Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
COMMISSIONER OF INCOME-TAX, MADRAS
Vs.
RESPONDENT:
M/S RAMBAL PRIVATE LTD
DATE OF JUDGMENT: 06/08/1997
BENCH:
B. N. KIRPAL, K. T. THOMAS
ACT:
HEADNOTE:
JUDGMENT:
Present:
Hon’ble Mr. Justice B.N. Kirpal
Hon’ble Mr. Justice K. T. Thomas
Ranbir Chandra, B. Krishna Prasad and Ms. Lakshmi Iyengar,
Advs. for the appellant
Ms. Janki Ramachandran, Adv. for the respondents
O R D E R
The following Order of the Court was delivered:
W I T H
Civil Appeal Nos. 1236 of 1982 and 5637 of 1995
O R D E R
Civil Appeal No.1286 of 1982
The assessee-respondent manufacturers nuts, bolts and
screws for automobiles which fall under item No. 20 in the
fifth Schedule being ’automobile ancillaries’. According to
the appellant the machinery which was installed was being
used not only or the manufacture of items falling in the
Fifth Schedule but also for the manufacture of some other
items. Whereas the respondent had claimed allowance on
development rebate in respect of assessment year 1969-70 at
the rate of 35%, the Income-tax Officer held that inasmuch
as the machinery was also being used for the manufacture of
some other times not falling under the Fifth Schedule,
therefore, the rate of development rebate should be
restricted to 20% only.
Being aggrieved the respondent succeeded in the appeal
filed before the Appellate Assistant Commissioner. The
department filed an appeal to the income Tax Appellate
Tribunal which, however, upheld the assessee’s contention.
At the instance of the department the Tribunal referred the
following question of law to the High Court.
Whether, in the assessment for the
assessment year 1969-70 the
assessee could be allowed
development rebate at 35% on Rs.
2.30.840 being the cost of the
machinery installed during the
relevant previous year, despite the
fact that they were used not merely
for the manufacture of nuts. bolts
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
and screws for automobiles, but
also for the manufacture of such
articles for other machinery:.
The High Court answered the question of all in favour
of the respondent by observing that the machinery which was
installed was used wholly for the purpose of business of the
assessee. This is a fact which had been found by the
Tribunal. The High Court, further observed that the
machinery installed for the purpose of manufacture of one of
the items mentioned in the Fifth Schedule need not
necessarily be used exclusively for the manufacture of those
items or any of the items in the Fifth Schedule. It
accordingly answered the question of law in favour of the
Respondent.
It is contended by the learned Counsel for the
appellant, in this appeal by special leave, it at the
respondent used the machinery for the manufacture of items
other than ’automobile ancillaries’ in addition to nuts,
bolts and screws and, therefor, the respondent was not
entitled to claim development rebate at the rate of 35%
Section 33(1)(a) and (b) with which we are concerned read as
follows:
"33 [1] [a]: In respect of a new
ship or new machinery or plant
(other than office appliances or
road transport vehicles) which is
owned by the assessee and is wholly
used for the purposes of the
business carried on by him, there
shall, in accordance with and
subject tot the provision of the is
section and of section 34, be
allowed a deduction, in respect of
the previous year in which; the
ship was acquired or the machinery
or plant was installed or, if the
ship, machinery or plant is first
put up to use in the immediately
succeeding previous year, then, in
respect of that previous year, a
sum by way of development rate as
specified in clause (b).
(b) The sum referred to in clause
(a) shall be
(A) In the case of a ship, forty
per cent of the actual cost thereof
the actual cost thereof to the
assessee;
(B) in the case of machinery or
plant-
(i) where the machinery or plant is
installed for the purposes of
business of construction,
manufacture or production of any
one or more of the articles or
things specified in the list in the
Fifth Schedule-
(a) thirty five per cent of the
actual cost of the machinery or
plant; to the assessee, where it is
installed before the 1st day of
April, 1970 and
(b) twenty five per cent of such
cost, where it is installed after
the 31st day of March, 19703
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
According to Section 33(1) (a) development rebate is
allowable if the assessee use the machinery wholly for the
purpose of business carried on the him. It is not in dispute
that in the present case, and as has been found by the
Tribunal, the items which are manufactured by the respondent
are wholly for the purpose of his business. Therefor. one of
the conditions stipulated by sub-section 1(a) of Section 33
stands satisfied.
Sub-Clause [b] deals with the rate at which the
development rebates is to be allowed. It, inter alia,
provides that in the case of machinery or plant which is
installed for the purposes of manufacturer or production of
any one or more of the articles specified in the list in the
Fifth Schedule and that machinery has been installed before
1st day of April, 1970, then the development rebate will be
allowed at the rate of 35% of the actual cost of the
machinery. In the instant case the machinery was installed
before 1st day of April, 1970. it cannot be disputed that it
was installed for the purpose of manufacture of nuts, bolts
and screws for automobiles falling under item 20 in the
Fifth Schedule being ‘automobile ancillaries’. These items
were in fact manufactured. Section 33[1] [b] does not state
that the machinery which has been installed for the
manufacture or production of one or more of the articles
specified in the Fifth Schedule should be used solely or
exclusively for the manufactures any of the articles
specified in the Fifth Schedule, the assessee would be
entitled to claim development rebate at the rate of 35% if
the machinery is installed before 1st day of April 1970,
notwithstanding the fact that in addition to the manufacture
of the listed items, the assessee also manufactures some
other goods with the help of that machinery. If the
contention of the department is accepted, the effect would
be that if the machinery is used for manufacture of one of
the items listed in the fifth schedule for few hours a day
and lies idle thereafter for the rest of the day, the
assessee would be entitled to claim development rebate at
the rate of 35% we do not see any logic in this contention
and nor does the language of Section 33 warrant such a
conclusion.
We are in agreement with the decision of the High Court
that the machinery, which was being used for the manufacture
of some of the items mentioned in the fifth Schedule, would
be entitled to development rebate at the rate of 35% and it
need not necessarily have been used exclusively for the
manufacture of those items alone.
For the aforesaid reason, we hold that the High Court
has rightly answered the question of law in the affirmative.
This appeal is accordingly dismissed with costs
Civil Appeal Nos. 4003-4004 of 1984 and Civil No.5637 of
1995
For the reason referred to in Civil Appeal No. 1286 of
1982, these appeals are dismissed and the decision of the
High Court is affirmed. There will be no order as to costs.