SUBODH SINGH vs. UNION OF INDIA

Case Type: Civil Appeal

Date of Judgment: 16-05-2024

Preview image for SUBODH SINGH vs. UNION OF INDIA

Full Judgment Text

2024 INSC 458 REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 6458 OF 2024 (@ PETITION FOR SPECIAL LEAVE TO APPEAL (CIVIL) NO. 29970 OF 2017) SUBODH SINGH PETITIONER VERSUS UNION OF INDIA AND OTHERS RESPONDENTS O R D E R 1. Leave granted.
The present appeal is directed against the order dated 31stAugust, 2017,
passed by the Division Bench of the High Court of Judicature at Allahabad whereby, the
Writ Petition filed by the appellant herein prayinginter aliafor issuing directions to the
respondents to pay additional compensation for the entire land area, subject matter of
the Notification dated 12thDecember, 2008, issued under Section 20(E)(1) of the Indian
Railways Act1, 1989, at the rate higher than 5% per month and further pay interest @
18% per annum for delay in payment from 30thMarch, 2011, i.e. the date on which this
Court had passed an order in Civil Appeal No. 2794 of 20112titled “Dedicated Freight
Signature Not Verified
Corridor Corporation of India Vs. Subodh Singh”, till the actual date of payment
Digitally signed by Nirmala Negi Date: 2024.06.12 12:02:31 IST Reason: 1 For short the ‘Act’ 2 (2011) 11 SCC 100 1
in respect of the award dated 08thFebruary, 2010.
3. It is submitted on behalf of the appellant that the respondents had acquired
land in Village Kakrahi, Tehsil and District Auriya, Uttar PradeshvideNotifications
dated 10thJune, 2008 and 16thDecember, 2008 issued under Section 20(E)(1) of the
Act. An award was declared on 08thFebruary, 2010 only in respect of the land that
the respondents required. As a result, a parcel of land admeasuring 0.0624 Hectare
was left out. Aggrieved by the said action, the appellant filed a Writ Petition3before
the High Court for quashing the award dated 08thFebruary, 2010, which was allowed
videorder dated 12thMay, 2010. Challenging the said order, the respondents filed a
Petition for Special Leave to Appeal4before this Court, which was allowedvide
judgment dated 30thMarch, 2011 holdinginter aliathat the acquisition in question had
not lapsed and having regard to the second proviso to section 20F(2) of the Act, the land owners would be entitled to an additional compensation for the delay in making
the payment in terms of the award dated 08thFebruary, 2010, at a rate not less than
5% of the value of the award for each month of delay. 4. Pursuant to the aforesaid order, the respondent no.2 issued a certificate in
respect of the entire parcel of land in terms of the Notification dated 12thDecember,
2008, again leaving an area of 0.0624 Hectare as free from acquisition proceedings.
Being aggrieved by the said decision, the appellant filed another petition5 before the
Writ C. No. 14945/2010 3 4 SLP(Civil) No. 26410 of 2010 (i.e. Civil Appeal No. 2794/2011) 5 Writ C. No. 63467/2011 2
High Court, which was allowedvideorder dated 20thSeptember, 2016 and the
respondents were directed to provide compensation to the appellant for 0.0624 Hectare of land along with additional compensation within a period of two months.
On 19thNovember, 2016, the respondents prepared a bank draft for a sum of
2,74,56,000/- (Rupees Two Crores Seventy Four Lakh Fifty Six Thousand) stating
that the same was in respect of the compensation payable to the appellant in terms of
the order passed by the High Court on 20thSeptember, 2016. While calculating the
additional compensation, the respondent no.2 confined the same to a period of two months for the delayed period. 6. Aggrieved by the compensation offered by the respondents limiting the delay to only two months, the appellant approached the High Court by filing yet another
petition6claiming that he was entitled to compensation for a period of 84 months,
which would come to Rs.10,23,28,000/- (Rupees Ten Crores Twenty Three Lakh and
Twenty Eight Thousand), on which the impugned order dated 31stAugust, 2017, has
been passed observing that the appellant ought to approach the Arbitrator for determining the additional compensation, by invoking Section 20F (1) of the Act. 7. It is submitted on behalf of the appellant that the respondents have adopted a pick and choose policy in the instant case. While they have paid additional compensation for a period of delay of 66 months to one Smt. Kamla Devi & Ors., who were similarly situated persons like the appellant and their land was also acquired 6 Writ C No. 39875/2017 3 under the very same award, in the case of the appellant the respondents have arbitrarily confined the payment towards the delay only to two months, instead of 84 months. 8. We have perused the record and heard the arguments advanced by learned counsel for the parties.
At the outset, we may note that the order dated 18thSeptember, 2017, passed
by the Competent Authority refers to an order dated 19thJuly, 2017, passed by the
High Court in a Writ Petition7filed by Kamla Devi and others and goes on to record
that after completion of formalities of publication, some portion of the land admeasuring 0.0890 Hectare had been left out, as the same was not required for the
subject project. Subsequently, another award8was declared in respect of the left out
area and additional compensation was paid to the land owners @ 5% per month of
the award for a period of 66 months, i.e. from 19thApril, 2012 to 12thSeptember, 2017.
In the light of the above, the appellant herein is justified in arguing that he cannot be treated differently and in his case, the respondents ought not to have confined the delayed payment on the awarded amount for the left out portion of land to only two months. 10. The aforesaid submission is disputed by learned counsel for the respondents on a plea that no such direction was issued either by this Court or the High Court permitting compensation for the delayed period beyond two months, for which
Award No. 1/2011-12, dated 19thApril, 2012
4
reliance is sought to be placed on the order dated 20thSeptember, 2016 passed by
the High Court. 11. The aforesaid submission is taken note of only to be turned down. The period
of two months referred to by the High Court in its order dated 20thSeptember, 2016
was only for making payment of the amount. Not that any direction was issued to the respondents to confine the payment of additional compensation only to a period of
two months. In fact, the order passed by this Court on 30thMarch, 2011 is crystal
clear and needs no interpretation. Highlighting certain anomalies noticed in Chapter IV A of the Act, particularly Section 20F, this Court referred to the proviso to Section 20F (2) and observed as follows: “12. (iii) The second proviso to section 20F (2) requires payment of additional compensation for the delay in making of the award, at the rate of not less than five percent of the value of award, for each month of delay. This vests unguided discretion in the competent authority or the Arbitrator to award additional compensation at any higher rate and gives room for unnecessary litigation at the instance of “entitled persons” claiming higher percentages as additional compensation. It is necessary to consider whether specifying a fixed monthly rate of increase would serve the ends of justice better instead of indicating a minimum rate per month. xxxx xxxx xxxx “13. In view of our finding that the acquisition has not lapsed, we allow this appeal, set aside the judgment of the High Court, and dismiss the challenge to the acquisition. It is however made clear that in view of the delay in making the award beyond one year, the first respondent shall be entitled to additional compensation as provided under the second proviso to section 20F (2) of the Act. Parties to bear their respective costs.” 12. It is apparent from the above that the appellant would be entitled to additional compensation for the delay in making the award @ not less than 5% of the value of the award for each month’s delay. In our opinion, there was no reason for the High 5 Court to have relegated the appellant to initiate any arbitration proceedings for determining the additional compensation when the order passed by this Court had clarified the manner in which compensation would be calculated and paid for the delay in making the award for the left out parcel of land. 13. In view of the above discussion, the present appeal succeeds. The appellant is held entitled to additional compensation for the left out portion of land at least @ 5% of the value of the award for a period spreading over 84 months. Needless to state that the amount already paid by the respondents towards the delay, i.e., for a period of two months, shall be duly adjusted. The remaining amount shall be released by the respondents within eight weeks from today. Besides the aforesaid amount, the appellant shall also be entitled to simple interest on the outstanding amount calculated @ 7% per annum from the date the said amount became due and payable, till the same is realized. 14. The appeal is allowed on the above terms while leaving the parties to bear their own expenses. .....…...........…………………......J. [HIMA KOHLI] ..................……………………...J. [AHSANUDDIN AMANULLAH] NEW DELHI MAY 16, 2024 PS 6