Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
CASE NO.:
Appeal (civil) 12930 of 1996
PETITIONER:
SMITA CONDUCTORS LTD.
Vs.
RESPONDENT:
EURO ALLOYS LTD.
DATE OF JUDGMENT: 31/08/2001
BENCH:
S. Rajendra Babu & S.N. Phukan
JUDGMENT:
RAJENDRA BABU, J. :
A contract [bearing No. S-142] for supply of aluminum rods of
2400 metric tones @ 200 MT per shipment every month from January to
December 1991 was proposed by the respondent to the appellant on
31.8.1990 containing an arbitration clause. In the letter accompanying
the contract, it was stated to sign and return copy for sake of good order.
The appellant did not sign nor return the said contract. Reminders were
sent in this regard from time to time. On 4.2.1991, letter from the
respondent enclosing the amendment to the contract was sent to the
appellant but without any result. On 25.2.1991, another contract
[bearing No.S-336] was proposed by the respondent to the appellant for
supply of 2,000 MT of aluminum rods @ 500 MT per shipment. In the
first contract, initially there was no arbitration clause. However, on
18.3.1991, the contract bearing the same number, i.e., S-142, was sent
containing the arbitration clause with certain amendment for signature
and return of the second copy. But the contract was not signed and sent
by the appellant. On the basis of certain irrevocable letters of credit for
US$ 243,250 opened by the appellant, shipments were made in January,
February and March 1991. In the meanwhile, a circular was issued on
19.3.1991 by the Reserve Bank of India [for the sake of brevity referred to
as RBI] to all scheduled commercial banks placing restrictions on
import of goods. It was followed up by another letter of the same date
addressed by the Executive Director, RBI to the Chairmen of all
commercial banks explaining the circulate dated 19.3.1991 in relation to
the foreign exchange reserve. On 22.4.1991, one more circular was
issued by the RBI modifying the margins for opening letters of credit as
prescribed by circular dated 19.3.1991. The appellant sent a telex on
30.4.1991 to the respondent to the effect that severe restrictions had
been imposed by the RBI due to unprecedented foreign exchange crisis
and the RBI had not cleared the application for letter of credit.
Therefore, the appellant wanted to invoke the force majeure clause
canceling April shipment for both the contracts. The respondent wrote to
the appellant on 30.5.1991 to the effect that they had closed their
position and initiated arbitration proceedings with reference to both the
contracts. When the appellant did not respond to the same, letter was
received by the appellant from London Metal Exchange appointing the
second arbitrator in terms of the arbitration clause.
On 30.8.1991, a suit [bearing No.2963/91] was filed by the
appellant seeking a declaration that there is no valid agreement between
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
the parties and that arbitration before the London Metal Exchange was
void. The learned Single Judge of the Bombay High Court did not grant
any interim order and recorded a statement that the appellant would
participate in the arbitration proceedings under protest. The appeal filed
against it stood dismissed by an order on 18.12.1991. In the meanwhile,
suit was treated as a petition under Section 33 of the Arbitration Act,
1940 which stood dismissed on the ground that the arbitration clause
bound the parties. The arbitrators published an award on 29.7.1992
awarding damages amounting to US$ 676,000 including pre-award
interest but did not award post-award interest. The appellant filed an
appeal to the Appeal Board of the London Metal Exchange seeking to set
aside the award as also dispensation of deposit. Since the London Metal
Exchange rejected the request for waiver of deposit, the appeal could not
be pursued. Thereafter, a petition was filed in the Bombay High Court
by the respondent under the Foreign Awards (Recognition &
Enforcement) Act, 1961 [hereinafter referred to as the Act] for
enforcement of the award. The High Court allowed the petition and
granted the certificate under Article 134-A of the Constitution. The High
Court, while disposing the petition, awarded interest @ 15 per cent for
the post-award period until payment. This order is in challenge before
us.
Shri K.K.Venugopal, learned Senior Advocate appearing for the
appellant, raised three contentions. The first contention is to the effect
that the foreign award could be enforced if it is in pursuance of an
agreement in writing for arbitration to which the Convention set forth in
the Schedule to the Act applies as per Section 2(a) of the Act and
inasmuch as the Schedule pertains to the Convention on the recognition
and enforcement of foreign arbitral awards, otherwise known as the New
York Convention. It is submitted that the arbitration in the present case
is not pursuant to an agreement in terms of Article II of the Schedule to
the Act. Shri Venugopal submitted that an agreement has to be in
writing under which the parties undertake to submit to arbitration any
differences which have arisen in respect of any legal relationship arising
out of a contract or otherwise and capable of settlement by arbitration
and the expression agreement in writing would include an arbitral
clause in a contract or an arbitration clause signed by the parties or
contained in the exchange of letters or telegrams. He submitted that in
the present case there being no written contract either in contract
bearing No.S-142 or contract bearing No. S-336 because the contracts
were signed by the respondent but not signed by the appellant and thus
resulting only an oral agreement between the parties for supply of goods;
such an agreement cannot be termed to be one made in writing to attract
paras 1 and 2 of Article II of the Schedule to the Act and that there has
been no exchange of letters or telegrams between the parties so as to
include the arbitral clause. In this context, he referred to the decisions
of different courts reported in the Yearbook Commercial Arbitration,
Vol.II, 1977. Referring to the decision in the court of Oberlandesgericht
Dusseldorf on 8.11.1971 between a Dutch seller and a German buyer
[Yearbook Commercial Arbitration, Vol.II, 1977, p.237] wherein it was
held that Article II of the Convention requires the arbitration agreement
to be in writing and signed by the parties, including an exchange of
letters or telegrams. In any case, therefore, a declaration in writing of
both sides is required. A one-sided confirmation does not suffice and
that the lack of a declaration in writing by the other party cannot be
cured by his appearance before the arbitrator. Enforcement can,
therefore, be granted under the New York Convention. In a case decided
by the United States District Court between Sen Mar, Inc.[US] v. Tiger
Petroleum Corporation N.V., [Yearbook Commercial Arbitration,
Vol.XVIII, 1993, p.493] in which the respondent had contended that the
purported arbitration clause does not satisfy the Conventions writing
requirement, which defines in Art.II(2), a writing as an arbitral clause in
a contract or an arbitration agreement, signed by the parties or
contained in an exchange of letters. It was held that the respondents
responsive telexes are not only devoid of arbitration language they also
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
disavow the entire contents of the Petitioners 17 July telexes. Shri
Venugopal next referred to the decision of the Italian Court of appeal in
Finagrain Compagnie Commerciale Agricole et Financiere S.A. vs.
Patano snc(Italy) [Yearbook Commercial Arbitration, Vol.XXI, 1996,
p.571]. In that case, the three contracts were concluded for sale of
colzaseed oil. One of the contracts was concluded in writing, was signed
by the parties and contained a specific reference to FOSFA Contract
No.54 and the arbitration clause therein contained. The other two
contracts were concluded through telexes sent to the parties by a broker
and not signed by them. The telexes also referred to FOSFA Contract
No.54 which had the arbitration clause. In those circumstances, the
Court granted enforcement to award No.2912 which was based on the
contract signed by the parties, but found that no valid arbitration
agreement under the Convention had been concluded as to the further
two contracts and, therefore, denied enforcement to the other two awards
pertaining to the rest of the two contacts. Shri Venugopal next relied
upon the decision of the Swiss Court in Gaetano Butera (Italy) v. Pietro
e Romano Pagnan (Italy) [Yearbook Commercial Arbitration, Vol.IV,
1979, p. 296]. The Court of Appeal considered that the validity of the
arbitration clause had to be determined by the Italian law under which
the clause would have had to be in writing. But on appeal against the
decision of the Court of Appeal, the Supreme Court stated that no valid
agreement existed because the terms of the New York Convention had
not been applied. It was noticed therein that the arbitral clause was
inserted in writing in the contract of sale and was completed by the
reference to the Arbitration Rules of the LCTA. This reference was not a
reference, which is invalid according to Italian case law. In the case
under consideration, however, the arbitration agreement was contained
and explicitly mentioned in the sales contract itself. The reference had
as sold object the procedural regulation of the arbitration and, therefore,
validly completed the arbitral clause mentioned above as it ascertained
the existence and the specific contents of that regulation. But the
Supreme Court, however, held that the arbitral clause was null and void
because it was signed only by the seller who invoked the clause. Shri
Venugopal referred to another decision of the Italian Court in Corte Di
Cassazione in Begro B.V. vs. Ditta Voccia & Ditta Antonio Lamberti
[Yearbook Commercial Arbitration, Vol.III, 1978, 278]. The court
interpreted Art.II, paras 1 and 2 of the Convention, as requiring a specific
agreement to submit to arbitration signed by the parties or contained in
an exchange of letters or telegrams. According to the court, such a
specific agreement could not be found in an arbitration clause printed on
the contract-form and signed by the parties and, therefore, held that the
arbitration clause to be without effect. Shri Venugopal next referred to
the decision of Corte Di Cassazione in Societa Atlas General Timbers v.
Agenzia Concordia Line, [Yearbook Commercial Arbitration, Vol.III,
1978, 267]. It was held therein that the validity of the arbitral clause in
question had to be judged under the New York Convention. According to
Art.II, para 2 of the Convention, the arbitration clause in writing means
an arbitral clause in a contract or an arbitration agreement, signed by
the parties or contained in an exchange of letters or telegrams. This
provision, therefore, requires clearly the signature as a minimum
element for the effectiveness of the contract containing the arbitral
clause. The court concluded that not the arbitration clause itself, but
the contract in which it is contained must be signed by both parties
under Art.II, para 2 of the Convention. The court examined whether the
requirement was met in the present case and found that the signature of
the agent of the carrier was not sufficient since his power of attorney was
not in writing and that the signature of the other party was also lacking
and his endorsement does not replace the signature, since the former
concerns only a transfer of title, whilst the latter is necessary for the
formation of the contract.
In reply Dr.A.M.Singhvi, learned Senior Advocate appearing for the
respondent, submitted that this contention is not available to the
appellant inasmuch as the Bombay High Court had already decided the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
case when a suit had been filed by the appellant and that the conclusion
reached by the Bombay High Court while dismissing the suit treating the
same as an application filed under Section 33 of the Arbitration Act,
1940 amounts to res judicata and, therefore, it is not open to the
appellant to urge that point again in these proceedings. He further
submitted that the correspondence between the parties and the conduct
of the appellant clearly establish that there existed an arbitration clause
between the parties and, therefore, there was full compliance with Art.II,
paras 1 and 2 of the Convention which forms part of the Schedule to the
Act. He submitted that the definition of what constitutes a written
arbitration agreement given in Art.II(2) can be deemed to be an
internationally uniform rule which prevails over any provisions of
municipal law regarding the form of the arbitration agreement in those
cases where the Convention is applicable. The courts in the contracting
states have generally affirmed the uniform rule character of Art.II(2). The
Italian courts formed an exception to this general affirmation as they
determined the formal requirements for the arbitration agreement on the
basis of a municipal law which they found applicable according to Italian
conflict of rules and in even the Italian Supreme Court has in recent
decisions affirmed the uniform principle of Art.II(2) as well and has
placed reliance upon certain decisions of other courts in support of the
proposition made by him.
This Court in Renusagar Power Co. Ltd. vs. General Electric
Company, 1994 Supp (1) SCC 644, held that the New York Convention
controls the proceedings in arbitration. Even the plain language of
Section 2(a) of the Act makes it clear that the Act is applicable in respect
of a foreign award made in pursuance of an agreement in writing for
arbitration to which the Convention set forth in the Schedule applies and
the terms of the Convention are available in the Schedule to the Act.
Art.II, paras 1 and 2 pertain to this aspect of the matter and they read as
under:
Article II
1. Each contracting State shall recognise an agreement in
writing under which the parties undertake to submit to arbitration
all or any differences which have arisen or which may arise
between them in respect of defined legal relationship, whether
contractual or not, concerning a subject-matter capable of
settlement by arbitration.
2. The term agreement in writing shall include an arbitral
clause in a contract or an arbitration agreement, signed by the
parties or contained in an exchange of letters or telegrams.
What needs to be understood in this context is that the agreement
to submit to arbitration must be in writing. What is an agreement in
writing is explained by para 2 of Article II. If we break down para 2 into
elementary parts, it consists of four aspects. It includes an arbitral
clause (1) in a contract containing an arbitration clause signed by the
parties, (2) an arbitration agreement signed by the parties, (3) an arbitral
clause in a contract contained in exchange of letters or telegrams, and (4)
an arbitral agreement contained in exchange of letters or telegrams. If
an arbitration clause falls in any one of these four categories, it must be
treated as an agreement in writing. In the present case, we may advert
to the fact that there is no letter or telegram confirming the contract as
such but there is certain correspondence which indicates a reference to
the contract in opening the letters of credit addressed to the Bank to
which we shall presently refer to. There is no correspondence between
the parties either disagreeing with the terms of the contract or arbitration
clause. Apart from opening the letters of credit pursuant to the two
contracts, the appellant also addressed a telex message on 23.4.1990 in
which there is a reference to two contracts bearing Nos.S-142 and S-336
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
in which they stated that they want to invoke force majeure and the
arbitration clauses in both the contracts which are set forth successively
and thus it is clear that the appellant had these contracts in mind while
opening the letters of credit in the bank and in addressing the letters to
the bank in this regard. May be, the appellant may not have addressed
letters to the respondent in this regard but once they state that they are
acting in respect of the contracts pursuant to which letters of credit had
been opened and they are invoking the force majeure clause in these two
contracts, it obviously means that they had in mind only these two
contracts which stood affirmed by reason of these letters of credit. If the
two contracts stood affirmed by reason of their conduct as indicated in
the letters exchanged, it must be held that there is an agreement in
writing between the parties in this regard.
Shri Venugopal seriously objected to this line of approach on the
basis that what we are spelling out is only a course of conduct on the
part of the appellant and not a written agreement emanating out of a
contract or correspondence between the parties. When the appellant and
the respondent agreed to deal in certain goods, certain terms had to be
agreed between them. Those terms were set out in the contracts referred
to as S-142 and S-336. If those are the two contracts pursuant to which
the appellant is trading with the respondent, the conclusion is obvious
that those terms are reduced to writing and acknowledged by reason of
opening of letters of credit of which reference is made in these two
contracts. It would be illogical to contend that those letters of credit
though not addressed to the respondent would indicate that they were
not acting in pursuant to the contracts [S-142 and S-336] with the
respondent and now it is not possible for the appellant to wriggle out of
the same. It cannot be said that what is agreed to by them is only
regarding the supply of goods and not in regard to other terms.
Therefore, the contention advanced by Shri Venugopal in this connection
stands rejected.
Dr. Singhvi, however, contended that the scheme of the Act would
indicate that the agreement need not be signed by the parties at all nor
even para 2 of Art.II of the Schedule would arise for consideration at all.
According to him, under Section 2(a) of the Act, if there is an award in
pursuance of an agreement in writing for arbitration to which the
Convention set forth in the Schedule applies, the court has jurisdiction
to enforce the same and each contracting State shall recognise an
agreement in writing which does not refer to any signature by the parties
nor refer to exchange of letters or telegrams and, therefore, submitted
that even in the absence of the signatures of the parties or exchange of
letters an agreement in writing simplicitor if the contract contains such
arbitration clause is enough to hold that the arbitration clause is binding
on the parties. His contention is that there is an agreement in writing
though not signed by both the parties but by the course of conduct
between the parties can be spelt out that such an agreement in writing is
enough and he further submitted that para 2 of Art.II only explains the
meaning of the expression agreement in writing which includes
contracts or agreements signed by parties or contained in exchange of
letters or telegrams. If really, as contended by Dr. Singhvi, the position
is clear, then there is no need for para 2 of Art.II at all. Para 1 of Art.II
would have been enough. When the expression agreement in writing is
sought to be explained and indicates that it may be in the nature of a
contract then obviously the parties have got to sign the same or it may be
in the nature of exchange of letters or telegrams, an agreement similarly
signed by the parties or resulting as a consequence of exchange of letters
or telegrams. Therefore, when the position is not that clear, we would
not wish to hazard a decision on this aspect of the matter but rest our
conclusion on the principle applicable to the facts emerging in the case
and not widen the scope of consideration in this case.
Shri Venugopal next contended that the decision in the arbitration
suit No.2963/91 which was treated as an arbitration petition under
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
Section 33 of the Arbitration Act, 1940 made on January 20, 1992 by the
Bombay High Court holding that there is an arbitration agreement
between the parties and the petition having been dismissed is binding on
the parties and, therefore, clearly the principle of res judicata would be
applicable to them and thus it is no longer open to the appellant to raise
this contention over again. Shri Venugopal submitted that the occasion
to recognise or enforce a foreign award would arise only on an award
being passed which is sought to be recognised or enforced in terms of the
Act. It is only in those circumstances that such consideration could be
made and not earlier and, therefore, he submitted that the principle of
res judicata would not be attracted at all inasmuch as the Bombay High
Court had no jurisdiction to deal with a question prior to determination
of the rights of the parties because the Act is applicable to an award
made on differences between persons not considered as domestic awards
and, therefore, an application under Section 33 of the Arbitration Act,
1940 and consideration of the same will not amount to a decision in the
case as to be binding on the parties much less can such a decision be
treated as a bar on further proceedings on the principle of res judicata.
This Court in Renusagars case [supra] had occasion to consider the
schemes of the provisions of the Act and the Arbitration Act, 1940. It
was noticed therein that the schemes of the Act and the Arbitration Act,
1940 materially differ on several aspects and an examination was made
of Sections 3, 4 and 7 of the Act in comparison with Sections 32, 33 and
34 of the Arbitration Act, 1940 to bring out such differences. However, it
was noticed that the scheme under Sections 3 and 7 of the Act
contemplates that questions of existence, validity or effect of the
arbitration agreement differ in cases where such an agreement is wide
enough to include within its ambit such questions which could be
decided by the arbitrators but their determination is subject to the
decision of the court and such decision of the court can be had either
before the arbitration proceedings commence or during their pendency if
the matter is decided, or can be had under Section 7 of the Act after the
award is made and filed in the court and is sought to be enforced by the
parties thereto. Thus this Court made it clear that the existence, validity
or effect of an arbitration agreement can be determined by the court at
three stages : (1) before the arbitration proceedings commence, (2) during
their pendency, and (3) after the award is made and filed in the court. If
that is so and the question in this regard was raised before the court in a
proceeding and that aspect was determined by the court, it cannot be
said that such decision is not binding on the parties. Independent of
application of the principle of res judicata, we have arrived at the
conclusion that we can spell out the existence of an arbitration clause
between the parties in terms of the New York Convention to result in an
arbitration and that further gets reinforced by the decision of the High
Court in the original suit inasmuch as that High Court took the view that
there is an arbitration agreement between the parties which is
enforceable.
In the light of this discussion, we are firmly of the view that the
appellant cannot any longer challenge the existence of an arbitration
agreement between the parties and such an agreement was not covered
by the New York Convention.
This Court in Renusagars case [supra], examined the scope of
enquiry in proceedings for recognition and enforcement of foreign award
under the Act and after referring to the concepts in private international
law, Geneva Convention of 1927 and the New York Convention on
Arbitration of 1958, held that it is limited to the grounds mentioned in
Section 7 of the Act and does not enable a party to the said proceedings
to impeach the award on merits.
Shri Venugopal next contended that the award is contrary to
public policy of India and Reserve Bank of India had issued certain
circulars imposing restrictions on imports and, therefore, attracted the
force majeure clause. The question of what is the public policy has
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
been considered by this Court in Renusagars case [supra] by
interpreting the words in Section 7(1)(b)(ii) of the Act to mean public
policy of India and not of the country whose law governs the contract or
of the country of place of arbitration. In doing so, this Court took note
of the fact that under Arbitration (Protocol and Convention) Act, 1937 the
expression public policy of India had been used, whereas the
expression public policy is used in the Act; that after the decision of
this Court in V/O Tractoroexport, Moscow v. Tarapore & Co., 1970
(3) SCR 53, Section 3 was substituted to bring it in accord with the
provisions of the New York Convention on Arbitration of 1958 which
seeks to remedy the defects in the Geneva Convention of 1927 that
hampered the speedy settlement of disputes through arbitration; that to
achieve this objective by dispensing with the requirement of the leave to
enforce the award by the courts where the award is made and thereby
avoid the problem of double exequatur; that the scope of enquiry is
restricted before the court enforcing the award by eliminating the
requirement that the award should not be contrary to the principles of
the law of the country in which it is sought to be relied upon; that
enlarging the field of enquiry to include public policy of the country
whose law governs the contract or of the country of place of arbitration
would run counter to the expressed intent of the legislation. Therefore, it
was held that the words public policy is intended to broaden the scope
of enquiry so as to cover the policy of other countries, that is, the
country whose law governs the contract or the country of the place of the
arbitration. In the absence of a definition of the expression public
policy, it is construed to mean the doctrine of public policy as applied by
the courts in which the foreign award is sought to be enforced and this
Court referred to a large catena of cases in this regard. Therefore, we will
proceed on the basis that the expression public policy means public
policy of India and the recognition and enforcement of foreign award
cannot be questioned on the ground that it is contrary to the foreign
country public policy and this expression has been used in a narrow
sense must necessarily be construed as applied in private international
law which means that a foreign award cannot be recognised or enforced
if it is contrary to (1) fundamental policy of Indian law; or (2) the
interests of India; or (3) justice or morality. Shri Venugopal strongly
attacked the correctness of the conclusions reached by the Arbitrators on
the effect of force majeure clause.
In the award it is stated:
.Under the force majeure clause the respondents did not have the right
to cancel April 1991 and May 1991 quota under contracts S142 and
S336 and neither by the same reasoning did the seller have the right to
close out the June through November 1991 quotas against contract
number S142 and the June quota against contract No. S336.
It may be seen as a commercial oversight, nevertheless the force majeure
clause as it is constructed in both contracts, would require both parties
to maintain the contracts in being for an indefinite period of time until
the force majeure clause had ended, failing alternative arrangements
between the parties for delivery and payment.
Further, the arbitrators had held that having considered the March
1991 Reserve Bank of India circular imposing restrictions on the imports
of certain categories of goods due to difficult balance of payments
position prevailing at the relevant time and letter of credit of Rs. 25 lakhs
and above should be referred by the local bank branch to the head office
for prior approval and in excess of Rs. 50 lakhs and above should be
referred by the banks to the Controller, Exchange Control Department,
Central Office, Reserve Bank of India, for clearance, and there is no time
limit so far as these restrictions are concerned. The arbitrators noticed
that the restrictions set by the Reserve Bank of India had created a
situation in which the appellants had difficulty in arranging the opening
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
of letters of credit so as to conform with the terms of the contract
although it could be noted that many applications were submitted by the
appellant to the Bank of Baroda after the contractual deadline; that
several shipments were made against the letter of credit opened after the
contractual deadline; that thus it has been established by the
documentary evidence to both contracts Nos. S142 and S336 that
declaration of force majeure clause was present though belatedly. The
arbitrators ultimately concluded that the Reserve Bank of India directives
interfered with the contracts Nos. S142 and S336 which would have the
effect of delaying the opening of the letters of credit by the buyer under
the specified contracts. The arbitrators were of the opinion that the force
majeure clause had no limitation on the period of suspension of the
contract while the execution was affected by a valid force majeure; that it
had been accepted by both the parties and that the restriction and
requirements imposed by the Reserve Bank of India directives must be
construed as having caused interference in and/or hindrance to the
execution of the contract time wise; that though time had been
considered to be of the essence condition, the inclusion of the force
majeure clause which provided no time limit to the suspension of the
contract caused by conditions envisaged herein though unusual it was
accepted that the earlier contracts would be negotiated and executed
successfully by the parties to the dispute.
The view taken by the arbitrators on the effect of the force majeure
clause in the light of the Reserve Bank of India directives is a plausible
view and cannot be ruled out as impossible of acceptance, and, therefore,
question of substituting our view for that of the arbitrators would not
arise. Question of public policy would have arisen if there was complete
restriction on the implementation of the terms of the contract. There was
no such restriction imposed. But, on the other hand, certain restrictions
were imposed which could have been worked out by resorting to
appropriate measures in terms of the contract as held by the arbitrators.
In that view of the matter, we do not think any question of public policy
as such arises for consideration in a situation of this sort. The argument
is almost a red-herring and does not constitute a valid reason for
interference with the award. Therefore, we reject the contentions raised
on behalf of the appellant.
It is lastly contended that the interest awarded by the arbitrators
needs interference and gave a break-up of the details. Interest has been
awarded from period prior to reference in 1991 and after reference till
termination of the proceedings before the arbitrators, pendente lite and
after decree. This Court in Renusagars case [supra], held that award of
such interest after the Interest Act, 1978 is permissible, however, on the
facts of the case the High Court not having given a direction to the
payment of interest pendente lite did not modify that part of the order.
We do not find that it is appropriate to modify the award made by
the arbitrators or decree passed pursuant to it as no exceptional
circumstances arise. The fact that there is fluctuation in the exchange
rate is no reason for us to interfere with the same.
The appellant having failed on all points we dismiss this appeal,
however, with no order as to costs.
.J.
[ S. RAJENDRA BABU ]
J.
[ S.N. PHUKAN ]
AUGUST 31, 2001.