Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
CASE NO.:
Appeal (civil) 1099 of 2007
PETITIONER:
State of Arunachal Pradesh
RESPONDENT:
M/s. Damani Construction
DATE OF JUDGMENT: 28/02/2007
BENCH:
A.K.MATHUR & V.S. SIRPURKAR
JUDGMENT:
J U D G M E N T
ARISING OUT OF S.L.P.(C) NO.14804 OF 2005
With
CIVIL APPEAL NO. 1100 OF 2007
(Arising out of S.L.P.(c) No.12954 of 2005)
A.K.MATHUR,J.
Leave granted in both the Special Leave Petitions.
Since the question of law involved in both the
appeals is common, they are disposed of by this common
judgment. For the sake of convenience, the facts stated in Civil
Appeal arising out of S.L.P.(c) No.14804 of 2005 are taken
into consideration.
This appeal is directed against the order passed by
learned Single Judge of the Gauhati High Court, Itanagar Bench
in Writ Petition No.408 of 2004 whereby learned Single Judge
set aside the order dated 15.9.2004 passed by the Deputy
Commissioner cum District Judge, Papum Pare, District, Yupia
in Miscellaneous Application No.10 of 2004 condoning the
delay in making application under Section 34 of the Arbitration
and Conciliation Act, 1996 (hereinafter to be referred to as ’the
Act’ ), being not maintainable. Hence, the order dated
15.9.2004 was set aside and the writ petition was allowed.
Aggrieved against this order passed by the High Court of
Gauhati, Itanagar Bench, State of Arunachal Pradesh has
preferred the present appeal.
Brief facts which are necessary for disposal of this
appeal are that the respondent herein entered into a contract
agreement bearing No.DD/03 of 1992-93 with the State of
Arunachal Pradesh in Public Works Department for executing
the contractual work of construction of road bridges. The value
of the work in question although was initially fixed at Rs.77.43
lakhs but on the basis of the post tender negotiation by and
between the parties, the price of the work was re-fixed at
Rs.1.15 crores. The work was to be completed within two
calendar years from the date of commencement of the work.
The work commenced on 10.4.1993 and it was completed in
March, 1999. According to the petitioner-respondent herein
the delay in execution of the work was due to deviation from
the original scope of work and several obstructions and
difficulties including delay in approval of the design and
drawings and also in making payment against running
accounts bills from time to time. The respondent herein raised
bill for the contractual work which according to the respondent
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
was refused to be paid due to certain arbitrary and untenable
reasons. Such refusal gave rise to a dispute and accordingly,
need arose for arbitration. The respondent then approached
the Court under section 11(6) of the Act which was numbered
and registered as Arbitration Case No.21 of 2000 and the
same was disposed of by the High Court appointing an
arbitrator to adjudicate the dispute between the parties. One
arbitrator was appointed on 18.10.2001 but subsequently that
arbitrator was changed by the present arbitrator. On
12.10.2003 the arbitrator passed an interim award awarding
Rs.65,52,878/- with simple interest to be calculated if the
award amount was not paid within 60 days from the date of
the award. However, the period of limitation prescribed under
Section 34 (3) of the Act for setting aside the award expired in
the meantime. The appellant then wrote a letter to the
arbitrator for review of the award and also sought clarification
in respect of the award on 2.4.2004. On 10.4.2004 the
arbitrator by his letter stated that he had no jurisdiction to
entertain the request for review of the award and also informed
that the award dated 12.10.2003 was in fact a final award
pertaining to the issues involved. On 21.6.2004 the
respondent- petitioner filed an application for execution of the
interim award dated 12.10.2003 before the Deputy
Commissioner. On 6.8.2004 the appellant filed an application
under Section 34 of the Act for setting aside the award dated
12.10.2003 together with an application under Section 5 of the
Limitation Act read with Section 34(3) of the Act for
condonation of delay in filing the application for setting aside
the award. The said application was entertained and was fixed
for hearing on condonation of delay after 15 days. Aggrieved
against this order, a writ petition was filed by the respondent
herein but the same was disposed of by the High Court with
the observation that as the matter was pending before the
court below it would not be appropriate to interfere at this
stage and left the Deputy Commissioner to decide the matter.
The Deputy Commissioner, Papum Pare, Itanagar by the
impugned order dated 15.9.2004 decided the application
condoning the delay in preferring the application under Section
34 of the Act by the appellant. Aggrieved against this order,
the present writ petition was filed by the respondent herein. It
is the legality of this order which was challenged before the
High Court. Learned Single Judge of the High Court after
hearing both the parties came to the conclusion that the order
passed by the Deputy Commissioner in condoning the delay
was not correct and it took the view that under section 34 of
the Act, there was a delay of seven months from the date of
first order and a delay of six months from the date of second
order.
The plea of the appellant- State before the court
below was that the award was passed on 12.10.2003 and a
copy was received on 23.10.2003. As such, the period of
limitation started from 23.10.2003. Since the letter was sent
by the appellant to the arbitrator on 2.4.20043 for review of
the award and a reply thereof was received on 10.4.2004
whereby the matter was clarified by the arbitrator, therefore,
the cause of action accrued in favour of the appellant on
10.4.2004 and application under Section 34 of the Act was
filed on 6.8.2004 i.e. within three months and the extended
period of one month, therefore, it was within limitation.
Though this contention prevailed before the trial court but the
same failed before the High Court on the ground that the
cause of action accrued to the appellant on 23.10.2003 when
the appellant received the copy of the award and the letter
which was written on 2.4.2004 was totally misconceived. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
interim award was final with regard to the claims raised
therein, therefore, the whole exercise undertaken by the
appellant was totally misconceived. Hence, learned Single
Judge allowed the writ petition and set aside the order of the
trial court. Aggrieved against this order passed by the learned
Single Judge, the present appeal was filed.
We have heard learned counsel for the parties and
perused the record. Learned counsel for the appellant tried to
persuade us that in fact the cause of action has arisen to the
appellant on 10.4.2004 when the letter was received from the
arbitrator and therefore, the appellant was entitled to count
the period of limitation from the date of receipt of the letter
from the arbitrator and if the limitation was to start from
10.4.2004 then the appellant has a right to move an
application for setting aside of the award under section 34 of
the Act within three months and the extended period of one
month and the appellant having filed the application on
6.8.2004, therefore, it was within time. The submission of
learned counsel for the appellant is totally misconceived and it
cannot be accepted. A perusal of the interim award passed by
the arbitrator clearly shows that it was final to the extent of
the claims decided therein and it may be relevant to refer to
the concluding portion of the award which reads as under :
" I further direct that the awarded
amount is indicated above along with the
interest, wherever shown till the date of interim
award amounting to Rs.65,52,878.00 (Rupees
Sixty five lakhs fifty two thousand Eight
hundred seventy eight only), shall be paid by
the Respondents to the Claimant within 60 days
from the date of the award, failing which a
simple interest on the unpaid amount @ 18%
(Eighteen percent) per annum shall be payable
to the Claimant by the respondents after 60
days of this interim award."
Therefore, this interim award which did not mince any word
and determined the amount after discussing the claims in
detail and finally calculated the amount under each of the
claims. Therefore, there was no confusion in this award. It
was absolutely thoughtlessness on the part of the appellant to
have written a letter after six months i.e. on 2.4.2004 seeking
review of the interim award to the following effect:
" While submitting the request for
review the case, it is also requested that your
honour may kindly consider (sic.) the following
points regarding mode of payments, if at all,
the payment is to be made, as the award given
by your honour is for the interim payment.
(a) Whether payment is to be
made directly to M/s. Damani Construction
Co. or through honourable court.
(b) In case, the payment is to
be made directly to M/s.Damani
Construction Co., an equivalent Bank
Guarantee Bond from any Nationalized Bank
shall be required from the Contractor since
it will be an interim payment and final
verdict awaited.
Submitted for your kind consideration please."
Firstly, the letter had been designed not strictly under section
33 of the Act because under Section 33 of the Act a party can
seek certain correction in computation of errors, or clerical or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
typographical errors or any other errors of a similar nature
occurring in the award with notice to the other party or if
agreed between the parties, a party may request the arbitral
tribunal to give an interpretation of a specific point or part of
the award. This application which was moved by the appellant
does not come within any of the criteria falling under Section
33(1) of the Act. It was designed as if the appellant was
seeking review of the award. Since the Tribunal had no power
of review on merit, therefore, the application moved by the
appellant was wholly misconceived. Secondly, it was prayed
whether the payment was to be made directly to the
respondent or through the Court or that the respondent
might be asked to furnish Bank guarantee from a nationalized
Bank as it was an interim award, till final verdict was awaited.
Both these prayers in this case were not within the scope of
Section 33. Neither review was maintainable nor the prayer
which had been made in the application had anything to do
with Section 33 of the Act. The prayer was with regard to the
mode of payment. When this application does not come within
the purview of Section 33 of the Act, the application was totally
misconceived and accordingly the arbitrator by communication
dated 10.4.2004 replied to the following effect.
" However, for your benefit I may
mention here that as per the scheme of the Act
of 1996, the issues/ claims that have been
adjudicated by the interim award dated
12.10.2003 are final and the same issues
cannot be gone into once again at the time of
passing the final award."
Therefore, the reply given by the arbitrator does not give any
fresh cause of action to the appellant so as to move an
application under Section 34 (3) of the Act. In fact, when the
award dated 12.10.2003 was passed the only option with the
appellant was either to have moved an application under
Section 34 within three months as required under sub-section
(3) of Section 34 or within the extended period of another 30
days. But in stead of that a totally misconceived application
was filed and there too the prayer was for review and with
regard to mode of payment. The question of review was totally
misconceived as there is no such provision in the Act for
review of the award by the arbitrator and the clarification
sought for as to the mode of payment is not contemplated
under Section 33 of the Act. Therefore, in this background,
the application was totally misconceived and the reply sent by
the arbitrator does not entitle the appellant a fresh cause of
action so as to file an application under Section 34(3) of the
Act, taking it as the starting point of limitation from the date
of reply given by the arbitrator i.e. 10.4.2004.
Thus, in this background, the view taken by learned
Single Judge appears to be justified and there is no ground to
interfere in this appeal. Consequently, there is no merit in both
the appeals and the same are dismissed with no order as to
costs.