MUNICIPAL CORPORATION OF GREATER BOMBAY vs. NAGARJUNA CONSTRUCTION CO. LTD.

Case Type: N/A

Date of Judgment: 22-01-2019

Preview image for MUNICIPAL CORPORATION OF GREATER BOMBAY vs. NAGARJUNA CONSTRUCTION CO. LTD.

Full Judgment Text


2019:BHC-OS:2978
1/7 6.ARBP 90-13.odt
Chittewan
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
 
ARBITRATION PETITION NO.90 OF 2013
    
Municipal Corporation of Greater 
Bombay  … Petitioner   
     Versus 
M/s Nagarjuna Construction 
Company Limited  … Respondent    
…..
Mr. P. G. Lad a/w Ms. Aparna M. Kalathil & Mr. D.S. Shingade, for the
Petitioner­MCGM.
Mr. Kishore M. Jawle, for the Respondent. 
 …..
CORAM :    S.C. GUPTE, J.
DATE     :  22 JANUARY 2019  
(Oral Judgement) 
. This arbitration petition challenges an award passed by an arbitral
tribunal of three arbitrators in a reference arising out of a construction
contract. 
2 In   June   2004,   the   Petitioner­corporation   invited   tenders   for
construction   of   grade   separators   at   Gadkari   Chowk,   Mumbai.     The
Respondent­contractor submitted its bid.  The same was accepted by the
Petitioner and accordingly, on 2 December 2004, a contract was entered
into between the  parties.  Following the contract, on 3 December 2014,
the site was handed over by the Petitioner to the Respondent, whereupon
::: Uploaded on - 24/01/2019 ::: Downloaded on - 26/06/2024 07:28:59 :::

2/7 6.ARBP 90-13.odt
Chittewan
the latter claimed to have started the work on the project.  On 26 February
2005,   the   Petitioner   wrote   a   letter   to   the   Respondent   demanding
suspension of work.  It is an admission position that this suspension was
never revoked.  During the continuance of the suspension, the Petitioner,
by its letter dated 22 November 2007, claimed that the contract had come
to an end by efflux of time. Finally, by its consultant's letter dated 17 April
2008,   the   Petitioner   informed   the   Respondent   that   the   contract   was
deemed to have been terminated. The Respondent raised several claims.
Since these were not accepted by the Petitioner,  disputes arose between
the parties, which were referred to arbitration.  The arbitral tribunal, by its
award dated 24 March 2012 (corrected on 12 September 2012), allowed
three claims of the Respondent, namely, (i) claim for reimbursement of
expenses incurred by the Respondent to fulfill its contractual obligations
(Claim   No.1),     (ii)   claim   for   compensation   for   infructuous   expenses
incurred for preparation of casting yard and fabricating moulds for pre­cast
unit (Claim No.5) and (iii) claim for loss of overheads and profits (Claim
No.8).  Each of these three claims was awarded partly, claim No.1 in the
sum of Rs.1,35,880, Claim No.5 sum of Rs. 1,36,421 and claim no.8 of
Rs.1,17,53,180.  
3 The   amount   of   Rs.1,35,880   for   Claim   No.1   was   said   to   be   the
expenditure actually incurred for performance guarantee, whereas the  sum
of Rs.1,36,421, awarded under claim No.5, was actually the payment made
to a consultant firm, one Structon Consultants.   These payments were
found by the arbitral tribunal to be genuine and payable accordingly.  None
of these claims admits of any acceptable challenge under the provisions of
Section 34 of the Arbitration and Conciliation Act, 1996 (“Act”).  These are
::: Uploaded on - 24/01/2019 ::: Downloaded on - 26/06/2024 07:28:59 :::

3/7 6.ARBP 90-13.odt
Chittewan
matters of assessment of evidence, on which the arbitrators have come to
possible views.   The   views are supported by evidence on record.   The
award on these claims cannot be termed as an award not supported by any
evidence; no irrelevant or non­germane material has been considered by
the   the   arbitrators;   and   no   relevant   or   germane   material   has   been
disregarded for arriving at these conclusions.   The award on these two
claims accordingly does not merit any interference.  
4 The main submissions made by learned Counsel for the Petitioner
pertain   to   the   award   of   loss   of   profit   (Claim   No.8).   Learned  Counsel
submits that, in the first place, the Petitioner­corporation was justified in
first suspending and then terminating the contract on account of public
outcry.  Learned Counsel submits that the contract work was meant to be
for   the   benefit   of   public   and   since   the   public   themselves   had   serious
objection to the work, the Petitioner­corporation was constrained to first
suspend and later terminate the contract work.  Learned Counsel submits
that the corporation's act in this behalf is effectively covered by Section 56
of the Contract Act.   Learned Counsel secondly submits that not having
carried out the contract work or produced any evidence of loss of profits,
the Respondent­contractor could not have claimed any amount towards
loss of overheads or profits and that the award for loss of  profits is vitiated
by breach of public policy of India as well as patent illegality appearing on
the face of the award.  None of the contentions has any merit, as I shall
presently point out.  
5 What the arbitrators have awarded here is the Respondent's claim for
loss of profits and not for loss of overheads.  Considering the Indian law of
::: Uploaded on - 24/01/2019 ::: Downloaded on - 26/06/2024 07:28:59 :::

4/7 6.ARBP 90-13.odt
Chittewan
damages  for  breach of  contract,  the  court,  tasked  with  adjudicating  a
contractor's claim for loss of profits on   being denied the opportunity to
carry out the work under a works contract by any act of the employer, has
to see whether  such denial was wrongful or whether the contractor was at
fault  justifying the denial.  The court has to then consider  the measure of
loss or damage caused to the contractor as a result of his being denied the
opportunity to carry out the contract work.  As held by the Supreme Court
1
in   A.T. Brij Paul Singh Vs. State of Gujara t  it is well established that if
rescission or termination of the contract by the employer is held to be
unjustified and the plaintiff­contractor is shown to have executed a part of
the works contract, the contractor would be entitled to claim damages for
loss   of   profits,   which   he   expected   to   earn   by   undertaking   the   works
contract.  Such claim of expected profits is legally admissible on proof of
breach of the contract by the erring party.   Though what would be a
measure of such profits would depend upon facts and circumstances of
each case, it is  always  accepted that a reasonable expectation of profit is
implicit in a works contract and its loss has to be compensated by way of
damages if the other party to the contract is guilty of its breach.  In  A.T.
Brij Paul 's case, 15 per cent of the value of the balance work  considered as
reasonable   damages towards loss of profits for the same type of work
between   the   same  parties   at   a  nearby   work   site,     was   accepted  as   a
reasonable measure of damages.   Relying on the dicta   in the case of
2
Dwarkadas Vs. State of MP , the Supreme Court in  MSK Projects India
3
(JV) Limited Vs. State of Rajasthan  held that a claim of a contractor for
damages as expected profits out of the contract could not be disallowed on
1 (1984) 4 S.C.C. 59
(1999) 3 S.S.C. 500
2
3(2011) 10 S..C.C. 573
::: Uploaded on - 24/01/2019 ::: Downloaded on - 26/06/2024 07:28:59 :::

5/7 6.ARBP 90-13.odt
Chittewan
the ground that   there was no proof that he suffered actual loss   to the
extent of the amount claimed on account of breach of contract.  Relying on
these cases, a Division Bench of our court in   Mahanagar Gas Ltd Vs.
4
Babulal Uttamchand & Co .   considered 10 per cent   of the value of
balance work awarded towards loss of profits as a reasonable measure of
damages.  
6 We have to test the present award on the basis of the law stated
above.  The focus of our inquiry under Section 34 of the act is, as explained
by   the   Supreme   Court   in   case   of   Associate   Builders   Vs.   Delhi
5
Development   Authority ,     to   see   if   the   award   under   challenge   is   in
contravention of public policy of India; in particular, if it contains an
impossible view or a view which no fair or judicially minded person would
take or a view that would shock the conscience of the court.  The court has
also to see if   there is any patent illegality appearing on the face of the
award; in particular, if the award is in accordance with the terms of the
contract or contains any adjudication prohibited by the terms.   In the
present case, the arbitrators have come to a conclusion that there was no
breach of contract on the part of the Respondent­contract;  the contractor
was in no way responsible for suspension of work.   The suspension was
ordered unilaterally by the Petitioner­corporation on 26 February 2005 and
it was never revoked thereafter. Though the suspension was not revoked or
withdrawn within  28 days from  the date of suspension,  under Clause
59.2(b)   of   the   contract,   the   Claimant   did   not   treat   the   same   as   a
“fundamental breach of contract”  or treat the contract  as voidable under
Clause 59.1. It instead claimed damages for its breach by the employer.
2013 (5) Bom.C.R.756
4
5 AIR 2015 SC 620
::: Uploaded on - 24/01/2019 ::: Downloaded on - 26/06/2024 07:28:59 :::

6/7 6.ARBP 90-13.odt
Chittewan
The Petitioner­corporation's argument in this behalf was that the case fell
within the scope of Section 55 of the Contract   Act (the third part of
Section 55).  The arbitrators were of the view that the case fell not within
the third part of Section 55, but  the second part of Section 55;   though
the   contract   did   not   become   voidable   for   the   employer's   failure,   the
promisee was entitled to receive compensation from the promiser for any
loss occasioned by such failure.  The arbitrators also noted the stand of the
Petitioner's engineer that the contract was deemed to have been terminated
on the expiry of 28 days of suspension of work.  The arbitrators held the
stand to be incorrect and accordingly, ruled that the contract had come to
an end by efflux of time, i.e.  at the expiry of the contract period, without
anyone terminating the same for any reason.  Since the suspension of the
contract during the entire period of its subsistence was entirely to the
Petitioner­employer's account, the arbitrators held such unilateral act on
the   part   of   the   Petitioner   as   a   breach   of   contract   and   accordingly,
considered the claim of the Respondent for loss of profits.  The arbitrators
held that (a) the claimant, having been prevented from carrying out the
work awarded to it for no fault of it,  was denied profits, and (b) under
normal circumstances, 10 per cent amount of the value of work which was
denied could  be accepted as a reasonable measure of pure profits.  After
excluding     profit   attributable   to   the   actual   work   executed   at   site,   as
certified by the engineer of the Petitioner, the arbitrators awarded a sum of
Rs.1,17,53,180  towards loss of profits.  In the light of the law stated and
the  evidence discussed above, the arbitrators'  award of loss of profits can
certainly   be   termed   as   a   possible   conclusion,   which   is   supported   by
evidence.  It cannot be termed as a conclusion, which is either impossible
or a conclusion which no fair or judiciously minded person could have
::: Uploaded on - 24/01/2019 ::: Downloaded on - 26/06/2024 07:28:59 :::

7/7 6.ARBP 90-13.odt
Chittewan
arrived at or a conclusion that  would shock the conscience of the court.  In
so far as the the terms of the contract are concerned, the interpretation of
the arbitrators demonstrates a reasonable view and not an unreasonable or
impossible view.  The arbitrators have not taken into account any irrelevant
or non­germane material or circumstance or disregarded any relevant or
germane material or circumstance to arrive at the conclusion.  It does not
accordingly merit any interference under Section 34 of the Arbitration and
Conciliation Act, 1996.   
7 As for the submission of learned Counsel for the Petitioner under
Section   56   of   the   Contract,   no   such   ground   was   urged   before   the
arbitrators or is even pleaded in the present petition.   Besides, the mere
fact that there were objections raised to the proposed work by the members
of public does not signify that the construction work ordered under the
contract was an impossible act.  
8 In the premises, there is no merit in the arbitration petition.   The
petition is dismissed.

    
(S.C. GUPTE, J.)
::: Uploaded on - 24/01/2019 ::: Downloaded on - 26/06/2024 07:28:59 :::