Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
URBAN IMPROVEMENT TRUST, JODHPUR
Vs.
RESPONDENT:
GOKUL NARAIN & ANR.
DATE OF JUDGMENT: 10/04/1996
BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
G.B. PATTANAIK (J)
CITATION:
1996 AIR 1819 1996 SCC (4) 178
JT 1996 (4) 446 1996 SCALE (3)721
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
K. Ramaswamy, J.
Leave granted.
This appeal by special leave arises from the judgment
dated May 27, 1994 made in Civil Revision No.553 of 1993 by
a learned single Judge of the Rajasthan High Court at
Jodhpur. The admitted facts are that under Section 52 of the
Rajasthan Urban Improvement Act, 1959 [for short, the ’Act’]
the land of Gokul Narain, the first respondent, along with
otherlands, for construction of over-bridge, was acquired
and possession thereof was taken on June 22, 1965. The
Additional Collector made his award on June 30, 1976
awarding a sum of Rs.70,699.82 as compensation which
included value of the building also. On appeal, the District
Judge by order dated January 27, 1978 enhanced the
compensation to Rs.2/- per square foot. The appellant as
well as the respondents carried the matter in revision to
the High Court. By order dated March 18, 1983 the High Court
remanded the matter to the District Judge, with certain
directions, for fresh disposal thereof. The District Judge
by order dated November 19, 1985 enhanced the compensation
to Rs.11.50 per square foot and on further revision and
remand by the High Court by order dated December 18, 1989
also applied the provisions of the land Acquisition Act,
1894 [Central LA Act] as amended by Act 68 of 1984 and
awarded solatium, interest and additional amount under
Sections 23 [2], 28 and 23 1-A] of the Central LA Act. In
the meanwhile, the appellant had paid the compensation
amount on March 7, 1977 in a sum of Rs.1,18,760/- and a
further sum of Rs.44,195.60 on May 11, 1982. The respondent
claimed adjustment of the said amounts towards interest and
filed the execution for the balance amount. The High Court
by order dated August 4, 1988 dismissed the revision of the
respondent claiming adjustment of the amounts paid towards
interest and his entitlement to claim the balance amount
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
observing that the respondent is not entitled to benefit
under Act 68 of 1984. The respondent filed the execution for
recovery of the balance amount. The appellant filed
objections under Section 47 of the Code of Civil Procedure,
1908 [CPC] claiming that the cost of the acquired land
worked out @ Rs.11.50 per square foot to Rs.1,19,026.22 and
the cost of the building was Rs.3,423.00. Interest payable @
6% for period from June 22, 1965 upto July 3, 1977, the date
of deposit, worked out to Rs.85,981.16. The total
compensation payable and interest worked out to
Rs.2,08,432,36. The balance excess amount as on that date
including interest was Rs.89,672.38. Interest on the balance
principal compensation @ 6% from that date upto May 11, 1982
worked out to Rs.90,819.12. Balance compensation amount as
on May 11, 1982 and interest thereon was Rs.90,819.12.
Balance compensation amount as on May 11, 1982 and interest
thereon was Rs.46,623.62. The amount paid in compliance of
the order of the High Court dated December 12, 1987 was
Rs.1,23,000/-. Therefore, the excess amount paid to the
respondent was Rs.76,376.38. Interest calculated @ 6% on the
said excess amount for period from the date of the deposit
till date of objections, viz., January 16, 1991 to which the
appellant claims to be entitled is Rs.14,231.46. Thus the
appellant claims that he is entitled to receive from the
respondents a total refund of Rs.90,607.84 plus interest
thereon @ 6% from January 18, 1991 till date of decision.
The District Judge by the impugned order dated April 25,
1984 had dismissed the objections. On revision, the High
Court by the impugned order dismissed the claim. Thus this
appeal by special leave.
The Act was amended by Rajasthan Amendment Act 29 of
1987 which came into force w.e.f August 1, 1987. By reason
thereof, the Central Amendment Act 68 of 1984 became
applicable to acquisition under the Act from August 1, 1987.
Section 60A of the Act, as inserted by the Amendment Act 29
of 1987, made transitory provision applicable to the pending
matters. Pending the special leave petition, the first
respondent died on February 17, 1995. A notice was issued on
January 2, 1995. When the notice was not served, the
appellant was permitted to take out dasti service by order
dated by order dated February 5, 1996 and when the notice
was taken, the appellant was informed that the respondent
had died. Consequently, application for substitution under
Order 22 Rule 4, CPC was filed on February 12, 1996. The
legal representatives received the notice as per the orders
of this Court dated March 18, 1996. We have heard learned
counsel on both sides.
It is stated in the written arguments of the counsel or
the respondents that the District Judge by order dated May
27, 1995 brought the legal representatives of the first
respondent on record. When application came to be filed in
the District Court on May 5, 1995 to the knowledge of the
counsel or the appellant, it was ordered on May 27, 1995.
The application for substitution is barred by limitation.
The special leave petition had abated and, therefore, appeal
is not maintainable. We find no force in the contention.
Under Order 22, Rule 10A, CPC, whenever a pleader appearing
for a party to the suit comes to the knowledge of the death
of the party, he has to inform about it and the court
thereupon gives notice of such death to the other party and
for this purpose the contract between the pleader and the
deceased party is deemed to subsist. It would, therefore, be
clear that though the legal representatives have been
brought on record in the executing Court on May 27, 1995
pending proceedings in this Court, since the counsel for the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
appellant did not have had the information, on coming to
know of the death after dasti service was taken out,
immediately application under Order 22, Rule 4, CPC came to
be filed within 30 days of the date of the knowledge.
Accordingly, there is no abatement of the appeal. The State
is not expected to keep watch over the survival of the
respondent and lapse of counsel to intimate to the counsel
appearing in this Court cannot be construed to be knowledge
of death. Even if it is assumed that abatement was caused,
since application was filed under Order 22, Rule 4, CPC
within 30 days from the date of the knowledge there is no
delay in making the application to bring the legal
representatives on record in this Appeal. There is, hence,
no abatement by reason of the death of the respondent. The
application to bring the legal representatives is
accordingly ordered.
It is contended by Shri Badridas Sharma, learned
counsel for the appellant that the Amendment Act 68 of 1984
was extended for the acquisition of the land under the Act
w.e.f. August 1, 1987. Under the Act, there is no provision
for payment of solatium, interest and additional amount
either under the State Land Acquisition Act, 1953 or the
Central LA Act. The Act grants interest @ 6%. The District
Judge, therefore, was wrong in applying the provisions of
the Central LA Act as amended by Act 68 of 1984. The
District Judge, inherently lacked jurisdiction to apply the
provisions of Amendment Act 68 of 1984. The order dated
December 18, 1989 is a nullity to award solatium, interest
and additional amount under Sections 23 [2], 28 and 23 [1-A]
of the Central LA Act as amended by Act 68 of 1984. Nullity
of the decree can be raised even in execution. The
objection, therefore, was accordingly raised. The respondent
is not entitled to claim these additional benefits except
the principal amount @ Rs. 11.50 per square foot and
interest @ 6%. The District Judge as well as the High Court,
are, therefore, wrong in law in dismissing the objections.
Shri Arvind Kumar, learned counsel for the respondents
contended that the order awarding additional benefits under
Sections 23 [2], 28 and 23 [1-A] of the Central LA Act as
amended by Act 68 of 1984 was allowed to become final. The
Court, though wrongly, applied the Amendment Act, it did not
lack inherent jurisdiction. Therefore, having allowed the
decree to become final, it would not be open to the
respondent to contend that the decree is a nullity. It is
further contended that Section 47, CPC contemplates
correcting the errors in execution, discharge or
satisfaction of the decree. The modification sought by way
of objections amounts to review of the decree which has
become final. Therefore, it does not come within the ambit
of Section 47, CPC. The question, therefore, is: whether the
District Judge and the High court were right in concluding
that the appellant was not entitled to raise the objections
to the execution of the decree? The admitted position is
that the Act does not provide for payment of solatium and
additional amount. It empowers the Court to award interest @
6% on the amount awarded from the date of taking possession.
The appellant having allowed the enhanced compensation at
Rs. 11.50 per square foot, though on wrong principle, to
become final, it si bound by it. The only objection raised
by the appellant is as to the executability of the decree of
additional benefits under Central Amendment Act 68 of 1984.
The respondent is entitled only to the principal amount and
interest @ 6% per annum from the date of taking possession,
viz., June 22, 1965. The amounts claimed and paid have
already been specified and hence need no reiteration. It is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
settled law by catena of decisions of this Court that
determination of the compensation under Section 23 [1] of
the Central LA Act is towards market value of the land
prevailing as on the date of the publication of the Section
4 [1] notification in the Gazette. Equally, so under Section
52 of the Act.
In Prem Nath Kapur & Anr. v. National Fertilizers
Corporation of India Ltd. & Ors. [(1996) 2 SCC 71] a three-
Judge Bench of this Court had considered the scope of power
to award additional benefits under Sections 23 [2], 28 and
23 [1-A] of the Central LA Act and of the jurisdiction of
the court to decide as to when they are to be awarded; on
what items interest and solatium is claimable and upto what
date. Equally, of the power to adjust the amount towards
interest was considered. The facts in that case were that
the notification under Section 4 [1] was published on
February 5, 1973. On October 5, 1975, the Collector made his
award. On October 5, 1975, the Collector made his award. On
January 24, 1980 the reference Court enhanced the
compensation. The High Court dismissed the revision on May
23, 1983. When an application was made later, the High Court
awarded damages for severance and on further application it
awarded solatium, interest and additional amount under the
Amended Central LA Act. In execution, the respondent raised
the objection as to the executability of the decree of the
enhanced solatium, interest and additional amount. The
executing Court overruled the objections. The High Court
allowed the revision. The appellant had computed the total
liability deducting the amount paid toward interest and
additional amount payable including interest on solatium,
solatium and interest on additional amount under section 23
(1-A) and interest till the date f satisfaction under Order
21, Rule 1 CPC and laid execution for the balance amount
with interest. The appellant had raised objections which
were rejected by the executing Court. In the revision, the
High Court set aside the order and directed to compute the
principal amount, adjust the amounts deposited towards
principal amount and to proceed with the execution of the
balance amount. When the special leave petition was filed,
another Bench of this Court suo motu issued notice as to why
the additional benefits ordered under Sections 23 [2], 28
and 23 [1-A] as well as damages for severance and additional
benefits thereon should not be set aside. When the matter
came up on reference before a three Judge Bench, this had
held that payment of solatium under Section 23 (2) and
additional amount under Section 3 (1-A) are "in addition to"
the compensation determined under Section 23 [1]. Payment of
interest under Section 28 is on the excess amount or part
thereof awarded on reference under Section 26 or on appeal
under Section 54. The award of each component is
independent, after determination of market value under
Section 23 (1). The Court gets jurisdiction to awarded
additional benefits under Sections 23 [2], 28 and 23 [1-A]
only when the Court enhances the compensation and is not
independent of the power under section 23 (1). It was held
that the claimants were not entitled to solatium under
Section 23[2], interest under Section 28 and additional
amount under Section 23(1-A). The liability to pay interest
subsists till date of deposit of the amount into Court.
There is no liability to pay interest on salatium; or
solatium and interest on additional amount under Section 23
(1-A) which cannot be calculated and claimed in execution.
The claimant cannot adjust the amount deposited and received
towards principal amount as against interest. The doctrine
of Section 60 of the Contract Act is inapplicable to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
execution of the award under the Act. Therefore, the
claimant cannot appropriate the amounts paid for
compensation towards interest.
In Union of India vs. Raghubir Singh [(1989) 2 SCC
754], Constitution Bench of this Court had held that the
claimant is not entitled to the benefit of the Amendment Act
68 of 1984 in the pending appeals to pay enhanced solatium
and interest covered by transitory Section 30 of the
Amendment Act 68 of 1984. It would be applicable only when
the proceedings are pending either before the reference
Court or the Land Acquisition Officer. In K.S. Paripoornan
[II] v. State of Kerala [1995) 1 SCC 367] another
Constitution Bench per majority had held that the claimant
is not entitled to additional amount when the award was made
or possession take before the Amendment Act was introduced.
Since both the events had occurred prior to the introduction
of Amendment Act 68 of 1984, the claimant was not entitled
to additional amount. That ratio is being allowed in catena
of decisions of this Court subsequently including Prem Nath
Kapur’s case [supra].
In State of Punjab & Anr. vs. Jagir Singh & Ors. [1995)
supp. 4 SCC 626] the Additional District Judge had enhanced
the compensation on March 2, 1978. When the state had gone
in appeal, while dismissing the state appeal the High Court
granted benefits of the enhanced solatium, interest and
additional amount under Section 23 [2], 28 and 23 [1-A].
Objections were raised in education. When it was rejected,
this Court had held that the High Court had no power to
award the statutory benefits. It was, therefore, held that
the award of the High Court of the additional benefits was
without jurisdiction. This ratio is an authority for
proposition that though the High Court has power under
Section 54 to entertain appeal, it lacks jurisdiction to
aware independently additional benefits under the Amendment
Act, when it confirms the award of the reference Court. In
state of Punjab vs. Avtar Singh & Ors. [(1995) 1 SCC 383]
after the disposal of the appeal by the High Court on
November 11, 1982, an application came to be made under
sections 151 and 152 CPC after the Amendment Act 68 of 1984
came into force. Upon that the High Court on July 22, 1986,
had granted the benefits under Act 68 of 1984. On appeal,
this Court had held that the High Court had no power to
award the additional benefits. The same view was reiterated
in stats of Punjab & Anr. vs. Babu Singh & ors. [(1995)
supp. 2 SCC 406, major Pakhar Singh Atwal & ors. vs.. state
of Punjab & ors. [1995 supp (2) SCC 401], Union of India vs.
Rangila ram (Dead) by LRS. [(1995) 5 SCC 585]. Gurdial Singh
& Anr. vs. state of Punjab [(1995) 3 SCC 333] and
Improvement Trust. Patiala vs. Land Acquisition Tribunal &
Ors. [(1995) 3 SCC 724].
In Union of India & Ors. vs. Pratap Kaur (smt.) (Dead)
through LRs. & Anr. [(1995) 3 SCC 263], the facts were that
the High Court had disposed of the appeals under Section 54
of the Central LA Act which became final. Thereafter,
miscellaneous applications were filed before the Additional
District Judge to redetermine the compensation. He enhanced
the compensation on redetermination applying the principle
of belting. When the order came to be questioned, the High
Court dismissed the revision. On appeal, this Court had held
that District Court had no jurisdiction under Section 13-A
of the Central LA Act as it was neither a clerical error nor
an arithmetical mistake. The order was held to be without
jurisdiction. The Court gets jurisdiction only on a valid
reference made under Section 18. This case is an authority
for the proposition that Court has on inherent or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
independent power to determine compensation except on a
reference under Section 18 and so District Judge has no
inherent jurisdiction or authority to award compensation
under the guise of correcting the award or decree under
section 13A.
In State of Maharashtra vs. Maharau Srawan Hatkar
[(1995) 3 SCC 316], after the decree of the enhanced
compensation became final, on an application filed, the
Civil Judge awarded the additional benefits under the
Amendment Act 68 of 1984 and the High Court dismissed the
appeal. This Court had held that the Civil Court had no
jurisdiction to amend the decree awarding additional
benefits under Amendment Act 68 of 1984. In other words, the
award of additional benefits was held without jurisdiction
and authority of law. In Ishwarlal Premchand Shah & Ors.
etc. etc. v. State of Gujarat & Ors. [C.A. @ SLP 19039/94
etc.] decided on March 15, 1996 a contention was raised that
though the parties had entered into an agreement under
Section 11 [2] of the Central LA Act, they are entitled to
the additional benefits under Sections 23(2), 28 and 23 (1-
A) since those components are part of the compensation under
the guise of correcting the award or decree under section
13A.
In State of Maharashtra vs. Maharau Srawan Hatkar
[(1995) 3 SCC 316], after the decree of the enhanced
compensation became final, on an application filed, the
Civil Judge awarded the additional benefits under the
Amendment Act 68 of 1984 and the High Court dismissed the
appeal. This Court had held that the Civil Court had no
jurisdiction to amend the decree awarding additional
benefits under Amendment Act 68 of 1984. In other words, the
award of additional benefits was held without jurisdiction
and authority of law. In Ishwarlal Premchand Shah & Ors.
etc.etc. v. State of Gujarat & Ors. [C.A. @ SLP 19039/94
etc.] decided on March 15, 1996 a contention was raised that
though the parties had entered into an agreement under
Section 11 [2] of the Central LA Act, they are entitled to
the additional benefits under Sections 23(2), 28 and 23 (1-
A) since those components are part of the compensation. The
Land Acquisition Officer did not make an award in terms of
the form prescribed which included the additional amounts.
This Court had held that payment of additional amounts is
not part of the compensation. They are distinct and
independent. On the parties having entered into an agreement
under Section 11 [2], they are entitled to compensation only
in terms of the contract and not under the Act. In Union of
India v. Hari Kishan Khosla [(1993) Supp. 2 SCC 149] a
three-Judge Bench of this Court had held that payment of
solatium, interest and additional amount for the properties
acquired under the Requisition and Acquisition of Immovable
Property Act, 1952 would not be made, since the Act does not
provide for such payment.
In umed Industries and Land Development Co. & Ors. vs.
State of Rajasthan & ors. [(1995) 2 SCC 563], the question
arose: whether the Amendment Act 68 of 1984 would be
available to the lands acquired under the Act, and Rajasthan
Land Acquisition Act, 1953? It was held that by operation of
Section 60A of Rajasthan Amendment Act 29 of 1987, the
Central Amendment Act would be applicable only with effect
from August 1, 1987. Since the proceedings were pending for
determination of the compensation, it was held that solatium
and interest under the Amendment Act would be applicable,
but the claim for additional amount under Section 23 (1-A)
was rejected.
It would, thus, be settled law that payment of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
additional amounts independent of the compensation
determined for the value of the land. They are not part of
the component of the compensation for value of the acquired
land. They are in addition to and independent of the
component of the compensation under Section 23 (1) of
Central LA. Act or Section 52 of the Act. The payment of
solatium, interest and additional amount under Section 23
[2], 28 and 23 [1-A] is in addition to the payment of the
compensation in terms of the provisions of the Act under
which the property came to be acquired. Admittedly, the Act
does not provide for payment of solatium and additional
benefits except interest @ 6% per annum from the date of
taking possession. The Amendment Act 68 of 1984 would be
applicable. The Amendment Act 68 of 1984 would be applicable
prospectively from August 1, 1987 to the land acquired
thereafter, Act 68 of 1984 would be applicable under section
60A to the pending cases as on August 1, 1987 to determine
compensation.
It would be seen that under the Central Amendment Act
payment of additional amount under Section 23 [1-A] and of
solatium under Section 23 [2] cannot be applied to the award
made prior to coming into force of the Rajasthan Amendment
Act 29 of 1987. Section 60A provides that notwithstanding
anything contained in sub-section [11 of Section 52 of the
Act, where any matter relating to acquisition of land is
pending on the date of the commencement of the Amendment
Ordinance, viz., August 1, 1987 such matters being conducted
or action taken, shall be subject to the provisions of the
Central LA Act. The District Judge was, therefore, not right
in applying the Amendment Act on December 18, 1989 awarding
enhanced solatium and interest and additional amount.
The question then is: whether the objections can be
raised in execution? This controversy is no longer res
integra. In Sushil Kumar Mehta vs. Gobind Ram Bohra (Dead)
through his Lrs. [(1990) 1 SCC 193] a three-Judge Bench of
this Court was to consider whether the nullity of a decree
can be raised in execution. Under the Haryana Urban [Control
of Rent and Eviction) Act, 1973 the building was governed by
the provisions of the said Act. The Civil Court granted
decree of eviction. When objection was raised in execution
the executing Court rejected the same. On appeal, this Court
had held that a decree passed by a Court jurisdiction over
the subject matter or on any other ground which goes to the
root of its exercise of jurisdiction or inherent
jurisdiction, is a nullity. A decree passed by such a court
is a nullity and is non est. Its invalidity can be set up
whenever it is sought to be enforced or is acted upon as a
foundation for a right even at the stage of execution or in
collateral proceedings. The defect of jurisdiction strikes
at the authority of the court to pass a decree which cannot
be cured by consent or waiver of the party. If the court has
jurisdiction but there is any defect in its exercise of
jurisdiction it does not go to the root of its authority.
Such a defect like territorial jurisdiction could be waived
by the party which could be corrected only by way of an
appeal or revision. In that case it was held that since the
decree was a nullity the validity was upheld in execution.
In Jaipur Development Authority vs. Radhey Shyam & Ors.
[(1994) 4 SCC 370] this Court had upheld the same objection
raised under Section 47, CPC when the decree awarding
allotment of land in addition to compensation was held to be
a nullity. That objection was allowed to be raised in
execution and was upheld. Hiralal Moolchand Doshi vs.
Barotraman Lal Ranchhoddas [1993) 2 SCC 458] relied on by
the respondents is of no avail. In that case though nullity
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
of a decree on the basis of a compromise for eviction of a
tenant governed by the provisions of the Rent Act was
pressed for acceptance, this Court had held that the party
cannot be permitted to lead fresh evidence as to the
existence of that ground for eviction. On the facts in that
case, it was held that the tenant impliedly admitted
existence of statutory ground for eviction. Therefore, the
decree was held to be not a nullity. As regards the nullity
or lack of inherent jurisdiction, this Court observed that
the decree can be said to be a nullity if it is passed by a
court having no inherent jurisdiction. Erroneous decree
cannot be said to be a nullity; nor can a decree based on an
error be a nullity. Nullity has to be understood in the
sense that it is ultra vires the power of the Court passing
the decree and not merely avoidable decree. As stated
earlier, if the decree strikes at the jurisdiction of the
court or the court lacks jurisdiction it strikes at the very
root of the authority to pass the order or the decree. As
seen, the Amendment Act 68 of 1984 has no application to the
lands acquired under the Act. It was amended only w.e.f.
August 1, 1987 and it was made applicable only to the
pending proceedings. It would, therefore, be clear that the
order awarding additional benefits is clearly without
jurisdiction and thereby it is a nullity. Its nullity can be
assailed at any stage including at the execution or in a
collateral proceedings since it strikes at the very
jurisdiction and authority of the court.
Under these circumstances, the District Judge and the
High Court are not right and their finding that the
appellant is not entitled to raise objection in the
execution, is wrong in law. It should be considered in
execution only under section 47 CPC and not by a separate
suit. The orders of the District Judge and the High Court
stand set aside. The executing Court is directed to
recompute the liability of the appellant to pay the
compensation and interest @ 6% from the date of taking
possession i.e., June 22, 1965 and order execution
accordingly. In case it finds that the appellant is entitled
to restitution the same would be ordered under Section 144,
CPC as prayed for. The District Judge is directed to correct
the decree accordingly and recompute the liability to pay
compensation in the light of the law declared above and pass
appropriate orders according to law.
The appeal is allowed accordingly. In the
circumstances, parties are directed to bear their own costs.