M/S STAR WIRE (INDIA) VIDYUT PVT LTD vs. HARYANA ELECTRICITY REGULATORY COMMISSION

Case Type: Civil Appeal

Date of Judgment: 02-07-2019

Preview image for M/S STAR WIRE (INDIA) VIDYUT PVT LTD vs. HARYANA ELECTRICITY REGULATORY COMMISSION

Full Judgment Text

1 REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 5139 OF 2019 (Arising out of SLP (C) No.8432 of 2017) M/S Star Wire (India) Vidyut Pvt. Ltd. & Anr.    ..…Appellant(s)  Versus Haryana Electricity Regulatory Commission   ….Respondent(s) J U D G M E N T A.M. Khanwilkar, J. 1. Leave granted.  2. This appeal takes exception to the judgment and order of the High Court of Punjab and Haryana at Chandigarh passed in C.W.P. rd No.25337   of   2015   (O   &   M)   dated   23   November,   2016.   The appellants   had   challenged   the   fourth   amendment   to   Haryana Electricity   Regulatory   Commission   (Terms   and   Conditions   for Signature Not Verified determination of Tariff from Renewable Energy Sources, Renewable Digitally signed by CHARANJEET KAUR Date: 2019.10.05 10:00:33 IST Reason: Purchase Obligation and Renewable Energy Certificate) Regulations, 2 2010   (for   short,   “ principal   Regulations ”)   published   vide th notification   dated   12   August,   2015   (for   short,   “ impugned ”)   which   sought   to   amend   the   principal Amended   Regulations Regulations. The appellants had also challenged the order passed th by   the   respondent­Commission   dated   4   August,   2015,   in furtherance   whereof,   the   impugned   Amended   Regulations   were framed   by   the   appropriate   authority   for   revision   of   norms   for determination   of   generic   tariff   for   the   second   control   period st beginning from 1  April, 2013.  3. The appellants had set up a 9.90 MW independent Biomass rd Power Plant, which was declared commercially operational on 3 rd May, 2013. The principal Regulations were notified on 3  February, 2011, providing for the norms and parameters for determination of tariff   for   various   renewal   energy   project   developers.   As   per Regulation 4 of the principal Regulations, the first control period of st three years was to end on 31   March, 2013. The third proviso of Regulation 4 posits that in case, the regulations for the next control period were not notified after the expiry of the first control period, the tariff  norms  as  per  these  regulations   (principal  Regulations) would continue to apply until notification of the revised regulations, 3 subject to adjustments as per the revised regulations. As the first control   period   had   already   ended,   the   appropriate   authority initiated  suo motu  proceedings for revision of tariff and issued draft fourth amendment to the principal Regulations, seeking to amend Regulation   4   and   including   Regulation   5   of   the   principal th Regulations. This draft amendment was issued on 29   December, 2014.   Pursuant   thereto,   the   concerned   parties   submitted   their response. After giving opportunity to all concerned, the Commission th proceeded to pass an order dated 4  August, 2015, which attempts to analyse and adjudicate all the issues raised by the concerned parties. On the basis of the said order, the impugned Amended Regulations came to be notified. The effect whereof was to deny the applicability   of   tariff   norms   adjustments   to   the   appellant   No.1, rd which had commenced its commercial operations on 3  May, 2013. The  said   amendment   has   been   given   prospective   effect   qua  the appellants.   It   has   made   classification   between   the   projects commissioned/to be commissioned in   financial years 2013­14 on the one hand and 2014­15, 2015­16 and 2016­17 on the other, without any intelligible differentia or any rational basis therefor. Neither   the   principal   Regulations   nor   the   impugned   Amended Regulations envisage classification on the basis of commissioning of 4 renewable energy projects in a particular financial year during the same   control   period.   Similarly,   the   regulations   do   not   envisage determination of separate tariff on such differentiation. Indeed, the authority has been invested with power to determine project specific tariff under Regulation 6. In the present case, however, the power exercised   by   the   Commission   is   indisputably   with   reference   to Regulation 4 namely, to determine a generic tariff for the control st period commencing from 1  April, 2013 and ending with financial st year 2016­17 i.e. 31  March, 2017, for a period of 4 years.  4. In this back drop, the appellants filed writ petition and prayed for the following reliefs:  “PRAYER It   is   therefore   most   respectfully   prayed   that   this Hon’ble Court may graciously be pleased to: a. Issue an appropriate writ under Article 226/227 of the Constitution of India for issuance of, order or direction in   the   nature   of   Certiorari   for   setting   aside   the Impugned Notification dated 12.08.2015 (Annexure P­ 1)   and   the   Impugned   Order   dated   04.08.2015 (Annexure P­2) passed by the Respondent to the extent the same seeks to apply the revised regulations with effect from the date of the Impugned Notification; and  Issue an appropriate writ under Article 226/227 of the b. Constitution of India for issuance of, order or direction in the nature of   Mandamus   directing the Respondent to apply the revised regulations on and from the date of commencement of the Second Control Period i.e. with effect from 01.04.2013; and  5 c. Issue an appropriate writ under Article 226/227 of the Constitution of India for issuance of, order or direction in the nature of   directing the Respondent Mandamus   to publish the revised tariff after adjusting the same as per the revised regulations from the first day of the Second Control Period i.e. 01.04.2013, and to further allow carrying cost on the overdue amounts; and Issue   an   appropriate   interim   direction   granting   ad­ d. interim   ex­parte   stay   of   operation   of   the   Impugned Notification dated 12.08.2015 (Annexure P­1) and the Impugned   Order   dated   04.08.2015   (Annexure   P­2) passed by the Respondent; and  Dispense   with   serving   advance   notice   upon   the e. Respondent; and  f. Costs   of   the   Writ   Petition   be   awarded   to   the Petitioners; and  g. Dispense   with   filing   of   certified   copies/true   typed copies of Annexures P­1 to P­10, and the photo/typed copies of the Annexures may kindly taken on record and   the   requirement   of   filing   typed/certified   copies thereof be dispensed with; and  Pass such other order(s) as this Hon’ble Court may h. deem fit and proper in the facts of the case.”  5. The appellants raised almost thirty grounds as articulated in the writ petition, in support of the reliefs claimed by them. They have attempted to demonstrate as to how the amended regulations were arbitrary, unreasonable, capricious and discriminatory. The respondent   refuted   the   stand   taken   by   the   appellants   by   filing 6 elaborate counter affidavit and mainly relied on the order passed by th the Commission dated 4  August, 2015, which was the foundation for   the   amendment   of   the   relevant   provisions   of   the   principal Regulations. The reply affidavit filed by the respondents before the High Court runs into about 60 typed pages (forming part of volume II of the paper book). Accordingly, the writ petition proceeded before the   Division   Bench   of   the   High   Court.   The   High   Court   in   the impugned judgment has noted that the appellants had raised only two   contentions,   as   can   be   discerned   from   paragraph   6   of   the impugned judgment. The same reads thus:   “6. The   grievance   of   the   petitioners   is   two   fold. Firstly   with   the   issuance   of   notification   of   the Amended Regulations on 12.8.2015, there would be different treatment  for  the persons operating  in the same control period; namely, who had commissioned their projects in the year 2013­14 and the persons, who had commissioned thereafter, the control period being same i.e. for the years from 2013­14 to 2016­17. Further,   it   was   submitted   that   out   of   the   control period prior to the date of notification of the Amended Regulations   only   financial   year   2013­14   has   been isolated   for   different   treatment,   which   is discriminatory.   How   any   of   alleged   Regulation   is affecting   the   petitioner   was   not   specifically   pointed out.” We would proceed on the basis that this was the limited argument canvassed before the High Court during the hearing of the writ petition. However, what is intriguing to note is that even these two 7 points have been disposed of by the Division Bench of the High Court in a most cursory manner without analysing the issues in proper   perspective,   as   can   be   discerned   from   the   discussion   in paragraph Nos.13 to 15 of the impugned judgment. The same reads thus:  “13. It is not in dispute that exercise for revision of the   2010   Regulations   was   not   started   six   months before   the   expiry   of   the   existing   control   period   on 31.3.2013. The exercise was started only in the year 2015.   Public   hearing   was   held   in   which   even   the petitioner­company was represented. Vide order dated 4.8.2015,   the   Commission   approved   the   proposed amendments in the 2010 Regulations. The Amended Regulations   in   terms   of   the   order   passed   by   the Commission   were   notified   on   12.8.2015.   Regulation 1(2)   of   the   Amended   Regulations   provides   that   the Regulations shall be applicable to all the Renewable Energy   Projects   Commissioned/to   be   commissioned from   Financial   Years   2013­14   to   2016­17,   as   the control period of four years was provided. Regulation 1(3) of the Amended Regulations provides that for the existing   projects   commissioned   from   Financial   year 2013­14   onwards,   the   revised   norms   shall   be applicable prospectively from the date of notification of the Amended Regulations unless otherwise provided in the Amended Regulations. For the period prior to the date of notification, existing norms as per the 2010 Regulations   shall   continue   to   be   applicable.   The Amended Regulations were to come into force from the date of publication in the official gazette. The Amended Regulation (4) provides that the second control period shall be of four years commencing from Financial year rd 2013­14.   3   proviso   thereto   provides   that   in   case revised regulations for the next control period are not notified on or before the commencement of that period, the tariff norms as per the Amended Regulations shall continue to remain applicable, until notification of the revised regulations and the second control period shall be deemed to have been extended upto the date of notification   of   the   regulations   for   the   next   control period.  8 14. The contention raised by learned counsel for the petitioners that there is discriminatory application of regulations qua the petitioners’ company only because it started operation in the Financial year 2013­14, as compared   to   the   other   projects,   which   started functioning after Financial year 2013­14 is merely to be noticed and rejected. Though the control period is from   the   Financial   Years   2013­14   to   2016­17, however, the Amended Regulations clearly provide that for the existing projects from Financial year 2013­14 onwards,   the   revised   norms   shall   be   applicable prospectively,   from   the   date   of   notification   of   the Amended Regulations.  15. As   far   as   the   second   contention   raised   by learned   counsel   for   the   petitioners   regarding rd application of the Amended Regulations in terms of 3 proviso   to   Regulation   4   of   the   2010   Regulations   is concerned, it clearly provides that the existing norms, even for the period subsequent to the expiry of control period,   shall   be   applicable   till   such   time   revised Regulations are notified. However, the same shall be subject to adjustments as per revised regulations. That would mean, adjustments, if any, are to be specifically provided for in the Amended Regulations for the period prior   to   the   notification   of   Amended   Regulations. Wherever special conditions have been provided for in the Amended Regulations for different years, learned counsel for the petitioners did not point out how that prejudiced   the   petitioners.   It   is   all   matter   of calculations   for   which   facts   were   examined   by   the Commission while passing the order on 4.8.2015, on the basis of which, the Regulations were amended.” As a matter of fact, paragraph 13 of the impugned judgment merely notices some factual aspects. The reason which weighed with the High Court to negative the issues agitated by the appellants can be noticed only from paragraph Nos.14 and 15, which  ex facie  to say the least is cryptic.  9 6. Resultantly, the appellants have approached this Court by way of present appeal. The main argument of the appellants is that the principal Regulations which indeed, applied to the control period rd st from 3  February, 2011 until 31  March, 2013, but envisaged that the same would continue to remain applicable until notification of the revised regulations is issued, subject to adjustments as per revised regulations. These regulations make no distinction on the basis of commissioning of project on financial year basis during the same  block   period   or   thereafter   until   its   application   during   the extended period. Rather, the control period referred to in Regulation 4 encompasses  all the  projects  commissioned  during  that block period and including extended period and must be treated alike. In other words, the same generic tariff must apply to all the projects rd commissioned   during   the   relevant   block   period   i.e.   from   3 st February, 2011 to 31  March, 2013 and until the issue of revised regulations,   subject   to   adjustments   as   per   revised   regulations. Therefore, the amended regulations must be read in light of the principal Regulations. However, the amended regulations entail in denying the   applicability of the revised regulations to R.E. projects commissioned in FY 2013­14, such as the appellant, which was 10 rd commissioned on 3   May, 2013. The amended regulations are for st the second control period commencing from 1   April, 2013 and st ending on 31  March, 2017 for a period of four years, of which the first year has been defined as FY 2013­14. Despite this position, the amended regulation 1(3) makes exception to the applicability of the revised regulations to the projects commissioned during FY 2013­ 14,   by   making   it   applicable   prospectively   from   the   date   of th notification   of   the   impugned   Regulations   on   12   August,   2015. Whereas, the projects commissioned during 20014­15 and onwards during the selfsame second control period referred to therein would get the benefit of the revised regulations for the entire period from the date of commissioning commercial production, without there being any intelligible differentia. In other words, the appellants have been denied benefit of the revised regulations for the period between rd th 3  May, 2013 to 12  August, 2015. The effect of such a provision is to take away the benefit which had  enured  to the appellants in terms of Regulation 4 of the principal Regulations, which predicates that the tariff norms as per the principal Regulations shall continue to remain applicable until notification of the revised regulations, subject to adjustments as per the revised regulations. Resultantly, the impugned Amended Regulations suffer from the vice of hostile 11 discrimination between persons similarly placed namely, projects commissioned during the block of second control period governed by the Amended Regulations, without any intelligible differentia. We need not elaborate on other arguments which are either to buttress the above­mentioned points or if we may say so, in the nature of another   shade   of   the   same   argument   with   reference   to   factual aspects relevant for examining the same. The sum and substance of the argument is that the appellants have been denuded of their right   to   get   adjustments   in   the   same   manner   as   extended   to projects commissioned in the same control period and despite the stipulation in the third proviso of the Regulation 4 of the principal Regulations.   Inasmuch   as,   the   impugned   Amended   Regulations th were notified on 12  August, 2015, therefore, the rights accrued to the   appellants   in   terms   of   Regulation   4   would   take   effect   from rd commissioning   of   their   project   on   3   May,   2013   because   the principal Regulations were still applicable and in force. Taking away that fructified right, is impermissible in law. Further, the impugned Amended Regulations,  ex facie,  discriminates between the projects commissioned during the same control period i.e. second control st st period from 1  April, 2013 till 31  March, 2017, by singling out the projects commissioned   in FY 2013­14. It is not open to make such 12 classification in respect of projects commissioned during the same control period. Further, there can be no two tariffs operating during the same control period. In that, no express provision to prescribe two sets of tariffs concerning the same control period is found in the principal   Regulations   or   the   impugned   Amended   Regulations. Therefore,   classification   sought   to   be   done   in   the   impugned Amended Regulations, cannot be countenanced.  7. Indeed,   the   respondents   have   vehemently   supported   the impugned decision of the High Court and would contend that the provisions engrafted in the impugned notification are manifestation th of the order passed by the Commission dated 4  August, 2015. The Commission   had   elaborately   analysed   all   aspects   of   the   matter before passing the said order. In other words, the respondents have drawn support from the analysis done by the Commission in the suo moto  proceedings initiated by it for revision of norms (for tariff st operation for the second control period commencing from 1  April, 2013). That order runs into over 100 typed pages and has analysed the necessity  of revision vis­à­vis each head  to be reckoned for determination of tariff. The appellants had participated in the said proceedings. However, the stand taken by the appellants did not 13 commend   to   the   Commission,   as   can   be   discerned   from   the th discussion in the order passed by it on 4  August, 2015. Further, it was open to the appellants to approach the Commission by way of a review if they had any reservation with regard to the view taken by Commission in the said order. It was also open to the appellants to file appeal against the said order. However, without resorting to such remedies, the appellants chose to file writ petition and have raised   grounds   which   are   untenable   in   light   of   the   discussion th recorded by the Commission in its order dated 4  August, 2015. It is certainly not a case of hostile discrimination considering the fact that   Commission   has   recorded   tangible   reasons   as   to   why   the applicability of the revised regulations was required to be made prospective in respect of projects commissioned during FY 2013­14. It is urged that the exercise of power in framing regulations ­ be it principal Regulations or impugned Amended Regulations ­ in terms of Section 61 read with Section 181 of the Electricity Act, 2003 permits classification on the basis of the date of commissioning of the project during the relevant period and which may inevitably result in providing for two sets of tariffs during the same control period. It is submitted that even though the impugned judgment of 14 the   High   Court   is   brief,   the   conclusions   reached   therein   are unexceptionable and therefore, this appeal ought to be dismissed.  8. After perusing the impugned judgment, we have no hesitation in taking the view that the High Court has committed manifest error or so to speak, failed to exercise jurisdiction vested in it for adjudicating the relevant issues raised by the appellants. For, there is hardly any intelligible discussion in the impugned judgment in that regard. If we may say so, it is cryptic and cannot stand the test of judicial scrutiny. We say so because, up to paragraph 9 of the judgment   the   High   Court   has   only   reproduced   the   rival   stand. Paragraph 11 refers  to  the relevant  provisions.  Paragraph  12 is mere narration of some facts concerning this case. Paragraph 13, broadly   refers   to   the   purport   of   the   provisions   in   the   principal Regulations   and   the   impugned   Amended   Regulations.   The discussion   with   regard   to   the   merits   of   the   challenge,   can   be discerned only from paragraph Nos.14 and 15 reproduced hitherto. Paragraph   14   even   if   fairly   analysed,   merely   adverts   to   the argument   of   discriminatory   application   of   regulations   qua   the appellant company and proceeds to reject the same. No logic can be deduced as to why the Court was persuaded to reject the argument 15 despite the multifaceted issues raised by the appellants. The second sentence in the said paragraph then proceeds to record that the control   period   may   be   from  FY   2013­14   onwards,  however,   the impugned   Amended   Regulations   envisage   application   of   revised norms to projects commissioned in FY 2013­14 prospectively from the date of notification of the impugned Amended Regulations. In other   words,   the   High   Court   has   not   analysed   the   grounds   of challenge   regarding   the   validity   of   the   impugned   Amended Regulations   and   including   the   competency   to   frame   such   a regulation,   appropriately.   Strikingly,   the   High   Court   then straightaway proceeds to examine the second contention raised by the appellants  in reference to the third proviso in the principal Regulations providing for adjustments as per revised regulations. The Court merely noted that the appellants failed to point out any prejudice caused to them because of exclusion from the benefit flowing from the principal Regulations. The appellants, on the other hand, have invited our attention to the specific grounds taken by the appellants in the writ petition and also noted in the order of the th Commission dated 4  August, 2015 and additionally articulated in the ground  No. B  of the special leave petition, giving comparative chart   indicating   substantial   disparity   regarding   the   norms 16 applicable as per principal Regulations and the impugned Amended Regulations. In other words, the argument of prejudice was raised by the appellants to the detail but the High Court has failed to deal with the same, to say the least satisfactorily. Similarly, the detail arguments   regarding   the   validity   of   the   impugned   Amended Regulations and the competency to frame such a regulation has not been analysed by the High Court.  9. Suffice it to observe that the discussion in two paragraphs (para 14 and 15), to say the least, is one of disposing of the writ petition in a  most casual  and cavalier manner. That cannot be countenanced. Having said this, we are of the considered opinion that it would be appropriate to relegate the parties before the High Court for fresh consideration of the writ petition on its own merits in accordance with law. We refrain from expressing any opinion either   way   on   the   merits   of   the   controversy   or   the   grounds   of challenge regarding the impugned Amended Regulations. In other words, the High Court must consider all relevant aspects of the matter   agitated   by   the   appellants   and   deal   with   the   same appropriately in accordance with law.  17 10. For completion of the record, we must note the decision of the Constitution Bench of this Court in   PTC India Ltd. Vs. Central  1 , which Electricity Regulatory Commission, Through Secretary has held that the challenge to the validity of the regulations can be decided only in judicial review proceedings before the courts and not by way of appeal or review. The appellants having invoked such a remedy before the High Court, all contentions available to the appellants in that regard ought to have been adjudicated in proper perspective.   We   agree   with   the   appellants   that   the   nature   of th elaborate order passed by the Commission on 4   August, 2015, which culminated with the framing of Amendment Regulations the only remedy available to challenge the same is by way of a writ petition under Article 226/227 of the Constitution of India.             11. Accordingly, this appeal is allowed. The impugned judgment and   order   is   set   aside.   The   CWP   No.285337   of   2015   (O&M)   is restored to the file of the High Court to its original number, for being considered afresh by the High Court on its own merits in accordance with law. All pending applications are disposed of. No order as to costs.  1  (2010) 4 SCC 603 18       ……………………………..J       (A.M. Khanwilkar)       ……………………………..J       (Ajay Rastogi) New Delhi;   July 2, 2019.