Full Judgment Text
1
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.585 2016
[Arising out of SLP [C] No.18910 of 2010]
Bihar State Electricity Board & Ors. … Appellants
Vs.
M/s. Bhola Ram Steel Pvt. Ltd. & Ors. … Respondents
J U D G M E N T
ARUN MISHRA, J.
JUDGMENT
1. Leave granted.
2. The appeal has been preferred aggrieved by the judgment and
order passed by the High Court of Judicature at Patna in the writ
petition and the appeal, thereby quashing the demand raised by the
appellant for the year 1999-2000. M/s. Bhola Ram Steel Pvt. Ltd. filed
a writ application that it was an industrial unit to manufacture iron and
Page 1
2
steel structure and section like bar roll, place angle, channel, square,
tor and round, general fabrication and annulling of sheets it applied as
HTIS consumer for a connected load of 500 KVA. The competent
| oad of 500 | KVA vid |
|---|
The respondent-industry commenced production w.e.f. 28.3.1998. The
appellant averred that on 23.1.1999 the premises of the respondent
were inspected. Connected load was found to be 495 HP. Appellant
submitted that as per the Industrial Policy of 1995 announced by the
State Government, Resolution dated 3.9.1996 was passed by the
Energy Department of the State Government to grant exemption from
payment of minimum guarantee charges to the industrial unit having
connected load of 500 KVA and accordingly in exercise of power
under section 78 of the Electricity Supply Act, 1948 issued directives
JUDGMENT
to the Electricity Board for grant of such incentives. The industrial
units commencing production between 1.4.1993 and 31.8.2000 were
to be exempted from payment of minimum guarantee charges for a
period of 5 years from the date of commencement of production.
3. The maximum demand indicator in the Trivector meter had
wrongly shown more than the contracted demand of 500 KVA. The
industry also submitted that the meter stopped functioning in the
Page 2
3
month of January, 2000. It was replaced on 9.2.2000, again the meter
was found to be faulty and again replaced on 21.3.2000. Thus the
readings of the meter could not be relied upon.
| l was serve | d on the r |
|---|
which had been questioned in the writ application filed by the
industry.
5. It was contended on behalf of the Electricity Board that an
agreement entered into on 2.3.1988 for a contract demand of 500
KVA. Appellant installed transformer of 750 KVA. During the
financial year 1999-2000 i.e. from April, 1999 to March, 2000
maximum demand of the respondent has exceeded the contract
demand of 500 KVA in as many as six months. In the month of
March, 2000, maximum demand reached all time high of 621.06
JUDGMENT
KVA. Since it was more than 110% of the existing contract demand of
500 KVA the contract demand as per clause 16.5 of the tariff
notification dated 21.6.1993 has been taken to be 621.06 KVA.
6. The maximum demand which is the actual demand of the
consumer can never be more than the connected load when expressed
in terms of the KVA. The industry has increased its connected load
Page 3
4
without information to the Board. Thus it has crossed the maximum
limit of connected load i.e. 500 KVA and could not be said to be
entitled for exemption from payment of minimum charges.
| ded by the | Board tha |
|---|
was conducted and it was found to be correct and maximum demand
recorded was found to be 508.20 KVA. It was again checked on
8.12.1999. Maximum demand in the month of December, 1999 was
recorded as 616.20 KVA which was not disputed by the industry.
8. The Single Bench quashed the demand on the ground that on
account of consumption of electricity in excess of contract demand,
connected load automatically gets altered, has not been established by
the Board. The benefit of exemption from annual minimum guarantee
charges could not be denied to the industry. It was not established by
JUDGMENT
the Board that the connected load was more than 500 KVA. The
Division Bench has affirmed the order on the ground that greater
consumption of power will result in economic development,
generation of employment and income and it is better for the State of
Bihar. If the industry has exceeded the connected load or has
consumed electricity in excess, it could not be deprived of the benefit
of power incentives. It also opined that no evidence on record
Page 4
5
indicated that the consumption was beyond the connected load.
Aggrieved thereby, the Bihar State Electricity Board is in appeal
before us.
| on beha | lf of the |
|---|
maximum demand indicator has recorded the actual consumption. The
High Court has erred in quashing the demand. Reliance has been
placed upon Clause 16.5 of the notification of 1993 issued under
section 49 of the Indian Electricity Act, 1948. It was submitted on
behalf of the industry that there was no correlation between the
connected load and contract demand and the maximum demand
recorded by the indicator. At the time of inspection the connected load
was found to be 495 KVA. Thus as per the industrial policy of 1995
when connected load of 500 KVA has not exceeded at any point of
JUDGMENT
time, the High Court has rightly quashed the demand which was
raised.
10. The fact is not in dispute that the contract demand sanctioned
was 500 KVA as is apparent from the agreement entered into between
the parties.
Page 5
6
11. The basis of claim is notification dated 11.10.1996 issued by
the Bihar State Electricity Board pursuant to Industrial Policy of the
State Government of 1993 and 1995, relevant portion is extracted
hereunder:-
“The industrial units which commence production or
engage in defined expansion/diversification in between
the period 01.04.1993 to 31.08.2000 and whose
connected electricity load is upto 500 KVA will be
exempted from payment of minimum guarantee
(minimum base charges) for a period of five years from
the date of connection.”
12. Before dilating further it is appropriate to take note of clause
16.5 of the statutory notification of 21.06.1993 issued under section
49 of the Indian Electricity (Supply) Act, 1948. Clause 16.5 is
extracted hereunder :
JUDGMENT
“If during any month in a financial year (April to March
next year) the actual maximum demand of a consumer
exceeds 110 percent of the contract demand then the
highest demand so recorded shall be treated as the
contract demand for that financial year and the minimum
base charges, both in respect of maximum demand and
energy charge shall be payable on that basis.”
Page 6
7
13. The installed load means a sum of the rated inputs of the
electrical apparatus installed on the consumer’s premises. Connected
load means that part of the load of consumer supplied by the Supply
| act deman | d means |
|---|
agreement that the consumer may not exceed except according to the
conditions of the tariff.
14. It is not in dispute that the maximum demand indicator meter
hereinafter referred to as MDI meter was installed which is a device to
measure the maximum demand at a particular half an hour cycle of
running of the machinery in the factory; meaning thereby it measures
the maximum demand of the electrical energy in the cycle of half an
hour in a month. The electricity actually consumed is recorded in the
JUDGMENT
MDI meter. The demand in the instant case has been raised by the
Electricity Board on the basis of reading recorded by the MDI meter.
The MDI meter has recorded the consumption of energy in excess of
the contracted load on the basis of which demand has been raised.
There was excess drawal of electrical energy than the actual permitted
load. The MDI meter is also called Trivector meter. As per the
readings recorded by the MDI meter it is apparent that consumer has
Page 7
8
availed and drawn electricity in excess of the contracted load in
contravention of the agreement with the Electricity Board. The
reading of MDI meter is indicator of total connected loads, the total
| availed of | during |
|---|
consumption of energy. In the facts of instant case it is apparent that
for six months in the year 1999-2000 the MDI meter has recorded
excess load. Thus we find that the High Court has erred in the facts of
the instant case in holding that it has not been established in the
instant case that the connected load was more than 500 KVA.
15. This Court in Orissa State Electricity Board & Anr. v. IPI Steel
Ltd. & Ors . (1995) 4 SCC 320 has noted how a trivector meter works
and efficacy of MDI meters. It has been followed by this Court in
Bhilai Rerollers & Ors. v. M.P. Electricity Board & Ors . (2003) 7
JUDGMENT
SCC 185. This Court in Bhilai Rerollers (supra) has referred to MDI
meters and the decision of Orissa State Electricity Board (supra).
Relevant portions are extracted hereunder :
“16. We have carefully considered the submissions on
behalf of parties on either side. This Court, in the
decision reported in Orissa SEB case (1995) 4 SCC 320
though in dealing with the rights of the Electricity Board
Page 8
9
for enforcing payment of maximum demand charges and
minimum monthly charges noticed about the utility of
MDI meter also called “trivector meter” and observed as
hereunder at para 10: (SCC pp. 326-27)
| e is called<br>normal m | the ‘trivec<br>eter which |
|---|
JUDGMENT
Page 9
10
| has drawn<br>te period o | energy at<br>n the first |
|---|
17. The provisions contained in sub-section (7) of
Section 26 of the Indian Electricity Act, 1910 envisage
the installation of additional meters and checking
apparatus, in addition to the meter for ascertaining the
amount of energy supplied and quantity consumed. By
and large it seems to be that the utility of MDI meter to
record effectively and correctly the drawal of power at a
continuous block period of 30 minutes in a month by a
consumer has come to stay as a reasonably safe method
with due credibility and recognition in the field and
appears to be in vogue even at the global level. The
question as to whether it can also safely be relied upon as
the basis for investigating and determining the excess
quantity of load said to have been availed of by a
consumer over and above the contracted load as per the
agreement is concerned, in our view admits of no doubt
and we could find no reasonable or tenable and valid
objection to exist so far as its relevance, utility and
purpose of determination are concerned. If the reading by
such a device installed could provide a sound basis and
yardstick as accepted by this Court in the decision
noticed supra for adjudging liability to pay the maximum
demand charges/minimum monthly charge, it should in
our view be considered to be equally efficacious for the
purpose on hand also in adjudging the issue as to whether
JUDGMENT
Page 10
11
the consumer has at any given point of time, in
contravention of the agreement with the Board, availed
and drawn electricity in excess of the contracted load.
| he commu<br>king of the | nication f<br>Steel Au |
|---|
JUDGMENT
16. This Court has in Bhilai Rerollers (supra) held that the reading
of the MDI meter could provide a sound basis and yardstick to pay
maximum demand charges and for adjudging the issue as to whether
Page 11
12
the consumer at any given point of time of the agreement has availed
and drawn excess electricity. This Court has also indicated that lock
rotor test is normally held to determine the capacity of the meter and
| oad or the t | otal load |
|---|
during the course of actual consumption of energy. Merely in an
inspection in January, 1999 if the connected load was found to be of
495 HP when for six months in a subsequent period of April, 1999 to
March, 2000 maximum demand has increased beyond the contracted
load of 500 KVA and it is not disputed that it was more than 110% of
the contract load. Thus as per clause 16.5 of the notification dated
21.06.1993 issued under the Electricity Supply Act, 1949 in our
opinion the Electricity Board was well within its rights to realize the
amount as per tariff notification. We find that the High Court has erred
JUDGMENT
in holding in the facts of the case that there can be no correlation with
the maximum demand and the connected load. Similarly the High
Court has proceeded on irrelevant consideration while it has observed
that entrepreneur has stepped up production, which will result in
economic development, generation of employment and income and
higher consumption is better for the State of Bihar. This was not a
question to be gone into by the High Court. The High Court was
Page 12
13
required to consider the reliability of the MDI meter and frequent
violation of contract demand and the tariff notification dated
21.6.1993. There is material on record indicating that the connected
| as reflecte | d in the m |
|---|
be due to wrong recording of meter or short circuit etc. as MDI meter
records excess capacity drawn over a continuous period of 30
minutes’ duration during a month. The MDI meter’s method is well
recognized and widely accepted one. The plea taken that there was
defect in the meter and they were changed in January, 2000 and again
in March, 2000 has no legs to stand. However MDI meter readings for
earlier periods too indicated demand exceeding 500 KVA and in the
month of November 1999, the meter was found to be in order and
maximum demand exceeded contract demand. Once maximum load
JUDGMENT
drawn had exceeded the contracted load, in the fact of the case, it can
safely be held that there is violation of the permissible connected load.
The recording in MDI meter is more credible and reliable than the
stand of the industry that the meter was faulty, set up just to escape
from the liability.
Page 13
14
17. In the circumstances we have no hesitation in setting aside the
orders passed by the Single Bench and Division Bench of the High
Court. The impugned demand is held to be legal and valid. Let the
| culated as | on today, |
|---|
the Board within a period of six weeks from today. The appeal is
allowed. The impugned judgment and orders are set aside and writ
petition is dismissed. Parties to bear their own costs.
…………………………J.
(M.Y. Eqbal)
New Delhi; ………………………..J.
January 28, 2016. (Arun Mishra)
JUDGMENT
Page 14