Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
SHIVA JUTE BALING LIMITED
Vs.
RESPONDENT:
HINDLEY AND COMPANY LIMITED
DATE OF JUDGMENT:
21/08/1959
BENCH:
WANCHOO, K.N.
BENCH:
WANCHOO, K.N.
SINHA, BHUVNESHWAR P.
GAJENDRAGADKAR, P.B.
CITATION:
1959 AIR 1357 1960 SCR (1) 569
ACT:
Arbitration-Contract-Award Passed Pending legal proceedings
challenging the existence and validity of contract-Validity-
Breach of contract-Contract providing for Penalty as
liquidated damages Award granting maximum-Legality--Indian
Contract Act, 1872 (9 of 1872), ss. 73, 74-Arbitration
(Protocol and Convention Act, 1937 (6 of 1937) s. 7(e)-
Arbitration Act, 1940 (10 of 1940), ss 33, 35.
HEADNOTE:
The appellant company, incorporated in India, entered into a
contract on June 18, 1945, for the supply of five hundred
bales of jute, with the respondent company which was
incorporated in England and which had its registered office
in London. The contract, inter alia, provided that in the
event of default of tender or delivery, the seller shall pay
to the buyer as and for liquidated damages 10s. per ton plus
the excess (if any) of the market value over the contract
price, the market value being that of jute contracted for on
the day following the date of default. There was a
provision for arbitration, under which any claim or dispute
whatever arising out of, or in relation to this contract or
its construction or fulfilment shall be referred to
arbitration in London in accordance with the bye-laws of the
London jute Association. Disputes having arisen regarding
the performance of the contract the respondent referred the
matter to the arbitration of the London jute Association,
who appointed two of its members as the arbitrators. The
appellant did not reply to the notice given by the
arbitrators but filed an application on
570
August 10, 1949, under s. 33 Of the Arbitration Act, 1940,
in the Calcutta High Court, praying, inter alia, (a) for a
declaration that the arbitration agreement was void on the
ground of uncertainty, and (b) for a declaration that there
was in fact and in law no contract between the parties on
account of mutual mistake of the parties. Notice was given
by the appellant to the respondent and the London jute
Association that further steps in the arbitration
proceedings should not be taken pending disposal of the
application under S. 33 Of the Arbitration Act, 1940. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
arbitrators, however, proceeded with the arbitration and
gave their award on October 17, 1949. On November 26, 195i,
an application was filed by the respondent in the Calcutta
High Court under s. 5 of the Arbitration (Protocol and
Convention) Act, 1937, praying that judgment be pronounced
in accordance with the award. The appellant contended that
the award was invalid on the grounds, inter alia, (i) that
the award was bad under s. 35 of the Arbitration Act, 1940,
as it was made after the receipt of the notice of filing of
the petition dated August 10, 1940, under s. 33 of the
Arbitration Act, by the respondent and the arbitrators and
during the pendency of the said application, and (2) that
the liquidated damages provided under the award included not
only the difference between the contract price and the
market price on the date of default but also a further sum
of 10s. per ton, that the extra amount was against the
provisions Of ss. 73 and 74 of the Indian Contract Act,
1872, and that, therefore, the award was bad on the face of
it and could not be enforced in view of the provisions Of s.
7(e) of the Arbitration (Protocol and Convention) Act, 1937,
which lays down that an award cannot be enforced in India if
it is contrary to the Law of India.
Held: (i) that the subject-matter of the legal
proceedings under s. 33 Of the Arbitration Act, 1940, which
relates to the existence and validity of the arbitration
agreement, are not matters within the competence of the
arbitrators, and do not therefore cover any part of the
subject-matter of the reference. Consequently, S. 35 of the
Arbitration Act is inapplicable.
(2) The award does not violate the provisions of ss. 73 and
74 Of the Indian Contract Act, 1872, as the arbitrators have
only awarded the maximum amount named in the contract.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 262 of 1955.
Appeal by special leave from the, judgment and decree dated
February 4, 1953, of the Calcutta -High Court, in Appeal
from original decree No. 68 of 1952 arising out of the
judgment and decree dated’ January 14, 1952, of the said
High Court, in Special Suit No. 2 of 1951.
571
N. C. Chatterjee, C. B. Agarwala and Sukumar Ghose, for
the appellants.
B. Sen, S. N. Mukherjee, S. N. Andley, J. B. Dadachanji
and Rameshwar Nath, for the respondents.
1959. August 21. The Judgment of the Court was delivered
by
WANCHOO J.-This is an appeal by special leave against the
judgment of the Calcutta High Court. The appellant is a
company, incorporated in India, with its registered office
in Calcutta dealing in jute. It entered into a contract on
June 18, 1945, with the respondent-company, which is
incorporated in England and has its registered office in
London. The contract was for the supply of five hundred
bales of jute of crop 1945-46 to be shipped from Calcutta or
Chittagong to Rio de Janeiro, when freight became available.
The contract provides that in the event of default of tender
or delivery, the seller shall pay to the buyer as and for
liquidated damages 10s. per ton plus the excess (if any) of
the market value over the contract price, the market value
being that of jute contracted for on the day following the
date, of default. This date was to be the date in London on
declaration of default by telegram or without such
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
declaration if default was eventually made by lapse of time
on the 21st day after expiry of the extended period. There
is also a provision for arbitration, which lays down that
any claim or dispute whatever arising out of, or in relation
to this contract or its construction or fulfilment shall be
referred to arbitration in London in accordance with the
bye-laws of the London Jute Association, and it was open to
either party to claim arbitration whenever and as often as
disputes arose. The contract also provides for an appeal by
any party dissenting from an arbitration award to the London
Jute Association in accordance with the regulations in force
for the time being. Lastly, it is provided that the
contract would be construed according to the laws ,of
England whatever the residence and nationality of the
parties might be or become and would be deemed to be
performed there. The courts of England or
572
arbitrators, as the case might be, would have exclusive
jurisdiction over all disputes which might arise under the
contract, except for the purpose of enforcing in the
Colonies or abroad any arbitration award made under this
contract,
On. June 23, 1947, thirty-nine bales of jute were consigned
by the appellant to Rio de Janeiro in part performance of
the contract and information of this was given to the
respondent by letter on July 17, 1947. It was said in this
letter that difficulty had arisen because of the non-
availability of quota and it was hoped that the balance
remaining under the contract would be shipped as soon as
quota was available. The respondent sent a reply to this
letter on July 25, 1947, and the appellant wrote a further
letter on August 1, 1947, in which it was said that the
remaining amount of jute under the contract would be shipped
as soon as the quota was available.
We do not know what happened thereafter till we come to
August 1948. It seems that the respondent received a cable
on August 12, 1948, from the appellant stating that the
contract stood cancelled long ago. The respondent by its
letter dated August 12, 1948, refused to %accept this
position. Thereafter there were disputes and differences
between the parties and eventually the respondent claimed
default on or about June 1949 in terms of the contract. On
or about July 14, 1949, the respondent referred the matter
to the arbitration of the London Jute Association, which
appointed two of its member as arbitrators. The respondent
filed its claim before the arbitrators on July 23, 1949. On
July 27, 1949, the arbitrators gave notice to the appellant
to file its answer by August 19, 1949. The appellant,
however, filed no answer before the arbitrators. What the
appellant did in reply was to file an application under s.
33 of the Indian Arbitration Act, 1940 (hereinafter called
the Arbitration Act), on the original side of the Calcutta
High Court, in which it made three prayers, namely-
(a) declaration that the arbitration agreement, if any,
between the parties was void ab initio on the
573
ground of uncertainty and was not binding on the appellant;
(b) declaration that there was in fact and in law no
contract between the parties on account of mutual mistake of
the parties; and
(c) that the court might be pleased to adjudicate on the
existence and/or validity of the alleged arbitration
agreement and the effect of the same.
This application was moved on August 12, 1949. It appears
that on August 13, 1949, the appellant sent a cable to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
respondent and the London Jute Association informing them
that an application had been made in the Calcutta High Court
challenging the submissions contained in the contract and
that the arbitrators had become functus officio pending
disposal of the application, which was fixed for August 29.
The appellant received a reply to its cable in which it was
asserted that no such application as the appellant bad made
to the Calcutta High Court could be made there and that the
arbitrators would proceed with the adjudication on August 27
as already fixed. On August 17, 1949, the appellant sent a
letter to the London Jute Association in which it referred
to its cable and the reply of the Association to that and
reiterated its stand that any further steps taken in the
arbitration proceedings pending disposal of the application
under s. 33 would be invalid under the Arbitration Act. The
arbitrators, however, proceeded with the arbitration and
gave their award on October 17, 1949.
No proceedings thereafter were taken by the appellant in
London, nor does it appear that any steps were taken by it
to have its application under s. 33 decided, till we come to
November 26, 1951. On that date, an application was filed
by the respondent in the Calcutta High Court under s. 5 of
the Arbitration (Protocol and Convention) Act, 1937,
(hereinafter called the Protocol Act). Along with this
application it filed the award dated October 17, 1949, and
prayed that judgment be pronounced in accordance with the
award and decree be passed accordingly. Notice of this was
issued to the appellant, which filed its reply on January
14,
73
574
1952, We do not think it necessary to set’ out the petition
of the respondent under s. 5 of the Protocol Act and the
appellant’s reply thereto in detail, because when the matter
came to be heard in court only two points were urged on
behalf of the appellant, namely
(1) that the award was made after the notice of filing of
the petition dated August 10, 1949, under s. 33 of the
Arbitration Act had been given to the respondent and the
arbitrators, and consequently the award made after the
receipt of the said notice and during the pendency of the
said application was bad under s. 35 of the Arbitration Act;
and
(2) that the award was bad on the face of it and could not
therefore be enforced in view of the provisions of s. 7(e)
of the Protocol Act, which lays down that an award cannot be
enforced in India if it is contrary to the law of India. It
was contended that the award was contrary to the law of
India and this appeared on the face of it inasmuch as the
arbitrators had purported to award such damages as could not
be done under the provisions of the Indian Contract Act,
1872.
Both these contentions were negatived by the learned Single
Judge and he ordered the award to be filed, in court and
passed a decree in terms thereof.
The appellant then went up in appeal, which was heard by a
Division Bench of the Calcutta High Court. The grounds of
appeal show that the same two points, which were urged
before the learned Single Judge’ were reiterated therein.
When the matter came to be heard before the Division Bench,
the same two points were raised on behalf of the appellant
there also. The Division Bench negatived the two
contentions raised before it on behalf of the appellant and
confirmed the judgment of the learned Single Judge. It is
curious, however’ to notice that though all these
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
proceedings were being taken on the application under s. 5
of the Protocol Act the appellant apparently took no steps
to have its application under s. 33 of the Arbitration Act,
which seems to have been adjourned sine die, decided along
with the respondent’s application under s. 5 of the Protocol
Act,
575
This was followed by an application for a certificate to
appeal to this Court, which was refused. Then the appellant
applied to this Court for special leave to appeal, which was
granted. In the special leave petition also the appellant
raised the same to points, namely, (i) the construction of
ss. 33 and 35 of the Arbitration Act and the application of
these provisions to the facts of this case, and (ii) the
construction of s. 7 of the Protocol Act and the Indian
Contract Act with respect to the damages awarded by the
award.
In the statement of case also after narrating the facts and
circumstances, the same two points were mentioned as the
principal questions which arose for determination in the
appeal, namely, (i) the effect of ss. 33 and 35 of the
Arbitration Act on the facts and circumstances of this case,
and (ii) the interpretation of s. 7 of the Protocol Act in
the light of ss. 73 and 74 of the Indian Contract Act and
their bearing on the damages awarded by the arbitrators and
its effect on the validity of the award.
Learned counsel for appellant, however, wanted to raise
before us other points arising out of s. 7 of the Protocol
Act. We do not think that the appellant should be permitted
to raise at this late stage any new point in addition to the
two points which were urged before the learned Single Judge
and which only have all along been raised in the appeal to
the High Court and in the appeal before this Court. We
shall therefore confine the appellant to these two points
only and proceed on the assumption in the same manner as has
been done by the High Court, namely, that an application
under s. 33 of the Arbitration Act would lie in the
circumstances of this case and therefore the provisions of
s. 35 of the Arbitration Act would be attracted.
Re. (1).
The part of s. 33 of the Arbitration Act, relevant for our
purpose, lays down that any party to an arbitration
agreement desiring to challenge the existence or validity of
an arbitration agreement or to have its effect determined
shall apply to the court and the court shall decide the
question. It will thus be clear that
576
s.33 contemplates an application for three purposes, namely,
(i) when it is desired to challenge the existence of an
arbitration agreement, (ii) when it is desired to challenge
its validity, and (iii) when it is desired to have its
effect determined. An arbitration agreement may come into
existence in one of two ways; it may either arise out of an
agreement which contains nothing else besides the
arbitration agreement, or it may arise out of a term
contained in a contract which deals with various other
matters relating to the contract, which is the present case.
Where one is dealing with an arbitration agreement of the
second kind, s. 33 is concerned only with the term relating
to arbitration in the contract and not with the other terms
of the contract which do not arise for consideration on an
application under that section.
Then we come to s. 35. It provides that no reference or
award shall be rendered invalid by reason only of the
commencement of legal proceedings upon the subject-matter of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
the reference, but when legal proceedings upon the whole of
the subject-matter of the reference has been commenced
between all the parties to the reference and a notice
thereof has been given to the arbitrators or umpire, all
further proceedings in a pending reference shall, unless a
stay of proceedings is granted under s. 34, be invalid. It
will be seen, therefore, ’that s. 35 makes proceedings
before the arbitrators invalid in the absence of an order
under s. 34 staying the legal proceedings, where whole of
the subject-matter of the reference is covered by any legal
proceedings taken with respect to it. In other words, an
arbitrator can continue the proceedings and proceed to make
the award on the reference, unless the whole of the subject-
matter of the reference is covered by the legal proceedings
which have been instituted. Assuming that the proceedings
taken under s. 33 are " legal proceedings ", mentioned in s.
35, the question which immediately arises on the facts of
the present case is whether the whole of the subject-matter
of the reference in this case was covered by the legal pro-
ceedings taken by the appellant by its application under s.
33 of the Arbitration Act.
577
In dealing with this aspect of the case, learned counsel for
the appellant raised the question of frustration of the
contract and the powers of the court and the arbitrator in
that behalf. It is true that the words " frustration of
contract " have been used in paragraph 8 of the application.
But the prayers do not show that any relief was claimed on
that ground, relief (c) being merely a repetition of the
words of s. 33 of the Arbitration Act. Learned counsel
relied on Heymen v. Darwins Ltd. (1) in this connection. We
do not think we should permit the appellant to raise this
contention at this late stage and would content ourselves by
pointing out incidentally that even if the dictum in
Heymen’s case (1) is accepted, it will not help the
appellant, for on that dictum the question of frustration
would be for the arbitrators to decide on the basis of the
terms used in this contract which are of the widest
amplitude and would not be a matter for consideration of the
court. On this basis there would be no identity of subject-
matter between what can be raised in an application under s.
33 on the facts of this case and what can be decided by the
arbitrators. However, we do not propose to pursue this
matter any further and to decide it.
Then we turn to prayers (a) and (b) of paragraph 9 of the
application based on paragraphs 6 and 7 thereof. These
prayers undoubtedly cannot be the subject-matter of
arbitration, for they go to the very root of the contract
and imply that there was no contract between the parties at
all and therefore no arbitration agreement. These prayers
can certainly form the basis of an application under s. 33,
for they relate to the existence and validity of the
arbitration agreement contained in the contract; but not
being matters within the competence of the arbitrators,
there can be no identity of the subject-matter under
reference to the arbitrators and the subject-matter of
prayers (a) and (b). The conclusion, therefore, is that
prayers (a) and (b) can be the subject-matter of an
application under s. 33 but they cannot be the subject-
matter of the reference to the arbitrators. Therefore,
(1) [19421 2 A.C. 356.
578
the subject-matter of the legal proceedings under s. 33 in
this case cannot and does not cover any part of the subject-
matter of the reference. Section 35 in consequence can have
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
no application and the award cannot be assailed as invalid
on the ground that it violates s. 35 of the Arbitration Act.
The first contention, therefore, must fail.
Re. (2).
The argument under this head is that the liquidated damages
provided under cl. (1 2) of the contract include not only
the difference between the contract price and the market
price on the date of default but also a further sum of 10s.
per ton. Reference in this connection is made to ss. 73 and
74 of the Indian Contract Act, and it is said that the extra
amount of 10s. per ton included in the sum of liquidated
damages is against the provision of these, sections and
therefore the award being against the law of India is bad on
the face of it and should not be enforced in India. Section
73 provides for compensation for loss or damage caused by
breach of contract. It lays down that when a contract has
been broken, the party who suffers by such breach is
entitled to receive from the party who has broken the
contract compensation for any loss or damage caused to him
thereby, which naturally arose in the usual course of things
from such breach, or which the parties knew, when they made
the contract, to be likely to result from the breach of it.
Section 74, provides for breach of contract where penalty is
stipulated for or a sum is named and lays down that when a
contract has been broken, if a sum is named in the contract
as the amount to be paid in case of such breach, or if the
contract contains any other stipulation by way of penalty,
the party complaining of the breach is entitled, whether or
not actual damage or loss is proved to have been caused
thereby, to receive from the party who has broken the
contract reasonable compensation not exceeding the amount so
named or, as the case may be, the penalty stipulated for.
What cl. (12) of the contract provides in this case is the
measure of liquidated damages and that consists of
579
two things, namely, (i) the difference between the contract
price and the market price on the date of default, and (ii)
an addition of 10s. per ton above that. There is nothing in
s. 73 or s. 74 of the Contract Act, which makes the award of
such liquidated damages illegal. Assuming that the case is
covered by s. 74, it is provided therein that reasonable
compensation may be awarded for breach of contract subject
to the maximum amount named in the contract. What the
arbitrators have done is to award the maximum amount named
in the contract. If the appellant wanted to challenge the
reasonableness of that provision in cl. (12) it should have
appeared before the arbitrators and represented its case.
It cannot now be heard to say that simply because cl. (12)
provided for a further sum of 10s. per ton over and above
the difference between the contract price and the market
price on the date of the default, this was per se
unreasonable and was therefore bad according to the law of
India as laid down in ss. 73 and 74, of the Contract Act.
Both these sections provide for reasonable compensation and
s. 74 contemplates that the maximum reasonable compensation
may be the amount which may be named in the contract. In
this case the arbitrators have awarded the maximum amount so
named and nothing more. Their award in the circumstances
cannot be said to be bad on the face of it, nor can it be
said to be against the law of India as contained in these
sections of the Contract Act. The second contention must
also fail.
We, therefore, dismiss the appeal with costs to the
respondent.
Appeal dismissed.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
580