Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
PETITIONER:
STATE OF U.P.
Vs.
RESPONDENT:
M/S. RAM NATH INTERNATIONALCONST. PVT. LTD.
DATE OF JUDGMENT10/11/1995
BENCH:
G.B. PATTANAIK (J)
BENCH:
G.B. PATTANAIK (J)
AGRAWAL, S.C. (J)
CITATION:
1996 AIR 782 1996 SCC (1) 18
JT 1995 (8) 396 1995 SCALE (6)321
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
PATTANAIK, J.
This appeal is directed against the Judgment of the
Allahabad High Court dated 16th December, 1993 in First
Appeal From Order
No. 930 of 1991, arising out of an arbitration proceeding.
The Respondent - contractor had entered into an
agreement with the appellant for construction of non
overflow and overflow sections with bridge spillway and
other appurtenant works of Maudaha Dam in Hamirpur district
in the State of Uttar Pradesh. The agreement was entered
into on 26th August, 1985 and work commenced from 1st
September, 1985. The period stipulated for completion of the
work was 42 months. In the year 1987 in respect of two items
of work namely Items 13 and 15, it is alleged that the
appellant changed the designs and drawings as a result of
which the quantity of work became abnormally high compared
to the estimated quantity of work in the agreement. On
account of such abnormal increase of the quantity of work
the contractor claimed higher rate than what was agreed to
in the agreement. The State having refused to acceed to the
contractor’s demand and disputes having arisen between the
parties, the arbitration clause of the agreement was invoked
and dispute was referred to the sole arbitration of the
Joint Secretary and Joint Legal Remembrancer to the
Government of Uttar Pradesh. Before the arbitrator the
respondent - contractor made a claim of Rs. 91,56,750/- for
the increased quantity of work in respect of Item No. 13
executed till 30.4.90 and Rs. 9,92,402.50 for the increased
quantity of work in respect of Item No. 15 executed till
30.4.90 together with interest @ 10% thereon. The entire
basis of the claim of the contractor was that in respect of
the quantity of work in excess of the estimated quantity in
the agreement he is entitled to be paid @ Rs. 453.50 per
cubic meter in place of the agreed rate of Rs. 243.00 for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
Item No. 13 and the rate of Rs. 739.55 per cubic meter in
place of agreed rate of Rs. 460.00 for Item No. 15. It was
alleged in the claim petition that the State of Uttar
Pradesh has paid and is paying the agreed rate of Rs. 243.00
per cubic meter in respect of the additional quantity of
work in Item No. 13 and similarly has paid and is paying @
460.00 per cubic meter even in respect of the additional
quantity of work in respect of Item No.15. According to the
respondent contractor, on account of substantial change in
designs and drawings there has been abnormal increase in the
quantities of work compared to the estimated quantity of
work in the original agreement and in respect of such
additional quantity of work he is not bound to be paid at
the agreed rate but at an enhanced rate on the basis of the
analysis of rate submitted by him. It was further averred
that when the drawings and designs were changed, the
contractor had resisted and prayed for the alteration in the
rate but the concerned authorities had assured him orally
for such change though ultimately did not agree to the same.
It was also averred in the claim petition that under the
agreement he was bound to carry out the work as per the
directions of the concerned authorities and accordingly he
has carried out the same.
The appellant - State filed written statement before
the arbitrator denying its liability to pay at the revised
rate as claimed by the contractor. It was admitted that
there has been a change in the drawings and designs relating
to Item Nos. 13 and 15 and on account of such change, the
quantity of work in respect of the aforesaid two items has
increased. But the claimant is not entitled to any enhanced
rate, in view of the different clauses of the agreement
itself. It was also averred in the written statement that
the so called variation in the quantity of work is covered
by clauses 11.25 and 13.1.1 of the agreement and therfore
the contractor is not entitled to any higher rate.
The learned arbitrator after analysing the different
clauses of the agreement, came to the conclusion that the
contractor could not have refused the work in accordance
with the alterations and modifications in the drawings and
designs. He further held that there has been a fundamental
change in the drawings and designs which abnormally
increased the quantum of work than the estimated quantum
indicated in the agreement and under the agreement though
the contractor cannot claim any excess rate for work upto
the excess of 10%, but beyond the same the contractor would
be entitled to claim a higher rate. The arbitrator accepted
the analysis of rate. The arbitrator accepted the analysis
of rate given by the contractor and accordingly in respect
of the quantity of work executed after the date of the
completion of the work indicated in the agreement namely
28.2.1989, he granted as per the rate claimed by the
contractor. In all he awarded a total sum of Rs.
90,21,765.65 together with interest @ 9% per annum from
21.5.90 till the date of the award and further interest @ 6%
per annum from the date of the award till the payment or
till the decree, if any, passed on the basis of the order.
The arbitrator also held that in respect of works executed
after 30th April, 1990 the claimant would be paid at the
same rate i.e. Rs. 453.50 per cubic meter in respect of Item
No. 13 and Rs. 739.55 per cubic meter in respect of Item No.
15 after adjusting the payments already made as per the
rates given in the contract.
The contractor filed an application before the Civil
Judge, Hamirpur for making the award a rule of court which
was registered as Suit No. 53 of 1991. The appellant - State
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
filed his objections challenging the legality of the award.
The learned Judge being of the opinion that the court has no
jurisdiction to interfere with an award of the arbitrator
since the arbitrator had decided all the issues properly
with detailed analysis as well as after perusing all the
necessary documents, made the award a rule of the Court. The
learned Trial Judge also came to the conclusion that the
arbitrator was fully within his powers to accept the
analysis of rate submitted by the contractor which was
infact not disputed by the State and therefore there is no
error in the award which could be interfered with by the
court. On the question whether the objections filed by the
State could at all be entertained the same having been filed
beyond 30 days the Civil Judge came to the conclusion that
the objections cannot be entertained and perused as the same
was filed beyond the period of 30 days. With these
conclusions the award having been made a rule of court and
the objection of the State having been rejected, the State
preferred an appeal in the High Court of Allahabad under
Section 39 of the Arbitration Act. The High Court set aside
the conclusion of the Trial Judge with regard to the
entertainability of the objection filed by the State and
held that taking into account the magnitude of the claim of
Rs. 1 crore and taking into account that the objection could
not be filed on 23rd March, 1991 was a Sunday, the objection
filed on 25th of March, 1991 has to be considered on
condoning the delay, in the interest of Justice. But so far
as the conclusion of the Trial Judge on merits of the case
is concerned the High Court refused to interfere with the
decision of the Trial Judge on the ground that the
arbotrator has not committed any error in allowing the claim
of the contractor as per the analysis of rates given by it
in respect of the extra quantity of work and it is not
permissible for the court within the parameter for exercise
of its jurisdiction to interfere with the award. Thus appeal
having been dismissed, the State has preferred the present
appeal.
Mr. Sehgal, the learned senior counsel for the
appellant contended that in view of the escalation clause in
the contract itself, the arbitrator had no jurisdiction to
allow the contractor’s claim at a new rate on the basis of
the analysis of rates and the award, therefore, is vitiated
on that score. He further contended that even if it was
permissible for the arbitrator to accept the analysis of
rates submitted by the contractor for the excess quantity of
work executed by him beyond the stipulated period of the
contract, yet the arbitrator committed gross error in
allowing the total claim without taking into account the
payments already made to the contractor in accordance with
the escalation clause of the contract and the award is,
therefore, vitiated on that score. Mr. Sanghi, the learned
senior counsel appearing for the respondent on the other
hand contended that the quantity of work executed by the
contractor being far more in excess of the anticipated
quantity of work in the contract and such excess being on
account of alteration of drawings and designs, the
arbitrator was fully within his jurisdiction to accept the
analysis of rates submitted by the contractor and award the
contractor’s claim. It was further contended that the State
not having objected to the analysis of rates given by the
contractor, the arbitrator was fully justified in awarding
the claim of the contractor. Mr. Sanghi also contended that
the payments already made to the contractor at the escalated
rate in respect of the extra quantity of work in accordance
with the terms of the contract is of no consequence since
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
the contractor claimed the change of the basic rate which
the arbitrator has allowed and on such basic rate the
contractor would otherwise be entitled to the escalation in
accordance with the clauses of the contract. According to
Mr. Sanghi, the High Court rightly did not interfere with
the award as no error appears to have been pointed out in
the award itself.
The jurisdiction of the court to interfere with an
award of an arbitrator is undoubtedly a limited one. The
adjudication of the arbitrator is generally binding between
the parties and it is not open to the court to attempt to
probe the mental process by which the arbitrator has reached
his conclusion. Award of an arbitrator can be set aside by a
court only on the grounds indicated in Section 30 of the
Arbitration Act. It is not open to the court to re-assess
the evidence to find whether arbitrator has committed ay
error or to decide the question of adequacy of evidence and
the court cannot sit on the conclusion of the arbitrator by
re-examining and reappreciating the evidence considered by
the arbitrator. At the same time the arbitrator is a
creature of the agreement itself and therefore is duty bound
to enforce the terms of the agreement and cannot adjudicate
a matter beyond the agreement itself. If the arbitrator
adjudicates a claim of a contractor with reference to the
clauses of the agreement itself whereby the agreement gets
engrafted into the award, it will be open to the court to
examine those clauses of the agreement and find out the
correctness of the conclusion of the arbitrator with
reference to those clauses. Bearing in mind the aforesaid
parameters for exercise of jurisdiction by Court in
examining the legality of an award of an arbitrator, the
award in hand as well as the order of the subordinate Judge
and that of the High Court requires scrutiny.
Admittedly under the agreement the completion period of
work was 28.2.1989. The stipulated quantity of work in
respect of Item No. 13 was 57000 cubic meters and in respect
of Item No. 15 it was 3500 cubic meters. In the course of
execution of the contract, drawings and designs were changed
as a result of which there was abnormal increase of the
quantity of work and for such increase of quantity of work
when the contractor claimed a higher rate and gave the
analysis before the arbitrator, which was not disputed by
the State and the arbitrator accepted the rate, the court
will not be justified in interfering with the same. It is
not possible for us to accept the contention of Mr. Sehgal
that under the terms of the agreement the contractor was not
entitled to claim any higher rate. The arbitrator having
considered all the relevant materials and there being no
legal proposition which has formed the basis for acceptance
of a higher rate and no the other hand the same being
arrived at on account of the abnormal increase in the
quantity of work which was on account of change of drawings
and designs, the court will not be justified in interfering
with the same. The first contention of Mr. Sehgal,
therefore, cannot be accepted.
But the second submission of Mr. Sehgal is
unassailable. After expiry of the period stipulated in the
agreement in respect of further quantity of work executed by
the contractor, the State has been praying at a higher rate
by calculating in terms of the escalation clause in the
contract itself. When the claimant filed his claim petition
before the arbitrator an assertion was made in paragraph 27
of the Claim Petition that the opposite party in respect of
the extra quantity of work executed in Item No. 13 has paid
and is paying at the rate of Rs. 243.00 per cubic meter
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
though the claimant is entitled to a rate of Rs. 453.50 per
cubic meter and hence the claimant is entitled to an
additional amount at the rate of Rs. 210.50 per cubic meter
(Rs. 453.50 - 243.00) and the amount thus comes to Rs.
91,56,750. Similarly, in respect of extra quantity of work
in Item No. 15 it was averred in paragraph 30 of the Claim
Petition that the Opposite party in respect of this extra
quantity has paid and is paying at the rate of Rs. 460/- per
cubic meter though the claimant is entitled to a rate of Rs.
739.55 per cubic meter and hence the claimant is entitled to
an additional amount at the rate of Rs.279.55 per cubic
meter (Rs. 739.55-460.00) and the amount thus comes to Rs.
9,92,402.50. The Claim Petition was filed on May 19, 1990.
But it was brought to our notice in the course of hearing of
this appeal by Mr. Seghal, learned senior counsel appearing
for the appellant that subsequent to 28.2.1989 which was the
period contemplated under the agreement for completion of
work, the contractor - claimant has been paid at an
escalated rate in accordance with the escalation clause in
the agreement itself. Neither the arbitrator nor any of the
forums below have taken note of the aforesaid fact. Mr.
Sanghi, learned senior counsel appearing for the respondent
- contractor, however, vehemently urged that the claim of
Rs. 453.50 per cubic meter in respect of Item No. 13 and Rs.
739.55 per cubic meter in respect of Item No. 15 was the
basic rate claimed by the contractor and therefore any
payment already made for excess quantity of work after the
stipulated period in the agreement in accordance with the
escalation clause in the agreement cannot be taken into
account in adjudicating the claim of the contractor. We are
unable to accept this contention of Mr. Sanghi in as much as
the claimant himself, as has stated earlier unequivocally in
the Claim Petition averred that the claimant has been paid
and is being paid at the old rate stipulated in the
agreement and he is entitled to the higher claim. In respect
of the excess quantity of work executed by the claimant
subsequent to the completion period indicated in the
agreement when the claimant has made the claim at a higher
rate and that claim is allowed by the arbitrator on the
basis of analysis of rates given by him, then the amount
already paid to him by the State in accordance with the
escalation clause in the agreement has to be adjusted and
the claimant would not be entitled to double benefit on that
score. Unfortunately, this position has been lost sight off
by the arbitrator as well as by the subordinate Judge and
the High Court possibly because this has not been brought to
the notice by the State. Mr. Sanghi learned counsel
appearing for the respondent on instruction from his client
does not dispute the position that subsequent to 28.2.1989,
in respect of the quantity of work executed by the
contractor, he has been paid at an escalated rate on the
basis of calculation made in accordance with the escalation
clause in the agreement. This being the position, we would
have ordinarily set aside the award of the arbitrator and
remitted the matter for recalculation. But in the course of
hearing Mr. Sanghi, learned counsel appearing for the
respondent submitted that the matter may be decided by this
Court since a considerable period has lapsed in the meantime
and did not dispute the calculation sheet that was filed by
Mr. Seghal, learned counsel appearing for the State, as well
as the affidavit of Shri Ambika Prasad, Executive Engineer,
Maudha Dam, Construction Division. In the same affidavit
after making necessary adjustments of payment, made at the
escalated rate, it has been stated that the contractor would
be entitled to the amount of Rs. 37,26,917.22 in respect of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
Item No. 13 for the extra work executed between 1.3.1989 to
30.4.1990 and a sum of Rs. 1,71,542,41 in respect of extra
quantity of work for Item No. 15 for the period between
1.3.1989 to 30.4.1990 and thus in all the claimant -
contractor would be entitled to Rs. 38,98,459.63 in respect
of the extra quantity of work executed by him for the period
1.3.1989 to 30.4.1990. Since the calculation made in this
affidavit is not disputed and in view of the submission made
by Mr. Sanghi appearing for the claimant contractor, we
modify the award of the arbitrator and direct that the
claimant would be entitled to an additional sum of Rs.
38,98,549.63 in respect of the work executed by him upto
30.4.1990 and the same amount would also carry interest at
the rate of 9% per annum from 21.5.1990 till payment is
made, as awarded by the Arbitrator himself.
The arbitrator has also held in the award that the
claimant would be entitled to be paid at the same rate as
indicated in the award in respect of the work executed
subsequent to 30th April, 1990. Mr. Sanghi, the learned
senior counsel appearing for the contractor submitted that
no reference has been made to the arbitrator as to at what
rate the contractor would be paid in respect of the work
executed subsequent to 30th April, 1990 and infact the
claimant contractor had not made any claim on that score.
And as such the said direction of the arbitrator must be
held to be without jurisdiction. Mr. Sehgal the learned
senior counsel appearing for the State also could not point
out any material to indicate that the reference included the
dispute with regard to the rate at which the contractor
would be paid even subsequent to 30th April, 1990. The
arbitrator obviously cannot entertaion and decide any
dispute which has not been referred to it. In this view of
the matter the direction of the arbitrator must be held to
be without jurisdiction and we accordingly quash that part
of the direction. In the net result, therefore, the appeal
is allowed in part to the extent already indicated. There
will be no order as to costs.