Full Judgment Text
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 29.01.2020
% Judgment pronounced on: 02.03.2020
+ FAO(OS) 532/2015 & CM.APPL 20560/2015
MMTC LIMITED ..... Appellant
Through Mr. P.V. Kapur, Senior Advocate,
Mr.Sanjeev Puri, Senior Advocate,
Mr. Rajeev Mehra, Senior Advocate
with Ms. Suman Yadav, Mr. Aditya
Sarin, Ms. Divya Krishan and
Mr.Hitendra, Advocates.
versus
ANGLO AMERICAN METALLURGICAL COAL PTY LTD
..... Respondent
Through Mr. Neeraj Kishan Kaul, Senior
Advocate with Mr.Samar Kachwaha,
Ms. Ankit Khushu, Mr. Ashok Sagar
and Mr. Aayush Marwah, Advocates
CORAM:
HON’BLE MR. JUSTICE G.S.SISTANI
HON’BLE MR. JUSTICE ANUP JAIRAM BHAMBHANI
ANUP JAIRAM BHAMBHANI, J.
This is an appeal under section 37 of the Arbitration and Conciliation
Act, 1996 (hereinafter the “A&C Act”) against judgment dated 10.07.2015
passed by a learned single Judge of this Court by which objections to the
majority arbitral award dated 12.05.2014 (hereinafter referred to as the
“Award”) filed under section 34 of the A&C Act have been dismissed. By
way of the Award, the claim filed by the respondent/Anglo American
Metallurgical Coal Pty. Ltd. for damages on account of non-lifting of
453,034 MT of coking coal by the appellant/MMTC Ltd. was allowed and
the respondent was held to be entitled to recover damages in the sum of
USD 78,720,414.92 alongwith pendente lite and future interest and costs. A
FAO(OS) 532/2015 Page 1 of 72
dissenting award dated 13.03.2014 was passed by the third arbitrator,
dismissing the claim petition filed by the respondent.
2. Some basic facts, which are not disputed, that are required to be
noticed for the disposal of this appeal are that the appellant, which is a
Government of India enterprise, entered into a Long-Term Agreement
(„Agreement‟) dated 07.03.2007 with the respondent. Under the
Agreement, the appellant agreed to purchase a certain quantity of freshly
mined and washed coking coal from the respondent over three delivery
periods between 01.07.2004 and 30.06.2007. Under clause 1.3 of the
Agreement, vide addendum dated 20.11.2008, the period of agreement was
extended by two years, thereby adding two delivery periods i.e. a Fourth
Delivery period commencing 01.07.2007 and ending 30.06.2008; and a
Fifth Delivery period commencing 01.07.2008 and ending 30.06.2009. By
consensus between the parties, the Fifth Delivery period was further
extended till 30.09.2009; and it was agreed that the respondent would
supply 466,000 MT of coal to the appellant at USD 300 per MT for the said
delivery period.
3. As it would appear from the record, in view of the global financial
crisis, after issuance of addendum dated 20.11.2008, vide letter dated
20.11.2008, the appellant requested the respondent for reduction in the
price of coal for quantities to be supplied for the Fifth Delivery period. It
may be noted that the subject matter of the arbitration proceedings are
disputes between the parties pertaining to the Fifth Delivery period i.e.
01.07.2008 to 30.06.2009 as extended up to 30.09.2009. It is during the
Fifth Delivery period that the respondent was required to supply to the
appellant 466,000 MT of coking coal at the rate of USD 300 per MT or
such other rate as agreed between the respondent and Rashtriya Ispat
FAO(OS) 532/2015 Page 2 of 72
Nigam Ltd. (RINL)/Steel Authority of India Ltd. (SAIL) during the
delivery period between 01.07.2008 and 30.06.2009. The essential
contention of the appellant is that the respondent failed to supply 454,034
MT of coking coal; whereas the respondent‟s contention is that the
appellant failed to buy the coal in breach of the Agreement.
Appellant’s Submissions :
4. Mr. P.V.Kapur, learned senior counsel appearing for the appellant
submits as under:
4.1. On 02.07.2009 the appellant wrote to the respondent inter alia
stating that the appellant was arranging for a vessel, namely a cargo
ship, for receiving/lifting a certain quantity of coal, referred to as a
„stem‟, in July 2009. By the same communication, and bearing in
mind the backlog under the Fifth Delivery period, the appellant
additionally requested for two stems, one each in August 2009 and
September 2009 respectively; and requested the respondent to
confirm availability of coal and convey the „lay-cans‟ as was
required on the part of the respondent under clause 7.2.1 of the
Agreement.
4.2. Vide reply e-mail dated 03.07.2009 the respondent
acknowledged the request for the supply in July 2009; but as regards
other shipments, the respondent did not offer a stem but stated that
it would "revert shortly". Through the aforesaid e-mail the
respondent therefore sought time to revert on the availability of
coal under the Agreement and for conveying the lay-cans.
4.3. In the meantime, by way of an ad-hoc arrangement, by way of
what the parties refer to as „letter agreement‟ dated 15.07.2009 the
parties agreed for a one-time ad-hoc supply of 50,000 MT of coking
FAO(OS) 532/2015 Page 3 of 72
coal. The parties agreed that 40,400 MT of coal was to be lifted at
USD 128.25 per MT and the balance 9,600 MT at USD 300 per MT
i.e. the contracted price for the Fifth Delivery period, as carry-over
under the Agreement. It is contended by the appellant that this „ ad-
hoc supply‟ was entirely distinct from the „contracted supply‟ under
the Agreement.
4.4. Since the respondent failed to revert as promised vide e-mail
dated 03.07.2009, the appellant wrote another e-mail dated
21.07.2009 inter alia again requesting for confirmation of stem
availability from the respondent for August 2009. Vide reply e-
mail dated 22.07.2009 the respondent inter alia informed the
appellant that:
"Unfortunately, at this stage we are unable to confirm
a stem in Aug/Sep for MMTC due to cargo
availability.
We are continuing to review our position and will
advise our preferred schedule for Oct-Dec 2009 as
soon as possible"
(Emphasis supplied)
4.5. Thereafter, on 04.09.2009 the appellant wrote to the
respondent inter alia stating that the appellant's requirement of
coking coal had increased but that after the ad-hoc shipment in July
2009, the respondent had not supplied any stem to the appellant; and
accordingly, the appellant requested one stem of 50,000 MT each in
October and November 2009. However, vide reply e-mail dated
07.09.2009 the respondent again expressed inability to supply coal
under the Fifth Delivery period on the ground of non-availability of
the contracted goods for the remainder of the year 2009.
FAO(OS) 532/2015 Page 4 of 72
4.6. It is submitted that the respondent had failed to confirm stem
availability for August and September 2009, which was within the
contracted period; and hence had failed to supply any material within
th
the Fifth Delivery period which was to expire on 30 September
2009.
4.7. Thereafter, vide its letter dated 21.09.2009 the respondent put
the agreement to an end inter alia stating that “The Fifth Delivery
Period of the Agreement has now finished bringing the term of the
Agreement to an end”.
4.8. Simultaneously with terminating the agreement, the
respondent also submitted a fresh proposal for delivery of the
balance quantity that was to be supplied by it under the Fifth
Delivery period and for renewal of the contractual arrangement. The
terms of the fresh proposal and proposed renewal of the agreement
appeared onerous to the appellant; which was communicated to the
respondent vide letter dated 25.09.2009, whereby the appellant
forwarded a counter-proposal, viz . to stagger the lifting/delivery
periods; but at the same time the appellant reiterated its request for
stems for October and November 2009. In this regard, the parties
exchanged correspondence dated 25.09.2009, 25.11.2009,
27.11.2009, 01.12.2009, 03.12.2009 and 07.12.2009 in which the
respondent refused to accept the proposals made by the appellant;
and accordingly, failed to arrive at any fresh agreement.
4.9. Subsequent to termination of the Agreement and upon the
negotiations and proposed renewal of the agreement not fructifying,
vide a legal notice dated 04.03.2010, the respondent demanded from
the appellant USD 78,720,414.92 along with interest @12% on
account of alleged breach of the appellant‟s obligation to lift 466,000
FAO(OS) 532/2015 Page 5 of 72
MT coal as envisaged under the Agreement. Vide its reply dated
24.04.2010 the appellant denied all allegations contained in the legal
notice inter alia stating that vide e-mails dated 22.07.2009 and
07.09.2009, it was the respondent who had expressed inability to
provide stems in August and September 2009 as also for the
remainder of the year on account of non-availability of cargo; and
that therefore, it was the respondent who was in breach of the
Agreement. By letter dated 02.11.2010 however, the respondent
reiterated its demand contained in legal notice dated 04.03.2010.
4.10. On 24.09.2012, i.e. more than 3 years after the respondent
terminated the Agreement, the respondent appointed Mr. Peter
Leaver, Q.C. as its arbitrator and submitted a request for arbitration
to the International Chamber of Commerce (ICC) along with its
Statement of Claim for USD 78,720,414.92, also claiming interest
and costs against the appellant. In the said claim, the respondent
alleged that the contracted quantities were available for supply with
the respondent; however, according to the respondent, it was the
appellant that had refused/failed to lift the quantities agreed to under
the Agreement. The respondent thus claimed damages in respect of
the 454,034 MT of coal that the appellant had allegedly not lifted, by
claiming the difference between the allegedly then prevailing market
price and the contracted price of goods. The appellant submits that it
is the common case between the parties that stem availability was
never confirmed within the Fifth Delivery period by the respondent
to the appellant as required under the terms of the Agreement.
4.11. It is further submitted that under the Agreement, the delivery
schedule and prices were to be mutually decided by the parties; and
the Tribunal had also not held that the appellant had an obligation to
FAO(OS) 532/2015 Page 6 of 72
offer a delivery schedule first in point of time. The single Judge
therefore erred in holding the appellant liable for breach of the
Agreement and for payment of damages. The Tribunal‟s observation
that the respondent had discharged its obligation under the
Agreement by relying upon respondent‟s letter dated 11.03.2009 is
misconceived. Under clause 7 of the General Conditions of the
Agreement, it was the respondent‟s obligation to intimate to the
appellant its readiness to deliver quantities of coal first, so that the
appellant could thereafter nominate a suitable vessel.
4.12. It is submitted that the plain language of communications
dated 02.07.2009 and 03.07.2009 indicates that the appellant sought
stems in August and September 2009 to clear contractual “backlogs”
and it was so understood by the respondent; and that though the
Tribunal accepted the plain language of the afore-stated
communications, it incorrectly held that the e-mails indicate that the
appellant had requested supplies at a discounted price of USD 128
pet MT and not at the price of USD 300 per MT as contracted under
the Agreement, which inference and interpretation is incorrect. Since
there is no ambiguity in the communications, the unilateral
understanding of the respondent‟s Marketing Manager Mr. John
Wilcox, as he deposed during evidence, that the e-mails pertained to
a request of discounted supply rather than fulfilment of the
obligations under the Agreement, could not have formed the basis of
the Tribunal‟s findings.
4.13. It is submitted on behalf of the appellant that reply e-mail
dated 07.09.2009 sent by the respondent shows that it did not have
coal for the remainder of the year 2009 and this constituted an
unqualified repudiation by the respondent of its obligation to supply
FAO(OS) 532/2015 Page 7 of 72
coal. Under section 37 of the Indian Contract Act 1872, when the
offer made for the performance of an agreement is not accepted, the
promisor is excused from performance provided the promise is
unconditional. The appellant herein performed its part of the
agreement by inviting intimations of stems; but the respondent put an
end to the contract, without there being any intimation by the
appellant that it was refusing to perform its obligation or that it was
disabled from performing the same. The said act of the respondent
violated the provision of section 30 of the Indian Contract Act. It is
also contended that under section 39 of the Indian Contract Act, non-
communication of an offer to perform, is not sufficient to entitle the
other party to terminate the contract.
4.14. Notwithstanding the fact that the appellant disputes receipt of
communication dated 11.03.2009 (the delivery of which is also not
proved by the respondent), it is the appellant's case that when, by
communication dated 11.03.2009, the respondent demanded that the
appellant give a delivery schedule, vide e-mails dated 02.07.2009 and
21.07.2009 the appellant provided such schedule and made an
unconditional offer. To this the respondent replied vide e-mail dated
07.09.2009 stating plainly that goods were not available for the
remainder of the year 2009; and vide letter dated 21.09.2009 the
respondent offered stems only for the year 2010. The respondent also
unambiguously stated that the Agreement and Fifth Delivery period
had come to an end; and thereafter made a fresh offer for supply of
coal for the year 2010. This shows that the respondent was unwilling
to perform its obligations under the Agreement and had repudiated
the same on 21.09.2009. In this backdrop, the appellant contends that
the single Judge incorrectly relied upon the appellant‟s letter dated
FAO(OS) 532/2015 Page 8 of 72
25.09.2009, to support the reason that in that letter the appellant did
not make an explicit statement as to the termination of the
Agreement.
4.15. It is further submitted that the Tribunal had failed to notice
that in June 2009 both parties had agreed that the discounted price
was only for that one-time transaction and that the other supplies
would be at the contracted price as agreed under the Agreement i.e.
USD 300 per MT.
4.16. Insofar as the calculation of the alleged damages is concerned,
it is submitted that for calculating damages, at the very least, the
respondent was required to prove the market price of coal on the date
of the alleged breach of the Agreement, that is 21.09.2009 or
30.09.2009. However, the respondent had not produced any evidence
to prove the market price but had only relied upon the negotiation
letters and correspondence seeking reduction in prices, which
correspondence related to nearly a year before the alleged date of
breach; and had tried to arrive at the market price through some
averages, which is contrary to the law laid down by the Supreme
Court in Murlidhar Chiranjilal v. Harshchandra Dwarakadas ,
(1961) 1 SCR 653.
4.17. It is submitted that the single Judge has ignored the erroneous
findings in the Award and has failed to notice that the Agreement
envisaged and required the parties to coordinate the supply and
delivery at the same time; and further, that indication of stem
availability by the respondent and nomination of vessel by the
appellant, were steps to be taken in „implementation‟ of the delivery
schedule and not „preparatory‟ to it. The single Judge has therefore
omitted to notice that the interpretation in this regard given by the
FAO(OS) 532/2015 Page 9 of 72
Tribunal is contrary to the terms of the Agreement. Clauses 7.2, 7.2.1
and clauses 2 and 4 of Annexure- IV to the Agreement clearly
establish the sequence in which the obligations contained in each of
the said clauses were to be performed, as per which, confirming stem
availability by the respondent was the first obligation; while the
agreement on the delivery schedule was a bilateral obligation; and
the nomination of vessel by the appellant was subsequent to that. The
delivery schedule had to be jointly prepared by the respondent and
the appellant based on the availability of stem. The Award however
erroneously accepted the contention of the respondent that it was not
obligatory for the respondent to first indicate stem availability to the
appellant. Thus the findings in the Award are contrary to the terms of
the Agreement; and hence, are in conflict with the public policy of
India, as per the decision rendered by the Supreme Court in the case
of Oil & Natural Gas Corporation Ltd. v. SAW Pipes (2003) 5 SCC
705 ; and is thus liable to be set-aside in terms of section 34 (2) (b)
(ii) of the A&C Act.
4.18. It is submitted that the single Judge also failed to appreciate
that the erroneous findings contained in the Award are also in
contravention of the provisions of section 52 of the Contract Act,
according to which it is incumbent upon contracting parties to follow
and comply with the sequence of obligations in the same order as
provided under a contract; and in the present case, upon failure of the
respondent to perform its first obligation under the Agreement in
such sequence, the appellant stood discharged from performing its
obligation for nominating the vessel. However the single Judge has
omitted to notice that the Tribunal had failed to return a finding on
the said issue. It if further the appellant‟s contention that the Award
FAO(OS) 532/2015 Page 10 of 72
is also in contravention of section 54 of the Contract Act, which
provides that in case of reciprocal promises, where one of them
cannot be performed or its performance cannot be claimed till some
other promise has been performed, then firstly, the failed promisor
cannot enforce the dependant promise; and secondly, the promisee of
the first promise need not perform the promise on its part. The
Tribunal however brushed aside the law laid down by the Supreme
Court in the case of Nathulal v. Phoolchand, (1969) 3 SCC 120 on
this aspect; and for this reason also therefore, the Award is liable to
be set-aside under section 34 of the Act.
4.19. It is submitted that the single Judge also failed to appreciate
that the findings in the Award, based on the oral testimony of the
respondent‟s witness Mr. Wilcox as recorded in paragraph 134 that:
“...the shipping arrangements throughout the period of the
Agreement were worked out through mutual discussions and
not subject to a sequence of obligations”
and that
“...the normal course was to meet and agree upon an
indicative Delivery Schedule. Only thereafter will the
Claimant offer stem.”
are findings which are contrary to the express written terms of
the Agreement and cannot therefore be accepted. The reliance by the
majority of arbitrators on the aforesaid oral testimony which is
contrary to the express terms of a written contract, is in the teeth of
the provisions of sections 91 and 92 of the Indian Evidence Act
1872, which prohibits and excludes oral evidence being led in
relation to a transaction which has been reduced into writing or in
relation to the terms of the contract, as has been held by the Supreme
Court in the case of Abdul Rashid Khan (Dead) & Ors. V. P.A.K.A.
Shahul Hamid & Ors (2000) 10 SCC 636 (para 5). Thus, the
FAO(OS) 532/2015 Page 11 of 72
findings in the Award based on oral evidence which evidence
contradicts the contractual terms, are liable to be set-aside, being
contrary to the written terms of the Agreement, as well as to the
provisions of law.
4.20. It is submitted that the single Judge failed to appreciate that
the findings in paragraphs 118 to 124 of the Award on the issue of
availability of coal with the respondent, are also contrary to the
material on record available in the form of e-mails sent by the
respondent on 03.07.2009, 22.07.2009 and 07.09.2009, which leaves
no manner of doubt and clearly establishes that firstly, the
respondent failed to confirm stem availability as required under
clause 7.2 of the Agreement; and secondly, the respondent had also
categorically communicated that it did not have any coal availability
for the remainder of the year upto December 2009.
4.21. It is submitted that the single Judge and the majority of
arbitrators had failed to appreciate that even if it is assumed that the
respondent owns coal mines, the same was no answer to e-mails
dated 22.07.2009 and 07.09.2009 in which the respondent, first
refused to confirm cargo availability and subsequently, in clear
words, admitted that it did not have coal for the remainder of the year
2009. The appellant point-outs that the respondent did not bring the
author of e-mail dated 22.07.2009 into the witness box. Instead of
noticing that the respondent had no answer to the said e-mails, the
majority of arbitrators relied upon and without basis accepted, the
oral evidence of Mr. Wilcox, including in relation to the contents of
the e-mail authored by another person namely Ms. Kim Street, who
is stated to be a subordinate officer of the respondent, who was not
produced to confirm the contents of the e-mails written by her in
FAO(OS) 532/2015 Page 12 of 72
response to the request made by the appellant‟s General Manager
Mr. Suresh Babu requesting confirmation of stems and supply of
coal. On the other hand the Tribunal ignored the evidence of the
appellant‟s witness Mr. Suresh Babu, who deposed that the e-mails
requesting the respondent to offer stems was under the Agreement
and therefore at the rate of USD 300 per MT and not under the one
time ad-hoc arrangement for supply of coal at the rate of USD 128
per MT.
4.22. The single Judge also failed to appreciate the erroneous
acceptance by the majority of arbitrators of the oral testimony of Mr.
Wilcox on account of so-called consistency with the appellant‟s
letter dated 20.11.2008. The single Judge erred in taking the view
that what was stated by Mr. Wilcox in his deposition was consistent
with the appellant's letter dated 20.11.2008; and omitted to notice
that a request by the appellant for a reduction in price was in fact
rejected by the respondent ; and that therefore Mr. Wilcox's
statement was not in line with what had transpired between the
appellant and the respondent in the context of appellant's letter dated
20.11.2008. It is urged that this in fact is an error apparent on the
face of the record. It is argued that the reliance on a letter issued in
2008 to decide availability of coal in July 2009 is also entirely
misconceived. The majority of arbitrators ignored the evidence of
Mr. Suresh Babu, who in his cross examination (Q6) answered that:
“... though it may not be viable for MMTC to buy and make
coke @ USD 300, MMTC realized its contractual obligation
with the supplier and therefore viability had taken a second
position”
FAO(OS) 532/2015 Page 13 of 72
in view of which there was no reason for the majority of
arbitrators to rely upon the letter dated 20 November 2008.
4.23. It is submitted that the single Judge could not have relied upon
letter dated 20.11.2008 to conclude that the appellant was not in a
position to continue buying coal at USD 300 per MT for the reason
that the said letter was only a request made by the appellant to the
respondent to reduce the price of the contracted quantity; and upon
the respondent‟s refusal to accede to such request, the appellant
never repeated its request. Secondly, on the same date in fact the
appellant had agreed to purchase the contracted material at USD 300
per MT. Thirdly, the letter was written ten months before the expiry
of the Fifth Delivery period; and seven months before the appellant
requested stem from the respondent.
4.24. It is further submitted on behalf of the appellant that letter
dated 11.03.2009 was never received by the appellant; but be that as
it may, as a prudent commercial person desirous of completing the
performance of the Agreement, the respondent would have
followed-up immediately with the appellant in that regard, which
the respondent did not do. It is pointed-out that the said letter has
been not been filed on record by the respondent; and even if it is
assumed that the appellant received the said letter, a reading of the
same does not establish any offer of delivery schedule made by the
respondent.
4.25. It is argued that the „backlog‟ referred to in e-mail dated
02.07.2009 was obviously, and could only have been, the remaining
quantity under the Agreement and not outside it. The single Judge
and majority of arbitrators ignored three material aspects: first, that
pursuant to a one-time ad-hoc arrangement 50,000 MT of mixed
FAO(OS) 532/2015 Page 14 of 72
cargo had already been shipped via MV Seavenus. Therefore, vide e-
mail dated 04.09.2009 when the Appellant requested for one stem of
50,000 MT and complained to the Respondent that
"after Seavenus (laycan 20-30 July), Anglo has not given any
stem to MMTC"
(Emphasis supplied)
the said request of 50,000 MT was, and could only have been,
under the Agreement at USD 300 per MT. Second, the lay-can i.e.
the period during which the ship chartered for carrying the coal was
required to be loaded, of the one-time ad-hoc shipment was 20-30
July 2009. Therefore, the refusal of the Respondent to confirm any
stem for August / September 2009 “due to cargo availability” by e-
mail dated 22 July 2009, could again, only have been under the
Agreement and not under any other understanding or arrangement.
Third, if the said e-mail pertained to an ad-hoc shipment or non-
contractual shipment, the same should have carried the proposed
price and specifications. Since there is no price or specification
mentioned in the said e-mail, the only possible conclusion is that the
e-mail sought deliveries under the Agreement at the rate of USD 300
per MT.
4.26. It is submitted that the single Judge relied upon the statement
of Mr. Wilcox to the effect that the price of coal had slumped and the
respondent had been dumping coal in China; and the respondent had
only declined to supply coal at below the contract price of USD 300
per MT. On the contrary, the respondent in its evidence had stated
that prices had started rising in June 2009; but the Award
FAO(OS) 532/2015 Page 15 of 72
erroneously records that the price of coal remained low during the
Fifth Delivery period.
4.27. It is submitted that the Award quantifies for damages on „no
evidence‟ since firstly, the affidavit and additional affidavit of Mr.
Wilcox is completely silent on the market price on 21.09.2009 or
30.09.2009. Secondly, letter dated 03.12.2009 of the appellant, relied
upon by the majority of arbitrators, also does not mention the rate of
coal on 21.09.2009 or 30.09.2009. Thirdly, the market rate of coal
cannot be established from a special long-term contract between the
Respondent and third parties, in this case SAIL and RINL. The
majority of arbitrators however ignored the fact that on 21.09.2009
or 30.09.2009 the only evidence available as regards the price of coal
were the special contracts between the Respondent and the
SAIL/RINL and the Agreement between the parties. Both these
contracts were special; and both these third-party contracts reflected
completely different rates. While the Agreement stipulated the rate of
USD 300 per MT, on the same date even as per the Respondent, the
contracts between the Respondent and SAIL/RINL stipulated a rate
of USD 128 PMT. Thus, there was no credible „market price‟ of coal
on 21.09.2009 or 30.09.2009 available before the Tribunal. These
special contracts are long term and are dependent on long term
dealings between parties and thus cannot establish the prevalent
„market price‟ on the date of alleged breach. Also, purchases made
by the appellant from BHP Mitsui were based on a long-term special
contract and at the relevant time purchases were made @USD 300
PMT.
FAO(OS) 532/2015 Page 16 of 72
4.28. While relying upon communication dated 21.09.2009, the
appellant has also submitted that the claim of the respondent was
patently beyond limitation, since having terminated the agreement on
21.09.2009, the respondent filed the claim on 24.09.2012, that is
beyond the limitation period of three years.
4.29. It is submitted that the finding of the single Judge and the
Tribunal with respect to interest is also perverse since the amount of
USD 27,239,420.29 calculated @7.5% p.a. on the principal awarded
amount of USD 78,720,414.92 from 30.09.2009 till 12.05.2014 is
exorbitant; and the LIBOR rate of interest or a lower rate of interest
should have been awarded, if at all. The date of commencement of
interest, that is 30.09.2009, is also incorrect. The post award interest
@15% p.a. till date of payment is also exorbitant. Furthermore, the
costs amounting to USD 977,395.00 is without any basis.
Case law relied upon by the Appellant:
5. Senior counsel for the appellant relies upon the following judicial
precedents in support of his contentions:
5.1. Oil & Natural Gas Corporation Ltd. v. Saw Pipes : (2003) 5
SCC 705 (paragraphs 1, 13 to 17, 22, 30, 31, 64 and 74), to submit
that the phrase “public policy of India” used in the context of section
34 should be given a wider meaning. What is for public good or in
public interest has been interpreted variously from time-to-time. An
award which prima facie violates statutory provisions cannot be held
to be in public interest and would adversely affect the administration
of justice, and should thus be set-aside. The Supreme Court has
added to the narrower meaning given to the term “public policy” in
Renusagar Power Co. Ltd. v. General Electric Co. : 1994 Supp (1)
SCC 644 and has observed that an award could also be set-aside on
FAO(OS) 532/2015 Page 17 of 72
the ground of patent illegality. Also, an award can be set-aside under
section 34 of the Act if the same is contrary to the fundamental
policy or interest of India, justice or morality. But the illegality must
go to the root of the matter; and if the illegality is of trivial nature, it
cannot be held that the award is against public policy. An award can
also be set-aside if it is so unreasonable or unfair that it shocks the
conscience of the court; and if such award is opposed to public
policy, it is required to be adjudged void;
5.2. National Thermal Power Corporation v. Siemens : 2012 SCC
OnLine Del 5686 (paragraph 47), to submit that an arbitral tribunal
must act according to the terms of contract; and the construction of
contractual terms has to be that of a fair-minded, reasonable person.
In the absence of a reasonable construction, the award should be set-
aside under section 34 or 37 of the A&C Act;
5.3. Oil & Natural Gas Corporation Ltd. v. Western Geco
International Ltd. : (2014) 9 SCC 263 to submit that perversity or
irrationality of decisions is to be tested on the Wednesbury principle
of reasonableness. If, on facts proved before the arbitrators, they
have failed to draw an inference which ought to have been drawn; or
if they have drawn an inference which, on the face of it, is untenable,
resulting is miscarriage of justice, the adjudication even when made
by an arbitral tribunal that enjoys considerable latitude and play at
the joints in making awards, will be open to challenge; and may be
cast away or modified depending upon whether the offending part is,
or is not, severable from the rest;
5.4. State of Orissa v. Samantary Construction Pvt. Ltd : 2015
SCC OnLine SC 856 (paragraph 22), to submit that the award is
required to be a reasoned one, unless the parties agree that no reasons
FAO(OS) 532/2015 Page 18 of 72
are to be given or the award is based on agreed terms under section
31 of the A&C Act. The arbitrator ought to have evaluated the claim
for damages, in the absence of which the award can be held to be
perverse or based on non-application of mind; and a perverse award
can be set aside under section 34 of the Act;
5.5. NHAI v. Progressive Construction : 2017 SCC OnLine Del
7867 (paragraphs 21-23), to submit that an award which is contrary
to substantive provisions of law or against the terms of the contract
or patently illegal or prejudicial to the rights of the parties, is open to
interference by the court under section 34(2) of the A&C Act. It is
open to the court to consider whether the award is against the
specific terms of the contract; and if so, interfere with it on the
ground that it is patently illegal and opposed to the public policy of
India;
5.6. HRD Corporation v. GAIL : (2018) 12 SCC 471 (paragraphs
19 to 20), to submit that under section 34 of the Act an arbitral award
governed by Part-I of the A&C Act can be challenged on the ground
of „patent illegality‟ appearing of the face of the award. Counsel
further relies on Associate Builders v. DDA : (2015) 3 SCC 49
(paragraphs 22, 27 to 61) to submit that where a finding in the award
is based on no evidence; or ignores vital evidence; or an arbitral
tribunal takes into consideration something irrelevant for arriving at
a decision, such decision would be perverse and can be set-aside
under section 34. An award is said to be against public policy if it is
against justice, morality or is patently illegal; and an award is against
justice, if it shocks the conscience of the court;
5.7. Emkay Global Financial Services v. Giridhar Sondhi :
(2018) 9 SCC 49 (paragraph 21) and on Promod Kumar v. Religare :
FAO(OS) 532/2015 Page 19 of 72
249 (2018) DLT 682; to submit that although ordinarily an
application under section 34 of the A & C Act does not require
anything beyond the record that was before the arbitrator, in the light
of the amendments made to sections 34(5) and 34(6), the Supreme
Court has now ruled that if there are matters not contained in such
record which are relevant to the determination of the issues arising
under section 34(2)(a) they may be brought to the notice of the court
by way of affidavits; and that cross-examination of deponents should
not be allowed unless absolutely necessary, since the truth will
emerge on a reading of the affidavits filed by the parties;
5.8. ADTV Communication Pvt. Ltd. v. Vibha Goel : 2018 V AD
(DELHI) 273 (paragraph 35), to submit that an appeal under section
37 of the Act is a form of second appeal; and therefore while the
court would be hesitant to interfere with the decision of the single
Judge, however if it is shown that the view taken by the single Judge
is palpably erroneous on facts or in law, or is manifestly perverse, the
court would interfere under section 37;
5.9. IRB Ahmedabad Vadodara Super Express Toll Ways Pvt.
Ltd. v. NHAI : 2018 SCC OnLine Del 8946 (paragraphs 29 to 31), to
submit that though construction of the terms of a contract is
primarily for an arbitrator to decide, if the arbitrator construes the
contract in a manner that it could be said to be something that no
fair-minded or reasonable person would do; and if the construction of
contractual terms is not a possibility, the legality of such construction
can be judged on the touchstone of section 34 of the A&C Act;
5.10. Delhi Metro Rail Corporation Ltd. v. Delhi Airport Metro
Express Private Limited reported as 2019 SCC OnLine Del 6562,
whereby, applying the principles enunciated in Associate Builders
FAO(OS) 532/2015 Page 20 of 72
(supra), the Division Bench partially set-aside an arbitral award as
suffering from perversity, irrationality and patent illegality on the
face of the award on account of confusion and ambivalence in the
award; holding that the arbitral tribunal had ignored and did not
consider vital evidence; and that the tribunal had relied upon
averments made in the statement of claim instead of evidence and
material to arrive at the award amount;
5.11. MMTC Ltd. v. M/s Vedanta Ltd. : Civil Appeal No. 1862 of
2014 decided on 18.02.2019 (paragraph 11), to submit that an
arbitral award can be set-aside under sections 34 and 37 of the A&C
Act on account of patent illegality, if the tribunal has ignored vital
evidence;
5.12. Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd. :
2019 SCC OnLine 1656 (paragraph 36), to submit that arbitral award
can be set-aside under sections 34 and 37 of the A&C Act on the
ground of insufficiency and inadequacy of reasoning;
5.13. With regard to the contention that the author of e-mail dated
22.07.2009 i.e. Ms. Kim Street was not cross-examined, counsel
places reliance on Sardar Gurbaksh Singh v. Gurdayal Singh : AIR
1927 PC 230 to submit that the true object to be achieved by a court
of justice can only be furthered with propriety by the testimony of
the party, who, personally knowing the whole circumstances of the
case, can dispel the suspicions attached to it. Senior counsel also
relies upon Vidhyadhar v. Manik Rao : (1999) 3 SCC 573 to submit
that if a party abstains from entering the witness-box, it would give
rise to an adverse inference against him. Where a party to the suit
does not appear in the witness-box and state his own case on oath
and does not offer himself to be cross-examined by the other side, a
FAO(OS) 532/2015 Page 21 of 72
presumption would arise that the case set-up by him is not correct.
Reliance was also placed upon Man Kaur (Dead) v. Hartar Singh :
(2010) 10 SCC 512, to submit that if a plaintiff has to prove that he
was ready and willing to perform his part of the contract, that is, to
perform his obligations in terms of the contract, he should
necessarily step into the witness box and give evidence that he was
willing to perform his part of the contract and subject himself to
cross-examination on that issue. On the rule of hearsay evidence,
counsel relied upon Kalyan Kumar Gogoi v. Ashutosh Agnihotri :
(2011) 2 SCC 532 to submit that since Ms. Kim Street was not
produced for examination and cross-examination her e-mail ought
not to have been relied upon;
5.14. Learned counsel relies next upon Gangabai w/o Rambilas
Gilda v. Chahhabubai w/o. Pukharajji Gandhi : (1982) 1 SCC 4, to
submit that the bar imposed by sub-section (1) of section 92 of the
Indian Evidence Act applies only when a party seeks to rely upon the
document embodying the terms of the transaction. In that event, the
law declares that the nature and intent of the transaction must be
gathered from the terms of the document itself; and no evidence of
any oral agreement or statement can be admitted as between the
parties to such document for the purpose of contradicting or
modifying its terms. Reliance is also placed upon Abdul Rashid
Khan v. PAKA Shahul Hamid (supra) to submit that the law
regarding pleas taken by parties beyond a written agreement is well
settled. In view of section 92 of the Indian Evidence Act, where any
contract is required by law to be reduced in writing, then no oral
evidence or understanding to the contrary or apart from the said
contract is admissible in law. While relying upon State Bank of
FAO(OS) 532/2015 Page 22 of 72
India v. Mula Sahakari Sakhar Karkhana Ltd : (2006) 6 SCC 293
counsel submits that in a commercial document, surrounding
circumstances are relevant for construction of a document only if any
ambiguity exists therein and not otherwise. Referring to oral
evidence, when section 92 of the Indian Evidence Act would be
attracted, is flawed;
5.15. Sahebzada Mohammad Kamgarh Shah v. Jagdish Chandra :
AIR 1960 SC 953 to submit that, if and when, parties have first
expressed themselves in one way and then go on to say something
which is irreconcilable with what has gone before, it is the duty of
the court to look at all parts of the document to identify what was
really intended by the parties. Reliance is also placed upon V.S.
Talwar v. Prem Chandra Sharma : (1984) 2 SCC 420 to submit that
while construing instruments, one must have regard not to the
presumed intention of the parties, but to the meaning of the words
which they have used; and while construing a lease deed, reference
to oral evidence or even the tenant‟s documents would be wholly out
of place. The terms of the document, if they make any good
meaning, must be given effect to. Reliance is also placed upon Roop
Kumar v. Mohan Thedani : AIR 2003 SC 2418 to submit that it is a
general and most inflexible rule that wherever written instruments
are appointed, either by requirement of law or by the contract of
parties, to be the repositories and memorials of truth, any other
evidence is excluded from being used either as a substitute for such
instruments, or to contradict or alter them. Relying upon
Transmission Corporation v. GMR Vemagiri Generation : AIR
2018 SC 2965, counsel submits that if the contract is capable of
interpretation on its plain meaning with regard to the true intention of
FAO(OS) 532/2015 Page 23 of 72
parties, it will not be prudent to read the implied terms on the
understanding of a party or by the court based on any notions of
business efficacy. A commercial document cannot be interpreted in a
manner so as to arrive at a conclusion that is at complete variance
with what may originally have been the intention of the parties. Such
a situation can only be contemplated when the implied term lends
efficacy to the terms of the contract;
5.16. In regard to the submission made by the appellant that the
respondent wrongfully repudiated the Agreement, counsel places
reliance upon Florrie Edridge v. Rustomji Danjibhoy Sethna : AIR
1933 PC 233 to submit that a wrongful repudiation by one party
cannot, except by the election of the other party so to treat it, put an
end to an obligation; if the other party still insists on performance of
the contract, the repudiation is what is called „brutum fulmen‟ , that is,
the parties are left with their rights and liabilities as before. Reliance
is also placed upon Gajjala Nagisetti v. Maddi Venkatasubbayya :
AIR 1935 Mad 345 to submit that repudiation of the contract by one
party does not release the other party from their own obligations
under the contract. The party which did not repudiate should not fail
to perform the condition precedent. Reliance in this regard is also
placed upon State of Kerala v. Cochin Chemical : AIR 1968 SC
1361 and Jhandoo Mal-Jagannath v. Phul Chand Fateh Chand :
AIR 1925 Lah 217.
5.17. With respect to the contention that the respondent filed the
claim before the Tribunal beyond the limitation period, counsel relies
upon Deepak Khosla v. Vikram Bakshi : 2018 (5) RAJ 222 (Del).
FAO(OS) 532/2015 Page 24 of 72
Respondent’s Submissions:
6. Per contra , Mr. Neeraj Kishan Kaul, learned senior counsel
appearing for the respondent submits as under:
6.1. By e-mails dated 08.10.2008 and 14.10.2008 the respondent
offered to deliver the contractual quantity of coal; but as recorded in
the respondent‟s internal e-mails (both) dated 11.11.2008, the
respondent had gathered that the appellant would not lift coal till
February 2009. Pursuant to several meetings held between them, the
respondent sent letter dated 11.03.2009 asking the respondent to lift
coal and provide a delivery schedule; however, the appellant did not
reply to the same.
6.2. Counsel submits that on account of inability on the part of the
appellant to lift coal, on 15.06.2009 the respondent agreed to supply
one mixed-price shipment of 50,000 MT of coal to the appellant.
This mixed-price shipment included 9,600 MT of coal at USD 300
per MT and 40,400 MT at USD 128.25 per MT. In this regard the
parties signed letter agreement dated 15.07.2009, which letter
agreement was signed by the appellant on 22.07.2009. By this date
over 9 months of the Fifth Delivery period had already elapsed but
the respondent was nowhere close to performing its part of the
bargain to lift the agreed quantity of coal under the Agreement for
the Fifth Delivery period. However, in order to preserve the
commercial relationship between the parties, the respondent made a
„without prejudice‟ offer on 21.09.2009 by which the respondent
proposed that the appellant should take delivery of the carryover
quantity of coal under the Agreement; and proposed further renewal
of the Agreement, which was kept open for acceptance by the
respondent till 30.09.2009. By letter dated 25.09.2009, the appellant
FAO(OS) 532/2015 Page 25 of 72
rejected the same, stating that the suggestion that the appellant
should lift a total quantity of 225,174 MT by 31.03.2010 seemed to
be a near impossibility in the backdrop of the prevailing harsh
economic conditions . In response to appellant‟s letter dated
25.09.2009, by its letter dated 25.11.2009 the respondent made a
revised „without prejudice‟ offer requiring the appellant to lift 85,000
MT at USD 300 by March 2010 and the balance over the next two
years. It is contended however that by its letter dated 27.11.2009, the
appellant stated that it could not accept this offer unless the
respondent agreed to supply mixed-price cargo, which would have
reduced the overall price to USD 160 per MT.
6.3. Senior counsel for the respondent further contends that the
submission of the appellant that it offered to lift the entire 466,000
MT of coal at USD 300 per MT during the Fifth Delivery period and
the respondent refused to deliver the same and therefore committed
breach of the Agreement, is irreconcilable with the admissions made
by the appellant in letters dated 20.11.2008, 25.09.2009, 27.11.2009
and 03.12.2009. The respondent argues that the said letters highlight
that the appellant was in no position to lift any shipment at USD 300
per MT.
6.4. It is further submitted that the letters sent by the appellant in
July/September 2009 amounted to a request to supply coal by way of
non-contractual, mixed-price shipments; and the respondent was not
obliged to accept the requests so made. Also, the only reason for the
appellant‟s non-acceptance of the „without prejudice‟ offers dated
21.09.2009 and 25.11.2009 made by the respondent was that it
required mixed-price shipments for the entire un-lifted quantity of
coal under the Fifth Delivery period.
FAO(OS) 532/2015 Page 26 of 72
Case law relied upon by the Respondent:
7. Senior counsel for the respondent relies upon the following judicial
precedents in support of his contentions:
7.1. On the proposition that the scope of interference of courts
under section 37 of the Act is even more restricted than that under
section 34 of the Act, counsel relies upon para 14 in the case of
Morepen Laboratories Limited v. Phafag AG. : 2013 (136) DRJ 668,
wherein the court has held that the Division Bench as an appellate
forum would intervene only if the single Judge‟s determination about
the award exceeding jurisdiction or being manifestly contrary to
Indian law or substantive provisions, is erroneous. Short of such
threshold, this court, as an appellate court would not substitute its
opinion for another plausible opinion adopted by the court of first
instance. Reliance is also placed on paras 15 to 18 and 21 to 23 in the
case of M/s L.G. Electronics India (P) Ltd. v. Dinesh Kalra : 2018
SCC OnLine Del 8367 in this regard;
7.2. Associate Builders (supra) (paras 17, 32, 33, 45, 48, 49 and
56) to submit that none of the grounds contained in section 34(2)(a)
of the Act deals with the merits of a decision rendered by an arbitral
award. It is only when an arbitral award is in conflict with the public
policy of India that the merits of the award are to be looked into,
under certain specified circumstances;
7.3. NHAI v. Progressive Constructions Ltd. : 2017 SCC OnLine
Del 7867 (paras 30, 31, 37 and 43), whereby this court held that a
possible view by the arbitrator on facts has necessarily to be accepted
as the arbitrator is the ultimate master of quantity and quality of
evidence to be relied upon when he delivers the award. Thus, an
award based on little evidence or no evidence, which does not
FAO(OS) 532/2015 Page 27 of 72
measure-up in quality to a trained legal mind would not be held to be
invalid on this score. Once it is found that the arbitrator‟s approach is
not arbitrary or capricious, the arbitrator is the last word on facts.
7.4. Maharashtra State Electricity Distribution Company Limited
v. Datar Switchgear Limited & Ors : (2018) 3 SCC 133 (paragraph
51), to submit that the scope of intervention of courts under section
34 of the A&C Act is limited since the Tribunal is the master of
evidence, and the findings of fact arrived at by the arbitrators on the
basis of evidence on record are not to be scrutinized as if the court
were sitting in appeal; which position now stands settled by a catena
of judgements pronounced by the courts without any exception.
7.5. In regard to the contention raised as to contextual
interpretation of a document, more particularly the e-mails and letters
exchanged between the parties, senior counsel relies upon para 12 of
Ram Kishore Lal v. Kamal Narayan : AIR 1963 SC 890, to submit
that to ascertain the intention of the parties to an instrument, the
court has to consider the circumstances under which particular words
in a document were used. Counsel relies next upon Investors
Compensation Scheme v. West Bromwich Building Society : [1997]
UKHL 28 , to contend that the meaning of a document must be taken
as what the parties, using the words in the document, would
reasonably have taken them to mean against the relevant background.
Counsel further relies upon paras 53 and 61 in Zurich Insurance
(Singapore) Pte Ltd v. B-Gold Interior Design & Construction Pte
Ltd : [2008] 3 SLR 1029 to contend that a contract ought to be
interpreted within its context, i.e. the circumstances surrounding the
formation of the contract, including the object or purpose for which it
was entered into; and that the plain meaning or literal approach is not
FAO(OS) 532/2015 Page 28 of 72
an alternative to contextual interpretation, but can only be understood
as operating within the contextual method. Counsel relies next upon
a decision of the High Court of Bombay in ICICI Bank v. United
Breweries (Holdings) Ltd. : 2015 SCC OnLine Bom 5913, arguing
that on construction of a commercial contract, the court must
consider the intention of the parties, which must be gathered not
from the recitals alone, but also from the main agreement itself.
Discussion and Conclusions :
8. We have heard learned senior counsel for the parties, perused the
relevant correspondences and have considered their rival contentions.
9. The arguments of Mr. P.V. Kapur may be summarised as follows:
(i) that the award suffers from perversity, irrationality and patent
illegality;
(ii) that the majority of arbitrators have exceeded their jurisdiction
by giving their own interpretation to the communications
between the parties, when in fact the communications
themselves are crystal clear; and there was no requirement of
interpretation; and thus, the award rendered is against public
policy;
(iii) that the findings of the Tribunal are patently illegal and lack
judicial approach by being unreasonable, unfair, arbitrary and
whimsical in the light of two vital communications dated
22.07.2009 and 07.09.2009 in which the respondent had
categorically stated that it did not have any coal available to
supply till the end of the year 2009;
(iv) that in view of the clear communication by the respondent that
it had no coal available to supply, the question of the appellant
having defaulted in its commitment to lift coal does not arise ;
and that therefore, there was no question of imposing damages
upon the appellant;
(v) that furthermore, the interpretation given in the Award to the
communication exchanged between the appellant and the
FAO(OS) 532/2015 Page 29 of 72
respondent, to the effect that the appellant had placed a request
for coal at a discounted rate of USD 128 per MT from the
respondent, is an inference which is baseless and perverse and
does not arise from the plain or contextual reading of the e-
mails and correspondence exchanged between the parties since
the rate of USD 128 per MT was discussed and agreed
between the parties only in relation to one mixed-price
shipment referred to in letter agreement dated 15/22.07.2009;
and the subsequent demand by the appellant for coal was
evidently at the contractually agreed rate of USD 300 per MT
under the Agreement.
10. The arguments of Mr. Neeraj Kishan Kaul, on the other hand may be
summarised as under:
(i) that the scope of interference in an appeal under section 37 of
the Act is even narrower than that under section 34 while
deciding the initial objections to an award;
(ii) that the Arbitral Tribunal is the final word on facts, on
interpretation of the documents and the application of the law.
In case the Tribunal has taken a plausible view the court
would not interfere under section 37, even though another
view may be possible;
(iii) that the arbitrators were entitled to read the documents
holistically, and based on the correspondences exchanged
between the parties, the only view possible has been accepted
by the Tribunal, which cannot be faulted. Nothing has been
placed before the court to show that the findings in the Award
are outrageous, illogical, perverse or irrational; or which no
reasonable person would arrive at. The court cannot sit as a
court of appeal and consequently correct errors of fact as the
arbitrators are the final arbiter of quantity and quality of
evidence. Section 34(2A) of the A&C Act requires patent
illegality to appear on the face of the award and re-
appreciation of evidence cannot be permitted. Additionally,
FAO(OS) 532/2015 Page 30 of 72
nothing on record in relation to the award is such as would
shock the conscience of the court;
(iv) that on merits, the respondent has clearly expressed reluctance
to lift the quantity of coal as per the Agreement, which is
evident from the fact that upto the Fifth Delivery period,
466000 MT of coal were to be lifted between 01.07.2008 to
30.09.2009 but only 11,966 MT were actually lifted;
(v) that furthermore, repeated communications by the appellant
show that the appellant was consistently requesting for
reduction of price of coal, thereby declining to lift coal at the
contractually agreed price of USD 300 per MT under the
Agreement.
11. Upon a conspectus of the submissions made by the parties, the
position that emerges is that as per the agreement entered into between the
parties, the Fifth Delivery period began from 01.07.2008 and, after
extension, ended on 30.09.2009. During the Fifth Delivery period 4,66,000
MT was to be supplied by the respondents to the appellant at 300 USD per
MT. Interestingly even as an addendum dated 20.11.2008 to this agreement
was being entered into, the appellant addressed a communication of the
same date to the respondent highlighting that due to worldwide crisis in the
financial markets, there had been an unprecedented fall in the price of
major commodities including steel. It was also highlighted that there was
an apprehension about the beginning of economic recession world-wide,
which may continue for a long time. In these circumstances, the appellant
pleaded that prices of iron and steel products in the international market
had nose-dived in the months of September and October 2008; and that pig
iron, the finished product manufactured by the appellant was not in demand
in the consumer market even at the rate of USD 300 per MT. Consequently,
the appellant requested the respondent for reduction in the price of coal
FAO(OS) 532/2015 Page 31 of 72
since it was not viable to manufacture pig iron to be sold at the rate of USD
300 per MT if the input cost of coal for such manufacture was itself USD
300 per MT. While on the one hand, it is the appellant's contention that the
request for reduction in price of the coal was made only in relation to an
ad-hoc supply of coal that was requested by the appellant from the
respondent and not a reduction in price as agreed to under the Agreement,
it is the respondent's contention that the appellant had requested a reduction
in the price of coal agreed to under the Agreement; and that therefore the
respondent had declined to supply coal, stating that the coal was not
available, only for the reason that the appellant was requesting supply of
coal at a price less than the contracted price under the Agreement.
12. As the dispute between the parties revolves around the interpretation
of the communications exchanged between them between July 2008 and
December 2009, we deem it appropriate to reproduce the relevant
correspondence in extenso hereinbelow:
Letter dated 20.11.2008 sent by the appellant to the respondent:
th
File no. MMTC/C&HC/08-09/CC/Anglo/798 20 November, 2008
"
M/s. Anglo Coal Australia Pty. Ltd.
201, Charlotte Street
Brisbane 4000
Queensland
Australia. Fax no. 0061-7-3834-1390
KIND ATTN: MR. JOHN B WILCOX, MARKETING MANAGER
Sub:- Addendum to Long Term supply of coking coal contract for the
Delivery Period 2008-09
Dear Sirs,
As discussed, we hereby confirm the acceptance of coking coal supply
during the period 2008-09 vide Addendum No. 2 To LT Agreement No.
th
MMTC/C&HC/LT/HCC/NINL/ANGLO/585 DATED 7 March 2007.
FAO(OS) 532/2015 Page 32 of 72
As you are aware, due to worldwide crisis in financial markets, there has
been unprecedented fall in prices of major commodities including steel.
Such a steep fall is a rare phenomenon and all over there is a feeling that
it is a beginning of economic recession in the world. It is feared that it
may continue for long time to come.
The prices of iron and steel products in the international market has
nose-dived in the month of September and October 2008 and pig iron, a
finished product manufactured by us and being exported is not getting
customer on date even at US$300 FOB. Same is the situation in the
domestic market and we are not able to sell our product. Under the
circumstances, you will appreciate it has become absolutely unviable to
produce and sell pig iron based on the imported coking coal having
price of US$300 per tonne FOB for hard coking coal. More than three-
fold increase in the price of coking coal during a period when the prices
of finished steel including pig iron had virtually crashed, will make
difficult for us to run the plant on sustainable basis. The sustainable
depreciation of Indian rupees to US$ has further added to our woes and
under the circumstances. We have already cut the production to a bare
minimum so as to just keep running our coke oven batteries as well as
blast furnace. In view of unprecedented recessionary trends in the
economy and consequent abnormal low realization on pig iron, we
request price reduction of coal for quantities finalized for delivery
st th
during 1 July 2008 to 30 June 2009 period to a level that was settled
st th
for delivery period 1 July 2007 to 30 June 2008. This only will help us
to keep the plant running and to produce on consistent basis.
We look forward for your positive response.
Yours faithfully,
For MMTC Ltd
Ved Prakash
Chief General Manager "
Letter dated 11.03.2009 sent by the respondent to the appellant :
“Mr.H.S. Mann Brisbane Corporate Office
Director (Marketing)
MMTC Limited Rod Elliott
Core-1 “Scope Complex” General Manager Marketing &
7 Institutional Area, Lodhi Road Transportation
New Delhi – 110003
India Direct Fax: +61 (0)7 3834 1366
Direct Line: +51 (0)7 38341297
e-mail: rod.elliott@anglocoal.com.au
11 March 2009
Dear Mr. Mann
FAO(OS) 532/2015 Page 33 of 72
AGREEMENT FOR THE SALE AND PURCHASE OF COKING
COAL NO. MMTC/C&HC/LT/HCC/NINL/ANGLO/585 DATED 7TH
MARCH 2007 BETWEEN ANGLO COAL AUSTRALIA PTY LTD
('ANGLO') AND MMTC LIMITED ('MMTC')
"We refer to discussions in New Delhi on 24th February 2009
between Mr. Suresh Babu and our Mr John Wllcox at your office.
Anglo remains very concerned that deliveries for the Fifth Delivery
Period of the Agreement remain unperformed by MMTC, and that to
date MMTC has not intimated arrangements for performance of
obligations arising under the Agreement.
Accordingly, kindly send MMTC's proposed Delivery Schedule for the
Fifth Delivery Period, as referred to in Clause 4 of Annexure IV of the
Agreement, for our consideration. Under the circumstances, we seek
your response by close of business Brisbane time on Friday 20th
March 2009."
Yours sincerely
Anglo Coal Australia Pty Ltd
Rod H.Elliott
General Manager, Marketing & Transportation”
E-mail dated 02.07.2009 sent by the appellant to the respondent:
“From: sureshbabu@mmtclimited.com
To: John.Wilcox@,anglocoal.com.au
Cc: chris.dhar@gauri.com.au
Sent: Thursday, July 02,2009 11:01 AM
Transchart has already entered the market on behalf of MMTC for the
vessel against July 09 stem.
Keeping the huge backlogs in mind, we would 1ike to avail two stems
in the August 09 and one in September 09. Please confirm availability
and convey the laycans.
With Thanks & Regards
Suresh Babu
GM(coal & Coke)
Cell: 91 9818913799
Fax +91 11 2436 6362”
E-mail dated 03.07.2009 sent by the respondent to the appellant:
“ From: Street Kim
To: sureshbabu@mmtclimited.com
FAO(OS) 532/2015 Page 34 of 72
Cc: chris.dhar@gauri.com.au ; Martvr, Rebecca ; Baxter, Alan
Sent: Friday, July 03, 2009, 9:46 AM
Subject: Anglo/MMTC Shipment July
Dear Suresh,
Thank you for your advice, we look forward to your vessel nomination
against agreed stem in laydays 20-30/July earliest.
Regarding other shipments planned in our schedule, we shall revert
shortly.
Regards,
Kim Street
Anglo Coal Australia Pty Ltd.”
Letter dated 15.07.2009 sent by the respondent to the appellant:
“MMTC Limited
Core – 1 Scope Complex, Brisbane Corporate Office
th
7 Institutional Area, Ian Wakely
Lodhi Road Head of Metallurgical Coal
New Delhi 110003
INDIA
Direct Fax +61(0)7 3834 1366
Direct Line +61 (0)7 3834 1256
e-mail Ian.Wakely@anglocoal.com.au
th
15 July 2009
Dear Mr. Suresh Babu,
Anglo/MMTC:09/10 Supplies under Long Term
Agreement
We refer to our existing agreement for the sale of coal namely,
Agreement No: MMTC/C & HC/LT/HCC/NINL/ANGLO/585 dated 7
March 2007 ("the Long Term Agreement")
th
Further to our meeting with you on 15 June 2009, we are pleased to
confirm our agreement to the following arrangement:
1. One full shipment of Isaac Hard Coking Coal to load 50,000mt +/-5%
from Dalrymple Bay Coal Terminal, Queensland under the Long Term
Agreement.
2. Laycan 20-30 July 2009
3. For this shipment, MV "SEAVENUS" (or substitute vessel), it is agreed
that:
(a) 9,600mt of carryover from the 2008/09 Delivery Period shall be supplied
at US$300.00 on the terms outlined in paragraphs 5 and 7 below; and
(b) the balance of approximately 40,400mt shall be supplied on an ad-hoc
th
basis at a price of US$128.25mt (as finalized with EJC on 16 June
2009) on the terms outlined in paragraphs 6 and 7 below.
4. The total carryover quantity remaining undelivered from the 08/09
st
Delivery Period as at 1 July 2009 is agreed as 463,634mt.
FAO(OS) 532/2015 Page 35 of 72
5. The carryover quantity to be performed from the 08/09 Delivery Period
is to be performed as per the terms & conditions applicable for the 08/09
Delivery Period except for shipping terms.
6. Terms and conditions agreed for the ad-hoc volume only are:
(a) Total Moisture The guaranteed value for 09/10 delivery (on 'as received
basis) will be from 10.0% to 9.5%.
(b) Chargeable Weight The invoice weight reduction for excess Total
Moisture above the guaranteed specs will be at the rate of 1.3 % for
every 1% increase (fractions pro-rata) above the guaranteed
specifications up to the absolute maximum tolerance limit of 12%. The
existing terms for exceptional circumstances shall remain.
(c) Ash – Guaranteed & Tolerances.
Guaranteed Tolerance
Isaac Coking Coal 8.5% 0.4%
(d) Demurrage – US$ 15,000 per day: and
(e) Except for shipping terms (see paragraph 7), all other terms and
conditions of the Long Term Agreement shall apply.
th
7. Shipping Terms as finalized with EJC on 16 June 2009 shall apply for
total shipment.
For the avoidance of doubt, the parties acknowledge and agree that this
arrangement ("Ad-hoc Sale") is made without prejudice to either
parties rights and obligations under the Long Term Agreement.
Please return this letter countersigned with your confirmation of this
arrangement.
Yours faithfully,
Ian Wakely
Head of Metallurgical Coal
Anglo Coal Australia Pty. Ltd.
For MMTC Confirmed and Accepted
E-mail dated 21.07.2009 sent by the appellant to the respondent:
“From: 'sureshbabu@mmtclimited.com'
To: Street. Kim
Sent: Tuesday, July 21, 2009 2.51 PM
Subject: Re: Anglo/MMTC shipment July
We are awaiting stem confirmation from Anglo for August 09. Please
note we have given our indent well in advance. The flexibility of
laycan is vested with you completely. We look forward to hear from
you.
With Thanks & Regards,
FAO(OS) 532/2015 Page 36 of 72
Suresh Babu
GM (Coal&Coke)
Cell: +919818913799
Fax: +9111 2436 6362”
E-mail dated 22.07.2009 sent by the respondent to the appellant :
“ From: Street.Kim
To: sureshbabu@mmtclimited.com'
CC: Chris Dhar'; Martyr, Rebecca ; Wilcox, John ; Baxter, Alan
Sent: Wednesday, July 22, 2009 1:08 PM
Subject: RE: Anglo/MMTC shipment July
Dear Suresh,
Unfortunately at this stage we are unable to confirm a stem in
Aug/Sep for MMTC due to cargo availability . We are continuing to
review our position and will advise our preferred schedule for Oct-
Dec 2009 as soon as possible.
Regards,
Kim Street
Anglo Coal Australia Pty Ltd”
E-mail dated 04.09.2009 sent by the appellant to the respondent :
“From: sureshbabu@mmtclimited.com'
To: Kim.Street@Anglocoal.com.au
CC: John.Wilcox@Anglocoal.com.au ; pravinaearwal rpm
Sent: Friday, September 04, 2009 5:08 PM
Subject: Fw: Anglo/MMTC shipment July
Our cokery has increased the pushings with the results requirement of
coking coal has gone upto 90,000t/month. After Seavenues (laycan
20-30 July 09). Anglo has not given any stem to MMTC give us one
stem of 50,000MT each in October and November 09.
With Thanks &Regards,
Suresh Babu
GM (Coal&Coke)
Cell: +91 9818913799
Fax: +91112436 6362”
FAO(OS) 532/2015 Page 37 of 72
E-mail dated 07.09.2009 sent by the respondent to the appellant :
“From: Wilcox. John
To: sureshbabu@mmtclimited.com ; Street. Kim
Cc: pravinagarwal rpm
Sent: Monday, September 07, 2009 7:36 AM
Subject: RE: Anglo/MMTC shipment July
Dear Suresh
Thank you for your email.
Unfortunately at this stage we do not have any coal availability for
the remainder of the year.
We will continue to monitor the situation and let you know if the
position changes.
With regards,
John B Wilcox
Marketing Manager
Anglo Coal Australia Pty Ltd”
Letter dated 21.09.2009 sent by the respondent to the appellant:
“Mr.H.S. Mann Brisbane Corporate Office
Director (Marketing)
MMTC Limited Rod Elliott
Core-1 “Scope Complex” General Manager Marketing &
7 Institutional Area, Lodhi Road Transportation
New Delhi – 110003
India Direct Fax: +61 (0)7 3834 1366
Direct Line: +51 (0)7 38341297
e-mail: rod.elliott@anglocoal.com.au
st
21 September 2009
Dear Mr. Mann
AGREEMENT NO. MMTC/C&HC/LT/HCC/NINL/ANGLO/585
DATED 7TH MARCH 2007 ('AGREEMENT‟) BETWEEN ANGLO
COAL AUSTRALIA PTY LTD ('ANGLO') AND MMTC LIMITED
('MMTC')
We refer to our letter of 11 March 2009 to which we have not yet
received a response.
The Fifth Delivery Period of the Agreement has now finished
bringing, the term of the Agreement to an end . However, to date,
FAO(OS) 532/2015 Page 38 of 72
MMTC has only taken delivery of 11,966 tonnes of coal out of a total
contracted tonnage of 466,000 tonnes for the Fifth Delivery Period.
Despite our repeated requests MMTC has not provided Anglo with a
schedule for taking delivery of the remaining 454,034 tonnes of coal
from the Fifth Delivery Period ('Carryover'), other than to say that it
will agree to the same arrangements made between Anglo and SAIL
and RINL with regards delivery of 2008 carryover tonnes.
It is a matter of public record that the carryover delivery
arrangements with SAIL and RINL have now been agreed as follows:
2009/10 Delivery Period - 18.7% of the total remaining
carryover tonnes will be performed.
The remainder of the carryover tonnes will be performed
equally over the following two Delivery Periods unless
otherwise agreed.
We therefore submit the following proposal for delivery of the
Carryover and renewal of the Agreement with MMTC :
MMTC to perform a total of 38% of the total contracted
tonnage for the Fifth Delivery Period on the terms and
conditions (including price) applicable under the
Agreement (a further 172,533 tonnes) by March 31, 2010.
This will bring MMTC into line with the contract
performance of SAIL and RINL for the 2008/09 Delivery
Period.
In addition, MMTC is to perform 18.7% of the remaining
Carryover (a further 52,641 tonnes) by March, 31, 2010
on the terms and conditions of the Agreement (including
price) as agreed with SAIL and RINL.
Anglo will enter into a new long term agreement with
MMTC on the same terms and conditions as the current
long term agreements with SAIL and RINL (including
performance of the remaining Carryover) for 466,000
tonnes per annum for a period of 3 years commencing 1
April 2010.
Therefore, in summary, MMTC will take delivery of 225,174 tonnes of
coal at 2008 price, terms and conditions between now and 31 March
2010 and, under the new 3 year contract, perform the remainder of
the Carryover evenly spread over the first 2 years of the contract.
This proposal is made without prejudice to our rights under the
Agreement. It will remain open and capable of acceptance until 5.00
th
pm (Brisbane time) on Wednesday 30 September 2009.
FAO(OS) 532/2015 Page 39 of 72
Yours faithfully
Anglo Coal Australia Pty Ltd
Rod H.Elliott
General Manager, Marketing & Transportation”
Letter dated 25.09.2009 sent from the appellant to the respondent :
“Mr.Rod Elliot 25.9.2009
General Manager Marketing & Transportation,
Anglo Coal Australia Pty Ltd.
210 Charlotte Street Brisbane 4000
Australia
Dear Sir,
Agreement no.MMTC/C&HC/LT/HCC/NINL/ANGLO/585 dated 7th
March 2007 (“Agreement”) between Anglo Coal Australia Pty Ltd
(“Anglo”) and MMTC Limited (“MMTC”).
We have for reference your letter dated 21.09.2009 on the above
subject. As usual we were awaiting the contract signed between SAIL
and Anglo as it forms the basis of contract between MMTC and
Anglo.
As you had conveyed in your letter referred above, the following
delivery arrangements SAIL and RINL had with the suppliers were in
the public domain.
1) 2009/10 Delivery Period – 18.7% of the total remaining carry
over tones will be performed.
2) The remainder of the carryover tones will be performed
equally over the following two delivery periods unless otherwise
agreed.
Accordingly, MMTC conveyed its intention to lift 18.7% of the carry
over quantity. However, Anglo had suggested MMTC to lift a total of
2.25.174 MT by 31.3.2010 which seems near to impossible as it works
out to 56.7% of the carry over tonnage.
In this connection, it may please be appreciated that NINL is basically
a producer of LAM coke and pig iron where the value addition is
negligible or negative sometimes. The Industry is yet to come out of
the shock of recession. Lifting even 18.7 % carry over tonnage
implies a loss of USD 25/1 coke produced. Keeping these issues in
mind, we had approached Anglo Coal for a reduction in price vie our
FAO(OS) 532/2015 Page 40 of 72
letter dated 20.11.2008. Lifting another 38% implies a further
increase in loss by another USD 80/1. For the sake of negotiation, we
hope you will not ignore the economic realities completely. Steel
Melting Shop at NNL is under implementation and the commissioning
is expected sometime in end 2010. Economy will also come out of
recession gradually.
In short we are not denying our obligation. The request is only for
staggering the time frame for lifting as explained in para 1 & 2
above. Please review and reconsider our request for allotting of least
one shipment 50,000 MT each from October 09 onwards instead of
zero stem till end of 2009.
Thanking you,
Yours faithfully,
For MMTC Ltd.
For (Suresh Babu)”
Letter dated 25.11.2009 sent by the respondent to the appellant :
“Mr.H.S. Mann Brisbane Corporate Office
Director (Marketing)
MMTC Limited Rod Elliott
Core-1 “Scope Complex” General Manager Marketing &
Transportation
7 Institutional Area, Lodhi Road
New Delhi – 110003
India Direct Fax: +61 (0)7 3834 1366
Direct Line: +51 (0)7 38341297
e-mail: rod.elliott@anglocoal.com.au
25th November 2009
Dear Mr.Mann
AGREEMENT FOR THE SALE AND PURCHASE OF COKING
TH
COAL NO. MMTC/C&HC/LT/HCC/ RINL/ANGLO/585 DATED 7
MARCH 2007 BETWEEN ANGLO COAL AUSTRALIA PTY LTD
(„ANGLO‟) AND MMTC LIMITED („MMTC‟)
We refer to our further proposal for dealing with the unperformed
2008 tonnage contained in our letter of 21st September 2009, your
counterproposal in your letter of 25th September 2009 and your
discussions with Mr John Wilcox in New Delhi on 13th November
2009.
FAO(OS) 532/2015 Page 41 of 72
In order to progress matter we now propose that MMTC perform the
remaining 454, 034 metric tonnes of 2008 Contract Year in line with
our agreements with SAIL and RINL, at the 2008 price of US$300,
according to the following schedule:-
January – March 2010 85,000 18.7 %
April 2010 – March 2011 184,566 40.65%
April 2011-March 2012 184,566 40.65%
We trust that this arrangement meets with your approval.
This proposal is made without prejudice to our rights under the
Agreement. It will remain open and capable of acceptance until 5.00
pm (Brisbane time) on Friday 4th December, 2009.
Yours sincerely
Anglo Coal Australia Pty Ltd
Rod H.Elliott
General Manager, Marketing & Transportation”
Letter dated 27.11.2009 sent by the appellant to the respondent :
“M/s Anglo Coal Australia Pty Ltd
th
201, Charlotte Street Brisbane 4000 27 November, 2009
Australia GPO Box 1410
Brisbane 4001 Australia
Kind Attn.: Shri Rod H. Elliott. General Manager
Sub : Agreement for sale and purchase of coking coal
th
No.MMTC/C&HC/LT/HCC/RINL/ANGLO/585, dated 7 March 2007
between M/s Anglo and MMTC.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - -
Dear Sir,
th
This has reference to your letter dated 25 Nov. 2009 regarding
supply of the following carry over quantities of coking coal pertaining
to the 2008 contract in line with your agreements with SAIL & RINL
at the 2008 price of US$ 300 PMT :-
| S.No. | Period of Supply | Quantity<br>(MT) | Percentage |
|---|---|---|---|
| 1. | Jan 2009 to March,<br>2010 | 85,000 | 18.7% |
| 2. | April 2010 to March<br>2011 | 1,84,566 | 40.65% |
FAO(OS) 532/2015 Page 42 of 72
| 3. | April 2011 to March<br>2012 | 1,84,566 | 40.65% |
|---|
The above proposal is acceptable to us subject to your allocating the
left over quantities pertaining to 2009 contract at 2009 prices based
on the terms and conditions agreed upon in the EJC of SAIL & RINL.
To be specific the balance supplier amounting to 4,25,600 MT at the
2009 price level of US$ 128/125 PMT shall also be made in
proportion alongwith the carryover quantities of 2008 as proposed
above in line with the terms agreed upon with SAIL & RINL.
We look forward for a comprehensive proposal.
Thanking you,
Yours faithfully
(SURESH BABU)
General Manager”
Letter dated 01.12.2009 sent by the respondent to the appellant:
“Mr.H.S. Mann Brisbane Corporate Office
Director (Marketing)
MMTC Limited Rod Elliott
Core-1 “Scope Complex” General Manager Marketing &
7 Institutional Area, Lodhi Road Transportation
New Delhi – 110003
India Direct Fax: +61 (0)7 3834 1366
Direct Line: +51 (0)7 38341297
e-mail: rod.elliott@anglocoal.com.au
st
1 December 2009
Dear Mr.Mann
AGREEMENT FOR THE SALE AND PURCHASE OF COKING
COAL NO. MMTC/C&HC/LT/HCC/ RINL/ANGLO/585 DATED 7TH
MARCH 2007 BETWEEN ANGLO COAL AUSTRALIA PTY LTD
(„ANGLO‟) AND MMTC LIMITED („MMTC‟)
th
We refer to our proposal dated 25 November 2009 and MMTC letter
th
dated 27 November 2009 for dealing with the unperformed 2008
tonnage.
Kindly be advised that it is not possible to make any additional
tonnage commitment to MMTC over and above that detailed in our
FAO(OS) 532/2015 Page 43 of 72
th
proposal of 25 November 2009, as restated below, for the shipment
of unperformed 2008 commitments at a price of US$300 :-
January – March 2010 85,000 tonnes
April 2010 – March 2011 184,566 tonnes
April 2011-March 2012 184,566 tonnes
We again recommend this proposal to MMTC and trust that it will be
accepted as a pragmatic approach that restores the working
relationship between our organisations.
This proposal is made without prejudice to our rights under the
Agreement. It will remain open and capable of acceptance until
th
5.00pm (Brisbane time) on Friday 4 December 2009.
Yours sincerely
Anglo Coal Australia Pty Ltd
Rod H.Elliott
General Manager, Marketing & Transportation”
(Emphasis supplied)
13. For completeness, it is also deemed appropriate to reproduce the
issues framed by the Tribunal, which are extracted below:
“A. Whether the Respondent committed breach of
contract in not lifting 454,034 MT of coking coal in terms of
Agreement and if so, the consequences thereof? If yes, what
is the date of such breach?
B. Whether the Claimant was in breach of contract in
failing to supply goods to the Respondent during the Fifth
Delivery Period? If yes, what is the date of such breach?
In considering this issue, and so far as relevant, was the
Claimant in a position to perform its obligations by making
available the requisite quantities in a timely manner as per
the stipulations under the Contract?
C. Whether the Claimant's claims are barred by
limitation?
FAO(OS) 532/2015 Page 44 of 72
Whether there was a failure on the part of any party to
perform the obligations cast upon it under the Contract, in
a timely manner, or at all and if so, the effect thereof.
D. Whether the Claimant is entitled to any damages and
if so to what amount?
E. Whether the Claimant is entitled to interest on any
damages to be awarded and (if so, at what rate and for
what period?
F. Whether the Claimant is entitled to interest pendente
lite and post pendente lite, and if so at what rate.
G. Costs of the arbitration, and interest, if any, on the
costs awarded.”
14. Also, since both counsels have relied upon certain portions of the
evidence recorded before the Tribunal, we deem it appropriate to reproduce
such portions hereinbelow:
Examination-in-chief of Respondent‟s Witness Mr. John Wilcox:
"… Nevertheless, as a goodwill gesture, Anglo offered the same terms to
MMTC on an ad hoc basis making it clear that it was without prejudice
to the parties obligations under the Long Term Agreement. It may be
stated that around this time the global steel market started picking up
and soon after the Claimant agreed to this ad hoc arrangement, MMTC
started asking for repeat cargos on the same basis i.e. with 18.7% at the
contractual price and the balance at an ad hoc price of 128.25 per MT
(the price then agreed with EJC for SAIL / RINL for Issac hard coking
coal). In this context MMTC's Mr. Suresh Babu sent me an email dated
nd
2 July 2009 asking for two stems in August and one in September 2009
(i.e. total of 150,000 MT of material). Upon receipt of this mail, I
directed my junior colleague, Ms. Kim Street to reply that while we look
th
forward to vessel nomination against the agreed stem in laydays 20 -
th
30 July, we would revert regarding other shipments. The reason for
this was that the coal demand was picking up and we had no agreement
with MMTC to supply them any further ad hoc quantities (thereby
stressing our other contractual commitments). Anglo had to prioritise its
contractual commitments in the first instance.
xxxxx
FAO(OS) 532/2015 Page 45 of 72
"(vi) At that time the Claimant's total annual commitment for hard
coking coal would be in the range of about 12 million MT and as stated
above Claimant had about 19 long term contractual agreements
(customers). The Claimant thus knew well in advance its contractual
commitments and made its production arrangements accordingly. It may
be stated that the Claimant was not merely in the business of marketing
of coal. It has an integrated business as a producer / seller of coal. As
th
reflected in the Long Term Agreement dated 7 March 2007 with
MMTC, the Claimant had a 70% participating interest in the Capricorn
Coal Developments Joint Venture (the Jena Pty. Ltd. is also a Claimant
group company) and the Claimant owned an 88% participating interest
in the Moranbah North Coal Joint Venture. Indeed, the Long Term
Agreement with MMTC records that the Claimant is authorised to act as
Seller on behalf of the aforesaid two coal mines i.e. Capricorn Coal
Developments Joint Venture and the Moranbah North Coal Joint
Venture. Thus, the Claimant was at all times fully capable of taking care
of its contractual commitments. At the same time, the Claimant did most
of its business through long term contracts and not through spot sales or
ad hoc sales. In a situation where the market demand was picking up (as
it was in the second half of the 2009 calendar year) there was little room
for the Claimant to enter into ad hoc sales or spot sales as MMTC was
requesting for.
(vii) MMTC through Mr. Suresh Babu signed the ad hoc Agreement
st nd
dated 1 July 2009 (Annexure C-10) on 22 July 2009. One day prior
thereto he once again asked for stem for August 2009. This was
promptly replied by our Ms. Kim Street on the very next day stating that
Anglo cannot confirm any stem in August / September due to cargo
availability and that we would revert later in October-December should
the position change.
th
(viii) On 4 September 2009 the Respondent's Mr. Suresh Babu again
emailed Ms. Kim Street with copy to me asking for stems in October and
November which for reasons stated hereinabove were declined vide my
th
email of 7 September 2009 and I made it clear that we do not have any
coal availability for the remainder of the year. Ms. Kim Street is my
subordinate and I am fully aware of the purport of this correspondence
which as stated above was all under my directions. I reiterate that all
these requests from MMTC were non contractual (as explained above).
MMTC also understood it in that light. This becomes clear if Mr. Suresh
th
Babu's letters dated 25 September 2009, 27th November 2009 and
Mr.H.S Mann's letter dated 3rd December 2009 (along with the rest of
the correspondence) are seen which are at Annexures C-12 to C-18.
xxxxx
"2. I respectfully state that the Claimant's ability to perform its
obligations by making available the contracted quantities of coal in a
timely manner can never be in doubt. This is for several reasons; Firstly
FAO(OS) 532/2015 Page 46 of 72
the Claimant is not a trader or an intermediary. It has an integrated
business with ownership of the coal mines and long term agreements
with the ports and railways in place to ensure smooth shipments as
contracted for. Secondly, during the Fifth Delivery Period the global
financial crisis was on in full swing bringing about a crash in the
demand for steel and consequently for hard coking coal. Far from
scarcity of material, the Claimant had a large quantity of surplus
production some of which had to be sold off by way of distress sales
during the Fifth Delivery Period. Despite the suppressed market demand
during the period (October 2008 to September 2009) the Claimant sold
about 12.21 million MT of hard coking coal (of the type contracted for
with MMTC) averaging over a million tonnes a month. MMTC's
contracted quantities (466,000 MT at US$ 300 per MT) if evenly spread
over the Delivery Period would be less than 3.9% of our monthly sales.
In such scenario there could have been no reason for the Claimant not to
be able to make available to MMTC the contracted quantities at the
contracted price. I elaborate the aforesaid below:
xxxxx
"12. As stated in my earlier Affidavit, the international benchmark
st st
price for hard coking coal for the period 1 April 2009-31 March 2010
dropped from US$ 300 to about US$ 128-129. Further almost all parties
with whom the Claimant was dealing with at that time (Including SAIL /
RINL) were asking for carryover arrangements which had to be worked
out with them as stated in my earlier Affidavit. In such scenario there
could have been no reason for the Claimant not to make available to
MMTC the contracted quantities at the contractual price as per the
contract.
13. I say that in the emails referred to and relied upon by MMTC
where I or Ms. Kim Street refer to "availability" of coal, It was with
reference to the non-contractual requests from MMTC. In other words
what we were saying was that we do not have any surplus coal available
for spot sales (which is what MMTC was requesting). By that time (i.e.
July 2009) having already reduced our surplus stock to manageable
limits (about 50% of the maximum capacity) and in view of the coal
market picking up, we wanted to refocus on our long term contractual
arrangements and commitments which in any case is our normal
preferred business model.
xxxxx
"14. … In various personal visits to India (as mentioned in my first
Affidavit) in the months of January, February, April, May and June
2009, I tried to convince MMTC to agree to lift at least some quantities
under the Agreement but to no avail.
15. It is submitted that the entire dispute has arisen only because
MMTC was not willing to lift the goods or comply with any of its
FAO(OS) 532/2015 Page 47 of 72
obligations under the contract. It is because MMTC simply refused to
lift material that there was occasion for the Claimant to make more than
one offer to MMTC to accept cargo on an ad hoc basis with a small
cargo at the contractual rate and the balance at the then market rate of
US$ 128. (Annexure C-8 to C-10 refer to this). "
(Emphasis supplied)
Cross-Examination of Respondent‟s Witness Mr. John Wilcox:
"Q12. Did you record some minutes of meeting or follow up what
transpired during the meeting by way of any means of communication?
Ans. Yes. I have brief meeting notes. The reason for the meeting was
th
that in October 2008 we had offered two stems to MMTC one on the 8
October 2008 for stem in 20-30 November 2009. The response to this
offer was communicated through our Indian Marketing Representative
as negative. This email communication is not in my Additional Affidavit
as I could not find the email. I have subsequently found the email which
th
I can produce if required. The offer of 14 October for the December
20-30 stem is in my supplementary affidavit.
In the meeting MMTC expressed its reluctance to lift any cargo until
January or February. We were in constant communication with our
Indian marketing representatives who were discussing the issue of stems
on a weekly basis with MMTC.
Examination-in-chief of Appellant‟s Witness Mr. Suresh Babu:
"33.As is clearly established from the e-mails and other correspondence
above, the Respondent had all along requested the Claimant to intimate
the availability of the stem for the supply of the contracted goods.
However, the Claimant categorically intimated the Respondent that they
had no availability of the material until the end of the 2009 which was
beyond the Fifth Delivery Period and beyond the LTA. It was not an
obligation on the part of the Respondent to agree to delivery schedule
prior to even the Claimant informing about the availability of the
material and stem availability as regards the contracted goods. At no
point of time the Claimant ever intimated to the Respondent during the
currency of the Fifth Delivery Period as regards the availability of the
stem apart from supplying 9036 MT supplied in July 2009.
34. Even in the alleged letter dated March 11, 2009 purportedly
issued by the Claimant, the Claimant does not indicate the availability of
the stem and/or intimation by the Claimant in accordance with clause
7.2.1 of the GCA. It is also surprising that the letter dated March 11,
2009 stated to have been sent was resent in an unconnected e-mail sent
on March 12, 2009. I reiterate and assert that the e-mails dated July 2,
FAO(OS) 532/2015 Page 48 of 72
2009, July 3, 2009, two emails of July 21, 2009 and September 4, 2009
and September 7, 2009 exchanged between myself and the Claimant
pertained to the supplies under the Long Term Agreement and under the
Fifth Delivery Period. Any suggestions to the contrary are vehemently
denied.
35. I say that the Claim of the Claimant is an afterthought as would
be evident from the fact that the Claimant waited for more than three
years to initiate arbitration after bringing an end to the LTA, vide its
letter dated September 21, 2009.
(Emphasis supplied)
Cross-Examination of Appellant‟s Witness Mr. Suresh Babu:
"Q1. Would it be correct to say that during the Fifth Delivery Period
there was a severe global financial crisis?
Ans. Yes.
Q2. Would it be correct to say that as a result, MMTC found it
unviable to produce steel on the basis of Imported coal having price of
US$ 300 per MT?
Ans. Yes. For some time we were trying to stagger the delivery of US$
300 coal.
xxxxx
"Q10. Would it be correct to say that you continued to pick up coal from
BMA at the market price of around US$ 128 through the Fifth Delivery
Period?
Ans. No. The entire quantity is not procured from BMA @ US$ 128 per
MT. Some quantities was picked @ US$ 300 per MT during the Fifth
Delivery Period from BMA. Since BMA had agreed to supply coal
continuously till end of December 2009 MMTC could make an offer to
Claimant for the purchase of coal @ US$ 300 per tonne. I made an offer
to Mr. John Wilcox for allotting two stems in the months of August and
September 2009 from the backlog MMTC had with the Claimant.
I had not put the rate @ US$ 300 per MT while making the offer to the
Claimant. MMTC had only one contract with the Claimant at that point
of time where the coal was priced at US$ 300 per MT. Therefore the
word "backlog" is in relation to US$ 300 coal only.
xxxxx
"By the Tribunal:
FAO(OS) 532/2015 Page 49 of 72
During the Fifth Delivery Period you were able to buy coal from the
Claimant at the contracted price of US$ 300 per MT?
Ans. Yes.
xxxxx
"Q23. Can you please state that when according to you in May 2009
you started discussions with the Claimant for a US$ 300 cargo and were
willing to lift at US$ 300, the Claimant did not agree but instead
negotiated with you a mixed price cargo as evidenced by Annexure C-
10?
Ans. We had already started negotiations with the Claimant for the
mixed cargo before May itself that culminated in July 2009 stem.
Subsequently our request were turned down by the Claimant. In this
rd
connection I would like to draw the attention to their emails dated 3
st th
July 2009, 21 July 2009 and 7 September 2009 wherein the Claimant
was saying either they will revert to our request for the stem or they are
unable to consider our request for the stem because they do not have
cargo. While replying they have not mentioned that they are refusing it
because we had asked for a mixed cargo or they did not mention that in
case of our request is for US$ 300 cargo they would consider the stem.
rd
As had been brought out earlier also in our email dated 3 July we had
stated that there is huge backlog to be serviced by the Claimant. Kindly
allot stem for August and September. We had only one signed contract
with the Claimant that is for supply of coal @ US$ 300 per tonne. All
our requests are for US$ 300 coal only since we have only one signed
agreement with Anglo.
xxxxx
"Q28. [Witness shown his answer to Q16]. Can you please elaborate.
Are you saying here that MMTC was willing to alternate vessels
between BMA and Anglo i.e. one vessel from BMA at US$ 128 and the
other from Claimant at US$ 300. Is this how you would have an
average price of about US$ 224 per MT as you have said in response to
this question ?
Ans. The Claimant had given the July shipment as a one time
arrangement and they were not willing to consider any other request.
Since the Claimant was taking a tough stand we had discussed with
BMA who will continue to supply at US$ 128 per tonne and we will
take coal from the Claimant at US$ 300 per tonne so the average price
will be US$ 224 per tonne .
xxxxx
th
"Q37. Please see your letter of 25 September 2009 and the reference
th
therein to MMTC's previous letter of 20 November 2008. Would it not
FAO(OS) 532/2015 Page 50 of 72
be correct to say that the difficulties stated by you in lifting the material
at the contractual rate of US$ 300 are the same as stated by Mr. Ved
th
Prakash in his letter of 20 November 2008?
th
Ans. This letter (25 September) is to be seen from the light of
st
Claimant's letter dated 21 September wherein they have put an end to
the Fifth Delivery Period and they could not supply cargo for want of
availability.
Q38. Is it not correct to say that MMTC's commercial position did not
change through the Fifth Delivery Period as to lifting of cargo at US$
300 per MT as what was stated by Mr. Ved Prakash in his letter dated
th th
20 November 2008 is repeated here and indeed the said letter of 20
November 2008 is referenced here?
Ans. Notwithstanding the commercial difficulties the Respondent had
come forward for taking cargo at US$ 300 per tonne. The Claimant was
not able to offer the cargo because of non-availability and for the same
reason they have to put an end to the Fifth Delivery Period. So MMTC
has also decided to ask for the same terms and conditions as is being
offered to SAIL/RINL.
th
Q39. In your letter of 25 September 2009, you say that it is "near to
st st
Impossible" to lift 225,174 MT between 21 September 2009 and 31
March 2010 but at the same time in the last para you request for one
shipment of 50,000 MT each from October 2009 onwards. Would it be
correct to say that this request for stem from October 2009 was on the
basis that 18.7% cargo would be at US$ 300 per MT and the balance
81.3% would be at the market price of US$ 128.25 per MT?
Ans. This is in continuation of my earlier reply. Since the Claimant
had put an end to the Fifth Delivery Period the Respondent has also
decided to ask for the terms and conditions being extended to SAIL. Yes.
We are only asking for the same terms and conditions with SAIL and
RINL i.e. 18.7% in the first year.
xxxxx
"By the Tribunal:
th
Please look at the last para of the letter of 25 September 2009. First
sentence says, in short we are not denying our obligation. What
obligation is that?
Ans. Our obligation is to lift US$ 300 coal.
I thought you told us that the Fifth Delivery Period had come to an end
so what was your obligation?
st
Ans. In fact subsequent to the letter dated 21 September from the
Claimant we were only trying to re-negotiate with the Claimant.
FAO(OS) 532/2015 Page 51 of 72
What was the obligation you were referring to in your letter?
Ans. I only meant that the US$ 300 coal was not lifted though by the
st
21 September letter the Claimant put an end to the Fifth Delivery
Period.
What, if the Claimant had put an end to the Fifth Delivery Period, was
the Respondent's obligation under the Long Term Agreement?
Ans. In fact there should not have been any obligation.
xxxxx
"Q43. Please see your Affidavit at page 45 (Volume 6) where you have
th
referred to Claimant's letter of 25 November 2009. You have stated
that Claimant's offer to supply the outstanding tonnage from January to
March 2010 "establishes the fact that the Claimant did not have any
contracted material…..". Is it not correct that the Claimant's offer to
th
supply as stated in Annexure C-14 is in response to your letter of 25
September 2009 where you have requested for "staggering the time
frame for lifting" (last para)?
st
Ans. The letter preceding this letter had offered coal from 21
st
September till 31 March 2010. Suddenly the offer is changed from
January to March 2010 together with various previous replies of the
Claimant clearly stating that cargo cannot be supplied for want of
th
availability. I feel that this may not be in response to my letter of 25
September 2009.
Q44. Is it your stand that under the Long Term Agreement in the first
instance the Seller has to offer stem and only thereafter there is any
other obligation upon the Buyer Including agreeing upon a delivery
schedule?
Ans. Stem, which represents availability of cargo with the Claimant
should be known then only the Respondent can give the delivery
schedule.
Q45. Do you say this as a matter of practice or otherwise?
Ans. This is a matter of practice."
(Emphasis supplied)
15. Drawing inferences from the e-mails/correspondence as aforesaid,
the majority of the members of the Arbitral Tribunal (that is to say two out
of three members) have reached the following conclusions:-
"117. The Claimant's case is somewhat self-evident in that it is
no more complicated than an assertion that there was an
FAO(OS) 532/2015 Page 52 of 72
agreement to purchase a certain quantity of coal which went
unfulfilled on the part of the Respondent which failed to lift the
requisite quantity in the relevant period. Accordingly It is
appropriate for us to consider matters as canvassed by the
Respondent in its defence while keeping in mind that the
burden of proof lies of course on the Claimant.
Availability of Coal
118. The first element to be considered is the assertion
advanced on behalf of the Respondent that the Claimant did
not have the contracted goods to deliver. This depends
nd
entirely upon two e-mails, one dated 22 July 2009 and the
th
other dated 7 September, 2009. The first of these stated that
the Claimant was unable to confirm the stem in
August/September "due to cargo availability" and was
reviewing the position in regard to October-December 2009.
nd
In the 2 the Claimant stated that "unfortunately at this stage
we do not have any coal availability for the remainder of the
year".
119. The Claimant's case, which we accept, is that there was
no shortage of supply at the relevant time. The e-mails have to
be read in context, and as we explain below, the context is that
the Respondent was seeking further deliveries of coal at below
the contract price.
xxxxx
"122. The Tribunal accepts Mr. Wilcox's evidence. It is
th
entirely consistent with the Respondent's own letter dated 20
November 2008 which reads:
“….As you are aware, due to worldwide crisis in
financial markets, there has been unprecedented fall in
prices of major commodities including steel...
The prices of iron and steel products in the International
market has nosedived In the month of September and
October 2008 and pig iron,... is not getting customer on
date even at US$300 FOB. Same is the situation in the
domestic market and we are not able to sell our product.
Under the circumstances, you will appreciate it has
become absolutely unreliable to produce and sell pig
FAO(OS) 532/2015 Page 53 of 72
iron based on the imported coking coal having prices
US$300 per tonne FOB for hard coking coal... The
substantial depreciation of Indian rupees to the US
dollar is further added to our woes.... In view of
unprecedented recessionary trends in the economy and
consequent abnormal lower realisation on pig iron, we
request price reduction of coal for quantities finalised
for delivery during 1 July, 2008 to 30 of June 2009
period to a level that was settled for delivery period 1
July, 2007 to 30 of June 2008."
123. It appears to us that the evidence is all one way, to the
effect that demand for coking coal was substantially reduced
during the last few months of 2008 and in, at least, the first
half of 2009, and it follows, it seems to us, that this strongly
corroborates Mr. Wilcox's evidence as to the availability of
coking coal for supply to the Respondent.
124. Accordingly we reject the Respondent's assertion that the
Claimant did not have the contract goods to deliver. The
Tribunal makes one further observation: the Fifth Delivery
Period price was agreed just over two months after the global
financial crisis which started at about the time of the collapse
th
of Lehman Brothers on the15 September 2008. The price
agreed by the parties for that period was significantly higher
than the price for any of the preceding periods. That is in itself
extraordinary, but what is even more extraordinary is that the
Respondent's request for a price reduction was made on the
very same day on which the Fifth Delivery Period price was
agreed.
Failure to Offer Stem?
125. The Respondent asserts in addition however that in any
event the Claimant failed to offer stem to the Respondent and
that, in consequence, the Respondent was discharged from any
further obligations under the Agreement. This primarily turns
on a construction of the contract, but involves also a
consideration of the way in which the parties implemented
their contract,
xxxxx
FAO(OS) 532/2015 Page 54 of 72
"128. The Tribunal does not accept that the Respondent's
construction is correct in this regard. Nor, as appears below,
do we agree with the Respondent's contention that there was a
failure to offer stem on the part of the Claimant.
xxxxx
"133. Accordingly we do not accept that the Agreement
required the Claimant to take the initiative and offer stem
wholly without reference to any obligation on the part of the
Respondent. Viewed overall, it is clear to us that the
Agreement envisaged and required the parties to coordinate
supply and delivery . The primary document for this was
intended to be the Delivery Schedule. Indications of stem
availability and nomination of vessels were steps to be taken
in the implementation of the Delivery Schedule, not
preparatory to it. It follows from this, it appears to us, that
there is no contractual basis on which the Respondent can
contend that the Claimant was in breach in failing to offer
stem to the Respondent. Absent an agreed Delivery Schedule
there was no obligation to do so.
xxxxx
"Offer of Supply
137. Whether that understanding of the contract is correct or
not however may be beside the point. On the facts, it appears
to the Tribunal that the Claimant did take steps towards
offering stem to the Respondent in any event. This came about,
st
at least by the Claimant's letter of 11 March 2009 in which
letter the Claimant said:
th
"We refer to discussions In New Delhi on 24 February
2009 between Mr Suresh Babu and our Mr John Wilcox
at your office. Anglo remains very concerned that
deliveries for the Fifth Delivery Period of the Agreement
remain unperformed by MMTC, and that to date MMTC
has not intimated arrangements for performance of
obligations arising under the Agreement.
Accordingly, kindly send MMTC's proposed Delivery
Schedule for the Fifth Delivery Period, as referred to in
FAO(OS) 532/2015 Page 55 of 72
Clause 4 of Annexure IV of the Agreement, for our
consideration. Under the circumstances, we seek your
response by close of business Brisbane time on Friday
20"' March 2009."
xxxxx
"141. In summary therefore there is much in the
contemporaneous correspondence to support the Claimant's
assertion that this letter was sent, and nothing to rebut that
assertion. So far as the witness evidence is concerned, not
least because it is corroborated by the documents, the
Tribunal prefers and accepts the evidence of Mr. Wilcox that
supply of coal was offered by the Claimant to the Respondent,
th
including by the letter of 11 March 2009.
xxxxx
"146. The Tribunal's view of the correspondence is that the
Respondent saw matters similarly, and was seeking to
purchase further quantities of coal at the lower rate obtained
in the Sea Venus agreement, in the e-mail of July 2009. Mr.
Babu referred to the Respondent having progressed the
chartering of a vessel for the Sea Venus agreement, and asked,
without apparent distinction about the availability of further
stems for August and September. Receiving no substantive
response to the enquiry regarding such further stems Mr. Babu
st
followed up by e-mail on 21 July 2009. He did not, as might
have been expected if this was part of the usual contractual
arrangements point out that the Claimant was obliged to fulfil
this order, nor did he make any complaint that the Claimant
had failed to comply with the "prerequisite" of indicating stem
availability before the Respondent was required to act.
nd
147. It was in this context of that Claimant wrote on 22 July
2009 referring to an inability to confirm stem in
August/September due to cargo availability . Seen in the
context of the exchanges between the parties, and seen against
the back ground of the evidence given by Mr. Wilcox to the
effect that prices had slumped and the Claimant was
"dumping" coal in China, the only possible understanding of
this e-mail is that the claimant was declining to supply further
coal at below the contract rate as had been done In the ad hoc
Sea Venus agreement.
FAO(OS) 532/2015 Page 56 of 72
th
148. On 4 September 2009 the Respondent wrote again
seeking stem (for delivery beyond the contract period), noting
that there had been no delivery since the Sea Venus
agreement. Once again the response received by the
Respondent was that there was a lack of availability.
149. None of these exchanges refer specifically to the price at
which the coal was being sought, or at which it might be
available. Mr. Wilcox's evidence was however clear that the
contemporaneous discussions between the parties were on the
basis that the Respondent was seeking further discounted
supplies, and indeed his understanding was that the
Respondent was purchasing from other suppliers at rates
lower than those to which it was bound under the Fifth
Delivery Period.
xxxxx
"151. Thus, the first relevant letter written by the Respondent
th
during the Fifth Delivery Period [C-5] on 20 November 2008
sought a reduction in the price of coal to be delivered under
th
the Fifth Delivery Period as did the last such letter, that of 25
September 2009. Following the conclusion of the Fifth
Delivery Period the Claimant made a further offer of supply
th
(on 25 November 2009) which the Respondent was prepared
to accept only at a price reduced from the contractual rate
th
(Respondent's letter of 27 November 2004 (sic, 2009). The
Respondent's arguments now are predicated on there having
been a temporary change of stance during the course of the
year such that, in June and July 2009 It was seeking no more
than to avail Itself of supplies of coal at the contract rate. Seen
In context, the correspondence relied on does not begin to
support that contention, and the Tribunal rejects it. The
Respondent was seeking coal at below the contract rate and
the Claimant was refusing to supply on those terms. The
Respondent failed to fulfil Its contractual obligation to lift the
contracted quantities of coal at the contract rate."
(Emphasis supplied)
16. We are unable to fathom as to how the respondent/claimant's
assertion that, it was "unable to confirm the stem in August/September due
FAO(OS) 532/2015 Page 57 of 72
to cargo availability" ; and "unfortunately at this stage we do not have any
coal availability for the remainder of the year" as extracted in para 118 of
the Award, leads the Tribunal to accept the respondent/claimant's case and
to hold that "there was no shortage of supply" as held in para 119 of the
Award. Instead of reading what was stated in plain English in the e-mails
and correspondences, the Tribunal imports into the discussion the fall in
demand for coking coal internationally to infer "that this strongly
corroborates Mr. Wilcox's evidence as to the availability of the coking coal
for supply to the respondent" in para 123. Nor do we understand as to how
the Tribunal ignores the equally clear and unqualified assertion in the
respondent's e-mail dated 07.09.2009 that "unfortunately at this stage we
do not have any coal availability for the remainder of the year" as
extracted in para 118 of the Award to hold that the respondent had coal
available to supply to the appellant.
17. We are further at a loss to understand as to how, having observed
that "None of these exchanges refer specifically to the price at which the
coal was being sought, or at which it might be available" in para 149, the
Tribunal infers that "Mr. Wilcox's evidence was however clear that
contemporaneous discussions between the parties were on the basis that
the respondents was seeking further discounted supplies" in the same para.
18. In the above manner, the Tribunal has reached the conclusion that
there was no shortage of availability of coal with the respondent at the
relevant time; and that e-mails dated 22.07.2009 and 07.09.2009 are to be
read to mean that the appellant was seeking delivery of coal at below the
contracted price. The Tribunal has also referred, with acceptance, to the
additional affidavit of Mr. Wilcox, wherein the witness had stated that the
respondent was not a trader in coal but owned coal mines in Australia and
FAO(OS) 532/2015 Page 58 of 72
had a railway system in place to ensure smooth shipments. In the additional
affidavit the witness also deposed that on account of the global financial
crisis there was a crash in the demand for steel, and consequently, for
coking coal. Mr. Wilcox also stated that at the relevant time, the respondent
had large quantity of surplus production, some of which the respondent had
sold by way of distress sale. Mr. Wilcox had also testified that he disagreed
that the respondent had no availability of coal since, as per Mr. Wilcox‟s
oral testimony, the respondent was producing 1,000,000 MT of coal per
month; and that it would have been easy for them to supply the coal
provided the appellant was willing to pay the contracted price. The
Tribunal accepted all this evidence, since according to the Tribunal, it was
consistent with letter dated 20.11.2008 of the appellant. In our view Mr.
Wilcox‟s additional affidavit as also his oral testimony could not have
effaced or changed what had been expressly stated in contemporaneous e-
mails/letters exchanged between the parties. Such additional affidavit and
oral testimony was therefore wholly irrelevant.
19. We are conscious of the limitations of our jurisdiction under section
37 of the A&C Act and the scope of interference by this court in such
proceedings. We are also cognizant of the fact that there is a majority
arbitral award in favour of the respondent; which has been upheld by a
single Judge of this court ; and that, on general principles of section 37, this
court is expected to forbear from interfering in conclusions of fact reached
by the Tribunal.
20. That being said however, it is also our understanding that if the court
finds that a conclusion or inference drawn by the Arbitral Tribunal, even if
upheld in proceedings under section 34, is not supported by a plain,
objective and clear-eyed reading of documents, this court would not flinch
FAO(OS) 532/2015 Page 59 of 72
in correcting such conclusion or inference, especially if it goes to the root
of the matter. We may only say that in this case, we have noticed exactly
such position, whereby the Arbitral Tribunal by majority, has chosen to
read words into written communications between parties which words do
not exist ; and to omit to read what is written in plain, simple and
uncomplicated English.
21. While there is a plethora of communications exchanged between the
parties in the form of letters and e-mails over a period of several months,
the Tribunal's decision as accepted by the single Judge, turns essentially on
the following three e-mails, which are extracted below again, though at the
cost of repetition:
E-mail dated 02.07.2009 :
" From:sureshbabu@mmtclimited.com
To : John.Wilcox@.anglocoal.com.au
Cc:chris.dhar@gauri. com. au
Sent: Thursday, July 02, 2009 11:01 AM
Transchart has already entered the market on behalf of MMTC for the
vessel against July 09 stem.
Keeping the huge backlogs in mind , we would like to avail two stems in
the August 09 and one in September 09. Please confirm availability and
convey the laycans.
With Thanks & Regards,
Suresh Babu
GM (coal and Coke)
Cell: 919818913799
Fax: + 911124366362"
E-mail dated 22.07.2009 :
"From: Street.Kim
To: sureshbabu@mmtclimited.com
FAO(OS) 532/2015 Page 60 of 72
Cc: Chris Dhar'; Martyr, Rebecca, Wilcox, John ; Baxter, Alan
Sent: Wednesday, July 22, 2009 1:08 PM
Subject: RE:Anglo/MMTC shipment July
Dear Suresh,
Unfortunately at this stage we are unable to confirm a stem in Aug/Sep
for MMTC due to cargo availability . We are continuing to review our
position and will advise our preferred schedule for Oct-Dec 2009 as
soon as possible.
Regards,
Kim Street
Anglo Coal Australia Pty Ltd"
E-mail dated 07.09.2009 :
"From: Wilcox.John
To: sureshbabu@mmtclimited.com
Cc: pravinagarwal rpm
Sent: Monday, September 07, 2009 7:36 AM
Subject: RE:Anglo/MMTC shipment July
Dear Suresh,
Thank you for your e-mail.
Unfortunately at this stage we do not have any coal availability for the
remainder of the year.
We will continue to monitor the situation and let you know if the
position changes.
With regards,
John B Wilcox
Marketing Manager
Anglo Coal Australia Pty Ltd"
(Emphasis supplied)
22. In the course of arguments, it has been strenuously urged on behalf
of the respondent that since the subject of the above e-mails is
FAO(OS) 532/2015 Page 61 of 72
“ RE:Anglo/MMTC shipment July”, the only shipment that was being
discussed by way of these e-mails was that relating to the month of July
2009. In our view, this is a misconception and we would like to dispel this
notion at the outset.
23. It is a matter of common knowledge, and we take judicial cognizance
of it, that in a series of e-mail communications exchanged between parties,
by way of replies, responses and rejoinders, commonly called e-mail trails,
it is not electronically possible to change the subject of the first e-mail. The
only way the subject can be changed is by starting a new e-mail trail, which
would result in dis-continuity in the conversation. For all practical intents
and purposes therefore, parties do not change the subject of an e-mail trail.
Accordingly, the subject of the e-mail trail would not be conclusive in
deciding the context of the e-mails, in the same way that the title of a
section or of a clause in a contract is not conclusive for purposes of
construing its meaning.
24. In the above background, a plain and straightforward reading of the
e-mails extracted above shows the following :
(i) E-mail dated 02.07.2009 was in two parts: firstly, it referred to
“July 09 stem” , namely the quantity of coal ordered by the appellant
from the respondent for the month of July, 2009. Secondly, by this e-
mail the appellant acknowledges the “huge backlogs” (sic) in relation
to the Long Term Agreement between the parties ; and proceeds to say
that the appellant would like to avail “two stems in October 09 and
one in Sept 09” ; and requests the respondent to confirm availability
of coal for such shipment. To be sure, e-mail dated 02.07.09 appears
not to be a part of any e-mail trail.
(ii) Now coming to the e-mail trail with the subject “RE:Anglo
MMTC shipment July” , e-mail dated 22.07.09 starts with the
respondent regretting (says „unfortunately‟) that they are unable to
FAO(OS) 532/2015 Page 62 of 72
confirm stems for “Aug/Sept for MMTC due to cargo availability” .
The plain and simple reference being to the non-availability of cargo
for the stems requested by the appellant for Aug/Sept 2009. The e-
mail then proceeds with the respondent saying that they are
“continuing to review our position” and that they “will advise our
preferred schedule for Oct-Dec-2009 as soon as possible” . Yet again
therefore, the respondent is saying that it will review its position and
would prefer a schedule for delivery in Oct-Dec-2009. On a plain and
simple reading of the e-mail it is clear that the review referred to is in
relation to the availability of coal since that is the only end of the
bargain that the respondent was responsible for.
(iii) Insofar as e-mail dated 07.09.09 is concerned, the e-mail again
begins with a regret (says „unfortunately‟) and proceeds to say that
“we do not have any coal availability for the remainder of the year” ;
which can mean only one thing, namely that the respondent did not
have any coal available to supply to the appellant for the remainder of
the year 2009. The e-mail concludes by the respondent stating that it
will “continue to monitor the situation and let you know if the position
changes” ; whereby the respondent takes on the responsibility to
monitor the situation, which can only mean the situation of
availability of coal for shipment to the appellant.
25. It is extremely important to note that in these three critical e-mails,
upon which the decision of the Arbitral Tribunal as well as single Judge
hinges, there is no reference whatsoever to the price of coal to be supplied.
Furthermore, nowhere does the respondent say that it does not have coal
available at any specified price. In the e-mails, the respondent simply says
that it does not have any coal available for the remaining part of the year
2009 period . However, what has not been said or even reflected in the
aforesaid e-mails, is read into the said e-mails by the majority of the
Arbitral Tribunal; and accepted by the single Judge. The aforesaid e-mail
communication is taken to mean that the respondent had coal available at
FAO(OS) 532/2015 Page 63 of 72
USD-300 per metric tonne ; and that the respondent meant that it did not
have coal available at USD 128 per metric tonne . The majority of the
Arbitral Tribunal as well as the single Judge therefore read the aforesaid e-
mails to mean that the appellant was requesting supply of coal only at USD
128 per metric tonne, which is something that has nowhere been said in any
of these e-mails.
26. We are at an utter loss to understand as to how the Arbitral Tribunal
can read into commercial communication between educated and worldly-
wise men of commerce, words that do not exist in the communications. In
our view, if such imaginary interpolations are allowed into the e-mails, then
the inferences and conclusions derived therefrom must be held to be
perverse in law.
27. In the circumstances, we do not think there is any scope for trying to
infer what was 'intended' by the parties, since it is not for the court to look
for intendment in matters such as this. The court must read what is plainly
said in the e-mails, nothing more, nothing less ; and no effort is called-for
to try and gather what may have been intended. This is not a case where a
legislative body has enacted a statutory provision and the court is called
upon to 'construe' it, looking at what the legislature may have intended. In
any written communication between parties, the court must assume that one
party understood what is plainly stated by the other ; and the court would
be loath to ascribing any meaning or context to what is plainly so stated. In
our view, the above e-mails ought to be 'read' and not 'interpreted',
especially since there is no ambiguity as regards what the parties have said
in plain terms. Where the Arbitral Tribunal has erred, is that it has
attempted to draw inferences as to what was being intended by what was
FAO(OS) 532/2015 Page 64 of 72
said in the e-mails, instead of merely going on the basis of what was
actually said.
28. Furthermore, even a cursory perusal of the depositions of the
respondent's witness Mr. John Wilcox and the appellant's witness Mr.
Suresh Babu, as extracted above, will show that while the deposition of Mr.
John Wilcox runs completely contrary to and against the text and the grain
of the e-mails/communications between the parties, that of Mr. Suresh
Babu is in complete consonance and accord with what is written in such e-
mails/communications. Mr. John Wilcox has even gone on to depose in
relation to e-mails/communications which had been authored by Ms. Kim
Street, while the latter was never produced as a witness; although Ms. Kim
Street is stated to be still in the employ of the respondent and therefore
available to depose.
29. We are aware that a court seized of proceedings under section 37 of
the A&C Act is not to re-appreciate evidence, muchless in a case where the
Arbitral Tribunal as well as the single Judge under Section 34 have agreed
with a certain view on the facts of the case. However, it is also the law that
where a factual inference is based on no evidence , the court may interfere
with such inference even under section 37. In our reading of the legal
position, a factual inference that is based on what is not stated in a
document or what may be called 'imaginary evidence', is the same as an
inference based on 'no evidence' ; or an inference derived ignoring vital
evidence. A decision based on such inference would necessarily be
perverse. If the majority of the Arbitral Tribunal ignores what is plainly
stated in commercial correspondence and reads into e-mails words that do
not exist, or ignores words that are contained in e-mails, this can only pave
the way for complete injustice. It is not the purport of any of the
precedents that inferences drawn from thin air would become sustainable,
FAO(OS) 532/2015 Page 65 of 72
hiding behind the shield of an arbitral award. As we see it, this is exactly
the position in the present case. There is no evidence to support the
conclusion that the appellant was demanding consignment of coal at any
reduced rate vis-à-vis the contractually agreed price. There is also no
evidence to support the conclusion that the respondent had coal available to
supply to the appellant, when the appellant demanded it. If anything, there
is a straight forward acknowledgement by the respondent that it had no coal
available till the end of the year 2009, without any qualification or
reservation that coal was available at the contracted rate but not at a
discounted rate.
30. What is more is that there is also no basis to the calculation of
damages. The Tribunal has calculated damages by taking the difference in
the agreed price of coal and the assumed 'market price' at the relevant time.
However there is no evidence to prove the market price of coal at that time.
The question of mitigation of damages by the respondent has not even been
alluded to.
31. We find the legal foundations of our views in the decision of the
Supreme Court in Associate Builders vs. DDA (supra), in which the
Supreme Court has laid down the following 'third principle' of the
fundamental policy of Indian law as to 'perversity' in the decision of an
Arbitral Tribunal, in the following words:-
| "31. The third juristic principle is that a decision which is | |
|---|---|
| perverse or so irrational that no reasonable person would | |
| have arrived at the same is important and requires some | |
| degree of explanation. It is settled law that where: | |
| (i) a finding is based on no evidence, or | |
| (ii) an Arbitral Tribunal takes into account something | |
| irrelevant to the decision which it arrives at; or | |
| (iii) ignores vital evidence in arriving at its decision, | |
| such decision would necessarily be perverse. |
FAO(OS) 532/2015 Page 66 of 72
| "32. A good working test of perversity is contained in two<br>judgments. In Excise and Taxation Officer-cum-Assessing<br>Authority v. Gopi Nath & Sons, it was held: (SCC p. 317, para<br>7)<br>“7. … It is, no doubt, true that if a finding of fact is<br>arrived at by ignoring or excluding relevant material or<br>by taking into consideration irrelevant material or if the<br>finding so outrageously defies logic as to suffer from the<br>vice of irrationality incurring the blame of being<br>perverse, then, the finding is rendered infirm in law.”<br>In Kuldeep Singh v. Commr. of Police, it was held:<br>(SCC p. 14, para 10)<br>“10. A broad distinction has, therefore, to be<br>maintained between the decisions which are perverse<br>and those which are not. If a decision is arrived at on no<br>evidence or evidence which is thoroughly unreliable and<br>no reasonable person would act upon it, the order would<br>be perverse. But if there is some evidence on record<br>which is acceptable and which could be relied upon,<br>howsoever compendious it may be, the conclusions<br>would not be treated as perverse and the findings would<br>not be interfered with.” "<br>(Emphasis supplied) | "32. A good working test of perversity is contained in two | ||||
|---|---|---|---|---|---|
| judgments. In Excise and Taxation Officer-cum-Assessing | |||||
| Authority v. Gopi Nath & Sons, it was held: (SCC p. 317, para | |||||
| 7) | |||||
| “7. … It is, no doubt, true that if a finding of fact is | |||||
| arrived at by ignoring or excluding relevant material or | |||||
| by taking into consideration irrelevant material or if the | |||||
| finding so outrageously defies logic as to suffer from the | |||||
| vice of irrationality incurring the blame of being | |||||
| perverse, then, the finding is rendered infirm in law.” | |||||
| In Kuldeep Singh v. Commr. of Police, it was held: | |||||
| (SCC p. 14, para 10) | |||||
| “10. A broad distinction has, therefore, to be | |||||
| maintained between the decisions which are perverse | |||||
| and those which are not. If a decision is arrived at on no | |||||
| evidence or evidence which is thoroughly unreliable and | |||||
| no reasonable person would act upon it, the order would | |||||
| be perverse. But if there is some evidence on record | |||||
| which is acceptable and which could be relied upon, | |||||
| howsoever compendious it may be, the conclusions | |||||
| would not be treated as perverse and the findings would | |||||
| not be interfered with.” " | |||||
| (Emphasis supplied) | |||||
| 32. We would also highlight the emphasis laid by the court in Associate | |||||
| Builders (supra), by quoting an earlier decision in ONGC Ltd. vs. Western | |||||
| Geco International Limited (supra), mandating that a court or an authority | |||||
| is bound to adopt a 'judicial approach' in deciding a matter. The following | |||||
| paras of Associate Builders (supra) may be noticed on this point: | |||||
| "28. In a recent judgment, ONGC Ltd. v. Western Geco<br>International Ltd., this Court added three other distinct and<br>fundamental juristic principles which must be understood as a<br>part and parcel of the fundamental policy of Indian law. The<br>Court held: (SCC pp. 278-80, paras 35 & 38-40)<br>“35. What then would constitute the „fundamental<br>policy of Indian law‟ is the question. The decision<br>in ONGC does not elaborate that aspect. Even so, the<br>expression must, in our opinion, include all such | "28. In a recent judgment, ONGC Ltd. v. Western Geco | ||||
| International Ltd., this Court added three other distinct and | |||||
| fundamental juristic principles which must be understood as a | |||||
| part and parcel of the fundamental policy of Indian law. The | |||||
| Court held: (SCC pp. 278-80, paras 35 & 38-40) | |||||
| “35. What then would constitute the „fundamental | |||||
| policy of Indian law‟ is the question. The decision | |||||
| in ONGC does not elaborate that aspect. Even so, the | |||||
| expression must, in our opinion, include all such |
FAO(OS) 532/2015 Page 67 of 72
| fundamental principles as providing a basis for | |
|---|---|
| administration of justice and enforcement of law in | |
| this country. Without meaning to exhaustively | |
| enumerate the purport of the expression „fundamental | |
| policy of Indian law‟, we may refer to three distinct | |
| and fundamental juristic principles that must | |
| necessarily be understood as a part and parcel of the | |
| fundamental policy of Indian law. The first and | |
| foremost is the principle that in every determination | |
| whether by a court or other authority that affects the | |
| rights of a citizen or leads to any civil consequences, | |
| the court or authority concerned is bound to adopt | |
| what is in legal parlance called a „judicial approach‟ | |
| in the matter. The duty to adopt a judicial approach | |
| arises from the very nature of the power exercised by | |
| the court or the authority does not have to be | |
| separately or additionally enjoined upon the fora | |
| concerned. What must be remembered is that the | |
| importance of a judicial approach in judicial and | |
| quasi-judicial determination lies in the fact that so | |
| long as the court, tribunal or the authority exercising | |
| powers that affect the rights or obligations of the | |
| parties before them shows fidelity to judicial | |
| approach, they cannot act in an arbitrary, capricious | |
| or whimsical manner. Judicial approach ensures that | |
| the authority acts bona fide and deals with the subject | |
| in a fair, reasonable and objective manner and that its | |
| decision is not actuated by any extraneous | |
| consideration. Judicial approach in that sense acts as | |
| a check against flaws and faults that can render the | |
| decision of a court, tribunal or authority vulnerable to | |
| challenge. | |
| *** | |
| 39. No less important is the principle now recognised | |
| as a salutary juristic fundamental in administrative | |
| law that a decision which is perverse or so irrational | |
| that no reasonable person would have arrived at the | |
| same will not be sustained in a court of law. | |
| Perversity or irrationality of decisions is tested on the | |
| touchstone of Wednesbury principle of | |
| reasonableness. Decisions that fall short of the |
FAO(OS) 532/2015 Page 68 of 72
| standards of reasonableness are open to challenge in | |||
|---|---|---|---|
| a court of law often in writ jurisdiction of the superior | |||
| courts but no less in statutory processes wherever the | |||
| same are available. | |||
| 40. It is neither necessary nor proper for us to attempt | |||
| an exhaustive enumeration of what would constitute | |||
| the fundamental policy of Indian law nor is it possible | |||
| to place the expression in the straitjacket of a | |||
| definition. What is important in the context of the case | |||
| at hand is that if on facts proved before them the | |||
| arbitrators fail to draw an inference which ought to | |||
| have been drawn or if they have drawn an inference | |||
| which is on the face of it, untenable resulting in | |||
| miscarriage of justice, the adjudication even when | |||
| made by an Arbitral Tribunal that enjoys considerable | |||
| latitude and play at the joints in making awards will | |||
| be open to challenge and may be cast away or | |||
| modified depending upon whether the offending part is | |||
| or is not severable from the rest.” | |||
| (emphasis in original) | |||
| 29. It is clear that the juristic principle of a “judicial | |||
| approach” demands that a decision be fair, reasonable and | |||
| objective. On the obverse side, anything arbitrary and | |||
| whimsical would obviously not be a determination which | |||
| would either be fair, reasonable or objective." | |||
(Emphasis supplied)
33. It is also important for us while dealing with this matter under
section 37, to express clearly as to why we are of the opinion that the view
taken by the majority of arbitrators deserves to be set-aside in spite of the
otherwise well-settled position that the arbitrator is the ultimate master of
the quality and quantity of evidence. The principle in this behalf is
enunciated in the following paragraph of Associate Builders (supra) :
"33 . It must clearly be understood that when a court is
applying the “public policy” test to an arbitration award, it
does not act as a court of appeal and consequently errors of
FAO(OS) 532/2015 Page 69 of 72
| fact cannot be corrected. A possible view by the arbitrator on | |
|---|---|
| facts has necessarily to pass muster as the arbitrator is the | |
| ultimate master of the quantity and quality of evidence to be | |
| relied upon when he delivers his arbitral award. Thus an | |
| award based on little evidence or on evidence which does not | |
| measure up in quality to a trained legal mind would not be | |
| held to be invalid on this score. Once it is found that the | |
| arbitrators approach is not arbitrary or capricious, then he is | |
| the last word on facts. …" |
(Emphasis supplied)
In the present case however, we find that the view taken by the
majority of arbitrators is not a possible view since it is not a question of the
'quantity' or 'quality' of evidence or of 'little evidence' or of 'evidence which
does not measure-up in quality to a trained legal mind' but this is a case
where the inferences drawn are a non-sequitur to the plain and simple
words of the e-mails/communications read in evidence, which were before
the Tribunal and which do not support the inferences drawn. In this view of
the matter, clearly the approach of the majority of arbitrators is arbitrary
and capricious ; and therefore cannot pass judicial muster.
34. In the passing, we may also refer to the observations of a three-Judge
Bench of the Supreme Court in Smt. Kamala Devi vs. Seth Takhatmal &
Anr. : (1964) 2 SCR 152 , in which the court observed as follows:-
"8. … Sections 94 to 98 of the Indian Evidence. Act afford
guidance in the construction of documents; they also indicate
when and under what circumstances extrensic evidence could
be relied upon in construing the terms of a document. Section
94 of the Evidence Act lays down a rule of interpretation of the
language of a document when it is plain and applies
accurately to existing facts. It says that evidence may be given
to show that it was not meant to apply to such facts. When a
Court is asked to interpret a document, it looks at its language.
If the language is clear and unambiguous and applies
accurately to existing facts, it shall accept the ordinary
meaning, for the duty of the Court is not to delve deep into the
FAO(OS) 532/2015 Page 70 of 72
| intricacies of the human mind to a certain one's undisclosed | |
|---|---|
| intention, but only to take the meaning of the words used by | |
| him, that is to say his expressed intentions. Sometimes when it | |
| is said that a Court should look into all the circumstances to | |
| find an author's intention, it is only for the purpose of finding | |
| out whether the words apply, accurately to existing facts. But | |
| if the words are clear in the context of the surrounding | |
| circumstances, the Court cannot rely on them to attribute to | |
| the author an intention contrary to the plain meaning of the | |
| words used in the document. The other sections in the said | |
| group of sections deal with ambiguities, peculiarities in | |
| expression and the inconsistencies between the written words | |
| and the existing facts. In the instant case, no such ambiguity or | |
| inconsistency exists as we shall demonstrate presently. The | |
| Privy Council's case was one of ambiguity and the | |
| surrounding circumstances gave the clue to find out the real | |
| intention of the parties expressed by them." |
(Emphasis Supplied)
In the present case, we find no reason to look for the 'undisclosed
intention' of the respondent since the clear and express words of the
respondent, as contained in the afore-cited e-mails/communications, are
perfectly in accord with and apply squarely to existing facts. We must
therefore accept the ordinary meaning of what is stated in those e-
mails/communications, namely that the respondent did not have any coal
available till the end of the year 2009 for supplying to the appellant.
35. Proceeding on this basis, by a majority, the Tribunal has awarded
USD 78,720,414.92 as damages alongwith interest of USD 27,239,420.29
calculated upto the date of the award, alongwith 15% p.a. future interest on
the principal sum, in addition to USD 977,395.00 as costs. This amount,
calculated at the ballpark prevailing exchange rate of approximately USD 1
= INR 70 translates to INR 7,48,56,06,115 that is to approximately INR
748 crores. In our view, such an award must rest on surer factual and
legal footing than only to say that it has been rendered by an arbitral
FAO(OS) 532/2015 Page 71 of 72
tribunal; and is therefore sacrosanct. In the above view of the matter, the
award of damages, interest and costs is a travesty of justice and the award
suffers from perversity.
36. In our consideration, the single Judge has also not appreciated the
aforesaid basic aspects, upon which the decision of the majority of the
Tribunal turns. While doing so the single Judge has therefore committed
error in the proceedings under section 34, which are amenable to be
corrected in the present proceedings under section 37.
37. In view of the above discussion, we set-aside the majority award
dated 12.05.2014 as also order dated 10.07.2015 of the single Judge made
under section 34 of the A&C Act.
38. In the circumstances, the parties are left to bear their own costs.
ANUP JAIRAM BHAMBHANI, J.
G.S.SISTANI, J.
MARCH 02, 2020//
FAO(OS) 532/2015 Page 72 of 72