties to bear their respective costs.”
12. It is apparent from the above that the appellant would be entitled to additional
compensation for the delay in making the award @ not less than 5% of the value of
the award for each month’s delay. In our opinion, there was no reason for the High
5
Court to have relegated the appellant to initiate any arbitration proceedings for
determining the additional compensation when the order passed by this Court had
clarified the manner in which compensation would be calculated and paid for the
delay in making the award for the left out parcel of land.
13. In view of the above discussion, the present appeal succeeds. The appellant
is held entitled to additional compensation for the left out portion of land at least @
5% of the value of the award for a period spreading over 84 months. Needless to
state that the amount already paid by the respondents towards the delay, i.e., for a
period of two months, shall be duly adjusted. The remaining amount shall be released
by the respondents within eight weeks from today. Besides the aforesaid amount, the
appellant shall also be entitled to simple interest on the outstanding amount
calculated @ 7% per annum from the date the said amount became due and payable,
till the same is realized.
14. The appeal is allowed on the above terms while leaving the parties to bear
their own expenses.
.....…...........…………………......J.
[HIMA KOHLI]
..................……………………...J.
[AHSANUDDIN AMANULLAH]
NEW DELHI
MAY 16, 2024
PS
6