Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
CASE NO.:
Appeal (civil) 4552 of 2006
PETITIONER:
Union of India & Ors
RESPONDENT:
Jummasha Diwan
DATE OF JUDGMENT: 19/10/2006
BENCH:
S.B. Sinha & Dalveer Bhandari
JUDGMENT:
J U D G M E N T
[Arising out of SLP (Civil) No. 7337 of 2006]
S.B. SINHA, J :
Leave granted.
Respondent was appointed as a daily wager in the Railway
Electrification Project at Vadodara Ratlam section. He was granted a
temporary status. He is said to have joined the Railway Electrification
Project as a skilled worker under the Divisional Electrical Engineer, Western
Railway (Overhead Equipment) Railway Electrification Railway Yard,
Pratapnagar, Baroda, Appellant No. 3 herein. He was retrenched
purportedly on the premise that railway electrification works at Vadodara
Ratlam section came to an end. He was paid retrenchment compensation in
terms of Section 25-F of the Industrial Disputes Act, 1947 (for short "the
Act").
He filed an original application before the Central Administrative
Tribunal (Tribunal) questioning the purported retrenchment on the ground
that he having put in 1060 days of continuous service should have been
placed much higher in the seniority list and, thus, could not have been
retrenched having regard to the principle of "last come first go". It was also
contended that while passing an order of retrenchment, the provisions of
Section 25-N of the Act was not complied with.
The Tribunal dismissed the said original application. A writ petition
came to be filed wherein the same pleas were raised by Respondent herein.
Invoking Section 25-N of the Act, the impugned judgment has been passed
setting aside the order of termination and directing reinstatement of
Respondent.
Mr. R. Mohan, learned Additional Solicitor General appearing on
behalf of Appellants inter alia submitted that the provisions of Section 25-N
of the Act will have no application to the facts and circumstances of the
case.
Mr. S.C. Patel, learned counsel appearing on behalf of Respondent, on
the other hand, submitted that Respondent having put in 1060 days of
continuous service, the order of retrenchment was vitiated in law. It had
been pointed out that different benches of the Central Administrative
Tribunal on almost identical issues had taken different views and in that
view of the matter, the impugned judgment should not be interfered with.
Respondent indisputably had started working under Appellant No. 3
1986. His services had been terminated inter alia on the premise that the
electrification project had come to a close. If the services of a project
employee is terminated, it is trite that statutory requirements of Section 25-F
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
of the Act are required to be complied with, but, indisputably, Respondent
was given one month’s notice pay as also the retrenchment compensation in
compliance thereof.
His name might not have appeared in the seniority list of the casual
labourers which was being maintained but the question, as to whether he had
been in continuous service in all the departments he had served, was a
disputed one. There are several establishments of the Railway
Administration. If a workman voluntarily gives up his job in one of the
establishments and joins another, the same would not amount to his being in
continuous service. When a casual employee is employed in different
establishments, maybe under the same employer, e.g., the Railway
Administration of India as a whole, having different administrative set up,
different requirements and different projects, the concept of continuous
service cannot be applied and it cannot be said that even in such a situation
he would be entitled to a higher status being in continuous service. It is not
in dispute that the establishment of Appellant No. 3 herein had started a
project. His recruitment in the said establishment would, therefore,
constitute a fresh employment. In a case of this nature, Respondent would
not be entitled to his seniority. If the project came to a close, the
requirements of Section 25-N of the Act were not required to be complied
with.
Lal Mohammad and Others v. Indian Railway Construction Co. Ltd.
and Another [(1999) 1 SCC 596], whereupon reliance has been placed by the
High Court, cannot have any application in the instant case. The Tribunal in
its order categorically opined that his employment was not in an ’industrial
establishment’ which would come inter alia within the purview of the
definition of a factory as contained in clause (m) of section 2 of the Factories
Act.
Our attention has been drawn to a decision of this Court in Oswal
Agro Furane Ltd. and Another v. Oswal Agro Furane Workers Union and
Others [(2005) 3 SCC 224]. In the said decision, this Court was concerned
with closure of an industrial establishment engaging more than 1000 people.
In the aforementioned fact situation obtaining therein, this Court held that
the consent of State Government before effecting closure of such
establishment was mandatory.
For the reasons aforementioned, we are of the opinion that the
impugned judgment cannot be sustained which is set aside accordingly.
This appeal is allowed. No costs.