Full Judgment Text
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 1182 OF 2003
State of West Bengal and others .......Appellants
Versus
Prafulla Churan Law and others ......Respondents
WITH
CIVIL APPEAL NO. 1183 OF 2003
J U D G M E N T
The appellants are aggrieved by the order of the Calcutta High Court,
which annulled the invoking of Section 17 of the Land Acquisition Act,
1894 (for short, “the Act”) by the State Government for the acquisition of
premises No. 14 and 12/1, Hare Street, Calcutta.
There is no dispute between the parties that possession of the
premises in question was taken by the Government before independence in
March, 1944 by invoking the provisions of the Defence of India Act. After
15 years, the State Government issued order dated 30.9.1959 under Section
3(1) of the West Bengal Premises Requisition and Control (Temporary
2
Provisions) Act, 1947 (for short, “the 1947 Act”) for requisition of the
premises.
After 31 years, the respondents filed Writ Petition No.3601 of
1990 questioning the continued possession of the premises by the appellants.
The learned Single Judge of the High Court allowed the writ petition and
issued a mandamus for restoration of the premises to the respondents.
Notification dated 27.8.1990, issued by the State Government under Section
4(1) of the Act for acquisition of the premises, was quashed by the High
Court in Writ Petition No. 1382 of 1991. Thereafter, the respondents filed
Writ Petition No. 3790 of 1993 and reiterated their prayer for restoration of
possession. The learned Single Judge allowed the writ petition and directed
that the possession of the premises be delivered to the writ petitioners within
four months. At the same time, he made it clear that during this period the
concerned authorities may acquire the property in accordance with law and
observed that if the property is acquired within that period, the question of
handing over the possession will not arise. The respondents challenged the
latter part of the order of the learned Single Judge in Appeal No. 35 of 1994,
which was disposed of by the Division Bench vide order dated 18.4.1994,
the relevant portions of which are extracted below:
“We are conscious of the contentions raised by the appellants in
this regard, but we think that we cannot prevent the State
authorities to acquire the premises in question in accordance
3
with the law after ad-hearing to the proper formulates as
delineated in the statute. Some steps have already been taken in
this regard in the meantime. Till such time the acquisition
proceedings are complete, the respondents cannot however take
advantage of the situation and continue at the old rate of
compensation which was fixed amount 40 to 50 years before.
In one case the requisition was made in 1944 and in other case
it was in 1956.
We would, accordingly, direct the respondent authorities to pay
by way of ad-interim measure a monthly compensation at the
rate of Rs.10/- per sq.ft. confirming to the market rate for their
occupation with a further direction upon the State respondents
to complete the acquisition proceeding within a period of six
months from this date. If this proceeding are not complete by
that date, the mandate as passed by the learned trial Judge
should definitely be operative and the writ petitioners, the
present appellants, would be entitled to get back the possession
of the disputed premises in accordance with law.”
Special Leave Petition (C) No. 4899 of 1996 filed by the
respondents was dismissed by this Court on 28.2.1996 with liberty to them
to claim damages for the occupation of the premises for the period between
the date on which the term of requisition came to an end and the date on
which the acquisition proceedings were initiated.
In the meanwhile, the State Government issued notification
dated 19.7.1994 under Section 4(1) read with Section 17(4) of the Act for
acquisition of the premises in question for the purpose of providing
permanent accommodation to the unit of Cottage and Small Scale Industries,
Bangasree and also for West Bengal Ceramic Development Corporation.
4
This was followed by notification under Section 6, which was published on
18.7.1995.
The respondents challenged the aforementioned notifications in
Writ Petition No. 870 of 1996 on several grounds including the one that
there was no valid ground for invoking Section 17(4) of the Act, which
resulted in depriving them of the right to file objection under Section 5-A. It
was pleaded that the purpose of acquisition was not such which could justify
dispensing with the inquiry envisaged under Section 5-A.
The learned Single Judge dismissed the writ petition by
observing that the decision of the State Government to invoke Section 17(4)
was legally correct and justified and the power of judicial review cannot be
exercised to interfere with the subjective satisfaction on the issue of urgency.
The Division Bench allowed the appeal filed by the respondents and quashed
the acquisition by recording the following observations:
“The virtue of a public enquiry case not be overstressed. It is
the very heart and soul of the rule of law. It stops high
handed action. It stops mere repetition or words found in
Act, when such repetition lacks substance, in the facts and
circumstances of a particular case. This is the reason why
such a hearing is usually compartmentalized as an important
compartment of the rules of natural justice. Had there been a
public enquiry, in a usual manner, the parties would know,
what is the reason for their losing their right to their property;
in that event, the court would also be in the know of far more
facts. When approving or disapproving of acquisition
5
proceedings, the details and the facts are necessary and
important, not only for the parties, but also for the court.
Here we know nothing. Everything has been short – circuited
by preliminary notifications doing away with public enquiry
without ever even trying to put it afoot. The Government
proceeded with a closed mind, in an authoritarian way,
paying attention only to words being repeated in the
Notifications, exactly as those appear in the L.A. Act.
We are thus of the opinion that both the notifications in
regard to both the premises issued in a combined way under
section 4 and 17(4) were the products of a closed mind,
which was already made up, that the premises being in the
possession of the government undertakings, would be kept by
such government undertakings, and a compensation would be
awarded to the public parties. The whole proceedings show
such a closed mind. The appellants had lost their property as
soon as the combined notice under section 4 and 17(4) had
been published.
In our opinion, this manner of proceeding to acquire land
vitiates the entire acquisition proceedings. Dispensing with
hearing of objections, when there was no real urgency, is a
fatal infirmity.”
Shri Avijit Bhattacharjee, learned counsel for the appellants
submitted that the premises were needed for a public purpose i.e., providing
permanent accommodation to the unit of Cottage and Small Scale Industries,
Bangasree and also for West Bengal Ceramic Development Corporation and,
as such, no exception could be taken to the procedure adopted by the
appellants. Learned counsel emphasized that Section 17(4) was invoked
because in terms of order dated 18.4.1994 passed by the Division Bench of
the High Court, the State Government was obliged to complete the
6
acquisition proceedings within six months and this could not have been
possible if objections were invited and opportunity of hearing was given to
the respondents as per requirement of Section 5-A. In support of his
argument, Shri Bhattacharjee relied upon the judgment of this Court in
Chameli Singh and others v. State of U.P. and another (1996) 2 SCC
549.
Shri Shyam Divan, learned senior counsel appearing for the
respondents supported the impugned order and argued that the Division
Bench of the High Court did not commit any error by quashing the
acquisition. He relied upon the recent judgment in Anand Singh and
another v. State of Uttar Pradesh and others (2010) 11 SCC 242, and
submitted that the High Court has rightly nullified the acquisition
proceedings on the ground that there was no such urgency which could
justify short circuiting the rule of hearing enshrined in Section 5-A of the
Act.
We have considered the respective submissions and carefully perused
the record. The applicability of Section 17 of the Act has been considered
in several cases, but it is not necessary to burden the judgment with large
number of precedents and it will be sufficient to notice the two judgments
which have direct bearing on the issue arising in these appeals. In Narayan
Govind Gavate v. State of Maharashtra (1977) 1 SCC 133, a three-Judge
7
Bench of this Court considered various facets of the issue relating to
invoking of urgency clause for the acquisition of land for development and
utilization as a residential-cum-industrial area. The Bombay High Court had
allowed the writ petitions filed by the land owners and quashed the invoking
of Section 17(4) of the Act. This Court first considered the question of
burden of proof in matters in which inquiry under Section 5A is dispensed
th
with, referred to Phipson on Evidence (11 Edition), the judgment in
Woolmington v. Director of Public Prosecutions 1935 AC 462, noticed
the provisions of Sections 101, 102, 103, 106 and 114 of the Evidence Act
and held:
“Our conclusion therefore is that where certain conditions
precedent have to be satisfied before a subordinate authority
can pass an order, (be it executive or of the character of
subordinate legislation), it is not necessary that the satisfaction
of those conditions must be recited in the order itself, unless the
statute requires it, though, as we have already remarked, it is
most desirable that it should be so, for in that case the
presumption that the conditions were satisfied would
immediately arise and burden would be thrown on the person
challenging the fact of satisfaction to show that what is recited
is not correct. But even where the recital is not there on the face
of the order, the order will not become illegal ab initio and only
a further burden is thrown on the authority passing the order to
satisfy the court by other means that the conditions precedent
were complied with. In the present case this has been done by
the filing of an affidavit before us.
It is also clear that, even a technically correct recital in an order
or notification stating that the conditions precedent to the
exercise of a power have been fulfilled may not debar the court
in a given case from considering the question whether, in fact,
those conditions have been fulfilled. And, a fortiori, the court
8
may consider and decide whether the authority concerned has
applied its mind to really relevant facts of a case with a view to
determining that a condition precedent to the exercise of a
power has been fulfilled. If it appears, upon an examination of
the totality of facts in the case, that the power conferred has
been exercised for an extraneous or irrelevant purpose or that
the mind has not been applied at all to the real object or purpose
of a power, so that the result is that the exercise of power could
only serve some other or collateral object, the court will
interfere.”
(emphasis supplied)
The Court then considered whether there was any justification for
invoking the urgency clause for acquisition of land for residential and
industrial purposes and observed:
“In the case before us, the public purpose indicated is the
development of an area for industrial and residential purposes.
This, in itself, on the face of it, does not call for any such
action, barring exceptional circumstances, as to make
immediate possession, without holding even a summary
enquiry under Section 5-A of the Act, imperative. On the other
hand, such schemes generally take sufficient period of time to
enable at least summary inquiries under Section 5-A of the Act
to be completed without any impediment whatsoever to the
execution of the scheme. Therefore, the very statement of the
public purpose for which the land was to be acquired indicated
the absence of such urgency, on the apparent facts of the case,
as to require the elimination of an enquiry under Section 5-A of
the Act.
All schemes relating to development of industrial and
residential areas must be urgent in the context of the country’s
need for increased production and more residential
accommodation. Yet, the very nature of such schemes of
development does not appear to demand such emergent action
as to eliminate summary enquiries under Section 5-A of the
Act. There is no indication whatsoever in the affidavit filed on
behalf of the State that the mind of the Commissioner was
9
applied at all to the question whether it was a case necessitating
the elimination of the enquiry under Section 5-A of the Act.
The recitals in the notifications, on the other hand, indicate that
elimination of the enquiry under Section 5-A of the Act was
treated as an automatic consequence of the opinion formed on
other matters. The recital does not say at all that any opinion
was formed on the need to dispense with the enquiry under
Section 5-A of the Act. It is certainly a ease in which the recital
was at least defective. The burden, therefore, rested upon the
State to remove the defect, if possible, by evidence to show that
some exceptional circumstances which necessitated the
elimination of an enquiry under Section 5-A of the Act and that
the mind of the Commissioner was applied to this essential
question. It seems to us that the High Court correctly applied
the provisions of Section 106 of the Evidence Act to place the
burden upon the State to prove those special circumstances,
although it also appears to us that the High Court was not quite
correct in stating its view in such a manner as to make it appear
that some part of the initial burden of the petitioners under
Sections 101 and 102 of the Evidence Act had been displaced
by the failure of the State to discharge its duty under Section
106 of the Act. The correct way of putting it would have been
to say that the failure of the State to produce the evidence of
facts especially within the knowledge of its officials, which
rested upon it under Section 106 of the Evidence Act, taken
together with the attendant facts and circumstances, including
the contents of recitals, had enabled the petitioners to discharge
their burden under Sections 101 and 102 of the Evidence Act.”
(emphasis supplied)
In Anand Singh’s case (supra), the two-Judge Bench
considered the question whether the State Government was justified in
invoking Section 17(4) for acquisition of land for residential colony to be
constructed by Gorakhpur Development Authority, Gorakhpur. The Court
noted that notifications under Section 4(1) read with Section 17(1) and (4)
were issued on November 23, 2003 and February 20, 2004 and declaration
10
under Section 6 was issued on December 24, 2004, referred to 16 judicial
precedents including those noticed hereinabove and held:
“The exceptional and extraordinary power of doing away with
an enquiry under Section 5-A in a case where possession of the
land is required urgently or in an unforeseen emergency is
provided in Section 17 of the Act. Such power is not a routine
power and save circumstances warranting immediate
possession it should not be lightly invoked. The guideline is
inbuilt in Section 17 itself for exercise of the exceptional power
in dispensing with enquiry under Section 5-A. Exceptional the
power, the more circumspect the Government must be in its
exercise. The Government obviously, therefore, has to apply its
mind before it dispenses with enquiry under Section 5-A on the
aspect whether the urgency is of such a nature that justifies
elimination of summary enquiry under Section 5-A.
A repetition of the statutory phrase in the notification that the
State Government is satisfied that the land specified in the
notification is urgently needed and the provision contained in
Section 5-A shall not apply, though may initially raise a
presumption in favour of the Government that prerequisite
conditions for exercise of such power have been satisfied, but
such presumption may be displaced by the circumstances
themselves having no reasonable nexus with the purpose for
which the power has been exercised. Upon challenge being
made to the use of power under Section 17, the Government
must produce appropriate material before the Court that the
opinion for dispensing with the enquiry under Section 5-A has
been formed by the Government after due application of mind
on the material placed before it.
It is true that power conferred upon the Government under
Section 17 is administrative and its opinion is entitled to due
weight, but in a case where the opinion is formed regarding the
urgency based on considerations not germane to the purpose,
the judicial review of such administrative decision may become
necessary.
As to in what circumstances the power of emergency can be
invoked are specified in Section 17(2) but circumstances
11
necessitating invocation of urgency under Section 17(1) are not
stated in the provision itself. Generally speaking, the
development of an area (for residential purposes) or a planned
development of city, takes many years if not decades and,
therefore, there is no reason why summary enquiry as
contemplated under Section 5-A may not be held and objections
of landowners/persons interested may not be considered. In
many cases, on general assumption likely delay in completion
of enquiry under Section 5-A is set up as a reason for
invocation of extraordinary power in dispensing with the
enquiry little realising that an important and valuable right of
the person interested in the land is being taken away and with
some effort enquiry could always be completed expeditiously.
The special provision has been made in Section 17 to eliminate
enquiry under Section 5-A in deserving and cases of real
urgency. The Government has to apply its mind on the aspect
that urgency is of such nature that necessitates dispensation of
enquiry under Section 5-A. We have already noticed a few
decisions of this Court. There is a conflict of view in the two
decisions of this Court viz. Narayan Govind Gavate and Pista
Devi. In Om Prakash this Court held that the decision in Pista
Devi must be confined to the fact situation in those days when
it was rendered and the two-Judge Bench could not have laid
down a proposition contrary to the decision in Narayan Govind
Gavate. We agree.
As regards the issue whether pre-notification and post-
notification delay would render the invocation of urgency
power void, again the case law is not consistent. The view of
this Court has differed on this aspect due to different fact
situation prevailing in those cases. In our opinion such delay
will have material bearing on the question of invocation of
urgency power, particularly in a situation where no material has
been placed by the appropriate Government before the Court
justifying that urgency was of such nature that necessitated
elimination of enquiry under Section 5-A.”
(emphasis supplied)
12
We may now revert to the case in hand. A brief recapitulation of the
facts shows that possession of the premises in question was taken in 1944
under the Defence of India Act. After 46 years, an attempt was made by the
appellants to acquire the premises but could not achieve their object because
notification dated 27.8.1990 issued under Section 4(1) was quashed by the
High Court. Thereafter, no action was taken for acquisition of the premises
till after the disposal of Appeal No.35 of 1994. The appellants have not
explained as to why appropriate steps could not be taken for acquisition of
the premises by complying with the requirement of Section 5-A of the Act.
The time gap of 3 years between the quashing of first notification and issue
of the second notification was too long to justify invoking of urgency clause
which resulted in depriving the respondents of their right to raise objection
against acquisition of the premises. If the appellants felt that six month’s
time was not sufficient for completing the acquisition proceedings, they
could have filed an application in Appeal No.34 of 1994 for extension of the
time. However, the fact of the matter is that no such effort was made by
them and the urgency clause was invoked on the pretext of completion of the
acquisition in terms of the direction given by the High Court in Appeal
No.35 of 1994. In our view, this was clearly impermissible and the
respondents could not be deprived of their legitimate right to raise objection
and to be heard against the proposed acquisition of the premises.
13
As a sequel to the above discussion, we hold that the Division Bench
of the High Court did not commit any error by quashing the Notifications
issued under Section 4(1) read with Section 17 and Section 6 of the Act.
In the result, the appeals are dismissed. The parties are left to bear
their own costs.
….………………….…J.
[G.S. Singhvi]
….………………….…J.
[Asok Kumar Ganguly]
New Delhi;
February 4, 2011
14