Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
M/S. SANT RAM & COMPANY
Vs.
RESPONDENT:
THE STATE OF RAJASTHAN & ORS.
DATE OF JUDGMENT: 20/11/1996
BENCH:
K. RAMASWAMY, G.T. NANAVATI, K. VENKATASWAMI
ACT:
HEADNOTE:
JUDGMENT:
O R D E R
This appeal by special leave arises from the order of
the single Judge of the Rajasthan High Court made in Civil
Revision Petition No. 293/90, dated August 7, 1990.
The admitted position is that the appellant had entered
into a contract with the respondent-State for execution of
the works of widening of Gagar Diversion Bridge at Bikaner
in Sri Ganganagar Section. Pursuant to a dispute which arose
between the parties, in terms of the contract, the matter by
mutual agreement, was referred to the arbitrator by name Sri
K.L. Sethia. Pending arbitration, the respondent sought to
adjust the amounts due to the appellant in another contract.
Thereon the appellant filed an application in the district
Court under Order XXXIX Rule 1, Code of Civil Procedure,
1908 read with Section 41(b) of the Arbitration and the
Second Schedule to the Arbitration Act, 1940 for ad interim
injunction restraining the respondent from adjusting the
same. The District Judge by his order held that such an
application is not maintainable without the intervention of
the Court; therefore, Section 41(b) and the Second Schedule
have no application. The same came to be upheld by the
learned Chief Justice in the impugned order. Thus this
appeal by special leave.
Shri A.B. Rohtagi, learned senior counsel for the
appellant, contends that for entertaining and application
under Section 41(b) read with the Second Schedule, it is not
a condition that the arbitration proceedings should be
pending through the intervention of the Court. Independently
thereof, when arbitration proceedings were pending between
the parties in respect of the claim or counter-claim and
when the respondent sough to adjust the same with the
amounts due from other contracts, the Court would, in the
circumstances, intervene and restrain the respondents from
adjusting the same as a counter-claim. Otherwise, the
arbitration proceeding would be nullified. He placed strong
reliance on the judgment of a two Judge Bench of this Court
in Union of India v. Raman Iron Foundry [(1974) 3 SCR 556].
The question is no longer res integra. A Bench of three
judges of this Court in Kamaluddin Ansari & Co. v. Union of
India [(1983) (3) SCR 607] has considered the scope of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
Section 41(b) and the Second Schedule and had held thus:
"The first question that falls for
consideration in this appeal is
about the exact scope and ambit of
Section 41 in order to appreciate
the contention raised on behalf of
the appellant:
"41. Procedure and powers of
Court:- Subject to the provisions
of this Act and of rules made
thereunder -
(a) the provisions of the Code of
Civil Procedure, 1908 shall apply
to all proceedings before the Court
and to all appeals, under this Act,
and
(b) the Court shall have, for the
purpose of , and in relation to,
arbitration proceeding, the same
power of making orders in respect
of any of the matters set out in
the Second Schedule as it has for
the purpose of, and in relation to,
any proceedings before the Court:-
Provided that nothing in clause (b)
shall be taken to prejudice any
power which may be vested in an
arbitrator or umpire for making
orders with respect to any of such
matters."
In view of cl.(b) of s.41 the Court
has been given power of passing
orders in respect of any of the
matters set out in second Schedule
for the purpose of and in relation
to any proceedings before the
Court. The Second Schedule of the
Arbitration Act inter alia includes
‘interim injunction’ and the
‘appointment of receiver’."
In that case an application under Section 33 of the
Arbitration Act had come to be filed and then an application
for ad interim injunction was filed. It will, therefore, be
clear that to avail the remedy under the provisions of the
Code of Civil Procedure, when an application for injunction
under Section 41(b) read with Schedule is filed, the Court
shall have, pending proceedings for the purpose of an in
relation to the arbitration proceedings availed through the
process of the Court, the same power of making orders in
respect of any matters set out in the Second Schedule as it
has for the purpose of and in relation to any proceeding
before the Court. The initiation of pendency of any
proceedings in the Court in relation to the arbitration
proceedings would, therefore, be a precondition for the
exercise of the power by the Civil Court under the Second
Schedule of the Act.
On merits, this Court had held in the similar
circumstances that such an injunction cannot be granted as
it amounts to granting a relief which is not warranted under
Section 41(b) read with the Schedule of the Act. This Court
had recorded a finding as under:
"We are clearly of the view that an
injunction order restraining
respondents from withholding the
amount due under other pending
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
bills to the contractor virtually
amounts to a direction to pay
amount to the contractor-
appellants. Such an order was
clearly beyond the purview of
cl.(b) of s.41 of the Arbitration
Act. The Union of India has no
objection to the grant of an
injunction restraining it from
recovering or appropriating the
amount lying with it in respect of
other claims of the contractor
towards its claim for damages. But
certainly cl. 18 of the standard
contract confers ample power upon
the Union of India to withhold the
amount and no injunction order
could be passed restraining the
Union of India from withholding the
amount."
The Division Bench decision on which the reliance was
placed, has reiterated that principle, namely, that "such an
injunction can only be for the purpose of an in relation to
the arbitration proceedings. The court could not make an
injunction order which, though ostensibly in the form of an
order of interim injunction, in substance, amounted to a
direction to the appellant to pay the amounts due to the
respondent under other contracts." In fact, the ratio
therein which the learned counsel tried to propound, was not
approved and the said decision was expressly overruled in
Kamaluddin’s case (supra).
It is seen that under Clause (50) of the contract, the
appellant has expressly agreed for adjustment of the amount
pending with the respondent in respect of the claim under
the dispute or any other contract with the Department. Under
these circumstances, neither on merits nor on principle of
law, we find any illegality in the order passed by the High
Court warranting interference.
The appeal is accordingly dismissed. No costs.