Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 11
PETITIONER:
PUNE CANTONMENT BOARD & ANR.
Vs.
RESPONDENT:
M.P.J. BUILDERS & ANR.
DATE OF JUDGMENT: 09/08/1996
BENCH:
VERMA, JAGDISH SARAN (J)
BENCH:
VERMA, JAGDISH SARAN (J)
VENKATASWAMI K. (J)
CITATION:
JT 1996 (7) 123 1996 SCALE (5)713
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
J.S. VERMA, J.
The dispute relates to the building sanction of House
No.2, Sholapur Bazar Road, Pune, which falls within the area
of Pune Cantonment governed by the Cantonments Act, 1924
(hereinafter referred to as ’the act)
The respondent no.1 was granted a building sanction
under Section 181 of the Act on 2.7.1981 effective from
6.7.1981. The building was intended to be used for
commercial residential purposes, it was to be an RCC framed
structure and to consist of ground and five upper stories
(i.e. Stilt + six upper stories); the nature of soil was
’hard rock’; the construction work was to be commenced
within one year of the sanction i.e. before 6.7.1982; and
was to be completed within 12 months from the date of
commencement of the work. The building bye-laws existing at
the time of the sanction did not contain any restrictions
with regard to the Floor Area Ratio (FAR) or number of
floors or height of the building. By a letter dated
3.7.1982, barely three days before expiry of the permissible
period for commencement of the work, a letter was sent by
the respondent No. 1 stating that the work had been
commenced on that day. For the purposes of this case, the
appellants did not dispute this claim of the respondent
no.1. According to the conditions of the building sanction
imposed under the relevant statutory provisions, the
construction of the building had to be completed within 12
calendar months from the date of commencement of the work
i.e. upto 3.7.1983. Admittedly, the construction of the
building was neither completed nor was extension of time
sought within that period. The respondent No. 1 claims to
have made an application for extension of time to complete
the construction on 24.9.1983, after expiry of the time
allowed. For the purposes of this case the appellants do not
dispute even this claim. The contents of that application
alleged to have been made by the respondent no.1, are as
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 11
under :
"MRJ: 9/86/736 24.9.1983
The Executive Officers,
Cantonment Board,
Pune
Sub: Extension of time.
Ref: Your sanction No. 2/SH/B3
dated 6.7.81, for our project at
No. 2, Sholapur Bazar road.
Sir,
We have commenced the above work
with effect from 3.7.82 and your
office was intimated accordingly
vide our letter No. MPJ:MK/7/82,
dated 3.7.1982.
It was not possible to complete the
works within a span of one year due
to the various following reasons:
1.Hard rock is met with for
basement foundation which requires
chiselling.
2.Non-availability of building
materials.
3.Due to change in the strata now
met with, structural detailing
requires some changes.
4.Due to various other
difficulties.
We, therefore, request you to
kindly grant us an extension of
time for a further period of 24
months and oblige.
Yours faithfully,
for MPJ Builders.
Sd/-
(Ramesh Kumar More)
Partner."
On 24.5.1984, an engineer of the Cantonment Board
inspected the site and submitted a report that no erection
work of the building had been commenced till then; the owner
had not made any application for extension of time and the
sanction had lapsed. The making of this report is
undisputed. Thereafter, on 9.9.1985, an application, said to
be the second application for extension of time was made by
the respondent no.1. That application is as under :
"BY REGISTERED A.D
HPJ\RRH\9\85\106 Sept. 9th 1985
Executive Officer,
Pune Cantonment Boards
PUNE 411 OO1
Ref. : (a) Your sanction No.2/SH/B-
3 of 6/7/1981 for our project at
No.2 Sholapur Bazar road.
(b)Our letter No . HPJ/MK/7/82/343
of 3.7.1982 regarding intimation of
commencement.
(c)Our letter No.MPJ/9/83/736 of
Sir,
Due to various unforeseen reasons
and difficulties, we could make
substantial progress with the work
at our site at 2 Sholapur Bazar
Road.
We request you to grant us further
extension of 18 months and oblige.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 11
We assure you that we will try our
best to complete the building
within this extended period.
Thanking you,
For MPJ Builders,
(Ramesh Kumar More)
Partner."
On that application, a report dated 3.10.1985 was
submitted by an Officer of the Cantonment Board. Relevant
part of that report is as under :
"The party has not started the
construction from the date of
sanction and not taken any
extension of time limit for
completion of work from this
office.
On site inspection, it is found
that the owner of this property had
started excavation work. Which work
is in progress.
Submitted to your order’s pl.
Sd/-
3.10.85"
The Cantonment Executive Officer, exercising the power
of the Board, granted extension of time for a period of one
year from the date of that order dated 2.5.1986 as under:
"02 May 1986
From
The Cantonment Executive Officer,
Poona Cantonment Boards Poona.
To
Shri Ramesh Kumar More, Partner,
C/o MPJ Builders, Poona Bottling
Co.Ltd., 4101/1, Bombay Poona Road,
Dapodi, PUNE 411 012.
-----------------------------------
Subject : Grant of Extension of
time for completion of work
H.No.2, sholapur Bazar, Pune Cantt.
Reference : Your application
dt.09.9.1985
Dear Sir,
Extension of time for completion of
work for a period of one year is
hereby granted.
Yours faithfully,
Sd/-
CANTT. EXECUTIVE OFFICER."
Prior to the grant of extension of time by the
Cantonment Executive Officer on 2.5.1986 or even the
8application for extension of time dated 9.9.1985, certain
changes had been made in the building bye-laws imposing
additional restrictions. All subsequent building sanctions
had to be granted thereafter subject to these additional
restrictions also. The first set of restrictions were
imposed on 24.12.1982 under which the maximum number of
stories which could be constructed were reduced to the
ground floor + two upper stories i.e. in all three stories
including the ground floor. The maximum permissible FAR
commonly known as FAR was two and the maximum permissible
built up area became 1/3rd. These restrictions were imposed
under Section 181(2) of the Act which later became Section
181-A, in the public interest to regulate the building
activities in the cantonment area. More restrictions were
imposed on 26.3.1984 under which the permissible FAR was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 11
reduced from two to one. It is to be remembered that the
report dated 24.5.1984 of the Cantonment Engineer clearly
mentioned the admitted fact that no erection work had been
commenced by the respondents till then. The question of
extension of time to make the construction according to the
initially sanctioned plan had to be decided in this
background taking into account the fact that no erection of
the building had commenced till both sets of further
restrictions had been imposed; and according to the
additional restrictions, the kind of building construction
sanctioned on 2.7.1981 could not be permitted, if the
question of sanction was to be considered afresh.
The GOC-in-Chief in exercise of his powers under
Section 52(1)(b) of the Act suspended the CEO’s order dated
2.5.1986 by an order dated 2.1.1987 and issued a show cause
notice to the Cantonment Board as well as the respondent
no.1 to show cause why the suspension order be not made
absolute. After hearing the parties, the GOC-in-Chief, by
order dated 14.2.1987 under Section 52(2)(c) made the
suspension order absolute. It appears that a portion of the
building had been constructed by then and therefore, on
14.3.1987 the GOC-in-Chief made the consequential order for
its demolition.
A writ petition was then filed on 27.3.1987 in the
Bombay High Court by the respondents which has been allowed
and the orders made by the GOC-in-Chief dated 14.2.1987 and
14.3.1987 have been set aside. The High Court granted some
further time to complete construction of the building
according to the initially sanctioned plan. Aggrieved by the
High Court’s order, the Pune Cantonment Board and the GOC-
in-Chief have preferred this appeal by special leave.
It was common ground before us that the stage of
construction till now is : the basement, a ground floor and
the first floor have been constructed; the ground floor is
of an extra height so as to accommodate mezzanine although
the mezzanine floor has not yet been cast; the mezzanine
floor sanctioned does not extend to the entire ground floor
area but only to a small portion thereof and the rest of the
ground floor has been left with the extra height. The
construction made so far is already in excess of the
permitted FAR of one, being approximately 1.59. The learned
Solicitor General, appearing for the appellants, on
instructions, stated that the appellants are prepared to
permit the respondent no 1 to retain the existing structure
and complete the finishing of the existing structure with
the mezzanine according to the initially sanctioned Plan
subject to the condition that no additional slab would be
laid anywhere else. This offer made on behalf of the
appellants at the hearing before us is mentioned since to
this extent the appellants consent to grant of relief to the
respondents even if the appeal is allowed.
Mention may also be made of another relevant fact. The
High Court in the impugned judgment invoked the doctrine of
estoppel on the ground that the builders had acted upon the
order of extension and had completed a portion of the
building. Shri F.S.Nariman, learned senior counsel for the
respondents, frankly conceded that he could not support the
High Court’s order on that ground. We need not, therefore,
consider the applicability of the doctrine of estoppel which
is a clearly untenable plea in the present case.
At this stages before we proceed to consider the rival
contentions, we may notice the relevant statutory
provisions:
"THE CANTONMENTS ACT, 1924
52 Power of Officer Commanding-in-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 11
Chief, the Command, on reference
under Sec 51 or otherwise - (1) The
Officer Commanding-in-chief, the
Command, may at any time-
(a) xxx xxx xxx
(b)direct the suspension, for such
period as may be stated in the
order of action on any decision of
a Board, other than a decision
which has been referred to him
under sub-section (1) of Sec. 51,
and thereafter cancel the
suspension or after giving the
Board a reasonable opportunity of
showing cause why such direction
should not be made, direct that the
decision shall not be carried into
effect, or that it shall be carried
into effect with such modifications
as he may specify.
xxx xxx xxx
180-A. Powers of Board under
certain sections exercisable by
Executive Officer.- The powers,
duties and functions of the Board
under Sec. 181, sub-section (1) of
Sec. 182, Sec. 183Sec. 183-A and
Sec. 185 (excluding the proviso to
sub-section (1) and the proviso to
sub-section (2) of the saidSec. 185
shall be exercised or discharged in
a civil area by the Executive
Officer)
181. Power refuse - (1) The Board
may either refuse to sanction the
erection or re-erection, as the
case may be, of the building, or
may sanction it either absolutely
or subject to such directions as it
thinks fit to make in writing in
respect of all or any of the
following matters, namely :
xxx xxx xxx
and the person erecting or re-
erecting the building shall obey
all such written directions in
every particular.
(2) The Board may refuse to
sanction the erection or re-
erection of any building on any
grounds sufficient in the opinion
of the Board affecting the
particular building
Provided that the Board shall
refuse to accord sanction the
erection or re-erection of any
building if such erection or re-
erection is not in conformity with
any general scheme sanctioned under
Sec.181-A.
xxx xxx xxx
(5) If the Board decides to refuse-
to sanction the erection or re-
erection of the building, it shall
communicate in writing the reasons
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 11
for such refusal to the person by
whom notice was given.
xxx xxx xxx
181-4. Power to sanction general
scheme for prevention of over-
crowding, etc. - The Officer
Commanding-in-Chief the Command may
sanction a general scheme for
erection or re-erection of
buildings within such limits as may
be specified in the sanction for
the prevention of over crowding or
for purpose of sanitation, or in
the interest of persons residing
within those limits or for any
other purpose, and may, in
pursuance of such scheme, impose
restrictions on the erection or re-
erection of buildings within those
limits :
Provided that no such scheme shall
be sanctioned by the officer
commanding-in-chief, the command,
unless an opportunity has been
given by a public notice to be
published locally by the Executive
Officer requiring persons affected
or likely to be affected by the
proposed scheme, to file their
objections or suggestions in the
manner specified in the notice,
within a period of fifteen days of
the publication of such notice, and
after considering such objections
and suggestions, if any, received
by the Executive Officer within the
said period.
xxx xxx xxx
183. Lapse of sanction - Every
sanction for the erection or re-
erection of a building given or
deemed to have been given by the
Board as herein-before provided
shall be available for one year
from the date on which it is given,
and, if the building so sanctioned
is not begun by the person who has
obtained the sanction or some one
lawfully claiming under him within
that period, it shall not
thereafter be begun unless the
Board on application made
therefore, has allowedan extension
of that period.
183-A. Period for completion of
building -A Board when sanctioning
the erection or re-erection, of a
building as herein-before provided
shall specify a reasonable period
after the work has commenced within
which the erection or re-erection
is to be completed, and, if the
erection or re-erection is not
completed within the period so
fixed, it shall not be continued
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 11
thereafter without fresh sanction
obtained in the manner herein-
before provided, unless the Board
on application made therefor has
allowed an extension of that period
:
Provided that not more than two
such extensions shall be allowed by
the Board in any case."
The learned Solicitor General appearing on behalf of
the appellants advanced several arguments. He submitted that
no reasons were given by the Cantonment Executive Officer
for extension of time, on these facts, to justify grant of
the extension. The relevant facts for this purpose were that
the sanction had expired on 3.7.1983 even prior to the
making of the alleged first application for extension of
time dated 24.9.1983, assuming that the application was
made, no construction of the building had been commenced
within the time ailowed or even till 3.10.1985 as evident
from the inspection note of that date and much before that
date additional restrictions had been imposed on 26.12.1982
and 26.3.1984 by amendments made in the building bye-laws
which did not Permit such a construction. It was contended
that these changed circumstances were of great significance
but they were not considered by the CEO and no reason was
given for the extension of time granted by the CEO on
2.5.1986. The learned Solicitor General also submitted that
the only ground mentioned in the application dated 9.9.1985
made by the respondent no.1 did not justify grant of
extension of time to make any construction in breach of the
restrictions imposed meanwhile in 1982 and 1984 when no
construction of the building had been commenced even till
3.10.1985 and the sanction had already lapsed on 3.7.1983.
It was urged that the exercise of power by the GOC-in-Chief
under Section 52 to set aside the order made by the CEO was
valid for the reasons given by him. We have already
mentioned the offer made by the appellants to permit
retention of the existing structure even if the appeal
succeeds.
In reply, Shri F.S.Nariman, learned senior counsel for
the respondents, submitted that the reasons given in the
order of the GOC-in-Chief setting aside the order of the CEO
are in applicable because the additional building
restrictions imposed in 1982 and 1984 did not apply to a
building sanction granted prior to the imposition of those
additional restrictions. Shri Nariman heavily relied on a
foot-note dated 4.4.1984 clarifying this position at the end
of the relevant public notice quoted in the decision in
Usman Gani J.Khatri &. Ors. etc. vs. Cantonment Board & Ors.
, 1992 (3) SCC 455 at 464 as under :
"Note - It is clarified for
information of the general public
that the above orders will be
effective from the date the GOC-in-
Chief, HQSC, has signed the above
order i.e.March 26, 1984. These
restrictions will apply only to the
buildings whose plans will be
considered/ passed on or after
March 26, 1984. Building plans
passed prior to March 26,1984 will
be governed by the FSI existing
during that period.
Dated April 4, 1984.
Sd/- S.P. Nijhawan
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 11
Cantonment Executive Officer, Pune"
It is not necsssary to quote in extenso the public
notices imposing the additional restrictions on 24.12.1982
and 26.3.1984, which have been summarised earlier and are
not disputed. The other submission of Shri Nariman was that
even though the delay in making the application for
extension of time after expiry of the period of sanction and
imposition of additional restrictions are relevant
circumstances to be considered for granting extension of
time yet its non- consideration is not a jurisdictional
defect to denude the CEO of the power to grant extension of
time, Shri Nariman submitted that the initial- building
sanction granted to the respondent no.1 being prior to the
imposition of the additional restrictions which were
prospective in operation the further extension of time to
complete the earlier sanctioned building would be governed
only by the building bye-laws existing at the time of grant
of the initial sanction. Shri Nariman, therefore, argued for
dismissal of the appeal for these reasons.
Section 180-A empowers the Executive Officer to
exercise certain powers, duties and functions of the Board
which include the Board’s power to sanction or to refuse to
sanction the erection or re-erection of the building under
Section 181, and to allow the extension of the period for
completion of the building. Extension of time granted by the
CEO in the present case was in exercise of this power. The
only question in the present case pertains to the validity
of the extension of the period by the order dated 2.6.1985
made by the CEO in exercise of the power under section 183-A
Section 183 prescribes the period of one year from the
date on which a building sanction has been given to begin
the building so sanctioned, failing which the sanction
lapses unless the Board, on an application made therefor has
allowed an extension of that period. In the present case,
the compliance of this provision is not disputed since the
claim of respondent no. 1 by a letter dated 3.7.1982 is not
contested. the significant provision is Section 183-A.
Section 183-A requires the period for completion of the
building to be specified when the sanction is granted. It is
to be a resonable period after the work has commenced. In
the present case the period so specified was one year. The
fixation of the period of one year as the reasonable period
for completion of the building after commencement of the
work was not challenged. Thus, the work having commenced on
3.7.1982 as claimed by the respondent no.1, the period for
its completion according to Section 183-A, expired on
3.7.1983. Section 183-A further provides that if the
erection of the building is not completed within the period
so fixed, it shall not be continued thereafter without fresh
sanction obtained in the manner herein-before provided i.e.
Section 181, unless the Board on an application made
therefor has allowed an extension of that period. The
proviso then limits the power of the Board to allow not more
than two such extensions.
In short, Section 183-A provides for the specification
of the period for completion of the building when the
sanction is granted and on expiry of that period
construction of the building cannot be continued without a
fresh sanction, unless an extension of that period has been
allowed on an application made therefor. It means that
unless the Board has allowed an extension of the period
specified for complotion of the building on an application
made therefor, the sanction lapses and the construction of
the building shall not be continued thereafter without a
fresh sanction. Section 183-A speaks of a fresh sanction on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 11
expiry of the period fixed for completion of the building as
well as extension of that period on an application made
therefor. Meaning must, therefore, be given to both the
provisions, namely, fresh sanction and extension of that
period; and the two powers must be construed to be available
in two different situations. This is necessary to exclude
any conflict and arbitrariness in exercise of the choice
between the two powers in similar cases. It appears that the
two powers are meant to be exercised in two different
situations and the provision does not leave it to the option
of the authority to deside which of the two powers is to be
exercised in the case. This means that unless time is
extended on an application made before its expiry, the
sanction lapses and the erection of the building cannot be
continued thereafter without a fresh sanction.
Effect of the proviso in Section 183-A must also be
kept in mind. Extension of time allowed has to be in
continuity and it cannot exceed the period fixed initially
for completion of the building. The limit is of two
extensions. In the present case, the period fixed was one
year and, therefore, the permissible two extensions could
not exceed two years because of the proviso. Thus, the total
extension of time could not be beyond two year from 3.7.1983
(upto which date time was allowed for completion). In other
words, time extended under Sec.183-A because of the proviso,
in the present case could not be beyond 3.7.1983 since the
extension had to be in continuity. In the pesent case that
application made much later on 9.9.1985 had to be rejected
by the CEO for this reason alone and the only power
available on that date was of a fresh sanction. This
obviously could not be granted in view of the additional
restrictions imposed meanwhile. Thus, extension of time by
the order dated 2.5.1986 was clearly without jurisdiction
for this reason alone.
Even assuming the power to allow extension of time was
available, the facts indicate that it could not be granted.
As earlier stated, the period fixed for completion of the
building under Section 183-A was one year which expired on
3.7.1983. Admittedly, no application for extension of time
was made by the respondent no.1 before the expiry of that
period and such an application is alleged to have been made
only on 24.9.1983. No extension was granted on that
application since the Board does not admit receiving the
same. There was total silence till almost two years
thereafter and then on 9.9.1985 the application for
extension of time was made by respondent no. 1. The period
fixed for completion of the building when the sanction was
granted had expired more than two years earlier. The report
of the officer of the Cantonment Board dated 3.10.1985
clearly showed that the construction of the building had not
commenced till then and the only thing done was some
excavation work. In spite of this report, the CEO granted
extension of time for completion of work for a further
period of one year without assigning any reason a in his
order dated 2.5.1986 made with reference only to the
application dated 9.9.1985.
It is obvious that the exercise of the statutory power
of grant of extension of time under Section 183-A is not
mechanical or automatic and required a decision for be taken
on application of mind with reference to the relevant facts
and circumstances of the case. The CEO should have
considered all the relevant facts and circumstances of the
present case. The CEO should have considered all the
relevant facts and circumstances of the present case before
he came to the conclusion that extension of that period was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 11
called for particularly, when no construction of the
building had been commenced till then and additional
restrictions had been imposed meanwhile according to which
such a building sanction could not be granted if the matter
were to be considered for grant of a fresh sanction
contemplated under Section 183-A. Shri Nariman rightly does
not dispute that even if the additional restrictions were to
apply prospectively to the grant of a fresh sanction
thereafter, this was a relevant circumstance to be
considered while deciding to grant extension of that period
even in this case. The total non-consideration of any
relevant fact by the CEO while granting extension of time by
order dated 2.5.1986 and the absence of any reason for grant
of the sanction is alone sufficient to vitiate the CEO’s
order dated 2.5.1986. This conclusion is reached even if it
is assumed that extension of time could be granted on an
application made after expiry of the period allowed for
completion of the construction and the embargo in the
proviso is overlooked.
The validity of the GOC-in-Chief’s order setting aside
the order of the CEO granting extension of time has to be
decided on the above conclusion reached by us. The GOC-in-
Chief’s order refers, inter alia, to the additional
restrictions imposed in the meantime as relevant factors for
consideration. It is rightly not disputed that this was a
relevant, factor to consider while deciding the question of
extending the period. In substance. the GOC-in-Chief took
the view that permitting the construction of such a building
which had not till then begun would flagrantly violate the
building restrictions which had come into force by then.
This reason cannot be said to be arbitrary since it relates
to a relevant fact for the grant of extension of time. A
perusal of the application dated 9.9.1985 made the
respondent no.1 indicates that no fact had been stated
therein to make out any ground for grant extension of time
and to explain the inability to even commence erection of
the building within the time allowed. Even a reference to
the earlier application dated 24.9.1983, assuming it was
filed, shows that nothing significant was mentioned therein
except some vague, general difficulties of which the
respondent no.1 must have been aware even while seeking the
initial sanction. Thus neither any facts or cogent grounds
for extension of time were mentioned in the application for
extension of time nor was any reason given by the CEO while
granting extension of time by order dated 2.5.1986. This is
sufficient to indicate that the grant of extension of time
by the CEO was an arbitrary exercise of tower under Section
183-A, even if the power was available. The GOC-in-Chief
was, therefore, right in setting aside that order in
exercise of his power under Section 52 of the Act.
In the above view, the High Court was not justified in
interfering with the orders made by the GOC-in-Chief in
exercise of his power under Section 52 of the Act. Exercise
of the power under Article 226 of the Constitution by the
High Court in favour of the respondents in such a case was,
therefore, clearly unwarranted. The High Court’s order has,
therefore, to be set aside.
Consequently, the appeal is allowed; the impugned
judgment of the High Court is set aside. However, in view of
the offer made on behalf of the appellants to permit
retention of the existing structure in the manner indicated
above and to permit finishing of the existing structure in
the manner stated, we permit retention of the same. The
orders of the GOC-in-Chief would therefore, stand modified
to this extent only. The respondents to pay Rs.5,000/- as
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 11
costs to the appellants.