Full Judgment Text
NEUTRAL CITATION No.2023:DHC:3610
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Reserved on : 18 April, 2023
th
Pronounced on: 24 May, 2023
+ O.M.P.(I) (COMM.) 41/2023 and I.A. Nos. 4029/2023, 6536/2023
and 6537/2023
ROADWAY SOLUTIONS INDIA INFRA LIMITED
..... Petitioner
Through: Mr.Rajiv Nayar, Senior Advocate
with Mr.Nirav Shah, Mr.Sourabh
Seth, Ms.Prachi Garg, Mr.Varun
Kalra and Mr.Krishan Kumar and
Mr.Saurabh Seth, Advocates
versus
NATIONAL HIGHWAY AUTHORITY OF INDIA
..... Respondent
Through: Mr.Parag P. Tripathi, Senior
Advocate with Mr.Ankur Mittal,
Mr.Abhay Gupta, Ms.Vasundhara
and Mr.Raushal Kumar, Advocates
CORAM:
HON’BLE MR. JUSTICE CHANDRA DHARI SINGH
J U D G M E N T
CHANDRA DHARI SINGH, J.
1. The instant petition under Section 9 of the Arbitration and
Conciliation Act, 1996 (hereinafter “the Act”) has been filed on behalf of
the petitioner seeking the following reliefs:
“(a) Pass an order staying the operation and effect of the
Notice dated 31.01.2023 of intent to terminate the
O.M.P.(I) (COMM.) 41/2023 Page 1 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
Contract issued by the Respondent to the Petitioner, and
restrain the Respondent from acting upon the said notice
pending the completion of the dispute resolution process
set out in Clause 67 of Conditions of Particular
Application in the Contract;
(b) Issue ex-parte ad interim stay to restrain the
Respondent, its principal officers, servants, agents and
all other acting for, and on their behalf, from invoking
and encashing the following bank guarantees submitted
by the Petitioner and its group concerns:
a. Performance Security Bank Guarantee dated
27.06.2022 bearing No. TTGGPGE221780068 issued
for an amount of Rs. 12,29,10,754/- by the Petitioner;
b. Additional Performance Security Bank Guarantee
dated 27.06.2022 bearing No. TTGGPGE221780066
issued for an amount of Rs. 3,51,37,643/- by the
Petitioner.
(c) Direct the Respondent to maintain status quo with
respect to the Performance Security Bank Guarantee
dated 27.06.2022 and Additional Performance Security
Bank Guarantee dated 27.06.2022, pending
determination of subject matter of dispute between the
parties in accordance with the terms of the Contract;
(d) Pass ad-interim orders reliefs in terms of the above
prayer;
(e) Pass any other order/direction which this Hon'ble
Court may deem just, fair and equitable in the
circumstances.”
FACTUAL MATRIX
2. The petitioner i.e. Roadway Solutions India Infra Limited is a
company incorporated under the provisions of the Companies Act, 2013,
having its registered office at SN-29 HN-20 Kondhwa Kd. Nr. Kubex
Soc. Nr. Shera School, Pune, Maharashtra - 411048. The petitioner is a
construction company having a wide experience in the construction of
O.M.P.(I) (COMM.) 41/2023 Page 2 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
roadways. The respondent i.e. National Highway Authority of India was
set up by the NHAI Act, 1988, as an autonomous agency of the
Government of India. The respondent invited bids for
strengthening/overlaying on Six Lane Gurgaon – Kotputli – Jaipur
section of NH-48 (Old NH-8) from Km 107+100 to Km 273+000 of main
carriage way (MCW) and additionally, about 312 Km both sides of
service road project in the State of Rajasthan at the risk and cost of
Concessionaire on item rate basis (percentage basis project). In August
2021, the petitioner also took part in said bid and being the lowest bidder,
the Letter of Award No. NHAI/NHDP-V/MC-II/Gur-Jpr/Raj/Item
th
Rate/2021 (Pt-1)/E-138079/55406 dated 30 May, 2022 (LOA) was
issued in favour of the petitioner.
th
3. On 19 July, 2022, the petitioner and respondent entered into item
rate Contract/Agreement (Contract), thereby materializing the terms and
th
conditions to carry out the works under the project. On 27 July, 2022,
the respondent issued the Notice of Commencement and declaration of
th
commencement date, whereby 27 July, 2022 was declared as the date of
commencement of the project. In terms of Clause 41.1 of the Conditions
of Particular Application (CoPA), the petitioner was supposed to
commence the works as soon as possible after the receipt of a notice from
the engineer.
th
4. The petitioner submitted the Performance Security dated 27 June,
th
2022 and Additional Performance Security dated 27 June, 2022,
amounting to Rs. 12,29,10,754/- (Rupees Twelve Crores Twenty Nine
Lakhs Ten Thousand Seven Hundred and Fifty Four Only) and Rs. 3,51,
37, 643/- (Rupees Three Crores Fifty One Lakhs Thirty Seven Thousand
O.M.P.(I) (COMM.) 41/2023 Page 3 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
Six Hundred and Forty Three Only) respectively to the respondent in the
form of bank guarantees in accordance with the Contract.
th
5. The petitioner commenced the maintenance work after 18 August,
th
2022. On 30 August, 2022, the Ministry of Road, Transport and
Highways (MoRTH) issued a circular with the objective of “adopting
worldwide best practice in engineering techniques in design, construction
th
and maintenance of highways, bridges and tunnels”. On 24 December,
2022, the petitioner submitted the mixed design of Reclaimed/Recycled
Asphalt Pavement (RAP) along with the Construction Methodology of
RAP for review and approval of the respondent. The petitioner sent a
rd
reminder letter dated 3 January, 2023 to the respondent seeking review
and approval of the RAP methodology for laying the road but the
respondent rejected the proposal for use of RAP.
th
6. The team leader/engineer issued a letter dated 11 January, 2023 to
petitioner stating therein that Dense Bituminous Macadam (DBM ) work
has been suspended by petitioner and asked for submission of work
th
programme. The respondent, on 17 January, 2023, rejected the use of
RAP material for DBM works stating that the same is not part of the Bill
of Quantities (BOQ ) under the Contract.
7. The petitioner was not satisfied with the decision by which the use
th
of RAP material was rejected vide letter dated 17 January, 2023, hence,
th
the petitioner issued the Mediation Notice dated 19 January, 2023 and
th
the Disputes Notice dated 19 January, 2023 to the respondent as per the
Contract.
th
8. On 20 January, 2023, the petitioner also raised objections towards
rejection of the use of RAP material for DBM works by the respondent.
O.M.P.(I) (COMM.) 41/2023 Page 4 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
9. The petitioner, in terms of Clause 60 of the Contract and Sub-
Clause 60 of the CoPA, had submitted the Interim Payment Certificate
th
(IPC-01) on 6 October, 2022 seeking release of 75% of the net payment
for the works done by the petitioner. The respondent did not consider the
request for releasing the payment to the petitioner in terms of Sub-Clause
th
60.2 of CoPA and only released 50% of the amount on 9 November,
2022. The 50% of the amount was accepted by the petitioner under
th
protest vide letter dated 04 January 2023.
th
10. The respondent, on 17 January, 2023, sent a Notice alleging
defaults of the petitioner under the Contract. In reply to the notice, the
th
petitioner sent a letter dated 24 January, 2023 and denied all the
allegations mentioned in the notice.
st
11. The respondent issued a notice of termination dated 31 January,
2023 under Clause 63.1 of CoPA, giving a notice of 14 days, upon the
expiry of which the respondent was automatically entitled to terminate
the contract. The petitioner sent a reply to the said notice vide response
th
dated 4 February, 2023. Thereafter disputes arose between the parties. It
is the respondent‟s case that due to non-performance on the part of the
petitioner which showed no progress in executing works even after lapse
th st
of six months (from 27 July, 2022 to 31 January, 2023) and after
repeated reminders, the respondent was left with no option but to issue
Notice of Intention To Terminate (NITT) . This contention was
vehemently refuted by the petitioner and it is under these circumstances
that the petitioner, aggrieved by such action, has approached this Court
through the present petition.
O.M.P.(I) (COMM.) 41/2023 Page 5 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
SUBMISSIONS
(On behalf of the petitioner)
12. Mr. Rajiv Nayar, learned senior counsel appearing on behalf of the
th
petitioner submitted that vide letter dated 18 August, 2022, the petitioner
asked for review and approval, the Work Program, Quality Assurance
Program and Construction Methodology, to the respondent in terms of
Clause 14.1 of the Contract. It is also submitted that the respondent
unilaterally took the decision regarding fixing the date of commencement
th
of the project on 27 July, 2022 despite there being no clarity on the
items to be executed, the stretch where work was to be executed and
quantities of the materials to be deployed. The petitioner thereafter
commenced the maintenance work such as pothole filling, patchwork,
drain cleaning, median maintenance, dewatering of stagnant water from
water-logged areas in MCW, etc.
13. Mr. Nayar, learned senior counsel appearing on behalf of the
th
petitioner submitted that on 30 August, 2022, the Ministry of Road
Transport and Highways (MoRTH) issued a circular with the objective of
"adopting worldwide best practice in engineering techniques in design,
construction and maintenance of highways, bridges and tunnels". He also
referred to the aforesaid circular and relied upon some provisions which
are relevant for the purpose of maintenance and construction of the
highways which are as follows:
''Further, the need is felt to adopt value engineering
practices in design, construction and maintenance with
regards to use of materials and technology as an n important
and vital step to meet the sustainable development of the NH
network throughout the country in a cost-effective manner
O.M.P.(I) (COMM.) 41/2023 Page 6 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
with improved durability & safety, de-carbonise & grow,
reduction in project execution timeline, increase in quality
and reduction in maintenance.
2. The value engineering is very crucial for sustainable
highway development. It is a systematic method to achieve
the targeted function of the highway at the lowest whole-of-
life cost without compromising on functionality, quality,
performance, safety and aesthetics. Value Engineering
practices aim at optimizing the value of the project at
various stages viz. project inception, project preparation,
Project bidding stage, project implementation and
maintenance management to achieve at least one or all of
the .following objectives:
a. Increasing the speed of construction without
compromising the quality
b. Reducing the cost of construction and maintenance
c. Improving asset durability
d. Improving aesthetics
e. Enhanced safety
f. Promoting environmental sustainability
g. increasing resilience to climate change and
h. Lowest life cycle cost
3. Value engineering can be applied at any point in a
project, even in construction. However, the earlier it is
applied the higher is the return of the time and effort
invested and also the acceptance. As per the World Bank
report on the Indian Road Construction Industry, it has been
established that the savings realized by undertaking value
engineering exercises can be in the order of 10.15% of the
cost of the originally designed project.
……………
5.3. Further during implementation, the concessionaire/
contractors shall be allowed to propose value-engineered
alternative design/material/technology. IE/AE shall review
O.M.P.(I) (COMM.) 41/2023 Page 7 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
the proposed value-engineered design and if it is not
reviewed within the stipulated time period specified in the
contract/concession Agreement or rejected for any frivolous
reason, Authority may take appropriate action against the
IE/AE
…………
7.4 Reuse of Reclaimed Bituminous layer material (RAP) of
existing flexible Pavement"
14. It is also argued that since the MoRTH Circular was binding on all
ongoing and upcoming projects with immediate effect, pursuant to the
th th
MoRTH Circular dated 30 August, 2022, on 24 December, 2022, the
petitioner submitted the mixed design of Reclaimed/Recycled Asphalt
Pavement (RAP) alongwith the Construction Methodology of RAP for
review and approval of the respondent. The respondent had not sent any
response to the said letter. The petitioner again sent a reminder letter to
the respondent seeking review and approval of the RAP methodology for
th
laying the road. On 7 January, 2023, the engineer/team leader, in terms
of its duties under Clause 2.1 of the Contract, gave its recommendations
for the use of RAP for the use of DBM works in the Project. It is
vehemently submitted that almost after a period of two months, the
respondent rejected the proposal for use of RAP contrary to MoRTH
Circular despite the approval given by the engineer/team leader vide
th
letter dated 7 January, 2023.
15. It is submitted that while adjudication of RAP technology was
pending before the respondent, the team leader/engineer proceeded to
th
issue a letter dated 11 January, 2023 to the petitioner stating therein that
O.M.P.(I) (COMM.) 41/2023 Page 8 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
the DBM work has been suspended by the petitioner which is clearly
contrary to the facts of the case.
16. Learned senior counsel appearing on behalf of the petitioner
th
referred to the minutes of meeting dated 16 January, 2023 and submitted
that the petitioner and respondent discussed the use of RAP material for
DBM works in the said meeting. Initially, the respondent took a stand
that the use of RAP material is not a part of the BOQ under the Contract.
However, after hearing the petitioner's explanation and considering
various circulars and notifications of the respondent and MoRTH, the
respondent instructed the petitioner to start the milling works and gave
them two days to provide the approvals of the said usage of RAP material
for doing DBM works.
17. It is vehemently submitted that the respondent rejected the use of
th
RAP materials on 17 January, 2023. Thereafter, the petitioner was left
th
with no option but to issue the Mediation Notice dated 19 January, 2023
th
and the Disputes Notice dated 19 January, 2023 to the respondent.
18. Learned senior counsel appearing on behalf of the petitioner
th
submitted that the Interim Payment Certificate (IPC-01) was issued on 6
October, 2022 seeking release of 75% of the net payment, for the work
done by the petitioner. The engineer/team leader scrutinized and
determined the value of the work done by the petitioner and
th
recommended the respondent for processing IPC-01 dated 12 October,
th
2022. It is also pointed out that in its email dated 19 October, 2022, the
respondent gave certain observations on the IPC-01. The same was duly
th
clarified by the engineer/team leader vide letter dated 19 October, 2022
and again recommendation was made by the engineer/team leader to the
O.M.P.(I) (COMM.) 41/2023 Page 9 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
concerned authority. The respondent again raised certain objections on
st
21 October, 2022 for the release of IPC-01.
19. It is submitted that the engineer/team leader had recommended to
the respondent to release of Rs. 12,61,99,153/- (Rupees Twelve Crores
Sixty One Lakhs Ninety Nine Thousand One Hundred Fifty Three Only)
in favour of the petitioner. It is further submitted that the respondent did
not consider the same in terms of Sub-Clause 60.2 of CoPA and released
only 50% of the amount i.e. Rs. 6,30,06,116/- (Rupees Six Crores Thirty
th
Lakhs Six Thousand One Hundred and Sixteen Only) on 9 November,
2022. The amount, which was released by the respondent contrary to the
provisions of the Contract, was accepted by the petitioner under protest
and the respondent was requested to release the remaining amount of the
IPC-01.
20. Learned senior counsel appearing on behalf of the petitioner
further submitted that the petitioner is not responsible for the delays in
the aforesaid project and is willing to complete the entire work as
awarded expeditiously. It is also submitted that the delay was caused due
to the reasons as stated above on behalf of the respondent.
21. Learned senior counsel appearing on behalf of the petitioner
submitted that in sheer violation of the terms of the Contract, the
respondent, instead of acting in terms of the arbitral mechanism
envisaged under Clause 67 of the CoPA and Contract and without
th
addressing the grievance raised in the Mediation Notice dated 19
January, 2023, unilaterally and arbitrarily issued the notice of intent to
st
terminate dated 31 January, 2023 under Clause 63.1 of CoPA giving a
O.M.P.(I) (COMM.) 41/2023 Page 10 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
notice of 14 days, upon the expiry of which it was entitled to terminate
the Contract.
22. It is submitted that in the aforesaid notice of intent to terminate
st
dated 31 January, 2023, the respondent made false allegations against
the petitioner pertaining to delay in carrying out of works at the project
owing to (i) shortage and non-availability of Bitumen at site, (ii) non-
submission of detailed drawings, (iii) breakdown of HMPs ( Hot Mixing
Plants ), and (iv) non-achievement of deadlines as per work program
th
dated 18 August, 2022.
23. It is further submitted that the allegation made in the notice of
th
intention to terminate were denied by the petitioner in the reply dated 4
February, 2023.
24. Learned senior counsel appearing on behalf of the petitioner
submitted that it had been falsely alleged that there was shortage and
non-availability of Bitumen at Site. It is submitted that the petitioner had,
at all times, the requisite material. However, since the process of carrying
out works i.e., the usage of RAP methodology for DBM works, was not
confirmed by the respondent, the material could not be brought to site. It
is further submitted that in fact, appropriate amount of Bitumen was
always available on site, the HMPs capacity was only 240 tonnes and for
the remaining work, the Bitumen could not be procured owing to the
pendency of approval of RAP. The Bitumen has certain requirements of
storage as per the plant's storage capacity, and hence cannot be stored
elsewhere.
st
25. It is submitted that the petitioner vide letter dated 1 November,
2022 submitted the third-party tests results for VG-40 for which a formal
O.M.P.(I) (COMM.) 41/2023 Page 11 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
source approval is still awaited from the respondent. However, the Job
rd
Mix Formula (JMF) was only approved by the respondent on 23
November, 2022. It is submitted that therefore, without the source
approval or JMF approval of the material to be procured, the Bitumen
could in no way be brought to the site.
26. It is submitted that petitioner's work progress was severely affected
for want of design and drawings of the balance works from the
Concessionaire, design and drawings of reconstruction stretches, and the
overlay stretches as per the engineering surveys which remained under
review with the engineer/team leader except for a 15 km. stretch for
which approval was received. Despite the same, the petitioner made all
the efforts for continuity of the works at the Project site and never
abandoned section of work. In fact, the petitioner mobilized additional
resources than required.
27. Learned senior counsel appearing on behalf of the petitioner
submitted that upon a bare perusal of the various correspondences, it is
evident that the respondent acted in a high-handed manner de hors the
provisions of the Contract and the applicable law. It is submitted that the
petitioner is not in default of any of its obligations under the Contract and
has always complied with the instructions of the respondent and the team
leader. The petitioner has expended huge costs for the performance of the
contract and has always been ready and willing to perform the contract.
28. It is submitted that the notice of intent to terminate the Contract
was issued by the respondent subsequent to the invocation of the dispute
resolution clause in the Contract by the petitioner to suppress lapses on
the part of the respondent. The said notice of intent to terminate was
O.M.P.(I) (COMM.) 41/2023 Page 12 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
issued without any application of mind and without consideration of the
various correspondences of the petitioner dealing with all baseless
allegations made by the respondent. It is submitted that the respondent
being machinery of the State is bound to act fairly and reasonably. It is
submitted that the petitioner has made out a prima facie case, thereby
making them entitled to the reliefs as prayed in the instant petition.
29. Learned senior counsel appearing on behalf of the petitioner
submitted that the instant Contract is at pre-termination stage and
currently not terminated, therefore, interim relief by way of Section 9 of
the Act may be granted.
30. It is submitted that there is no basis for issuance of Notice of Intent
st
to Terminate dated 31 January, 2023 as none of the provisions in the
Contract entitled the respondent to issue such a notice in the facts and
circumstances of the instant case. It is vehemently submitted that the
Contract is not per se a determinable contract and in any event, the
Government contracts are to be treated differently as there is an
obligation to act fairly and in an unarbitrary manner. It is submitted that
in the instant case, it is evident that the respondent has acted in arbitrary,
mala fide, illegal and unjust manner which is in derogation of the
Contract entered into between the parties. It is submitted that the present
Contract is still under effect and the petitioner is also ready and willing to
perform the Contract. In support of his arguments, he has placed reliance
on the following judgments i.e., A. Murugan and Ors. v. Rainbow
Foundation Ltd , 2019 SCC OnLine Mad 37961, DLF Home
Developers Limited Vs. Shipra Estate Limited and Ors , O.M.P. (I)
th
(COMM.) 209/2021 dated 08 November, 2021, Jumbo World
O.M.P.(I) (COMM.) 41/2023 Page 13 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
Holdings Limited and Anr vs. Embassy Property Developments Private
Limited , 2020 SCC OnLine Mad 61, Golden Tobacco Limited Vs.
Golden Tobie Private Limited O.M.P. (I) (COMM.)182/2021 dated
th
24 September, 2021, Atlas Interactive (India) Pvt. Ltd. Versus Bharat
Sanchar Nigam Limited & Anr. 2005 SCC OnLine Del 190, T.O.
th
Abraham Vs. Jose Thomas and Ors. R.F.A. No. 695 of 2015 dated 17
October 2017 , Kerala High Court, Indian Medicines Pharmaceuticals
Corporation Ltd. v. Kerala Ayurvedic Cooperative Society Ltd. & Ors.
2023 SCC OnLine SC 5, Gwalior-Jhansi Expressway Limited v.
National Highway Authority of India 2014 SCC OnLine Del 1124,
Pioneer Publicity Corporation v. Delhi Transport Corporation, (2003)
103 DLT 442, Simplex Infrastructures Ltd. v. National Highways
rd
Authority of India O.M.P.(I) Comm. 69/2023 dated 03 March, 2023 ,
Delhi High Court and Yassh Deep Builders LLP v. Sushil Kumar
Singh & Anr. 2023 SCC OnLine Del 1499.
31. It is submitted that the respondent is responsible for delaying the
approval of work programme, pending which, the petitioner cannot be
expected to continue carrying on the works in project. It is submitted that
the works were delayed as petitioner was asked to divert its resources
from Jaipur to Haryana, hence, the petitioner was required to expend
huge monies in mobilization of its resources and machinery based on the
directions of respondent, despite the same being outside scope of
Contract. The petitioner was further directed to execute works in
Rajasthan after completion of works in Haryana on account of emergency
flood like situation in Haryana.
O.M.P.(I) (COMM.) 41/2023 Page 14 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
32. It is submitted that the petitioner has already expended approx Rs.
80 crores in the project till date and out of total invoiced amount of Rs. 55
Crores, the respondent has only paid an amount of Rs. 11 crores. Despite
the huge outstanding amounts, the petitioner has always performed the
Contract and is ready and willing to complete the works stipulated in the
Contract.
33. Learned senior counsel appearing on behalf of the petitioner
submitted that the issuance of the new tender to another contractor would
be a heavy burden on the public exchequer. In fact, owing to huge
variation in the quantities of Milling, WMM, DBM, and other safety
items, the original BOQ price of Rs 409.76 Crores has increased by
around Rs. 318.03 Crores taking the total cost of the Project to Rs 727.80
Crores. In case a new tender is floated, owing to paucity of time, the same
would be awarded at the cost of over Rs 1000 Crores, therefore, costing
the public exchequer Rs. 250 Crores more than the present contract value.
It is further submitted that if a new tender is floated, it will take
substantial time to appoint a new contractor which will be an antithesis to
public interest.
34. Mr. Nayar, learned senior counsel appearing on behalf of the
petitioner vehemently argued that the operation of the impugned Notice
st
of Intention to Terminate dated 31 January, 2023 may be stayed till the
adjudication of the disputes between the parties by the Arbitrator.
35. Mr. Nayar, learned senior counsel appearing on behalf of the
th
petitioner mentioned the instant matter on 10 May, 2023 and supplied
the judgment passed by this Court in Fedders Electric and Engineering
Limited v. Srishti Constructions 2023 SCC OnLine Del 2356. He has
O.M.P.(I) (COMM.) 41/2023 Page 15 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
relied on paragraph 28 which is reproduced herein under:
“28. Under Section 9 (3) of the Act only in exceptional
circumstances, during the arbitration proceedings, the Court
should intervene only when the Arbitral Tribunal cannot
render an effective remedy under Section 17 of the Act This
position of law of law has been held and reiterated in a
plethora of judgments Energo Engineering Projects Ltd. v.
TRF Limited 2016 SCC Online Del 6560, M. Ashraf v.
Kasim V.K (2018) SCC OnLine Ker 4913, Srei Equipment
Finance Limited (Sefl) v. Ray Infra Services Private Limited
& Anr. (2016) SCC OnLine Cal 6765 , Avantha Holdings
Limited v. Vistra ITCL India Limited 2020 SCC OnLine Del
1717. Recently held by the Hon’ble Supreme Court in the
case of Arcelor Mittal Nippon Steel India Ltd. v. Essar Bulk
Terminal Ltd., Special Leave Petition (Civil) No.13129 of
2021, decided on 14th September 2021 as follows:
“62. Sub-Section (3) of Section 9 has two limbs. The
first limb prohibits an application under sub-Section
(1) from being entertained once an Arbitral Tribunal
has been constituted. The second limb carves out an
exception to that prohibition, if the Court finds that
circumstances exist, which may not render the remedy
provided under Section 17 efficacious.
63. To discourage the filing of applications for interim
measures in courts under Section 9(1) of the
Arbitration Act, Section 17 has also been amended to
clothe the Arbitral Tribunal with the same powers to
grant interim measures, as the Court under Section
9(1). The 2015 Amendment also introduces a deeming
fiction, whereby an order passed by the Arbitral
Tribunal under Section 17 is deemed to be an order of
court for all purposes and is enforceable as an order of
court.
64. With the law as it stands today, the Arbitral
Tribunal has the same power to grant interim relief as
the Court and the remedy under Section 17 is as
O.M.P.(I) (COMM.) 41/2023 Page 16 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
efficacious as the remedy under Section 9(1). There is,
therefore, no reason why the Court should continue to
take up applications for interim relief, once the
Arbitral Tribunal is constituted and is in seisin of the
dispute between the parties, unless there is some
impediment in approaching the Arbitral Tribunal, or
the interim relief sought cannot expeditiously be
obtained from the Arbitral Tribunal.”
36. The learned senior counsel for the petitioner submitted that in the
light of the judgment of this Court in Fedders(Supra) , since the Arbitral
Clause has already been invoked, therefore, this Court may pass the
order that the instant petition under Section 9 of the Act may be treated as
application under Section 17 of the Act before the learned Arbitrator.
(on behalf of the respondent)
37. Mr. Parag Tripathi, learned senior counsel appearing on behalf of
the respondent vehemently opposed the instant petition and submitted
that the instant petition is devoid of any merit and is liable to be
dismissed. It is submitted that instant petition is premature since no cause
of action has arisen in favour of the petitioner to file the same. It is
submitted that as per Clause 63.1 of the CoPA, the termination after
giving 14 days‟ notice is not inevitable but the use of the word „may‟
clearly show that the employer may or may not terminate the agreement.
Therefore, the respondent cannot be prevented from acting in terms of the
Contract and take recourse to appropriate action based on process laid
down therein.
38. Learned senior counsel appearing on behalf of the respondent,
st
during the arguments, referred to the letter dated 31 January, 2023 and
O.M.P.(I) (COMM.) 41/2023 Page 17 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
submitted that the contents clearly show complete lack of performance on
the part of the petitioner.
39. Mr. Tripathi submitted that the approval of the revised work
programme by the team leader was withdrawn by the engineer concerned
th th
vide letter dated 15 February, 2023, therefore, the letter dated 8
February, 2023 issued by the team leader to revise programme no longer
exists after withdrawal of the same by the engineer as stated above.
40. It is further submitted that as per the letter issued by the engineer,
team leader was not even competent to approve the revised work
programme as per Clauses 14.1/14.2 of the CoPA. As per the said
clauses, the work programme is to be submitted to the engineer for his
consent, therefore, any approval by team leader to any revised work
programme is extra-contractual and non-est .
41. Learned senior counsel appearing on behalf of the respondent
submitted that the revised work programme is not even realistic,
inasmuch as, petitioner has shown much less quantity of work to be
executed during the working season as compared to rainy season. During
the arguments, learned senior counsel for the respondent referred the
comparison chart which is as under:
| As per revised work programme dated 18.01.2023 | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| item | Working season | Rainy season | |||||||||
| Jan | Feb | March | April | May | Avg.<br>(per<br>month) | June | July | Aug | Sept | Avg.<br>(per<br>month) | |
| GSB | 0 | 1039 | 1039 | 1039 | 1039 | 831.2 | 1039 | 1039 | 1039 | 1039 | 1039 |
| WMM | 0 | 2138 | 2138 | 2138 | 2138 | 1710.4 | 2138 | 2138 | 2138 | 2138 | 2138 |
| DBM | 1445 | 2890 | 14452 | 16590 | 16590 | 10393.4 | 16590 | 16590 | 16590 | 23816 | 18396.5 |
| BC G-I | 0 | 0 | 0 | 0 | 24395 | 4879 | 12970 | 12970 | 24395 | 24395 | 18682.5 |
| BC G-II | 0 | 0 | 0 | 0 | 0 | 0 | - | - | - | 16612 | 4153 |
O.M.P.(I) (COMM.) 41/2023 Page 18 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
| DIC | 0 | 0 | 0 | 200 | 200 | 80 | 200 | 254 | - | - | 113.5 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| PQC | 0 | 0 | 0 | 0 | 333 | 66.6 | 333 | 352 | - | - | 171.25 |
42. It is submitted that the aforesaid chart sufficiently demonstrates
that the revised work plan is unrealistic, impractical and without any basis
and without considering the fact that there would be disruption in doing
bituminous work during rainy season. It is further submitted that even as
on date, the petitioner still does not have bitumen available at site. It is
therefore submitted that the team leader had wrongly approved the
revised work program being completely contrary to the ground reality and
without looking into the facts that insufficient resources were available at
the site.
43. It is submitted that the petitioner had sought for approval for DBM
st rd
only on 1 November, 2022 which was granted by SC/AE on 23
rd
November, 2022. It is further submitted that despite the approval on 23
November, 2022, the petitioner was not able to complete the given
th
stretch. As on 16 February, 2023, the progress on the above stretch was
just 10.474 Km, therefore, there is no force in the contention of the
petitioner that there was no delay on his part for completion of the
project.
44. It is submitted that contract price for the said work is Rs. 409.77
Crores, and comprises of various maintenance works such as renewal and
strengthening of pavement, repair and maintenance of earthen shoulder,
establishment of shoulder, road furniture etc. in the entire stretch of six
lane carriageway from Km. 107.100 to Km. 273.000 of NH-48. It is
further submitted that the stipulated period for completion of work was
th
18 months and the commencement date of the project was 27 July, 2022.
O.M.P.(I) (COMM.) 41/2023 Page 19 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
45. It is submitted that the financial value of work done by the
th
contractor upto 15 February, 2023 is Rs. 8.03 Crores i.e. only 1.95% of
the total amount of Rs. 409 crores which have been spent and the physical
progress of the work is 10.472 Km length of DBM on single side
carriageway of 6-lane out of 161.2 km. It is vehemently submitted that
the aforesaid facts and figures leave no scope of doubt that petitioner is
far behind schedule and any overrated revised work programme without
any basis, cannot meet up the pace to execute work of about Rs. 400
crores in the balance period of 11 months and make up for the loss of
time.
46. Learned senior counsel appearing on behalf of the respondent
submitted that there is no force in the argument of learned senior counsel
for the petitioner that without invoking Clause 67, the notice under
Clause 63.1 could not be issued. It is submitted that on mere perusal of
the Clause 67, it is clear that there is no embargo on party to exercise its
right under any other clause. i.e. Clause 63.1. It is also submitted that the
petitioner raised dispute regarding non-approval of RAP, whereas, NHAI
has been constrained to issue notice under Clause 63.1 due to non-
performance of petitioner. It is further submitted that no dispute has been
raised regarding alleged delay on the part of the respondent, therefore,
merely because petitioner has invoked dispute resolution clause, it cannot
restrain the respondent from exercising its rights as may be available to it
under the Contract.
47. Learned senior counsel appearing on behalf of the respondent
vehemently submitted that the Contract in question is determinable in
nature, hence in view of specific statutory provision under the Specific
O.M.P.(I) (COMM.) 41/2023 Page 20 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
Relief Act, 1963 no injunction could be granted to direct the respondent
to specifically perform the contract. It is submitted that by virtue of
Section 14(1)(c) of Specific Relief Act, 1963 (SRA), the contract which
in its nature determinable cannot be specifically enforceable. He has
relied upon several judgments to strengthen his arguments:
i . Indian Oil Corporation Ltd. v. Amritsar Gas Service, 1991 (1)
SCC 533.
ii . Rajasthan Breweries Limited v. The Stroh Brewery Company ,
2000 SCC OnLine Del 481.
48. It is also submitted that if eventually the termination is held illegal,
then also, in view of provisions of Section 41(e) of SRA, the petitioner is
not entitled for any interim order of stay of intention to terminate.
49. It is contended that the Clause 63.1 of the Contract Agreement
provides for termination of the Contract, subject to a 14-days‟ notice by
the respondent on account of concessionaire‟s default. It is further
contended that the CoPA permits NHAI to terminate the agreement in
two circumstances, firstly, under Clause 63.1(a) of CoPA, if the petitioner
fails to carry out any obligation under the Contract and secondly, under
Clause 63.1(f) of CoPA when the petitioner, despite previous warning
from the engineer, in writing, is otherwise persistently or flagrantly
neglecting to comply with any of his obligations under the Contract.
50. It is submitted on behalf of the senior counsel for the respondent
that NHAI and the engineer were repeatedly pointing out to petitioner
that it has miserably failed to carry out its obligations under the contract.
It is further submitted that despite multiple notices/ reminders including
rd
Independent Engineer letter no. 225 dated 03 December 2022,
O.M.P.(I) (COMM.) 41/2023 Page 21 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
th
Independent Engineer letter no. 237 dated 05 December 2022,
th
Independent Engineer letter no. 285 dated 28 December 2022,
th
Independent Engineer letter no. 344 dated 17 January 2023 and
th
Independent Engineer letter no. 352 dated 20 January 2023, no progress
was made by the petitioner. It is therefore, submitted that the respondent
is well within its right to proceed with the intended termination of the
contract. Under Section 14(d) of the SRA, such a determinable contract
cannot be specifically enforced by seeking injunction against proposed
action of termination of contract.
51. Learned senior counsel appearing on behalf of the respondent, in
support of his arguments on the aspect that the Contract was determinable
in nature, it could not be revived or restored by the Court and no specific
performance of the contract could be directed. He placed reliance on the
judgments of Inter Ads Exhibition v. Busworld International 2020 SCC
OnLine Del 2485 , Indian Oil Corporation Ltd. (Supra) , Rajasthan
Breweries Ltd. v. the Stroh Brewery Co . AIR 2000 Del 450, MIC
Electronics Ltd. v. Municipal Corporation of Delhi , 2011 SCC OnLine
Del 766, D.R. Sondhi v. Hella KG Hueck & Co. 2011 SCC OnLine Del
1273, Country Development v. Brookside Resort 2006 SCC OnLine Del
200, Progressive Constructions Ltd. v. Chairman, National Highways
Authority of India , 2009 SCC OnLine Del 195, Jindal Steel and Power
Limited v. M/s SAP India Pvt. Ltd 2015 SCC OnLine Del 10067,
Bharat Catering Corporation v. IRCTC 2009 SCC OnLine Del 3434,
Bharat Catering Corporation v. IRCTC 2009 SCC OnLine Del 1613
and Turnaround Logistics (P) Limited v. Jet Airways (India) & Ors.,
2006 SCC OnLine Del 1872.
O.M.P.(I) (COMM.) 41/2023 Page 22 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
52. Learned senior counsel appearing on behalf of the respondent
submitted that Sections 20A and 41(ha) of the SRA express the
legislative intent to not grant injunctions in relation to Infrastructure
Projects where delay may be caused by such an injunction. It is further
submitted that in the present case if an injunction is granted by this Court
to the petitioner who was a continuous non-performer, the same would
lead to significant delays in the infrastructure project.
53. It is asserted that this Court in the case of Hari Ram Nagar v. DDA
2019 SCC OnLine Del 9747 held that in a suit or proceedings, where an
injunction may result in delay of the Infrastructure Projects, then the
Courts shall in normal course not grant an injunction as per the SRA. It is
humbly submitted as per the documents on record, the petitioner has
failed to achieve their scheduled targets.
54. It is submitted that the contention of petitioner is erroneous as in a
period of more than 8 months, the petitioner has only completed about
10.47 km (one side) of Main carriage way out of 322.4 km (both side). It
is therefore submitted that, if any injunction is granted and petitioner,
who is a complete non-performer, is allowed to work, such continuance
would cause delay in the progress of infrastructure project.
55. Learned senior counsel appearing on behalf of the respondent
submitted that considering the importance of the subject Highway and the
urgency in this regard, NHAI would re-tender the works in an expedited
format within a period of 7 days.
56. It is lastly contended that if the petitioner is granted stay and is
allowed to continue, it would tantamount to granting the final relief.
57. Learned senior counsel appearing on behalf of the respondent
O.M.P.(I) (COMM.) 41/2023 Page 23 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
further submitted that on other hand, if the action of respondent is held to
be bad, eventually the petitioner can always be suitably compensated in
terms of damages. Therefore, neither the balance of convenience is in
favour of petitioner nor the petitioner would suffer irreparable loss in case
the injunction is refused. Therefore, the instant petition has no merits and
is liable to be dismissed.
ANALYSIS AND FINDINGS
58. Section 9 of the Arbitration and Conciliation Act, 1996 is set out
hereinbelow for convenience:
“ 9. Interim measures, etc., by Court. (1) A party may,
before or during arbitral proceedings or at any time after
the making of the arbitral award but before it is enforced in
accordance with section 36, apply to a court—
(i) for the appointment of a guardian for a minor or person
of unsound mind for the purposes of arbitral proceedings; or
(ii) for an interim measure of protection in respect of any of
the following matters, namely:—
(a) the preservation, interim custody or sale of any
goods which are the subject-matter of the arbitration
agreement;
(b) securing the amount in dispute in the arbitration;
(c) the detention, preservation or inspection of any
property or thing which is the subject-matter of the
dispute in arbitration, or as to which any question
may arise therein and authorising for any of the
aforesaid purposes any person to enter upon any land
or building in the possession of any party, or
authorising any samples to be taken or any
observation to be made, or experiment to be tried,
which may be necessary or expedient for the purpose
of obtaining full information or evidence;
(d) interim injunction or the appointment of a
O.M.P.(I) (COMM.) 41/2023 Page 24 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
receiver;
(e) such other interim measure of protection as may
appear to the Court to be just and convenient,
and the Court shall have the same power for making orders
as it has for the purpose of, and in relation to, any
proceedings before it.
(2) Where, before the commencement of the arbitral
proceedings, a Court passes an order for any interim
measure of protection under sub-section (1), the arbitral
proceedings shall be commenced within a period of ninety
days from the date of such order or within such further time
as the Court may determine.
(3) Once the arbitral tribunal has been constituted, the
Court shall not entertain an application under sub-
section (1), unless the Court finds that circumstances exist
which may not render the remedy provided under section 17
efficacious.”
59. Section 9 as originally enacted has been renumbered as Section
9(1) by the Arbitration and Conciliation (Amendment) Act (Act 3 of
rd
2016) with effect from 23 October 2015. The said 2015 amendment also
incorporated sub-section (2) and sub-section (3) as reproduced above.
60. While there is no denying of the fact by either party that the project
has suffered immensely and there has been dismal progress in work, both
the parties have claimed the reasons attributable for the same to the
delays/omissions on the part of the other.
Relevant submissions made on behalf of the petitioner and respondent
are briefly described hereunder for purpose of proper adjudication of
the instant case:
61. It was contented by the petitioner that the petitioner always
complied with the Contract and is ready to willing to perform the
O.M.P.(I) (COMM.) 41/2023 Page 25 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
contract. However, since the Contract contained reciprocal obligations,
until the respondent performed its obligations, the petitioner is unable to
proceed further with the execution of works. It was also submitted that
the respondent issued a Notice of Commencement without any readiness
and preparedness. Despite this, the petitioner complied with the Contract
and performed its obligations without any delay.
62. As per the petitioner, the delay in progress of works is attributable
to respondent owing to delayed approvals. According to the petitioner,
th
the work programme dated 18 August, 2022 was submitted in terms of
original BOQ and with the consideration that the reciprocal obligations of
the independent engineer/respondent were fulfilled before starting the
th
construction works. While the contract was signed on 19 July, 2022 and
th
the commencement date was fixed as 27 July, 2022, however, it is only
rd
on 23 November, 2022 that the team leader gave approval for DBM and
BC for km 107+100 to km 125+00 resulting in delay of 4 months. It is
also argued on behalf of the petitioner that the respondent was also guilty
of delaying the approval of work program, pending which, the petitioner
could not have been expected to continue carrying on the work in project.
th
The petitioner has also relied on the letter dated 8 February, 2023 to
contend that upon approval of the revised work program by team leader,
the entire basis of the dispute raised by the respondent through its NITT
would stand negated and any termination after approval of the revised
work program would be illegal. It was submitted by the respondent that
the team leader had no authority to approve the revised work programme.
It was submitted that the engineer had already issued a show cause
th
notice/letter dated 13 February, 2023 to team leader to explain his
O.M.P.(I) (COMM.) 41/2023 Page 26 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
conduct in the peculiar circumstances and that the engineer vide its letter
th
dated 15 February, 2023 had withdrawn/revoked the approval granted
by team leader to the revised programme.
63. It was contended by the petitioner that despite the Circular issued
th
by Ministry of Road and Transport on 30 August, 2022 mandating RAP
technology, the respondent belatedly withdrew the approval granted for
usage of RAP technology in execution of works. The time taken in initial
approval and thereafter rejection of RAP technology resulted in huge
wastage of time for no fault of the petitioner. Per contra , it is the
respondent's case that when the petitioner sought approval for RAP, the
team leader categorically recorded that RAP was not mentioned in BOQ.
The team leader did not give any approval as has been suggested by the
petitioner. It was further submitted that the petitioner on one hand alleged
that work was to be executed under respondent's direction but at the same
time extra-contractually insisted on RAP which was never approved.
64. It is also the case of the petitioner that it was required to expend
huge monies in mobilization of its resources and machinery to Haryana
based on the directions of the respondent despite the same being outside
the scope of the Contract. The petitioner was directed to execute works in
Rajasthan after completion of works in Haryana on account of emergency
flood-like situation in Haryana. Having itself directed, the petitioner had
to divert its resources i.e. equipment, machinery, personnel, etc. from the
project site to Haryana because of the flood like situation, therefore, the
petitioner could not be held responsible for any delay. It was also
submitted that it is inconceivable as to how the respondent can make
allegation of delay against the petitioner when the respondent itself
O.M.P.(I) (COMM.) 41/2023 Page 27 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
directed the petitioner to divert its resources from the project site to
Haryana.
65. At last, the petitioner submitted that the issuance of the new tender
to another contractor would cast a heavy burden on the public exchequer
and is against public interest. Further, if a new tender is floated, it will
take substantial time to appoint a new contractor, which will be an
antithesis to public interest.
66. The petitioner also averred that the Contract is not per se a
determinable contract. It was submitted that the present Contract is still
under effect and has not been terminated and the petitioner is ready and
willing to perform the Contract. As far as the NITT is concerned, it is
merely communicating an intention to terminate the Contract and has
been issued under Sub-Clause 63.1 of CoPA giving 14 days' time to the
petitioner to show cause as to why the Contract should not be terminated.
th
The said Notice has been duly replied to by the petitioner on 4 February,
2023. In support of his contention, the learned senior counsel for the
petitioner relied upon several judgments and judicial pronouncement in
the foregoing paragraphs. It is submitted that the contracts were classified
in five broad categories which included contracts that are terminable
unilaterally on "without cause" or "no fault" basis. Contracts that are
terminable subject to a breach notice and granting an opportunity to cure
the breach are not determinable in nature although they can be terminated
under specific circumstances.
67. It was further contended on behalf of the petitioner that in any
event, Government contracts are to be treated differently as there is an
obligation to act fairly and in an unarbitrary manner, being a machinery
O.M.P.(I) (COMM.) 41/2023 Page 28 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
of the State. Learned senior counsel for the respondent argued before this
Court that the Contract is determinable in nature, hence, no injunction can
be granted by way of specific performance. As per the respondent, Clause
63.1 of the Contract provides for termination of the Contract subject to a
14 days‟ notice by respondent on account of concessionaire default.
Clause 63.1 (a) and (f) permits respondent to terminate the agreement in
the following event i.e. (i) Clause 63.1(a) fails to carry out any obligation
under the contract and (ii) Clause 63.1(f) despite previous warning from
the engineer, in writing, is otherwise persistently or flagrantly neglecting
to comply with any of his obligations under the contract. The respondent
and the engineer were repeatedly pointing out to the petitioner that it had
miserably failed to carry out its obligations under the Contract and that
despite multiple notices/reminders including Independent Engineer letter
rd th th th
dated 3 December, 2022, 5 December, 2022, 28 December, 2022, 17
th
January, 2023 and 20 January, 2023, no progress was made by the
petitioner. Thus, the respondent was well within its right to proceed with
the intended termination of the Contract. In view of Section 14(d) of the
SRA, such a determinable Contract cannot be specifically enforced by
way of seeking injunction against proposed action of termination of
Contract. In support of his arguments, the respondent also relied on
several judgments as mentioned in the foregoing paragraphs.
68. It is also the case of the petitioner that the respondent had not
issued the NITT in terms of Clause 46.1 and that as such its issuance was
illegal. As per the petitioner, issuance of NITT required the respondent to
issue the notices under Clause 46.1 and Clause 37.4 of the GCC which
were not complied with by the respondent. Further, NITT could not have
O.M.P.(I) (COMM.) 41/2023 Page 29 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
been issued pending dispute resolution mechanism invoked by the
petitioner prior to issuance of the NITT. Per contra , learned senior
counsel for the respondent submitted that no notice under Clause 46.1
was required before issuing NITT for 14 days and reliance was placed on
Clause 63.1 to show that communication under the Clause 46 was non-
conjunctive or a pre-requisite to Clause 63.1, in case, the respondent
chose to invoke Clause 63.1(b)(ii). However, the NITT referred to
various warning letters from Independent Engineer including letters dated
th rd th th
28 November, 2022, 3 December, 2022, 5 December, 2022, 28
th th th
December, 2022, 17 January, 2023, 19 January, 2023, 20 January,
th th
2023, 25 January, 2023 and 27 January, 2023 to the petitioner and thus,
it is contended that the NITT was issued in terms of the Contract.
69. I think that I should refrain from discussing the various issues at
great length since I feel that any discussion by me in that behalf could
prejudice either of the parties before the Arbitrator or the Arbitral
Tribunal. I have, therefore, confined myself to making such general
observations as are necessary in the context of the elaborate arguments
raised before me by the learned counsel.
70. Without going into the merits of the aforesaid contentions, in my
view, the best case of the petitioner is that the NITT is wrongful and not
in terms of the Contract for which it can be adequately compensated by
way of damages. If the petitioner is aggrieved by the letter of intention of
termination of the Contract and is advised to challenge the validity
thereof, the petitioner can always invoke the arbitration clause to claim
damages, if any, suffered by the petitioner. In my view, this Court under
Section 9 of the Act cannot give direction to a party for not terminating
O.M.P.(I) (COMM.) 41/2023 Page 30 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
the contract or to continue with the Contract. If the Contract is
terminated, the applicant/petitioner shall have rights as available to it
under law. It is the right of a party not to continue with a Contract and the
Court cannot force a Contract on somebody under Section 9 of the Act
irrespective of it being terminated in accordance with the terms of the
Contract or not which is for the Arbitral Tribunal to determine.
71. In so far as the rival contentions on merits of the matter including
reasons for delay in progress of works and/or the party responsible for the
same are concerned, this Court is of the view that it is only an Arbitral
Tribunal which can adjudicate upon the same after thorough examination
of the pleadings and the materials placed on record and it is not for the
Court to comment on Section 9 of the Act and/or make any observations
regarding the same. The short question that comes up for consideration
before this Court is “whether the said Contract is terminable or not” .
The question as to whether material breach/delay has been committed or
not or if there is any breach/delay at all is not to be gone into for the
reason that it is not the question for determination in the petition under
Section 9 of the Act before the Court. Further, the petitioner's contention
that the respondent has a duty to act in fair, just and prudent manner
being a State machinery is also not tenable in the present case to go into
as the petition is based only on breach of contract and remedies flowing
therefrom and thus, the matter must be decided strictly in the realm of
private law rights governed by the general law relating to contracts with
reference to the provisions of the SRA providing for non-enforceability of
certain types of contracts.
O.M.P.(I) (COMM.) 41/2023 Page 31 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
72. With respect to the Contract being determinable or not, this Court
took note of the very eloquently put petitioner's submissions that the
Contract in question is not determinable and that the judgments relied
by the respondent are related to the case where termination has already
taken place, whereas in the present case it is only NITT that has been
issued and termination has yet not taken place. Having examined the
competing views, I am of the opinion that the contention of petitioner that
present Contract is not determinable is misconceived. The language of
Clause 63.1 leaves no manner of doubt that the agreement can be
terminated by the respondent and this Court is inclined to go with the
argument put forth by the respondent in this regard. It is important to note
that in a similar contract provision, the Division Bench of this Court in
NHAI v. Panipat Jalandhar NH-Tollway Pvt. Ltd in FAO(OS) No.
th
55/2021 dated 13 April, 2021 while dealing with Jumbo World Holding
Limited (supra) held as under:
“25. The Articles and Clauses of the CA leave no manner of
doubt that the CA is determinable. Just as in Indian Oil
Corporation Ltd. (supra), both parties have been given a
right to seek termination of the CA by issuing a notice under
Article 37 and specifically, Clause 37.1.2. (NHAI's right)
and Clause 37.2.2 (Concessionaire's right). Termination
under Article 37 would be on account of the various
concessionaire's defaults or Authority default. Various time
periods ranging from 15 days to 90 days have been provided
under Clause 37.1.1 and Clause 37.2 for removal of defaults
by the defaulting party, and the failure to remove such
defaults within the time specified would give the other party
a right to issue a termination notice of 15 days.”
O.M.P.(I) (COMM.) 41/2023 Page 32 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
73. Even in the present case, NHAI could terminate the Contract for
default of petitioner, therefore, contract is certainly determinable and no
interference as such is warranted in the facts of the case. Thus, Simplex
Infrastructure v. NHAI (Supra) which in any case was an ad-interim
order and Yassh Deep Builders LLP (Supra) are not per se applicable
since whether the contract has been terminated or not, bears little or no
relevance once it is determined that the Contract by its very nature is
determinable, which is the case in the present case. The other judgments
relied upon by the petitioner on this issue also have no applicability, to
the facts of the case. The Division Bench of this Court in Panipat
Jalandhar case (Supra) has negated similar contention by respondent
therein to the effect that since the agreement provides for termination of
contract on account of a default, it is not per se determinable contract.
Similarly, in Inter Ads Exhibition vs Busworld International (Supra) ,
another Division Bench of this Court negated the contention to aforesaid
effect, and held the contract to be determinable by holding as under:
“40. Suffice it is to state that in either event, the agreement
was terminable and therefore, the conclusion arrived at by
the learned Single Judge that specific performance of the
Contract could not be granted and nor could any injunction
be issued restraining the respondent from giving effect to the
th
notice dated 15 March, 2019, as that would in effect
amount to enforcement of the contract beyond the said date
th
i.e. 15 March, 2019, cannot be faulted.”
74. The learned Single Judge has rightly relied on a decision of this
Court in MIC Electronics Ltd. (Supra) , to hold that legality of the
termination and the justification of the appellant for not paying the
O.M.P.(I) (COMM.) 41/2023 Page 33 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
balance due to the respondent, would have to be examined by the learned
Arbitrator.
75. In so far as DLF Home Developers Ltd. (Supra) is concerned, the
issue before the Court was regarding specific performance of an
Agreement to Sell of an immovable property (ATS). Clause 10 of the
Agreement to Sell which expressly stated in unambiguous terms that DLF
would be entitled to specific performance. An ATS in relation to
immovable property stands on a different footing in law, in view of
provisions of Section 10 of the SRA and hence, cannot come to the rescue
of the petitioner. Similarly, T.O Abraham v. Jose Thomas (Supra) ,
related to a contract to transfer equity shares of a company. All the sellers
except one, pursuant to agreement had already transferred their shares.
This was again completely a different fact situation as compared to the
present one. In Atlas Interactive (India) (Supra) , the subject matter was a
Franchise Agreement for proving broadband on the existing copper wires
of BSNL. This service was unique and the first of its kind in India for
BSNL only. Thus, the Court held that the unique opportunity, the
expenditure and return on the contract cannot be estimated, and damages
cannot be said to be an adequate remedy. This is not the case in the
present circumstances where damages would be adequate remedy. In
Golden Tabacco Ltd. (Supra) , the Court was approached by Golden
Tabacco (GT) seeking an injunction on production and supply of
cigarettes under the Trademarks of GT. The dispute related to obligations
of the parties under the Trademark License Agreement, which had been
terminated by GT due to non-payments of royalties. The Court after
considering the termination clause within the Agreement held that the
O.M.P.(I) (COMM.) 41/2023 Page 34 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
question whether a contract is determinable in its nature is required to be
examined in the facts of each case. The Court held that the “Trademarks
License Agreement granted GTPL the right to use the Exclusive Brands
of GTL in perpetuity. Clearly, a contract of this nature cannot be
considered as determinable in absence of any agreement entitling the
party to terminate the same without cause or default on the part of the
other party” .
76. At this juncture, it is also relevant to state that Sections 20A and
41(ha) of the SRA express the legislative intent not to grant injunctions
relating to infrastructure projects where delay may be caused by such an
injunction. The whole purpose and objective introduced this provision by
way of amendment was to promote foreign investment and build investor
confidence in the infrastructure sector of India. Public Private
Partnerships have long suffered due to the prolonged delays and cost-
overruns in timely execution of infrastructure projects. One cannot deny
the fact that infrastructure has a significant role in the growth and
development of a nation and helps in the development of overall
production and the GDP contribution of the nation. Hence, an obstruction
in the development of infrastructure would yield negative consequences
for the whole nation, leading to stagnancy in the economy and the
downfall of the nation's position in the global market. The amendment
was aimed at improving India's global standing in terms of enforcing
contracts and ease of doing business which would further increase FDI.
Any public work must progress without interruption. Thereby, the role of
courts in this exercise is to interfere to the minimum extent so that public
work projects are not impeded or stalled. In my considered view, Sections
O.M.P.(I) (COMM.) 41/2023 Page 35 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
20A and 41(ha) of the SRA squarely apply to the present case and an
injunction would tantamount to further delaying the infrastructure project.
77. The decisions of this Court in Hari Ram Nagar (Supra) further
highlight that whenever suit or proceedings where an injunction is sought
may lead to delay in the subject Infrastructure Projects, the operation of
the SRA gets attracted and that Courts should in normal course grant no
injunction. In the present case, it is clear that the scheduled targets of
progress have not been achieved. The petitioner's arguments that Section
20A deals with situation where injunction is being sought which may
result in not letting the work go on or that the respondent would take
months to tender the work after removal of petitioner do not hold much
ground. It is an admitted position that in a period of more than 8 months,
only about 10.47 km (one side) of main carriage way out of 322.4 km
(both side) of the works have been carried out, thus, if any injunction is
granted and petitioner is allowed to continue, such continuance would
cause impediment and delay in the progress or completion of
infrastructure project. Even otherwise, the time to be consumed in the
process of inviting fresh bids cannot be a reason to continue with
petitioner especially with a meagre physical progress of 3.08% in the last
8 months.
78. The petitioner during the arguments had further tried to impress
upon this Court that vide the present petition under Section 9 of the Act,
the petitioner has sought a stay on the NITT and not on Termination of
the Contract. However, the petitioner falls short in its argument as under
the present Contract, it is necessary for the respondent to issue a NITT at
least 14 days prior to the termination. A stay on the NITT would mean
O.M.P.(I) (COMM.) 41/2023 Page 36 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
stay on termination, inasmuch as, unless NITT is issued, the respondent
in such contracts will never be able to terminate the Contract. The
petitioner cannot seek to achieve something indirectly which it cannot
achieve directly. The petitioner in its petition has itself pleaded, “if at the
present stage, the respondent terminates the Contract with the petitioner,
considerable loss and prejudice will be caused to the petitioner....
Further, if the respondent terminates the Contract, it will lead to grave
loss of public money and inconvenience to the daily commuters of the
national highway.” Thus, the trinity test of granting an injunction as per
the petitioner's own case has rested on the termination of the Contract.
Further, this Court agrees with the argument put forth by the respondent
that the petitioner by making such argument is attempting to seek a relief
which otherwise cannot be granted directly. A court of law has to act
within the statutory command and not deviate from it. It is a well-settled
proposition of law what cannot be done directly, cannot be done
indirectly. While exercising a statutory power, a Court is bound to act
within the four corners thereof.
CONCLUSION
79. In view of the foregoing discussion on the facts and law, this Court
cannot grant the reliefs as sought for. The petitioner by way of present
petition has sought for stay of NITT and any such stay would result into
petitioner continuing the project and would tantamount to granting of
final relief which cannot be granted by this Court in the instant
proceedings under Section 9 of the Act. On the other hand, if the action of
respondent is held to be bad eventually, the petitioner can always be
suitably compensated in terms of damages.
O.M.P.(I) (COMM.) 41/2023 Page 37 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
80. I am also of the opinion that neither the balance of convenience is
in favour of the petitioner, nor the petitioner would suffer any irreparable
loss in case the reliefs as sought are not granted.
81. The petitioner has attempted to bring attention of this Court, the
judgment passed in Fedders Electric and Engineering Limited (Supra)
after almost 22 days from the date when the instant matter was reserved
th
for judgment on 18 April, 2023, suggesting that the arbitration
proceedings have commenced and the present petition be sent to the
learned Arbitral Tribunal for it to consider and adjudicate upon relief
sought by way of Section 9 of the Application under Section 17 of the
Act. The said argument is also not of much assistance to the petitioner for
the same cannot be done without the consent of both the parties as in the
present case and no consent has been sought from the respondent in this
regard.
82. Considering the aforesaid, I am of the view that the petitioner has
miserably failed to make out any case for granting interim injunction in
the instant matter.
83. Accordingly, the instant petition, being bereft of any merit, is
dismissed along with the pending applications, if any.
84. Before parting, I would like to clarify that whatever has been stated
hereinabove in this order/judgment is not in any manner intended to be a
reflection, much less a finding on the merits of the case of either party
which should be available to be determined on evidence and material
brought on record in duly constituted legal proceedings, whether before
the Arbitral Tribunal or Arbitrator. All that has been said hereinabove is
O.M.P.(I) (COMM.) 41/2023 Page 38 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21
NEUTRAL CITATION No.2023:DHC:3610
by way of prima facie observation confined to the disposal of the present
petition.
85. The judgment be uploaded on the website forthwith.
(CHANDRA DHARI SINGH)
JUDGE
MAY 24, 2023
gs/db
O.M.P.(I) (COMM.) 41/2023 Page 39 of 39
Signature Not Verified
Digitally Signed By:SARIKA
BHAMOO VERMA
Signing Date:24.05.2023
16:23:21