BALJEET SINGH (DEAD) THROUGH LRS vs. STATE OF UP

Case Type: Special Leave To Petition Civil

Date of Judgment: 08-08-2019

Preview image for BALJEET SINGH (DEAD) THROUGH LRS vs. STATE OF UP

Full Judgment Text

                                      REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION SPECIAL LEAVE PETITION (C) NOS.30404­30442/2017 Baljeet Singh (Dead) through Lrs. …Petitioners and others etc. etc. versus State of U.P. and others …Respondents WITH SPECIAL LEAVE PETITION (C) NOS.30455­30460/2017 SPECIAL LEAVE PETITION (C) NOS.23522­23530/2018 J U D G M E N T M.R. SHAH, J. Delay of 193, 224 and 142 days respectively in refiling the special leave petitions is condoned. Signature Not Verified Digitally signed by NARENDRA PRASAD Date: 2019.08.08 17:05:20 IST Reason: 2. Feeling   aggrieved   and   dissatisfied   with   the   common impugned   judgment   and   order   dated   2.4.1996   passed   by   the 1 High   Court   of   Judicature   at   Allahabad   in   First   Appeal   No. 919/1993 and other allied first appeals, the respective original claimants – land owners have preferred the present special leave petitions. 3. At the outset, it is required to be noted that there is an inordinate   delay   of   7534,   7542   and   7886   days   respectively (approximately 21 years) in preferring the special leave petitions before this Court challenging the impugned common judgment and order passed by the High Court. There is a further delay of 193, 224 and 142 days respectively in refiling the special leave petitions. 3.1. The application/applications for condonation of delay is/are vehemently opposed by the respondents herein.  Therefore, this Court   is   first   required   to   consider   and   decide   the application/applications submitted by the petitioners/applicants praying to condone the huge delay of 7534, 7542 and 7886 days respectively in preferring the special leave petitions. 4. Shri Rishi Malhotra, learned Advocate appearing on behalf of the respective petitioners has vehemently submitted that the lands   of   the   respective   petitioners   have   been   compulsorily 2 acquired under the provisions of the Land Acquisition Act, and therefore, they are entitled to the fair compensation for the lands acquired.  It is submitted that the dispute is with respect to the lands acquired of village Gulsitapur and Tilpta which are only 4 kms. away from village Kasna.  It is submitted that the location wise the lands of village Gulsitapur and Tilpta were better located and were abutting the national highway, i.e, Noida – Dadri Road. It   is   submitted   that   village   Kasna   is   4   kms.   behind   village Gulsitapur.  It is submitted that for the lands acquired of village Kasna, Section 4 notification was issued on 1.3.1989 and the compensation was awarded @ Rs.65/­ per square yard, which has been confirmed by this Court vide order dated 05.12.2016.  It is submitted that therefore the respective petitioners are entitled to   the   fair   compensation   for   the   lands   acquired   of   village Gulsitapur   and   Tilpta   at   par   with   the   land   owners   of   village Kasna, i.e., at Rs.65/­ per square yard.   It is submitted that therefore   the   agriculturists/farmers   are   entitled   to   the   fair compensation for the lands acquired.  It is submitted that for the lands   compulsorily   acquired,   the   delay   should   not   defeat   the valuable rights of the petitioners to get fair compensation.  It is submitted that the petitioners may not be awarded the interest 3 and other statutory benefits under the Land Acquisition Act for the period of delay. 4.1 Making   the   above   submissions   and   relying   upon   the decisions of this Court in the cases of  Market Committee, Hodal v. Krishan Murari reported in (1996) 1 SCC 311; Dhiraj Singh v. State of Haryana reported in (2014) 14 SCC 127; and K. Subbarayudu v. Special Deputy Collector (Land Acquisition) reported in (2017) 12 SCC 840 , it is prayed to condone the delay and consider the special leave petitions on merits. 5. All   these   applications   are   vehemently   opposed   by   the learned Advocates appearing on behalf of respondent no.3 – Uttar Pradesh State Industrial Development Corporation (UPSIDC) and on   behalf   of   respondent   no.4   –   Greater   Noida   Industrial Development Authority.   Counter affidavits are filed on behalf of respondent nos. 3 and 4 opposing the present applications for condonation of delay. 5.1 It is vehemently submitted by the learned counsel appearing on behalf of the respondents that there is an inordinate delay of approximately 21 years in preferring the special leave petitions. It is submitted that at no point of time earlier the respective 4 petitioners made any grievance with respect to inadequacy of the compensation as awarded by the High Court.   5.2 It is further submitted by the learned counsel appearing on behalf of the respondents that as such no sufficient cause has been shown explaining the huge delay of approximately 21 years. It is submitted that merely because in view of the subsequent decision in the case of lands acquired of another village, relying upon which the petitioners have preferred the present petitions, huge delay of approximately 21 years may not be condoned. 5.3 It is further submitted by the learned counsel appearing for the respondents that even otherwise the reliance placed upon the decisions of the High Court and this Court is with respect to entirely different village, i.e., village Kasna and that too in respect of   the   land   which   was   acquired   after   about   four   years   of acquisition of the petitioners’ land.  It is submitted that therefore the lands acquired of village Kasna are not comparable at all with respect to the lands acquired of village Gulsitapur and Tilpta. 5.4 It is further submitted that so far as the impugned common judgment and order dated 2.4.1996 is concerned, as such, the same has attained finality.   It is submitted that not only the 5 petitioners   accepted   the   compensation   but   after   the   said judgment   was   delivered   by   the   High   Court   no   special   leave petition has been filed by the present petitioners all these years. It   is   submitted   that   therefore   they   have   acquiesced   with   the impugned common judgment and order of the High Court. 5.5 It is further submitted by the learned counsel appearing on behalf   of   the   respondents   that   any   attempt   by   the   present petitioners to reopen the judgment shall lead to a cascading effect where   every   one   whose   land   has   been   acquired   by   the   said notification   with   respect   to   the   land   acquired   at   village Gulsitapur   and   Tilpta   would   start   demanding   enhanced compensation @ Rs.65/­ per square yard.   It is submitted that similarly the other land owners whose land has been acquired though at different villages between the years 1985­1989, too start demanding the same rate of compensation. 5.6 It is further submitted by the learned counsel appearing on behalf of the respondents that after the acquisition, the land is developed,   infrastructure   and   amenities   are   laid.   They   are maintained. The developed land has been allotted decades ago.  It is submitted that the rate of allotment is based on the cost of 6 acquisition and the amounts spent on development, laying out the infrastructure.  It is submitted that if the cost of acquisition is increased, then how this cost would now be recovered from the allottees after decades of allotment.  It is submitted therefore that to   entertain   the   present   petitions   now   after   a   period   of approximately   21   years   and   to   increase   the   amount   of compensation would have a cascading effect. 5.7 It is further submitted that it is disputed and denied that the land in village Gulsitapur is superior to the land in village Kasna. It is submitted that the correct fact is that village Kasna is located   on   the   main   road,   which   connects   Greater   Noida   to Sikanderabad,   District   Bulandshar,   unlike   the   land   of   village Gulsitapur which is in the interiors. 5.8 Now so far as the reliance placed upon the decisions of this Court   by   the   learned   Advocate   appearing   on   behalf   of   the petitioners,   referred   to   hereinabove,     is   concerned,   it   is vehemently   submitted   by   the   learned   counsel   appearing   on behalf of the respondents that none of the aforesaid decisions of this Court shall be applicable to the facts of the case on hand.  It is submitted that in the present case there is an inordinate delay 7 of approximately 21 years.   It is submitted that in the present case the petitioners have failed to make out a sufficient cause to condone the huge delay of approximately 21 years in preferring the special leave petitions. It is submitted that in the relied upon cases this Court was satisfied on the sufficient cause for delay.  It is submitted that in the relied upon cases the parity was claimed with respect to the land acquired under the very notification and it was pointed out that due to poverty and financial difficulty some of the land owners whose land was acquired under the same notification could not prefer the appeals earlier and they preferred   the   appeals   subsequently   and   claimed   parity   of compensation   at   par   with   the   lands   acquired   under   the   very notification.     It   is   submitted   that   in   the   present   case   the petitioners are claiming the parity in compensation with respect to the land acquired of another village and that too the land in the said village was acquired after a period of four years and location wise etc. the lands are different.   It is submitted that therefore on facts the same shall not be applicable to the facts of the case on hand. 8 5.9 Making the above submissions, it is prayed to dismiss the present applications for condonation of delay and consequently dismiss the special leave petitions as barred by limitation. 6. We   have   heard   the   learned   counsel   appearing   for   the respective parties at length. 6.1 At the outset, it is required to be noted that as such there is an inordinate delay of approximately 21 years in preferring the special   leave   petitions   before   this   Court   challenging   the impugned common judgment and order passed by the High Court which has been passed in the year 1996.   It is required to be noted   that   the   notification   under   Section   4   of   the   Land Acquisition   Act   with   respect   to   the   land   situated   in   village Gulsitapur and Tilpta was issued in the year 1985; possession was   taken   over   in   the   month   of   January,   1987;   the   Land Acquisition Officer declared the award in the year 1988 awarding compensation at the rate of Rs.8­10 per square yard.   At the instance   of   the   petitioners   herein   ­   the   original   land   owners, reference under Section 18 of the Land Acquisition Act was made to the reference Court.  By judgment and award dated 22.3.1993, the reference Court enhanced the compensation to Rs.30/­ per 9 square yard.  However, on appeals and considering the material on record, by the impugned common judgment and order, the High Court reduced the amount of compensation to Rs. 22­20 per square yard.  That thereafter, after a period of approximately 21 years, now the petitioners have preferred the present petitions claiming compensation at par with the compensation awarded for the land owners of another village Kasna.   It is required to be noted   that   so   far   as   the   land   acquisition   of   village   Kasna   is concerned, notification under Section 4 of the Land Acquisition Act was issued in the year 1989, i.e., after a gap of four years and it appears that in between certain developments have also taken place. 7. Having   considered   the   averments   made   in   the application/applications for condonation of delay, we are of the opinion   that   as   such   the   petitioners   have   miserably   failed   to make out a case to condone the huge delay of approximately 21 years.  No sufficient cause has been shown to condone the huge delay of approximately 21 years.  It is required to be noted that as such in the application itself it is submitted by the petitioners that there is an inordinate delay in approaching this Court.  The 10 only explanation in approaching this Court after about 21 years is given in paragraph 3 of the application, which reads as under: “That the primary reason in not approaching this Hon’ble Court in time was the fact that it was only in December, 2016, the claimants pertaining to village Kasana got the enhanced compensation from this Hon’ble Court to the tune of Rs.65/­ per sq. yard.  The petitioners herein came to know about the said fact in the month of January, 2017   causing   not   only   lots   of   heartburn   but   spelling miseries over them.   It took not only lots of courage in mustering support from number of affected families but also it took time for the petitioners to collectively file the instant   special   leave   petition   claiming   not   only   the enhanced compensation but also parity with regard to the compensation awarded to their co­villagers at village Kasana.” 7.1 That thereafter the petitioners have stated that though there is   a   reasonable   case   made   out   by   the   petitioners   to   get   the enhanced compensation to the tune of Rs.65/­ per square yard, but fairly enough in order to balance the equity, this Court may not grant interest from the date of the judgment of the High Court i.e., 2.4.1996 till the filing of the special leave petitions before this Court.     Except   the   explanation   in   paragraph   3,   reproduced hereinabove, there is no other explanation whatsoever explaining the huge delay of approximately 21 years.  Neither any poverty is pleaded nor any financial difficulty is pleaded.   Nothing is on 11 record that after the impugned common judgment and order is passed   by   the   High   Court,   the   petitioners   made   any grievance/objection   with   respect   to   inadequacy   of   the compensation determined by the High Court.  On the contrary, all the   petitioners   have   accepted   the   compensation   as   per   the judgment and award passed by the reference Court determining the compensation  at  the   rate   of  Rs.30/­  per  square   yard.   It appears that with respect to some of the land owners even the execution petitions are pending with respect to recovery of the differential amount of compensation, determined by the reference Court and the High Court as by the impugned common judgment and order the High Court has reduced the compensation from Rs.30­/ per sq. yard to Rs.22/­ per sq. yard.  Be that as it may, the fact remains that after the impugned common judgment and order is passed by the High Court, no grievance at all is made by the petitioners with respect to inadequacy of the compensation determined by the High Court. Thus, it can be said that for a period of approximately 21 years no grievance was made by the petitioners.     Therefore,   considering   the   terms   of   doctrine   of acquiescence, the petitioners lose their right to complain.   This principle is based on the doctrine of acquiescence implying that 12 in   such   a   case   the   party   who   did   not   make   any   objection acquiesced into the alleged wrongful act of the other party and therefore has no right to complain against that alleged wrong. 8. The matter requires examination from another aspect, viz., laches   and   delay.     It   is   a   very   recognised   principle   of jurisprudence that a right not exercised for a long time is non­ existent.  Even when there is no limitation period prescribed by any statute relating to certain proceedings, in such cases, courts have coined the doctrine of laches and delay as well as doctrine of acquiescence and non­suited the litigants who approached the court belatedly without any justifiable explanation for bringing the action after unreasonable delay.   In those cases, where the period of limitation is prescribed within which the action is to be brought before the court,  if the action is not brought within that prescribed period, the aggrieved party loses  remedy and cannot enforce   his   legal   right   after   the   period   of   limitation   is   over, however, subject to the prayer for condonation of delay and if there is a justifiable explanation for bringing the action after the prescribed   period   of   limitation   is   over   and   sufficient   cause   is shown, the court may condone the delay.   Therefore, in a case 13 where the period of limitation is prescribed and the action is not brought   within   the   period   of   limitation   and   subsequently proceedings are initiated after the period of limitation along with the prayer for condonation of delay, in that case, the applicant has to make out a sufficient cause and justify the cause for delay with a proper explanation.  It is not that in each and every case despite the sufficient cause is not shown and the delay is not properly explained, the court may condone the delay.   To make out a case for condonation of delay, the applicant has to make out a sufficient cause/reason which prevented him in initiating the proceedings within the period of limitation.  Otherwise, he will be accused of gross negligence.   If the aggrieved party does not initiate the proceedings within the period of limitation without any sufficient cause, he can be denied the relief on the ground of unexplained laches and delay and on the presumption that such person has waived his right or acquiesced with the order.  These principles are based on the principles relatable to sound public policy that if a person does not exercise his right for a long time then such right is non­existent. 14 9. Now so far as the reliance placed upon the decisions of this Court in the cases of   Market Committee, Hodal (supra); Dhiraj Singh (supra); and K. Subbarayudu (supra) , relied upon by the learned   Advocate   appearing   on   behalf   of   the   petitioners   is concerned, having gone through the said decisions, we are of the opinion that none of the said decisions shall be applicable to the facts of the case on hand and/or the said decisions shall be of any assistance to the petitioners.  First of all, in the relied upon cases, there was no such inordinate delay of approximately 21 years.  In the relied upon cases, this Court was satisfied on the sufficient cause for delay.   In the relied upon cases, parity was claimed   with   respect   to   the   land   acquired   under   the   very notification   and   it   was   pointed   out   that   due   to   poverty   and financial   difficulty   some   of   the   land   owners   whose   land   was acquired under the same notification could not prefer the appeals earlier  and  thereafter  they  preferred   the  appeals  subsequently and claimed parity of compensation at par with the land acquired under the same notification.  It is also required to be noted that as such in none of the aforesaid decisions, this Court had dealt with   and/or   considered   the   adverse   impact/effect   on   the State/acquiring   body   if   after   inordinate   delay/laches   the 15 State/acquiring body is directed to pay the enhanced amount of compensation.   In the present case, lands were acquired as far back as in the year 1985 and the award by the Special Land Acquisition Officer was declared in the year 1988.  The reference Court   enhanced   the   amount   of   compensation   to   Rs.30/­   per square yard, which came to be reduced by the High Court by the impugned common judgment and order in the year 1996.   It is required to be noted that the lands were acquired for Industrial development purposes.   That after the acquisition, the land has been developed, infrastructure and amenities are laid and the developed land has been allotted approximately before 30 years. It is the specific case on behalf of the respondents that the rate of allotment was based on the cost of acquisition and the amount spent on development, laying out the infrastructure.  Therefore, if the cost of acquisition is increased now and the State/acquiring body is directed to pay enhanced compensation, in that case, it would be   very   difficult  to   recover   the   difference   of   amount   of compensation from the allottees after decades of allotment.  The acquiring body will have to make additional budgetary provision and as observed hereinabove it would be very difficult for the acquiring body to recover the difference of compensation from the 16 allottees after so many years.  All these aspects and the cascading effect on the State/acquiring body if they are directed to pay the additional compensation after number of years, have not been considered by this Court in the aforesaid decisions relied upon by the learned Advocate for the petitioners.  Even if the petitioners are denied the interest and/or the other statutory benefits for the delayed   period   as   requested   by   the   learned   counsel   for   the petitioners, in that case also, to direct the State/acquiring body to pay the enhanced amount of compensation after number of years (21 years) would be unreasonable and would have a financial burden upon them and as observed hereinabove it would be very difficult for the State/acquiring body to recover the same from the allottees.     Under   the   circumstances,   none   of   the   aforesaid decisions shall be applicable to the facts of the case on hand and/or the same shall not be of any assistance to the petitioners. 10. In view of the above and for the reasons stated above, we refuse to condone the huge delay of 7534, 7542 and 7886 days respectively in filing the special leave petitions.  Accordingly, the applications   for   condonation   of   delay   stand   dismissed. Consequently, all these special leave petitions are dismissed on 17 the   ground   of   limitation.     However,   in   the   facts   and circumstances of the case, there shall be no order as to costs. …………………………………..J. [ARUN MISHRA] ……………………………………J. [S. ABDUL NAZEER] NEW DELHI; ……………………………………J. AUGUST 08, 2019. [M.R. SHAH]    18