Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
M/S DURGA RAM PRASAD
Vs.
RESPONDENT:
GOVT. OF ANDHRA PRADESH
DATE OF JUDGMENT23/11/1994
BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
REDDY, K. JAYACHANDRA (J)
CITATION:
1995 SCC (1) 418 JT 1995 (2) 86
1994 SCALE (5)42
ACT:
HEADNOTE:
JUDGMENT:
ORDER
1. These appeals by special leave arise from the judgment
of the Division Bench
of the Andhra Pradesh High Court in Memo of Cross Objection
in C.M.A No.191/75 dated 23.4.75. The appellant had entered
into a contract on 16.3.65 to construct foodgrains godown at
Karimnagar. In execution thereof, a dispute had arisen
whether the appellant had executed the work as per the
contract and is entitled to certain sums of money withheld
by the engineer and also to the interest payable thereon at
12% etc. The dispute has been referred to the Arbitrator, a
retired Chief Engineer, who in his Award dated 12.4.72
awarded a sum of Rs.27,776/ - with interest at 12% on the
amounts wrongfully withheld by the Engineer. We are
concerned in these appeals only with the entitlement of
interest on the amounts withheld by the engineer. The
Division Bench concluded, while negativing the claim for
interest, thus:
"We are, however, inclined to agree with the
first ground given by the Court below in
negativing the claim for interest. Under
clause 69 of M.D.S.S. which has to be treated
as part of the contract, it is provided "nor
shall the contractor be entitled to interest
upon any guarantee fund or payments in
arrears, nor upon any balance which may, on
the final settlement of his accounts, be found
to be due to him". Even if it is assumed that
the recoveries from the bills were wrongfully
made, such sums would be sums which would be
found due to the contractors on the final
settlement of accounts".
2. We are not concerned with the correctness of the views
expressed on other issues as the State did not file appeals.
Shri Kanta Rao, the learned counsel for the appellant
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
contended that when the appellant had executed the work
within the period- in terms of the contract, and the
officials of the respondent had wrongfully withheld the due
payment on the respective dates, the appellant is entitled
to the interest on the amounts wrongfully withheld. He
further contends that clause 69 of the M.D. S. S.. is
inapplicable to the facts of this situation. In support
thereof, he places reliance on the judgment of a learned
single Judge of that Court reported in A.P.S.R.TC. v. P.
Ramana Reddi, 1989 (1) ALT 195.
3.The question, therefore, is whether the appellant is
entitled to payment of interest from the respective dates on
which the amounts were withheld by the concerned engineer
and the dispute is arbitrable?
4. Clause 69 of M.D.S.S. reads thus:
"69. Interest on money due to the con-
tractor:-
(a)No omission by the Executive Engineer or
the Sub-Divisional officer to pay the amount
due upon certificates shall vitiate or make
void the contract, nor shall be contractor be
entitled to interest upon any guarantee found
or payments in arrear, nor upon any balance
which may, on the final settlement of his
accounts, be found to be due to him".
5. A reading of this clause gives an indication that
interest on money due to the contractor was negatived in the
following circumstances:
1)the omission by the Executive Engineer or Sub-Divisional
officer to pay the amount due upon certificates shall not
vitiate or make the contract void;
2)the contractor shall not be entitled to interest upon:
a) any guarantee found;
88
b) payments in arrears; and
c) upon any balance which may on final settlement of his
account to be found to be due to him. The question is
whether the contractor is entitled to the payment of
interest on the amounts wrongfully withheld from the
respective dates. Clause (c) of the second part of clause
69 of the MDSS would indicate that there should be a final
settlement of the account and upon its settlement, if it is
found to be due and payable to the contractor, on such
amount also the contractor is not entitled to the payment of
interest as contracted under clause 69 of the NOSS. When
such is the position, whether the contractor is entitled to
payment of interest on mere making a claim and reference
made to the arbitrator and whether the arbitrator gets
jurisdiction to award interest on the amount due from the
respective dates on which the payments were withheld by the
concerned engineer?
6. It is true that the learned single Judge of the A.P.
High Court appears to have considered the question and the
construction of clause 69 was put up is in favour of the
contractor as contended for. It is not a correct approach.
The construction put up on clause 69 of MDSS is not correct.
However, on the facts in that case there does not appear to
be any dispute as to the amount due. Therefore, the learned
judge had proceeded that since the contract provides for
withholding the payment for a suspended period of six
months, if the amount is withheld beyond that period, the
contractor would be entitled to the payment of interest.
That is not the factual scenario in this case. The very
dispute is whether the appellant is entitled to the Payment
of the amount pursuant to the contract. The claim of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
State appears to be that the appellant had not constructed
the godown in accordance with the specifications and that,
therefore, they withheld the payment. Unless the dispute is
resolved and the amount is found due, the contractor is not
entitled to the payment of it. Thereon interest in terms of
clause 69 of the MDSS is contracted out. When such be the
position, then mere reference does Five jurisdiction to the
arbitrator to award interest to the period prior to the
reference.
7. This Court in Executive Engineer (Irrigation) v.
Abhaduta Jena, 1988 (1) SCC 418, in para 20 held that:
"In the remaining cases which arose before the
commencement of the Interest Act, 1978, the
respondents are not entitled to claim interest
either before the commencement of the
proceedings.......... They are not entitled to
claim interest for the period prior to the
commencement of the arbitration proceedings
for the reason that the Interest Act, 1839
does not apply to their cases and there is no
agreement to pay interest or any usage of
trade having the force of law or any other
provision of law under which the claimants
were entitled to recover interest".
This ratio was followed by another Bench of this Court in
State of Orissa v. Niranjan Swain, 1989 (4) SCC 269. In
Secretary, Irrigation Department v. G.C. Roy, 1992(1) SCC
508, the Constitution Bench was concerned with the case
whether the contractor is entitled to interest pendente
lite. The controversy, therefore, centres round the
question whether the contractor is entitled to the interest
pendente lite. The ratio therein, therefore, has no
relevance for the purpose of this case. The ratio in Jena’s
case on the above
89
quoted ratio is still good law. Accordingly, we are of the
view that the contractor is not entitled to payment of
interest in terms of clause 69 of NDSS for the period
anterior to the reference for arbitration until the final
settlement of the amount due to the contractor of his
account is determined. In this case that dispute was
determined by the arbitrator in his award.Therefore, from
the date of withholding till the date of award the appellant
is not entitled to the payment of interest. The arbitrator
has no jurisdiction to arbitrate that dispute. The Division
Bench, therefore, rightly negatived the claim for interest.
8. The appeals are accordingly dismissed, but in the
circumstances, without costs.