M/S DYNA TECHNOLOGIES PVT.LTD. vs. M/S CROMPTON GREAVES LTD.

Case Type: Civil Appeal

Date of Judgment: 18-12-2019

Preview image for M/S DYNA TECHNOLOGIES PVT.LTD. vs. M/S CROMPTON GREAVES LTD.

Full Judgment Text

Reportable IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION   CIVIL APPEAL NO. 2153 O F  2010   M/ S . D YNA  T ECHNOLOGIES  P VT . L TD .      …A PPELLANT ( S ) V ERSUS M/ S . C ROMPTON  G REAVES  L TD .      …R ESPONDENT ( S )   J UDGMENT   AMANA   N. V. R , J.   1. The question involved herein revolves around the requirement of reasoned   award   and   the   cautionary   tale   for   the   parties   and arbitrators to have a clear award, rather than to have an award which   is   muddled   in   form   and   implied   in   its   content,   which inevitably leads to wastage of time and resources of the parties to get clarity, and in some cases, frustrate the very reason for going for an arbitration. 2. This appeal is  filed  against the  final  order  and  judgment dated 27.04.2007,  passed by the  High Court  of Judicature at Madras Signature Not Verified Digitally signed by SATISH KUMAR YADAV Date: 2019.12.18 13:34:36 IST Reason: whereby   the   High   Court   partly   allowed   the   appeal   filed   by   the respondent and set aside the award of Arbitral Tribunal relating to 1 claim no. 2 for payment of compensation for the losses suffered due to unproductive use of machineries.    3. Brief facts of the case are that a contract was entered into between DCM Shriram Aqua Foods Limited (hereinafter referred to as ‘DCM’ in short) and M/s. Crompton Greaves Limited (hereinafter referred to as “CGL” in short) for an aquaculture unit to be set up by such Principal,   namely,   DCM.   CGL   invited   tenders   for   carrying   out certain   works   for   construction   of   ponds,   channels,   drains   and associated works.  The appellant M/s Dyna Technologies Pvt. Ltd. gave its proposal, estimate and quotation for carrying out the work. th Thereafter, the respondent CGL placed a letter of intent dated 25 July, 1994, relevant portions of which are as under: “10. In the event that you are forced to keep your equipment   and   manpower   idle   due   to   non availability   of   work   fronts   due   to   reasons attributable to DCM or due to legal disturbances not connected with you, you shall be compensated as follows: (i) Maximum   seven   days   of   stoppage   of   work without any compensation. (ii) CGL   reserves   the   right   to   advice   you   to demobilize partially or fully in lieu of paying compensation   for   such   delays.   Under   such circumstances,   you   shall   be   paid   such 2 compensation   towards   transportation   of equipment to Site at mutually agreed rates. (iii) Suitable   time   extension   shall   be   given   to complete   the   work   to   compensate   the   delay caused due to the stoppage of work.  11. Storage & Security: you will be responsible to provide necessary stores, office and labour camps for   your   staff   at   site.   Only   open   area   for construction   of   above   will   be   given   to   you. Electricity   will   be   provided   at   one   point   on chargeable basis at actuals. You will be responsible to tap the same to your required place. A format work order will be charged subsequently which   will   cover   other   General   Terms   and Conditions. Labour rules, Workmen Compensation etc. which may not be covered by this LOI and the same shall also be part of this LOI.” 4. The appellant made certain queries and clarifications, and by letter th dated 10  October, 1994, CGL amended the contract as suggested by the appellant company. Thereafter, CGL issued work order on th 15   November, 1994 setting out the terms and conditions of the work, material portions of which are stated as under: “2. Termination of contract : The Company reserves the right to terminate this work at any stage without payment of compensation due to any of the following reasons: a. If the original contract between the client and the company is terminated/suspended. 3 b. The   company   is  unable   to  proceed  with  the work   due   to   reasons   like   non­availability   of work fronts, delay in availability of materials or delay in receipt of payments from clients etc. c. If the contractor is not able to carry out work to   the   satisfaction   of   the   company’s   clients representatives. d. If the contractor is unable to ensure adequate progress as required by the company and their purchaser. e. Upon termination of this contract/work order, all rights and obligation of the parties, shall cease provided that the termination shall not relieve the contractor of any of his obligations which   may   have   accrued   upto   the   date   of termination. Upon termination of this contract/work order due to default on the part of the contractor, he /it shall indemnify the company against all losses incurred by the company as a result of such termination.” th 5. After   commencement   of   the   work,   the   respondent   CGL   on   5 January, 1995 instructed the employees of the appellant company to stop the work. 6. The appellant company claimed compensation for such premature termination of the contract and ultimately the dispute was referred to Arbitral Tribunal consisting of three Arbitrators. 7. The appellant­claimant made the following claims:­ (1)Losses due to idle charges. 4 (2)Losses   due   to   unproductivity   of   the   men   and machineries which could not work due to hindrances. (3)Loss of profit as the contract got dissolved and  (4)Interest on the above claims and (5)Costs. 8. The aforementioned claims are listed in the statement of claims st totalling   to   Rs.   54,21,170.45   initially   on   21   June,   1997   and th revised to Rs. 53,83,980.45 on 5  July, 1997. 9. The following is a summary of the final claims:­
(1) Idle Charges for machineries and<br>demobilisation as approved by<br>Respondent…Rs. 4,18,551.50
(2)Losses due to unproductive use<br>of machineries…Rs. 45,85,286.00
(3)Loss of profit…Rs. 20,89,925.00
(4)And (5) Interest and Costs<br>Deduct Payment already received… to be assessed<br>Rs. 70,93,763.33<br>Rs. 17,09,782.88<br>_____________________
Balance dueRs. 53,83,980.45<br>+<br>Interest and costs
10. It may be relevant to note at this stage that so far as claim no. 1 in reference to the losses due to idle charges is concerned, it was 5 finally settled amicably by the parties and the balance towards the interest component also stands paid. 11. So far as claim no. 3 in reference to loss of profit is concerned, the same was disallowed by the Arbitral Tribunal and it was later not questioned by the appellant­claimant and that attained finality. 12. The only objection is in reference to claim no. 2,   i.e. , losses due to unproductive use of machineries which was accepted by the Arbitral Tribunal for a sum of Rs. 27,78,125/­ with interest @ 18% th p.a.  vide  its award dated 30  April, 1998 and Correction to award th dated 5  May, 1998. 13. Aggrieved by the award passed by the Tribunal, an original petition was filed before the learned Single Judge of the High Court of Judicature at Madras, questioning the award under Section 34 of the Arbitration and Conciliation Act, 1996 ( hereinafter  “Arbitration Act”), by the respondent. The learned Single Judge, while upholding the award of the Tribunal, observed as under: “7. Thus the Arbitrators have given a specific finding that the amount paid as compensation is actually   the   amount   expended   by   the   fourth 6 respondent and therefore the petitioner is liable to  reimburse   the  loss   sustained  by   the  fourth respondent.   Therefore,   this   contention   is   also . not acceptable    … 9. Further, the learned counsel for the petitioner took this court to various portions of the Award and tried   to   convince   this   Court   that   the   Arbitrators have  not decided the issue fully appreciating the evidence on record. In the judgment of the Supreme Court reported in M/s Sundarsan Trading Company v. Government of Kerala (AIR 1989 Supreme Court 890) it has been clearly held that the power of the Arbitrator   in   respect   of   the   interpretation   of   the contract in a matter for arbitration, the Arbitrator can pass the Award by taking a particular view of the contract and hence, the Court cannot substitute its   own   decision.   Therefore,   this   Court   cannot reappraise the evidence and  substitutes  its views and set aside the Award. Also in the case of Tamil Nadu Civil Supplies Corporation Limited v. Albert and Company (2000 (III) CTC 83), this Court has held that as per Section 34 of the Act, the Award of the Arbitrator can be set aside only on the limited grounds and the Award cannot be interfered with simply   because   another   view   is   possible   on   the available   materials.   The   arbitrator   is   a   Judge   of choice of parties and this Court cannot set aside unless it suffers from error apparent on the face of the record. It cannot be set aside even if the Court can come to different conclusion on the same facts. The   learned   counsel   for   the   petitioner   has   not pointed out any such ground. It cannot also be said that the Award is perverse or has error apparent on the face of the record. Therefore, the Award passed by the Arbitrator is not illegal or invalid and cannot be set aside. Therefore, the petition is dismissed.” 7 ( ) emphasis supplied 14. Aggrieved   by   the   aforesaid   decision   of   the   learned   Single Judge, the respondent appealed before the Division Bench in O.S.A No. 234 of 2001. As aforementioned, the High Court  vide  impugned order partly  allowed the  appeal and  set aside the  award of the Tribunal relating to claim no. 2.  The High Court was of the opinion that   the   award   does   not   contain   sufficient   reasons   and   the statements contained in paragraph 3.1 (a) to 3.1 (g) of the award does not provide any reasons, discussions or conclusion.  The High Court has observed in the following manner: “18.  It is of course true that an Arbitrator cannot be expected to write a detailed judgment as in a law Court. However, the present Act contemplates that the award of the Arbitrator should be supported by reason. The decision relied upon by the counsel for the   respondent,   rendered   on   the   basis   of   the Arbitration   Act,   1940,   cannot   be   pressed   into service   keeping   in   view   the   specific   provision contained in the Act. Moreover, even assuming that the   ratio   of   the   said   decision   is   applicable,   we cannot cull out any underlying reason in the award for directing payment of compensation. The basis for the right of the claimant and the basis of the liability   of   the   present   appellant   have   not   been indicated anywhere within four corners of the award 8 and in spite of the best efforts it is not possible to discover even any latent reason in the award. 19.  It was also contended that the discussion in para   3.1(g)   of   the   award   contains   the   basis   and reason given by the Tribunal. We   have   carefully   gone   through   such paragraph as well as the preceding and subsequent paragraphs.   In   our   considered   opinion,   the statements recited in para 3.1 including para 3.1(g) are only substance of the submissions/claim made by   the   claimant   and   para   3.1(g)   cannot   be construed  as  a conclusion or  even  the  reasoning given by the Tribunal.” 15. Having   come   to   a   conclusion   that   the   arbitral   award   was deficient due to the lack of reasoning, the High Court proceeded further to note that the option of Section 34 (4) of the Arbitration Act was not necessary as the compensation could not have been claimed   considering   the   fact   that   the   work   order   has   provision barring claim no. 2, in the following manner: “20.  Learned counsel for the respondent has relied upon Section 34(4) of the Arbitration Act and has submitted that in case if this Court finds that the Arbitral Tribunal has not given reason, even though it is so required under Section 31(3) by invoking jurisdiction under Section 31(4), this Court can give opportunity to the Arbitral Tribunal to resume the arbitral   proceedings   or   to   take   action   as   in   the 9 opinion of the Arbitral Tribunal would eliminate the grounds for setting aside the arbitral award. 21.  We do not think that the present case is a fit case where the Arbitral Tribunal can be called upon to give reasons in support of its conclusion. This is because, in our considered opinion, the terms of the contract clearly exclude the possibility of payment of   any   compensation   on   account   of   premature termination of the contract as envisaged in para C. 2(a).” 16. Thereafter, the High Court proceeded further to note that the arbitral proceeding was beyond the competence of the Tribunal by considering the conditions under the work order.  17. Learned counsel for the appellant submits that the Arbitral Tribunal comprising of three Arbitrators has looked into the entire material available on record and recorded a finding in reference to claim no. 2 (losses suffered due to unproductive use of machineries) based on the case set up by the parties taking note of Section 73 of the   Indian   Contract   Act,   1872   ( hereinafter   “Contract   Act”)   and relying   on   the   evidence   including   appraisal   of   the   log   books approved by the respondent and held that actual losses/expenses were incurred by the appellant. In the given circumstances it was not open for the High Court in appeal to reappraise and substitute 10 its   own   view   in   contravention   of   the   clause   of   the   agreement pursuant to which the arbitral dispute was raised and a finding came to be recorded in acceptance of the claim with regard to the losses   suffered   by   the   appellant   due   to   unproductive   use   of machineries and the interference made by the High Court is beyond the scope of Section 37 of the Arbitration Act. 18. Learned counsel further submits that the Division Bench of the High Court did not hold that the evidence relied upon by the Arbitral Tribunal,  i.e. , the log books were not proper or were lacking quality. As a matter of fact, there was no challenge to the same in the   appeal   filed   by   the   respondent   under   Section   37   of   the Arbitration Act and only the liability was questioned. The learned counsel further submitted that the only submission of the learned counsel for the respondent before the Arbitral Tribunal and also before the learned Single Judge of the High Court was that there was no provision under the contract granting compensation for loss incurred for unproductive use of machinery and that the Arbitral Tribunal has exceeded its jurisdiction. This issue was examined by the Tribunal and confirmed by the Single Judge of the High Court, 11 after   examining   the   objections   raised   by   the   respondent   under Section   34   of   the   Arbitration   Act.   The   learned   counsel   for   the appellant   contented   that   interference   at   the   appellate   stage   is beyond the scope of Section 37 of the Arbitration Act and in the given circumstances, claim no. 2 which has been set aside by the Division Bench of the High Court under the impugned judgment deserves to be interfered by this Court. 19. Learned counsel also submits that Section 73 of the Contract Act   confers   a   right   which   is   for   public   interest/benefit   and contractual   clause,   if   any,   which   takes   away   such   a   right unilaterally of a party is violative of Section 23 of the Contract Act. The law which is made for an individual’s benefit can be waived by only by such individual, however, where law is for public interest or has   policy   element,   then   such   rights   cannot   be   waived   by   an individual person inasmuch as such rights are a matter of public policy/public interest. 20. Learned counsel further submits that a contractual provision which   is   in   contravention   of   a   specific     statutory   provision,   if allowed to be implemented, the same will result in frustration of a 12 right conferred by law or if the contractual clause is immoral or opposed to public policy, in such cases the contractual clause is invalid   and   void   ab   initio   and   cannot   be   enforced   to   disentitle appellant in claiming the actual loss which has been suffered by it and   established   before   the   Arbitral   Tribunal   and   which   the respondent   is   under   an   obligation   to   reimburse.   In   the   given circumstances, claim no. 2 which has been set aside by the High Court   needs   interference   by   this   Court.   The   learned   counsel   in support has placed reliance on the judgment of this Court in  K .N. Sathyapalan (Dead) by Lrs. v. State of Kerala,   (2007) 13 SCC 43. 21. Per   contra ,   learned   counsel   for   the   respondent,   while supporting   the   findings   recorded   by   the   High   Court   in   the impugned   judgment,   submits   that   the   claim   which   has   been disallowed by the High Court in the impugned judgment is basically a claim for payment of compensation or damages on account of premature termination of contract and neither the Arbitral Tribunal nor   the   learned   Single   Judge   of   the   High   Court   has considered/examined the terms of the contract in appreciating the 13 right of the claimant to claim compensation of damages and the corresponding liability of the respondent to pay/settle the claim. According   to   him,   as   per   the   terms   of   contract,   no   such compensation was payable. 22. Learned counsel further submits that it is well settled that the Arbitral  Tribunal   cannot   travel   beyond   the   terms   of   contract  to award compensation. As a matter of fact, in the present case, the terms   of   contract   expressly   prohibit   that   no   compensation   is payable if the contract is terminated on account of termination of the project. In the face of such express prohibition, the Arbitral Tribunal has exceeded its jurisdiction and committed a manifest error   in   directing   the   payment   of   compensation   even   without disclosing the basis of arriving at such a conclusion. 23. Learned counsel for the respondent submits that Section 34(2) (a)(iv) of the Arbitration Act clearly envisages that such an award can be set aside if the award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration. When there is a specific exclusion/prohibition in the contract, it was not open for the Tribunal to travel beyond the terms of contract 14 in passing an award which has been taken note of by the Division Bench of the High Court in the impugned judgment and has been rightly set aside, supported by cogent reasons. The learned counsel further  submitted  that  what has  been observed   by   the  Division Bench of the High Court in the impugned judgment is based on settled principles of law and needs no interference.  24. We have heard learned counsel for the parties and with their assistance perused the material available on record. 25. Before  we   devolve   into   the   contractual   issues,   we   need   to observe   certain   pointers   on   the   jurisdiction   of   the   court   under Section 34 of the Arbitration Act. Section 34 as it stood before the Amendment Act of 2015, was as follows­
“34 Application for setting aside arbitral award.
(1) Recourse to a Court against an arbitral award<br>may be made only by an application for setting aside<br>such award in accordance with sub­section (2) and<br>sub­section (3).
(2) An arbitral award may be set aside by the Court<br>only if—
(a) the party making the application furnishes proof<br>that—
(i) a party was under some incapacity, or
15 (ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or (iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or (iv)  the   arbitral   award   deals   with   a   dispute   not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters   beyond   the   scope   of   the   submission   to arbitration: Provided that, if the decisions on matters submitted to  arbitration can be  separated  from  those  not so submitted, only that part of the arbitral award which contains   decisions   on   matters   not   submitted   to arbitration may be set aside; or (v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the   parties   cannot   derogate,   or,   failing   such agreement, was not in accordance with this Part; or (b) the Court finds that— (i) the subject­matter of the dispute is not capable of   settlement  by  arbitration  under   the   law  for  the time being in force, or (ii) the arbitral award is in conflict with the public policy of India. Explanation. —Without prejudice to the generality of sub­clause (ii) it is hereby declared, for the avoidance of any doubt, that an award is in conflict with the 16 public policy of India if the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81. (3) An   application   for   setting   aside   may   not   be made after three months have elapsed from the date on   which   the   party   making   that   application   had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal: Provided   that   if   the   Court   is   satisfied   that   the applicant   was   prevented   by   sufficient   cause   from making the application within the said period of three months   it   may   entertain   the   application   within   a further period of thirty days, but not thereafter. (4) On receipt of an application under sub­section (1), the Court may, where it is appropriate and it is so requested by a party, adjourn the proceedings for a period of time determined by it in order to give the arbitral   tribunal   an   opportunity   to   resume   the arbitral proceedings or to take such other action as in the opinion of arbitral tribunal will eliminate the grounds for setting aside the arbitral award. 26. There   is   no  dispute  that  Section  34   of   the   Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various Courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the Court comes to a conclusion that the perversity of the award goes to the root of the matter without 17 there being  a  possibility  of  alternative   interpretation  which  may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the Courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.  27. Moreover, umpteen number of judgments of this Court have categorically   held   that   the   Courts   should   not   interfere   with   an award   merely   because   an   alternative   view   on   facts   and interpretation of contract exists. The Courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays   perversity   unpardonable   under   Section   34   of   the Arbitration Act. 28. Having established the basic jurisprudence behind Section 34 of the Arbitration Act, we must focus on the analysis of the case. 18 The primary contention of the learned counsel appearing on behalf of the appellant is that the award by the learned Tribunal was perverse for want of reasons. The necessity of providing reasons has been provided under Section 31 of the Arbitration Act, which reads as under: “31. Form and contents of arbitral award.­ (3)   The   arbitral   award   shall   state   the   reasons , unless— upon which it is based (a) the parties have agreed that no reasons are to be given, or (b) the award is an arbitral award on agreed terms under section 30.” ( emphasis supplied ) Under the UNCITRAL Model Law the aforesaid provision is provided as under: “(2) The award shall state the reasons upon which it is based, unless  the parties have  agreed  that no reasons are to be given or the award is an award on agreed terms under article 30.” 29. Similar to the position under the Model Law, India also adopts a   default   rule   to   provide   for   reasons   unless   the   parties   agree 19 otherwise. As with most countries like England, America and Model Law, Indian law recognizes enforcement of the reasonless award if it has been so agreed between the parties.  30. There is no gainsaying that arbitration proceedings are not  per   comparable to judicial proceedings before the Court. A party se under Indian Arbitration Law can opt for an arbitration before any person, even those who do not have prior legal experience as well. In this regard, we need to understand that the intention of the legislature to provide for a default rule, should be given rational meaning in light of commercial wisdom inherent in the choice of arbitration. 31. A five­Judge Constitution Bench of this Court in the case of Raipur Development Authority v. Chokhamal Contractors , AIR 1990 SC 1426, considered the scope of Section 30 of the Arbitration Act, 1940 and held as under: 20 “It is now well settled that an award can neither be remitted nor set aside merely on the ground that it does   not   contain   reasons   in   support   of   the conclusion or decisions reached in it except where the arbitration agreement or the deed of submission requires   him   to   give   reasons.   The   arbitrator   or umpire   is   under  no  obligation to give  reasons  in support   of   the   decision   reached   by   him   unless under the arbitration agreement or in the deed of submission he is required to give such reasons and if the arbitrator or umpire chooses to give reasons in support of his decision it is open to the Court to set aside the award if it finds that an error of law has been committed by the arbitrator or umpire on the face of the record on going through such reasons. The arbitrator or umpire shall have to give reasons also where the court has directed in any order such as the one made Under Section 20 or Section 21 or Section 34 of the Act that reasons should be given or where the statute which governs an arbitration requires him to do so.” 32. A   three­Judge   Bench   of   this   Court   in   another   case   of   S. Harcharan Singh v. Union of India , (1990) 4 SCC 647, reiterated its   earlier   view   that   the   arbitrator's   adjudication   is   generally considered binding between the parties for he is a Tribunal selected by the parties and the power of the Court to set aside the award is restricted to cases set out in Section 30 of the Arbitration Act, 1940. 21 33. However, the ratio of  Chokhamal  case ( supra ) has not found favour of the Legislature, and accordingly Section 31(3) has been enacted in the Arbitration Act. This Court in   Som Datt Builders Ltd. v. State of Kerala , (2009) 4 ARB LR 13 SC, a Division Bench of this Court has indicated that passing of a reasoned award is not an empty formulation under the Arbitration Act.  rd 34. It may be relevant to note  Russell on Arbitration , 23  edn. (2007), wherein he notes that: “If the Court can deduce from the award and the materials before it, which may include extracts from evidence and the transcript of hearing, the thrust of the tribunal’s reasoning then no irregularity will be found…. Equally, the court should bear in mind that when considering awards produced by non­ lawyer arbitrators, the court should look at the substance   of   such   findings,   rather   than   their form, and that one should approch a reading of the award in a fair, and not in an unduly literal .” way ( ) emphasis supplied 35. The mandate under Section 31(3) of the Arbitration Act is to have reasoning which is intelligible and adequate and, which can in 22 appropriate cases be even implied by the Courts from a fair reading of the award and documents referred to thereunder, if the need be. The aforesaid provision does not require an elaborate judgment to be passed by the arbitrators having regards to the speedy resolution of dispute. 36. When we consider the requirement of a reasoned order three characteristics   of   a   reasoned   order   can   be   fathomed.   They   are: proper, intelligible and adequate. If the reasoning in the order are improper, they reveal a flaw in the decision­making process. If the challenge to an award is based on impropriety or perversity in the reasoning,   then   it   can   be   challenged   strictly   on   the   grounds provided under Section 34 of the Arbitration Act. If the challenge to an award is based on the ground that the same is unintelligible, the same would be equivalent of providing no reasons at all. Coming to the last aspect concerning the challenge on adequacy of reasons, the  Court  while   exercising   jurisdiction   under  Section  34   has to adjudicate the validity of such an award based on the degree of particularity of reasoning required having regard to the nature of 23 issues falling for consideration. The degree of particularity cannot be stated in a precise manner as the same would depend on the complexity of the issue. Even if the Court comes to a conclusion that there were gaps in the reasoning for the conclusions reached by the Tribunal, the Court needs to have regard to the documents submitted   by   the   parties   and   the   contentions   raised   before   the Tribunal so that awards with inadequate reasons are not set aside in   casual   and   cavalier   manner.   On   the   other   hand,   ordinarily unintelligible awards are to be set aside, subject to party autonomy to   do  away   with   the   reasoned   award.   Therefore,   the   courts   are required to be careful while distinguishing between inadequacy of reasons in an award and unintelligible awards. 37. At this juncture it must be noted that the legislative intention of providing Section 34 (4) in the Arbitration Act was to make the award enforceable, after giving an opportunity to the Tribunal to undo the curable defects. This provision cannot be brushed aside and the High Court could not have proceeded further to determine the issue on merits.  24 38. In case of absence of reasoning the utility has been provided under of Section 34(4) of the Arbitration Act to cure such defects. When there is complete perversity in the reasoning then only it can be challenged under the provisions of Section 34 of the Arbitration Act. The power vested under Section 34 (4) of the Arbitration Act to cure defects can be utilized in cases where the arbitral award does not provide any reasoning or if the award has some gap in the reasoning or otherwise and that can be cured so as to avoid a challenge based on the aforesaid curable defects under Section 34 of the Arbitration Act. However, in this case such remand to the Tribunal would not be beneficial as this case has taken more than 25 years for its adjudication. It is in this state of affairs that we lament   that   the   purpose   of   arbitration   as   an   effective   and expeditious forum itself stands effaced. 39. It may be noted that when the High Court concluded that there was no reasoned award, then the award ceased to exist and the Court was  functus officio  under Section 34 of the Arbitration Act for   hearing   the   challenge   to   the   award   under   the   provisions   of Section 34 and come to a conclusion that the arbitration award was 25 not in terms of the agreement. In such case, the High Court ought to have considered remanding the matter to the Tribunal in the usual course. However, the High Court analyzed the case on merits, but, for different reasons and we need not go into the validity of High Court’s interference. 40. Coming back to the award, we need to see whether the award of   the   Arbitral   Tribunal   can   be   sustained   in   the   instant   case. Although the Arbitral Tribunal has dealt with the claims separately under   different   sub­headings,   the   award   is   confusing   and   has jumbled the contentions, facts and reasoning, without appropriate distinction. The Tribunal rendered the award with narration of facts with references to the annexures wherever it relied upon by it. The Tribunal abruptly concluded at the end of the factual narration, without providing any reasons, in the following manner: “ (3) Claim for unproductive usage of machineries …. (g)  All the above facts clearly establish that the machineries deployed by the Claimant had to do unproductive work by shifting from one place to another   to   suit   the   availability   of   work.The contract contemplates only payment for actual turnover   of   earthwork   and   for   this   they   had received amount totaling to Rs. 1709782.88.  The 26 Claimant claims that the hire charges paid to the machineries,   men   and   engineers   should   be reimbursed   to   him.   He   has   given   the   actual expenses in his claim statement. ( emphasis supplied ) 41. Interestingly,   the   factual   narration   is   coupled   with   the claimant’s argument, which is bundled together. A close reading of the same is required to separate the same wherein the Arbitral Tribunal has mixed the arguments with the premise it intended to rely   upon  for   the   claimant’s   claim.   Further,   it  has   reduced   the reasons   for   respondent’s   defense.   In   spite   of   our   independent application   of   mind   based   on   the   documents   relied   upon,   but cannot   sustain   the   award   in   its   existing   form   as   there   is   a requirement of legal reasoning to supplement such conclusion. In this context, the complexity of the subject matter stops us from supplementing   such   legal   reasoning   and   we   cannot   sustain   the aforesaid award as being reasoned. 42. It may be beneficial to reduce the concluding paragraph of the award, which reads as under: “3.4. The above arguments and various authorities quoted by them have been studied by the Tribunal and   we   are   convinced   that   the   compensation   is 27 payable on the hire charges and expenses incurred by the claimant based on the claims made by him in June 95 and now submitted by the claimant in his revised   claim   petition     on   05.07.1997.   We   are convinced   that   the   machineries   have   been actually mobilized from the letter R­3, R­8 and R­10 issued by DCM reporting on the number of machineries   deployed   by   Claimant .   The Claimants have produced the log books and bills for the various machineries and modified their claims. The tribunal had perused the log books and idle wages approved in C­7 by Respondent and the claims made in R­17 .” ( emphasis supplied ) 43. From  the facts, we can only state that from a perusal of the award, in the facts and circumstances of the case, it has been rendered   without   reasons.   However,   the   muddled   and   confused form of the award has invited the High Court to state that the arbitrator has merely restated the contentions of both parties. From a perusal of the award, the inadequate reasoning and basing the award on the approval of the respondent herein cannot be stated to be   appropriate   considering   the   complexity   of   the   issue   involved herein, and accordingly the award is unintelligible and cannot be sustained. 28 44. In any case, the litigation has been protracted for more than 25 years, without any end for the parties. In totality of the matter, we consider it appropriate to direct the respondents to pay a sum of Rs. 30,00,000/­ (Rupees Thirty Lakhs only) to the appellant in full and final settlement against claim No. 2 within a period of 8 weeks, failing which the appellant will be entitled to interest at 12% per annum until payment, for providing quietus to the litigation.  45. In view of the conclusions reached, the appeal is disposed of to the extent indicated herein. There shall be no orders as to the costs. ..............................................J. (N.V. RAMANA)  ..............................................J.  (MOHAN M. SHANTANAGOUDAR) ..............................................J.  (AJAY RASTOGI) NEW DELHI; DECEMBER 18, 2019. 29 30