Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
CORPORATION OF CALCUTTA
Vs.
RESPONDENT:
MULCHAND AGARWALLA.
DATE OF JUDGMENT:
17/11/1955
BENCH:
AIYYAR, T.L. VENKATARAMA
BENCH:
AIYYAR, T.L. VENKATARAMA
IMAM, SYED JAFFER
CITATION:
1956 AIR 110 1955 SCR (2) 995
ACT:
Calcutta Municipal Act, 1923, (Bengal Act III of 1923), ss.
363, 488 and Rule 62 of Schedule XVII-Prior proceedings
taken by Corporation of Calcutta under s. 488 read with Rule
62 of Schedule XVII -Whether a bar to the subsequent
proceedings under s. 363 of the Act -Inconvenience to
neighbours-Whether relevant for making an order for
demolition under s. 363 of the Act-Proceedings on the same
facts competent to be taken under two different sections
providing different penalties-Whether distinct proceedings-
Word "may" in s. 363 of the Act, whether means "shall"-
Discretion vested in the Magistrate under s. 363-Order
passed by on authority entrusted with discretion to pass
such order-When liable to be interfered with by the appel-
late Court.
HEADNOTE:
The Corporation of Calcutta is not precluded from taking
proceedings under s. 363 of the Calcutta Municipal Act, 1923
by reason of its having taken proceedings prior thereto
under s. 488 of the Act read with Rule 62 of Schedule XVII.
The question of inconvenience to neighbours is not relevant
for the purpose of deciding whether an order for demolition
should be made under s. 363 of the Act.
When the Legislature provides that on the same facts
proceedings could be taken under two different sections and
the penalties provided in those sections are not the same,
it obviously intends to treat them as distinct, and,
therefore, where no question under s. 403 of the Code of
Criminal Procedure arises, proceedings taken under one
section cannot be treated as falling within the other.
The word. "may" in s. 363 of the Act does not mean "shall"
and the Magistrate has under that section discretion whether
he should pass an order for demolition or not.
It is a well-settled principle that when the legislature
entrusts to an authority the power to pass an order in its
discretion an order passed by that authority in exercise of
that discretion is, in general, not liable to be interfered
with by an appellate court, unless it can be shown to have
been based on some mistake of facts or misapprehension of
the principles applicable thereto.
In the present case, however, the orders of the courts below
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
were based on mistakes and misdirections and therefore could
not be supported.
But the Supreme Court did not think this to be a fit case
for an order for the demolition of the buildings in view of
certain special circumstances, viz, (1) though s., 363(2),
which directs that no appli-
126
996
cation for demolition shall be instituted after the lapse of
five years from the date of the work, did not, in terms,
apply as the proceedings had been started in time, it was
nearly five years since the building bad been completed and
the interests of the public did not call for its demolition,
and (2) the appeal came on a certificate granted under art.
134(1)(c) with a view to obtaining the decision of the
Supreme Court on certain questions of importance.
Abdul Samzad v. Corporation of Calcutta ([1905] I.L.R. 33
Cal. 287), referred to.
JUDGMENT:
CRIMINAL APPELLATE JURISDICTION: Criminal Appeal No. 60 of
1954.
Appeal under Article 134(1)(c) of the Constitution of India
from the Judgment and order dated the 19th January 1954 of
the Calcutta High Court in Criminal Revision No. 865 of 1953
arising out of the Judgment and Order dated the 29th April
1953 of the Court of Third Municipal Magistrate, Calcutta in
Case No. 108-A of 1951.
N. C. Chatterji, (S. K. Bose and Sukumar Ghose, with him)
for the appellant.
G. P. Kar, (A. K. Mukherjee and D. N. Mukherjee, with
him) for the respondent.
1955. November 17. The Judgment of the Court was delivered
by
VENKATARAMA AYYAR J.-This is an appeal against the judgment
of the High Court of Calcutta affirming the order of the
Municipal Magistrate, whereby he dismissed an application
filed by the appellant under section 363 of the Calcutta
Municipal Act, 1923, hereinafter referred to as the Act, for
demolition of certain constructions on the ground that they
had been erected without the previous permission of the
authorities and in contravention of the prescriptions laid
down in the building rules.
The respondent is the owner of house No. 36, Armenian
Street, Calcutta. On 28-10-1950 the Building Inspector of
the Corporation discovered that some new masonry structures
were being constructed on the fifth storey of that house. A
notice under section 365 of the Act was immediately served
on the respondent directing him to stop forthwith further
con-
997
structions pending an application to the Magistrate under
section 363 of the Act. What followed thereon is
graphically described by the learned Chief Justice of the
High Court in his order dated 9-4-1954 granting leave to
appeal to this Court, as a hide-and-seek game. On receipt
of the notice, the respondent stopped the work for a few
days, and thereby lulled the Building Inspector into the
belief that no further constructions would be made. When
the Inspector ceased to inspect the premises daily, the
respondent resumed the work, and on 7-11-1950 when the
Inspector came again on the scene, he found that the
construction was being proceeded with. A police -constable
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
was then posted for watch under section 365 (3) of the Act,
-and he continued there till 10-11-1950, on which date the
respondent wrote to the Corporation that he would not
proceed further with the construction. The police watch was
thereupon withdrawn on the respondent paying Rs. 40 being
the charges payable therefor. On 7-12-1950 the Inspector
again inspected the premises, and found that the construc-
tion was being proceeded with, and had a constable posted
again for watch. On 13-12-1950 the appellant lodged a
complaint before the Magistrate under section 488 read with
Rule 62 of Schedule XVII charging the respondent with
constructing two rooms in the fifth storey without obtaining
permission. Section 488(1)(a) enacts that whoever commits
any offence by contravening any provisions of any of the
sections or rules of the Act mentioned in the first column
of the table annexed thereto, shall be punished with fine as
specified in the said table. Rule 62 provides that the
erection of a new building shall not be commenced unless and
until the Corporation have granted written permission for
the execution of the same. The complaint was heard on 11-4-
1951. The respondent pleaded guilty, and was fined Rs. 200.
While the proceedings under section 488 were pending before
the Magistrate, the Corporation would appear to have
examined the nature of the constructions put up by the
respondent, and found that they contravened Rules 3, 14, 25
and 32 of Schedule XVII,
998
and decided to take action under section 363. They
accordingly issued a notice to the respondent to show cause
why action should not be taken under that section. The
respondent appeared by counsel on 13-2-1951, and after
hearing him, the appellant decided on 6-3-1951 to move the
court for an order under section 363, and the petition out
of which the present appeal arises, was actually filed on 4-
4-1951. There was delay in serving the respondent, and
after he was actually served which was on 17-9-1951, the
case underwent several adjournments, and finally on 29-4-
1953 the Magistrate passed an order dismissing the petition.
There was no dispute that the building rules had been
contravened. The Magistrate, however, held that he had a
discretion under section 363 whether he should direct
demolition, and that this was not a fit case in which an
order should be made for demolition, because the
constructions being on the fifth storey could not obstruct
light and air and thereby inconvenience the neighbours, and
there was no complaint from the residents of the locality,
and that as the respondent had already been fined in pro-
ceedings under section 488, an order for demolition would be
to penalise him twice over for the same offence.
Against this order, the appellant preferred a revision to
the High Court of Calcutta. That was heard by K. C.
Chunder, J. He agreed with the Magistrate that under section
363 the court had a discretion whether it should order
demolition or not, and that as the Corporation had taken
proceedings under section 488 and was content to have a fine
imposed on the respondent for breach of Rule 62, it would be
unjust to permit it thereafter to start proceedings under
section 363 for the further relief of demolition of the
building. He also commented on the undue ,delay on the part
of the Corporation in taking out the application, and took
into account the fact that no complaint had been received
from the locality. In the result, he dismissed the-
revision.
The appellant applied under article 134(1)(c) for leave to
appeal to this Court. Chakravarti, C. J. and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
999
S. R. Das Gupta, J. who heard this application, considered
that two questions of general importance arose on which it
was desirable to have the decision of this Court, viz., (1)
whether the Corporation was precluded from taking
proceedings under section 363 of the Act by reason of its
having taken proceedings prior thereto under section 488 of
the Act read with Rule 62 of Schedule XVII, and (2) whether
the question of inconvenience to neighbours was relevant for
the purpose of deciding whether an order for demolition
should be made under section 363 of the Act. They
accordingly granted leave under article 134 (1)(c), and that
is how the appeal is now before us.
The first question that arises for our determination is
whether the present proceedings under section 363 are barred
by reason of the application which was filed under section
488. It is conceded that there is nothing express in the
statute enacting such a bar, but it is contended that it is
to be implied from the proviso to section 363 that "where
the Corporation have instituted proceedings under section
493, no application shall be made under this section".
Admittedly, the appellant instituted no proceedings under
section 493; but it is argued that proceedings under section
488 substantially fall within section 493, and that the
proviso should therefore be held to be applicable. Under
section 493, if the erection of any new building is
commenced without obtaining the writen permission of the
Corporation, the owner of the building shall be liable to a
fine which may extend up to Rs. 500. Then, there is a
proviso that where an application had been made under
section 363, no proceeding shall be instituted under this
section. This corresponds to the proviso to section 363 set
out above, and reading the two provisions, it is clear that
the proceedings under the two sections are mutually
exclusive. Now, the contention of the respondent is that a
prosecution under section 488 for breach of rule 62 of
Schedule XVII is, in essence, a prosecution under section
493(a), and that, therefore, the proviso to section 363
becomes applicable. We are
1000
unable to agree with this contention. When the Legislature
provides that on the same facts proceedings could be taken
under two different sections and the penalties provided in
those sections are not the same, it obviously intends to
treat them as distinct, and, therefore, where no question
under section 403 of the Code of Criminal Procedure arises,
proceedings taken under one section cannot be treated as
falling within the other. The penalty prescribed in section
488 for breach of rule 62 of Schedule XVII is fine up to the
limit of Rs. 200, whereas the penalty provided for the same
offence under section 493(a) is fine which may extend to Rs.
500. It will not therefore be in consonance with the
intention of the Legislature to hold that proceedings under
section 488 are in substance the same as proceedings under
section 493, so as to be subject to the disability enacted
in the proviso to section 363. If the intention of the
Legislature was that proceedings taken under section 488
read with rule 62 of Schedule XVII should bar proceedings
under section 363, it could have said so expressly as it did
with reference to proceedings taken under section 493. To
accede to the contention of the respondent would be to read
into section 363 limitations which are not to be found
there. We cannot accept such a construction.
It was next argued by learned counsel for the respondent
that it was open to the Corporation to have asked for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
demolition of the building in the proceedings taken by it
under section 488, and as it did not ask for it and was
content with the imposition of fine, it was precluded from
claiming that relief in the present proceedings. This
argument is based on section 536, which is as follows:
"When under this Act or under any rule or bylaw made
thereunder any person is liable, in respect of any unlawful
work,-
(a) to pay a fine, and
(b) to be required to demolish the work,
a Magistrate may, in his discretion and subject to the
provisions of sections 363, 364 and 493, direct the said
person to pay the fine and also to demolish the work".
1001
In his order dated 9-4-1954, the learned Chief Justice
expressed a doubt whether the Corporation could apply for a
demolition order, when instituting an application under
section 488 for breach of Rule 62 of Schedule XVII. We are
inclined to share this doubt. What Rule 62 prohibits is the
erection of a building without permission, and under that
Rule, the breach is complete when the erection has
commenced, without reference to whether the construction is
being carried on or completed. A question of demolition
cannot therefore arise with reference to a breach of Rule
62. It can arise only when the construction of the building
is carried on or completed otherwise than in accordance with
the terms of the permission or in breach of any of the
provisions of the Act or the rules. Now, in the table
annexed to section 488, while a breach of Rule 62 of
Schedule XVII is made punishable with fine which may extend
to Rs. 200, there is no similar provision with reference to
breach of Rules 3, 14, 25 and 32 of that Schedule. But
there is, instead, a provision that when a direction is
asked for under section 363(1) for demolition, an order can
be passed imposing fine which may extend to Rs. 250. Under
that section, it should be noted, an application for an
order for demolition can be made on three grounds, viz., (1)
that the erection of building has been commenced without
permission, (2) that it has been carried on or completed
otherwise than in accordance with the terms of the
permission, or (3) that it has been carried on or completed
in breach of the provisions contained in the Act or the
rules. But there is this difference between an application
based on ground No. 1 aforesaid and one founded on grounds
Nos. 2 and 3, that while a question of demolition cannot
arise with reference to the former when the charge is com-
mencement or the construction without permission and at that
stage no question of demolition of, a building necessarily
arises, it does arise as regards the latter. Therefore, when
an application is made under section 488, whether an order
could be made under section 536 for demolition will depend
on the ground on which it is founded. And, where, as in the
1002
present case, the application was based solely and
exclusively on a breach of Rule 62 of Schedule XVII, no
order could have been passed for demolition under section
536. It is immaterial for the present purpose that the
building had been completed when the order was passed on 11-
4-1951 on the application under section 488, because the
power to pass an order under section 536 would depend on
what the charge as actually laid in the petition was and not
on what it might have been.
But even if the Magistrate had the power under section 536
to order demolition of the building, we cannot hold that the
appellant is precluded from asking for such an order under
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
section 363 merely by reason of the fact that the Magistrate
had failed to pass such an order, or even that the
Corporation did not ask for it in the prior proceedings.
There is no question of the application of any principle of
constructive res judicata, and there is nothing in the
statute which bars the appellant from claiming relief under
section 363. We cannot therefore uphold the contention that
the appellant is precluded in any manner by the prior
proceedings taken under section 488 from instituting the
present petition under section 363.
In this view, the point for decision is whether the order
passed by the Municipal Magistrate and affirmed by the
learned Judge in revision is open to attack on the merits.
The respondent contends that the Magistrate has under
section 363 a discretion whether he should pass an order for
demolition or not, and that this Court should not in appeal
interfere with the exercise of that discretion especially
when it has been concurred in by the High Court. Now, the
language of section 363 is that the Magistrate may pass an
order for demolition of the building, and though the word
’may’ might in some contexts be construed as meaning
’shall’, that is not the sense in which it is used in
section 363. We agree with the respondent that section 363
does not require that when a building is shown to have been
erected without permission or completed otherwise than in
accordance with the terms of the permission or in breach
1003
of the building rules, an order for its demolition should be
made as a matter of course. In our opinion, it does give
the Magistrate a discretion whether he should or should not
pass such an order. That was the construction put in Abdul
Samad v. Corporation of Calcutta(’) on section 449 of the
Calcutta Municipal Act, (Bengal Act III of 1899) which
corresponds to section 363 of the present Act on language
which is, so far as the present matter is concerned, the
same. in re-enacting the present section in the same terms
as section 449 of Bengal Act III of 1899, it must be taken
that the legislature has accepted the interpretation put on
them in Abdul Samad v. Corporation of Calcutta(1) as
correctly representing its intention. It should accordingly
be held that the word ’may’ in section 363 does not mean
"shall’, and that the Magistrate has under that section a
discretion whether be should pass an order for demolition or
not.
Then the question is whether the exercise of that discretion
by the courts below is open to review by this Court. It is
a well-settled principle that when the legislature entrusts
to an authority the power to pass an order in its
discretion, an order passed by that authority in exercise of
that discretion is, in general, not liable to be interfered
with by an appellate court, unless it can be shown to have
been based on some mistake of fact or misapprehension of the
principles applicable thereto. The appellant contends that
the orders under appeal are based on mistakes and
misapprehensions, and are therefore liable to be reversed,
and that contention must now be examined. The grounds on
which the orders of the courts below are based are (1) that
there has been considerable delay on the part of the
appellant in moving in the matter, (2) that as in the
proceedings taken under section 488 the respondent has been
fined, an order for demolition was not called for, and (3)
that the breach of the building rules has not resulted in
any inconvenience to the public, nor has there been any
complaint from the residents of the locality about this.
The materials placed before us do not show
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
(1) [1905] I.L.R. 33 Cal. 287.
127
1004
that there has been any great delay on the part of the
appellant, The learned Judge has stated that the present
proceedings for demolition were taken subsequent to the
imposition of fine on 11-4-1951 in the proceedings under
section 488. This is a mistake. The proceedings under
section 363 bad been commenced as early as February 1951
when notice was issued to the respondent under the
provisions of that section, and the petition was actually
filed in court on 4-4-1951. It is true that the proceedings
were pending for nearly two years before the Magistrate, but
as observed by the learned Chief Justice, far from the
Corporation being responsible for it, it appears to have
been the victim of delay on the part of the respondent.
Both the courts below have mainly based their order on the
fact that the, Corporation having taken proceedings under
section 488 and a fine having been imposed on the
respondent, it would be unjust to impose a further penalty
for the same offence by way of demolition. The assumption
on which this reasoning rests is that the charge on which
the present proceedings have been taken is the same as that
on which the petition under section 488 was laid. But, as
already pointed out, that is not correct. The proceedings
under section 488 were taken for erecting a building without
permission whereas the present proceedings are taken
substantially for breaches of the building rules, which are
quite independent of the charge under Rule 62, and the
respondent is therefore not punished twice over for the same
default. The learned Judge observes that this was not a fit
case for exercising the discretion in favour of the
appellant, because in the prior proceedings under section
488, it did not ask for an order for demolition, nor was
such an order made by the Magistrate. That is obviously
with reference to section 536 which we have held to be
inapplicable to the present case. Moreover , when that
section enacts that the Magistrate could both impose a fine
and order demolition of the building, that clearly indicates
that the fact that a fine has been imposed should not by
itself and with-
1005
out more, be taken as sufficient ground for refusing
demolition.
The courts below were also influenced by the fact that there
was no complaint from the neighbours about the erection of
the building. It must be remembered that the building rules
are enacted generally for the benefit of the public, and
where those rules have been violated and proceedings are
taken for an order for demolition of the building under
section 363, what has to be decided is whether the breaches
are of a formal or trivial character, in which case the im-
position of a fine might meet the requirements of the case,
or whether they are serious and likely to affect adversely
the interests of the public, in which case it would be
proper to pass an order for demolition. Whether there has
been a complaint from the public would not as such be
material for deciding the question, though if there was one,
it would be a piece of evidence in deciding whether the
interests of the public have suffered by reason of the
breaches.
The position, therefore, is that the orders of the courts
below are based on mistakes and misdirections, and cannot be
supported. The conduct of the respondent in adopting a
hide-and-seek attitude in completing the constructions in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
deliberate defiance of the law calls for severe action. It
would be most unfortunate, and the interests of the public
will greatly suffer, if the notion were to be encouraged
that a person might with impunity break the building rules
and put up a construction and get away with it on payment of
fine. All this would be good justification for making an
order for demolition. But then, it is now nearly five years
since the building was completed, and though section 363(2)
which directs that no application for demolition shall be
instituted after a lapse of five years from the date of the
work does not, in terms, apply as the proceedings have been
started in time, we do not feel that after the lapse of all
this time, an order for demolition is called for in the
interests of the public. We also take into account the fact
that the orders in question would not have come before Us in
the normal course by way of appeal,
1006
were it not that the appellant desired that the decision of
this Court should be obtained on certain questions of
importance, and that purpose has been achieved. On a
consideration of all the circumstances, we do not think that
this is a fit case in which we should pass an order for
demolition. We should, however, add that we find no
justification for the strictures passed on the appellant by
the court below.
In the result, the appeal is dismissed.