Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
STATE OF BIHAR & ORS.
Vs.
RESPONDENT:
HANUMAN MAL JAIN
DATE OF JUDGMENT: 17/07/1997
BENCH:
S.B. MAJMUDAR, M. JAGANNADHA RAO
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
S.B. Majmudar . J.
Leave granted in both these Special Leave Petitions.
By consent of learned advocates of parties the appeals
were heard finally and are being disposed of by this common
judgment. The appellants in both these appeals are State of
Bihar and its officers in Rural Engineering Organisation.
Respondent in both these appeals is also one and the same
contractor. The grievance raised by the appellants centers
round the orders passed by learned Subordinate Judge,
Chaibasa, making awards rules of the Court in two Title
Suits filed by the respondent against the appellants. These
orders of the learned Subordinate Judge in turn were
confirmed by the High Court of Patna in appeal moved by the
appellants and that is how the appellants are before in
these proceedings. We shall refer to the respondent as
plaintiff and the appellants as defendants in latter part of
this judgment.
The plaintiff filed twp Title Suits for recovering
money dues from the defendants, in the Court of the
Subordinate Judge, Chaibasa. His contention was that while
carrying out contract work entrusted to him by the
defendants he had incurred expenditure over various extra
items which were not paid for by the authorities concerned.
He also raised certain ancillary claims against the
defendants seeking money decrees against the defendants in
both these suits.
The defendants resisted the suits on diverse grounds.
After hearing the parties the Trial Court appointed the
Superintending Engineer, Rural Engineering Organisation.
Works Circle, Ranchi as the sole arbitrator to adjudicate
upon the disputes raised in the suits. It was subsequently
found that before the arbitrator could finish the
arbitration proceedings his office fell vacant due to
retirement. Consequently the plaintiff moved another
application under the Arbitration Act, 1940 (hereinafter
referred to as ‘the Act’) for appointment of a fresh
arbitrator. The appellant-defendants agreed to the name of
one Shri T. Ghosh, retired Chief Engineer to act as sole
arbitrator and that is how the disputes between the parties
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
in both these suits were referred to the said arbitrator who
after hearing the parties gave his award on 6th July 1992
for a sum of Rs. 3,99,400/- in favour of the plaintiff in
Title Suit No.7 of 1988 with 18% interest. He passed another
award dated 7th July 1992 for a sum of Rs. 2,38,200/- along
with interest and cost in favour of the respondent-plaintiff
in Title Suit No.8 of 1988. The plaintiff moved applications
under Section 20 of the Act in both the suits for making the
awards rules of the Court. The defendants filed objections
to these awards under Section 30 of the Act. The learned
Subordinate Judge, Chaibasa, after hearing the parties
overruled the objections of the defendants and decreed both
the suits in terms of the arbitration awards. As noted
earlier the appellant-defendants being aggrieved by both
these award decrees approached the High Court of Patna at
Ranchi in appeal. The High Court dismissed the appeal and
confirmed the arbitration awards.
Learned senior counsel Shri Sanyal in support of these
appeals placed before us two contentions for our
consideration:
1. The awards which were made rules of the Court suffered
from patent error of law on the ground that Clause 11
of the Agreement between the parties was not complied
with by the plaintiff and hence both the awards were
barred by limitation as per the second proviso to the
said Clause and both the Subordinate Court as well as
the High Court had patently erred in relying upon 11
dehors the second proviso while confirming the awards.
2. The award of interest by the arbitrator was patently
erroneous and without jurisdiction as it was contrary
to the tender notice Clause 2.32 which prohibited grant
of such interest on the disputed amounts. Initially
when these Special Leave Petitions reached admission
hearing before a Bench of this Court consisting of
Hon’ble B.P. Jeevan Reddy and K.S. Paripoornan, JJ., an
order was passed by the said Bench on 9th September
1996 adjourning for three weeks the said Special Leave
Petitions to enable Shri Sanyal, learned senior counsel
for the petitioners to produce the copy of the grounds
of appeal before the High Court to establish the
following facts:
(i) that the State did point out
that the District Judge has quoted
a wrong proviso to clause 11 of the
contract and that the correct
proviso to clause 11 reads
altogether in a different manner.
(ii) that a submission was raised
in the grounds of appeal that by
virtue of clause 2.32 of the
tendered document no interest shall
be payable to the contractor.
Pursuant to the said order the appellants through their
counsel have produced the grounds of appeal before the High
Court by way of compilation in Paper Book No.1. On a perusal
of these grounds it is found that the twin contentions
canvassed before us by Shri Sanyal in support of the appeals
have in terms been raised before the High Court in the Memo
of Appeal being Ground No. VII. We have, therefore, examined
these contentions on merits after hearing learned counsel
for both the sides.
Contention No.1
So far as the applicability of second proviso to Clause
11 of the Agreement is concerned Shri Sanyal was right when
he contended that Clause 11 as extracted by the learned
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
Subordinate Judge in both of his judgments in Title Suit
Nos.7 and 8 of 1988 has been reproduced without the second
proviso which is a part thereof. The second proviso to
Clause 11 which is found in the themselves before the
arbitrator and even the objections under Section 30 of the
Act of the Act filed by the defendants to the said awards
before the Trial court it is revealed that not only the
arbitrator was alive to the question of applicability of
entire Clause 11 of the Agreement including the second
proviso but the defendants wanted to object to the awards on
the ground that the decision of the arbitrator on the
question of limitation was erroneous. We will presently show
how this is clearly revealed from the record of the case.
When the plaintiff put forward his money claims before
the arbitrator for adjudication the defendants themselves
joined issued on the applicability of Clause 11 of the
Agreement. In their written objections filed before the
arbitrator in both these cases, at paragraph 9 the following
pertinent averments were made:
"9. That the statements made in
para 6 of the statement of claims
are not correct. It is submitted
that clause 11 of the agreement
executed between the parties relate
to additional or extra items of
work and it lays down that
certificate of Engineer in Charge
of the work shall be conclusive and
further says that in the event of a
dispute the decision of the
Superintending Engineer of Circle
will be final. In the instant suit
the Superintending Engineer R.E.O.
Work Circles, Ranchi did not agree
with the recommendations of the
Executive Engineer, Shri B.N. Puran
in view of the fact that the extra
items of work were not executed
during his incumbency and wanted
the orders and acceptance of Shri
P.C. Das in whose incumbency the
work was executed and only on his
recommendations any claim can be
considered. Under the facts and
circumstances of the case the
claimant is not entitled to any of
the claims or reliefs prayed by
him."
A mere look at the aforesaid written objections of the
defendants before the arbitrator on the applicability of
Clause 11 shows that their only grievance before the
arbitrator was that the procedure of Clause 11 was not
followed and there was not a whisper about the claim
becoming barred by limitation in the light of second proviso
to Clause 11. Even that apart when we turn to the awards
which are non-speaking awards we find the following
pertinent recitals:
"Now, therefore, I said Taradas
Ghosh (T. Ghosh) after going
through all the statements,
evidences, arguments etc. and
having duly considered all the
matters submitted to me by both the
parties do hereby make my award as
follows:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
1. That the Executive Engineer
Rural Engineering Organisation
Works Division Chaibasa should pay
Sri Hanuman Mal Jain Contractor
Chakradharpur a sum of Rs.
3,99,400/- (Rupees three lakhs
ninety nine thousand four hundred
only) after going through all the
documents and arguments by both the
parties.
2. That the aforesaid amount
carries simple interest @ 18%
(eighteen) per annum which I
consider reasonable with effect
from 1.1.86 till the date of award
and also from the date of award
till the date of payment or the
date of decree whichever is
earlier."
It becomes, therefore, clear that the arbitrator while
passing non-speaking awards in both these cases had
considered all statements, evidences and arguments offered
by the contesting parties before him and then he had passed
the awards. It is also pertinent to note that amongst the
documents considered by the arbitrator the Agreement between
the parties including Clause 11 with both its provisos duly
signed by the parties was obviously on the record and
whatever contentions were canvassed by the defendants
regarding the applicability of Clause 11 were stared to have
been considered by the arbitrator and then the non-speaking
awards were passed. Consequently it is impossible to
appreciate the contention that there was any patent error on
the part of the arbitrator in not considering the question
of limitation as mentioned in the second proviso to Clause
11. It is also necessary to note that the said second
proviso does not totally prohibit granting of a claim for
the work on extra items carried but by the contractor by it
only lays down the procedure how the claim could be lodged.
Consequently the second proviso cannot be said to have
ousted jurisdiction of the arbitrator in deciding the
dispute on merits as well as on the question of limitation.
Implicit in the observations in the award is the finding of
the arbitrator that the claims were not contrary to Clause
11 but were in compliance thereof. Not only that, in the
objections under Section 30 of the Act filed by the
defendants in both these cases before the Trial Court the
following contentions were raised by the defendants in
Objection No. (x):
"(x) For that the learned
Arbitrator ought to have disallowed
the claim as time barred and not
maintainable in terms of clause 11
of the Agreement."
This objection on the face of it shows that according
to the defendants the arbitrator had wrongly allowed the
claims which were time barred as per Clause 11. Thus the
objection was not on the ground of absence of jurisdiction
of the arbitrator wrongly held the claim to be within time.
This obviously was in the domain of the jurisdiction of
arbitrator and even if he had decided wrongly the question
of limitation it could not be made a subject-matter of
objection under Section 30 of the Act against a non-
speaking award. Nor would it show any misconduct on his
part. The court obviously could not sit as a Court of Appeal
against the decision rendered by the arbitrator on this
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
ground. Much more so when the awards were non-speaking
awards. In this connection we may refer to a decision of
this court in the case of Dandasi Sahu v. State of Orissa
(1990) 1 SCC 214 to which our attention was invited by Shri
Sanyal, learned senior counsel for the appellants. He
submitted that even in case of a non-speaking award the
arbitrator is bound to refer to all the documents and his
awards nowhere showed that he had considered all the
documents in this connection while passing the awards. The
observations found in paragraph 3 at page 218 of the Report
on which reliance was placed by Shri Sanyal read as under:
"... Though the arbitrator is not
bound to disclose as to what
interpretation he has made and what
inference he was derived from the
documentary evidence, he is bound
to refer in the award that he had
considered all the documents placed
before him no matter whether he
relies on them or discards them
from consideration. The arbitrator
in his award ex facie does not
mention that he has referred to or
considered the documents placed
before him in respect of the
original claim."
These observations made in connection with a non-
speaking award instead of helping the learned senior counsel
for the appellants on the facts of the present case go
against the appellants. The reason is obvious. In the awards
in question, as seen earlier, the arbitrator has clearly
mentioned that he had considered all matters submitted to
him by both the parties and he had gone through all the
statements, evidences, arguments etc. It is true that the
word ‘evidences, arguments etc. It is true that the word
‘evidences’ is mentioned and not ‘documents’ in that
paragraph. However it could not be urged with any emphasis
that evidence would include only oral evidence and not
documentary evidence. But even that apart the subsequent
identical paragraph found in the awards which is already
extracted by us earlier leaves no room for doubt that the
claims have been adjudicated after going through all the
documents and arguments by both the parties. Consequently it
must be held that even though the learned Trial Judge as
well as the High Court had not noticed the second proviso to
Clause 11 of the Agreement both the parties had joined issue
on the point before the arbitrator and the arbitrator having
considered all the relevant contentions of the parties on
this aspect had passed the impugned awards which even
according to the defendants were passed on consideration of
Clause 11 as a whole but only fault sought to the found by
the defendants against the awards was that the arbitrator
had wrongly treated the claims not to be time barred. That
question would squarely get connected with the second
proviso to Clause 11 to which we have made a reference
earlier and not dehors it. The first contention, therefore,
is found to be devoid of any substance. That takes us to the
second submission raised by Shri Sanyal, learned senior
counsel for the appellants.
Contention No.2
Shri Sanyal submitted that Clause 2.32 of the Tender
Terms which was binding on the plaintiff prohibited the
arbitrator from awarding any interest on the disputed
amounts. The said clause in the Tender Notice reads as
under:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
"2.32- CLAIMS FOR INTEREST :-
No claim for interest or damage
shall be made against the
department with respect to any
money or balance which may be lying
with the department owing to any
dispute, unsettled claim,
difference of understanding between
the Engineer-in-charge on the one
hand and the Contractor on the
other hand with respect to any
unavoidable delay on the part of
the Executive Engineer in making
final payment in any respect
whatsoever."
This contention was raised by the defendants for
consideration before the High Court in the Memo of Appeal.
Not only that but this contention was also canvassed for
consideration of the learned Trial Judge. It is also true
that the Trial Court while dealing with these objections has
made identical observations in both the proceedings in
identical paragraph 14 of its judgments. That identical
paragraph reads as under :
"14. The learned G.P. however
argues that clause 2.32 of Bihar
Public Works Department F-2
specifically debars interest and
hence on the basis of ruling relied
upon by the plaintiff reported in
AIR 1992 SC 732 the arbitrator
should not allow interest. I have
carefully gone through clause 2.32
of Form F-2 and it is debatable on
the point whether arbitrator should
allow interest or not? Hence it is
the duty of the arbitrator to
decide whether clause 2.32 fetters
his hand in allowing interest or
not."
It is true that the learned Trial Court thought that it
was a debatable question and that it was the duty of the
arbitrator to decide such questions. The learned Trial Judge
had not addressed himself to the question whether the
arbitrator had considered the said clause or not. When we
turn to the High Court’s judgment in appeal we find the
situation no better. In the impugned judgment at paragraph
no.6 the High Court has noted the contention that award of
interest @ 18% p.a. in absence of any agreement to this
effect was unwarranted. But when we turn to the discussion
in the said judgment the only discussion found is in
paragraph 10 of the judgment dealing with the main argument
regarding Clause 11. This would have required us to either
remand the proceedings to the High Court for consideration
of this second contention or decide the same ourselves. As
these are old claims arising out of suits of 1988, in our
view, interest of justice requires that we may ourselves
decide this question on its own merits. We have, therefore,
heard the learned advocates on this question.
When we turn to the said clause 2.32 we find that it
may prima facie he found to be applicable to the claims for
interest or damage in connection with any money or balance
which may be lying with the department and which the
plaintiff may rightfully claim to be refundable to him. The
phrase ‘money or balance which may be lying with the
department’ may cover not only any amount of money but even
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
any balance of money meaning thereby the claim may refer to
the whole amount which the plaintiff claims to be refundable
to him or any balance of it after having been refunded a
part of it and thus the claim is confined to only the
balance being left with the department. In either case it
would be a claim for refund of an amount of money already
lying with the department. However learned senior counsel
Shri Sanyal submitted that the term ‘any money’ is
independent of the balance which may be lying with the
department and, therefore, any money claimed by the
plaintiff against the defendants would be covered by the
said clause and it is not necessary that the money must be
lying with the department and only claim of refund would be
contemplated by the said clause. However even assuming that
such a construction of the clause is possible, the real
hurdle in the way of the defendants lies in the penultimate
part of the said clause. It clearly shows that the claim for
money or damage should have been made against the department
and the dispute regarding the same should have remained
unsettled between the Engineer-in-Charge on the one hand and
the Contractor on the other and in connection with such a
dispute it should be demonstrated that there was any
unavoidable delay on the part of the Executive Engineer in
making the final payment. It is, therefore, obvious that if
the delay was avoidable on the part of the Executive
Engineer in making the final payment then the claim of
interest in connection with the said amount of money would
not get barred under the said clause. So far as this aspect
is concerned it is interesting to note that nowhere in the
objections filed before the arbitrator or even before the
Court under Section 30 of the Act such a connection was
canvassed for consideration by the appellants. In the third
volume of additional documents filed by the appellants
themselves is found a copy of the Minutes maintained by the
arbitrator in connection with the proceedings before him in
the present two cases. At paragraph 6 of the said Minutes in
connection with the plaintiff’s claims the contention of his
counsel is noted. The summary of the submissions as noted in
the said paragraph reads as under:
"6. Sri Kar Roy, Counsel for the
Claimant, while summing up
submitted that the claims were
submitted to the Department before
completion of the work on 01.04.85.
Reminder notices were submitted by
the Claimant on 08.04.85 and
12.04.85. The E.E. might have
thought it fit to obtain
recommendations on 11.09.85 after
obtaining recommendations of J.E.
Thereafter unreasonable delay
occurred on the part of E.E. to
take next logical step and
ultimately recommended and/or dealt
with the claim on 21.08.87. The
concerned officers of the
Respondent generally accepted the
claims, but did not give any reason
for rejection of any item, which
was absolutely arbitrary."
[Emphasis supplied]
The aforesaid contentions before the arbitrator leave
no room for doubt that it was the case of the plaintiff
before the arbitrator that his claims were unreasonably
delayed by the Executive Engineer before considering the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
same. It is this contention which is accepted by the
arbitrator by passing the impugned awards though in a non-
speaking manner. Therefore, it is not possible to agree with
the contention of learned senior counsel for the appellants
that the claim for interest was barred by clause 2.32 of the
Tender Terms. If the contention of the plaintiff before the
arbitrator was that his claims were unduly delayed they
would obviously rule out the applicability of the said
clause as that would not amount to unavoidable delay on the
part of Executive Engineer in making the final payment. On
the contrary it would be avoidable delay which would take
out the claims from the fetters of Clause 2.32, even
assuming that Shri Sanyal, learned senior counsel for the
appellants is right in his submission that the said clause
would cover all money claims pertaining to the amounts which
may not be lying with the department and still would be
within the sweep of the first part of the said clause. In
this connection it is also profitable to refer to paragraph
13 of the written objections filed on behalf of the
defendants before he arbitrator:
"13. That there is specific
provision in the agreement between
the parties that claim for damage
or interest against the department
is not maintainable. Moreover the
facts and circumstances of the case
as well as under the provisions of
law the claimant is not entitled
for any damage or interest as
claimed by him."
This statement of objections clearly shows that the
defendants joined issue on the question whether any interest
could have been awarded against the defendants by the
arbitrator. Implicit in this contention would be the moot
question whether there was any unavoidable delay on the part
of the Executive Engineer in making the final payment which
according to the plaintiff fell short of his claim and it is
this connection which, as noted by the arbitrator in the
Minutes was pressed for consideration of the arbitrator. He
ultimately came to his own conclusion regarding the same by
rejecting this contention on merits by non-speaking awards.
It is, therefore, not possible to agree with the learned
senior counsel for the appellants that applicability of
Clause 2.32 of the terms of tender was not kept in view by
the arbitrator and consequently his awards suffered from any
patent error of law. We have to undertake this exercise on
the facts of the present cases as neither the learned Trial
Judge nor the High Court had come to the grip of this issue
and in order to avoid unnecessary protraction of litigation
we thought it fit, as noted earlier, after hearing the
parties to decide this controversy. We accordingly find that
on merits there is no substance even in this second
contention.
In the result, both these appeals fails and are
dismissed. However in the facts and circumstances of the
cases there shall be no order as to costs in each of them.