Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 12
PETITIONER:
AFLATOON AND OTHERS
Vs.
RESPONDENT:
LT. GOVERNOR OF DELHI & OTHERS
DATE OF JUDGMENT23/08/1974
BENCH:
MATHEW, KUTTYIL KURIEN
BENCH:
MATHEW, KUTTYIL KURIEN
RAY, A.N. (CJ)
ALAGIRISWAMI, A.
GOSWAMI, P.K.
SARKARIA, RANJIT SINGH
CITATION:
1974 AIR 2077 1975 SCR (1) 802
1975 SCC (4) 285
CITATOR INFO :
RF 1974 SC2085 (9)
F 1975 SC1699 (2,11,12)
R 1975 SC2112 (4)
RF 1978 SC 515 (7)
F 1979 SC1713 (11)
ACT:
Land Acquisition Act, Section 4, sab-sections (1) and
(2)--Initiation of proceedings under, a valid notification
sine, qua non-- Delay in moving the Court--Effect.
Land Acquisition Act, Section 23 and Constitution of India,
1950, Articles 19(1)(f) 31(2) and 31(5)--Compensation with
reference to value of property on the date of notification
under sec. 4--Adequacy of compensation, challenge
of--Challenge confined only to question of procedural
reasonableness.
Delhi Development Act, sections 12 and 15--Planned
development of Delhi to be in accordance with the
Act--Central Govt., if precluded from acquiring land for
planned development--Laches and acquiescence on the part of
the petitioners--Effect.
Land Acquisition Act, Section 3(a) and Part VII--Acquisition
of land for planned development of Delhi--Landing over a
portion of the acquired property to co-operative housing
societies--Provisions of Part VII of the Act, whether
attracted.
HEADNOTE:
A notification under sec. 4 of the Land Acquisition Act was
issued on Nov. 13, 1959, stating that an area of 34,070
acres of land was needed for a public purpose, viz. the
planned development of Delhi. Between 1959 and 1961, about
six thousand objections were filed under sec. 5A of the Act.
The objections were overruled. On March 18, 1966, the
declaration under sec. 6 of the Act was published in respect
of a portion of the area. Therefore, in 1970, notices were
issued under sec. 9(1) of the Act requiring the appellants
to state their objections, if any, to the assessment of
compensation. The appellants thereupon challenged the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 12
validity of proceedings for acquisition before the High
Court of Delhi. The High Court negatived their contentions
and dismissed the writ petitions. In the writ petitions and
civil appeals filed in the Supreme Court it was contended :
(i) The public purpose specified in the notification issued
under sec. 4, namely, the planned development of Delhi was
vague as neither a Master Plan nor a Zonal Plan was in
existence on the date of the notification and as the purpose
specified in the notification was vague, the appellants and
the petitioners were unable to exercise effectively their
right under sec. 5A of the Act; (ii) As there was inordinate
delay in finalizing the acquisition proceedings, they were
deprived of the benefit of the appreciation in the value of
the property between the date of notification under sec. 4
and the date of taking possession of the property. (iii) The
provisions of sec. 23 of the Act laying down that
compensation should be determined with reference to the
market value of the land as an the date of notification
under sec. 4 was an unreasonable restriction on the
fundamental right of the appellants to hold and dispose of
property under Article 19(1) (b); (iv) As the acquisition of
the property was for the purpose, of planned development of
Delhi, the only authority competent to issue the
notification under sec. 4 was the Central Govt. under see.
15 of Delhi Development Act and since the proceedings were
initiated by the Chief Commissioner of Delhi, the
proceedings were ab initial invalid; and (v) The acquisition
was not for any public purpose, but for companies as the
major portion of the land acquired was allotted without any
development to co-operative housing societies which were
companies within the definition of the word "company" in the
Act and as the provisions of part VII of the Act were not
complied with the proceedings for acquisition were bad.
Rejecting the contention and dismissing the appeals and the
petitions,
803
HELD : (i) A valid notification under sec. 4 is a sine qua
non for initiation of proceedings for acquisition of
property. It is necessary to specify the particular public
purpose, in the notification for which the land is needed or
likely to be needed as otherwise, the matters specified in
sub-sec. (2) of sec. (4) cannot be carried out. [807C]
Munsh Singh and Others v. Union of India, [1973] 1 S.C.R.
973 (975 and 984) relied on. Arnold Rodricks and Another
v. State of Maharashtra and others, [1966] 3 S.C.R. 885
referred to.
In the case of an acquisition of a large area of land
comprising several plots belonging to different persons, the
specification of the purpose can only, be with reference to
the acquisition of the whole area. Unlike in the case or an
acquisition of a small area, it might be practically
difficult to specify the particular purpose for which each
and every item of land comprised in the area is- needed.
[807G]
The appellants did not move in the matter even after the
declaration under sec. 6 was published in 1966. They
approached the High Court with their writ petitions only in
1970 when the notices under sec. 9 were issued, to them That
apart, the appellants did not contend before the High Court
that as the particulars of public purpose were not specified
in the-notification issued under sec. 4, they were
prejudiced in that they could not effectively exercise their
right under sec. 5A. As the plea was not raised by them
before the High Court, the appellants are not entitled to
have the plea considered in these appeals. To have sat on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 12
the fence and allowed the Govt. to complete the acquisition
proceedings on the basis of the notification under sec. 4
and the declaration under sec. 6 were valid and then to
attack the notification on grounds which were available to
the writ petitioners at the-time when the notification was
published would be putting a premium on dilatory tactics.
The writ petitions are liable to be dismissed on the ground
of laches and delay on the part of the petitioners. [808A-B;
D & F-G]
Tilok. Chand Moti Chand and others v. H. B. Munshi and
Another, [1969] 2 S.C.R. 824 and Rabindranath Bose and
Others v. Union of India and others [1970] 2 S.C.R. 697
referred to.
(ii) About 6,000 objections were filed under sec. 5A by
persons interested in the property. Several writ petitions
were also filed in 1966 and 1967 challenging the validity of
the acquisition proceedings. The Govt. had necessarily to
wait for the disposal of the objections and petitions before
proceeding further in the matter. The High Court was of the
view that there was no inordinate delay on the part of the
Govt. in completing the acquisition proceedings. The
conclusion of the High Court is correct. [809B-C]
(iii) The Land Acquisition Act is a pre-Constitution
Act. its provisions are not, therefore, liable to be
challenged on the ground that they are not in conformity
with the requirement of Article 31(2) of the Constitution.
What the appellants and writ petitioners complain is that
their properties were acquired by paying them compensation
computed with reference to the. market value of the land as
on the date of the notification under sec. 4 and that sec.
23 is, therefore, bad. This, in substance is nothing but a
challenge to the adequacy of compensation. Such a challenge
is precluded by reason of Art. 31(5) of the Constitution.
[809F-G]
Although a law for acquisition of property must pass the
test of Article 19(5), the challenge to the law would
ordinarily be limited to the question of procedural
unreasonableness. [810B]
R. C. Cooper v. Union of India [1970] 3 S.C.R. 530, (577)
relied on.
It follows that although sec. 23 of the Act can be
challenged on the, ground that it violates the fundamental
right of a citizen to held and dispose of property under
Article 19(1)(b), the challenge would practically be limited
to the question of procedural reasonableness. But sec. 23
does not deal with procedure and cannot, therefore, suffer
from any procedural unreasonableness. [810E-F]
804
(iv) The planned development of Delhi had been decided upon
by the Govt. before 1959, viz., even before the Delhi
Development Act came into force. It is true that there
could be no planned development of Delhi except in accord-
ance with the provisions of Delhi Development Act after that
Act came into force but there was no inhibition in acquiring
land for planned development of Delhi under the Act before
the Master Plan was ready. [812E]
Patna Improvement Trust v. Sint. Lakshmi Devi and others
[1963] Supp. 2 S.C.R. 812 referred to.
In other words, the fact that actual development is
permissible in an area other than a development area with
the approval or sanction of the local authority did not
preclude the Central Govt. from acquiring the land for
planned development under the Acts. Section 12 is concerned
only with the planned development. It has nothing to do
with acquisition of property-, acquisition generally
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 12
precedes development. For planned development in an area
other than a development area, it is only necessary to
obtain the sanction or approval of the local authority as
provided in sec. 12(3). The Central Govt. could acquire any
property under the Act and develop it after Obtaining the
approval of the local authority. As already held the
appellants and the writ petitioners cannot be allowed to
challenge the validity of notification under sec. 4 on the
ground of laches and acquiescence. The plea that the Chief
Commissioner of D.-]hi had no authority to initiate the
proceedings for acquisition by issuing the notification
under sec. 4 of the Act as sec. 15 of the Delhi Development
Act gives that power only to the Central Govt. relates
primarily to the validity of the notification. Even
assuming that the Chief Commissioner was not so authorized,
since the appellants and the writ petitioners are precluded
by their ]aches and acquiescence from questioning the,
notification, the plea must be negatived. [812F-H; 813A-B]
(v) The plea that the provisions of Part VII of the Act
have not been complied witin has also to be rejected. The
High Court was correct in giving the finding that the
acquisition was not for Company’. The mere fact that after
the acquisition the Govt. proposed to hand over, or, in
fact, handed over, a portion of the property acquired for
development to the cooperative housing societies would not
make the acquisition one for company’ and therefore, Part
VII of the Act was not attracted, [813C-E]
JUDGMENT:
ORIGINAL JURISDICTION : Writ Petitions Nos. 362 & 363 of
1972.
Petitions under Article 32 of the Constitution of India.
Civil Appeals Nos. 107, 968 to 971 and 1185 of 1972.
Appeals by special leave from the judgment and order dated
the September 24, 1971 of the Delhi High Court in L.PsAs.
NC3. 172, 177, 151, 170, 171 and 152 of 1971 respectively.
Civil Appeal No. 1168 of 1972.
Appeal by Special Leave from the judgment and Order dated
the 17th April, 1971 of the Delhi High Court in L.P.A. No.
94 of 1971.
A. K. Sen, (in W.P. No. 362/72), L. M. Singhvi (in W.P.
No. 363/72 & C.A. No. 968/72), S. K. Dhingra (in C.A. No.
968/72) and B. Dutta, for the petitioners (in W.Ps.)
and appellants (in C.As.)
L. N. Sinha, Sol. General of India, S. N. Prasad (in W.P.
No. 363/72 and C.A. No. 968 of 1972 only) and R. N.
Sachthey, for the respondents Nos. 1-3 (in C.A. No. 968,
970, 107/72 and W.P. Nos. 362-363 of 1972 and respondents in
other appeals.
805
Sardar Bahadur Saharya and Vishnu Bahadur Saharya, for
respondent No. 4 (in C.As. Nos. 107 & 968/72).
K. K. Sinha, S. K. Sinha and B. B. Sinha, for respondent
Nos. 5, 6, 8 (in C.A. No. 968/72).
Vinoo Bhagat, for respondent no. 4 (in C.A. No. 970/72).
Ashok Grover, for respondent no. 5 (in C.A. No. 107/72).
S. K. Dholakia, for respondent no. 6 (in C.A. No. 107/72).
T. V. S. Narasimhachari, for respondent no. 7 (in C.A. No.
107/72).
L. M. Singhvi and S. K. Dhingra, for the interveners.
The Judgment of the Court was delivered by
MATHEW, J. These writ petitions and civil appeals raise
common questions and they are, therefore, disposed of by a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 12
common judgment. The Civil Appeals arise out of the
decision of High Court of Delhi dismissing the writ
petitions filed by the appellants challenging-the, validity
of the proceedings for acquisition of the land in question
for "planned development of Delhi". In the writ petitions,
the validity of the same proceedings is being challenged on
certain additional grounds also.
A notification under s. 4 of the Land Acquisition Act
(hereinafter referred to as the Act’) was issued on November
13, 1950, stating that an area of 34,070 acres of land was
needed for a public purpose, viz., the planned development
of Delhi. Between 1959 and 1961, about six thousand
objections were filed under s. 5A of the Act. The objec-
tions were civerruled. On March 18, 1966, the declaration
under S. 6 of the Act was published in respect of a portion
of the area. Thereafter, in 1970, notices were issued under
s. 9(1) of the, Act requiring the appellants to state their
objections, if any, to the assessment of compensation. The
appellants thereupon challenged the validity of proceedings
for acquisition before the, High Court of Delhi on the
following, grounds : (1) that the acquisition was not for
public purpose but for companies and so the provisions of
Part VII of the Act ought to have been complied with, (2)
since no part of the compensation payable came from the
public exchequer, the acquisition was not for a public
purpose and (3) that the proceedings for acquisition
violated the fundamental right of the, appellants under
Article 19(1)(f) as there was unreasonable delay between the
publication of the notification under s. 4 and the issue of
the notices under s. 9 of the Act with the result that the
appellants were deprived of the benefit of the appreciation
in value of the property after the date of the notification
under s. 4. The High Court negatived the contentions and
dismissed the writ petitions.
The main arguments addressed before us on behalf of the
appellants and the writ petitioners were that the public
purpose specified in the notification issued under s. 4,
namely, the planned development of Delhi’ was vague as
neither a Master Plan nor a Zonal Plan was in existence on
the date of the notification and as the purpose specified
806
in die, notification was vague, the appellants were unable
to exercise effectively their right under s. 5A of the Act
and that as the notification under s. 4 was published in
1959, the compensation awarded was wholly inadequate with
reference to the market value of the property on the date
when the appellants are to be deprived of their possession
of the property. In other words the contention was that as
there was inordinate delay in finalizing the acquisition
proceedings, the appellants were deprived of the benefit of
the appreciation in the value of the property between the,
date of the notification under s. 4 and the date of taking
possession of the property. Linked with this contention was
the submission that the previsions of s. 23 of the Act which
lay down that compensation should be determined with
reference to the market value of the land as on the date of
the notification under s. 4 was an unreasonable restriction
on the fundamental right of the appellants to hold and
dispose of property under Article 19(1) (f). It was further
contended that as the acquisition of the property was for
the purpose of planned development of Delhi, the only
authority competent to issue the notification under s. 4 was
the Central Government under s. 15 of the Delhi Development
Act and since the proceedings were initiated by the Chief
Commissioner of Delhi, the proceedings were ab initio
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 12
invalid. The argument was that, as the acquisition was made
for the planned development of Delhi, it could be carried
out’ only in accordance with the provisions of the Delhi
Development Act, and that, under s. 15 of that Act, it was
only the Central Government which could have issued the
notification under s. 4, after having formed the opinion
that the acquisition of the land was necessary for the
planned development of Delhi and, since the notification was
issued by the Chief Commissioner of Delhi, the notification
was void ab initio. The last contention was that the
acquisition was not for any public purpose, but for
companies, as the major portion of the,land acquired was
allotted without any development to cooperative housing
societies which were companies within the definition of the
word Company’ in the Act and as the provisions of Part VII
of the Act were not complied with, the proceedings for
acquisition were bad.
The influx of displaced persons in 1947 from West Pakistan
into Delhi aggravated the problem of housing accommodation
in Delhi. With the extension of industrial and commercial
activities and the setting up of the foreign embassies,
Delhi acquired enormous potential as an employment centre.
The consequent increase in the population was not
accompanied by an adequate expansion of lousing facilities.
There was haphazard and unplanned growth of houses in
different areas; land also was not available at reasonable
price as substantial portion of the available land, suitable
for development, had passed into the hands of private
enterprises. The Government found it necessary to take
effective steps to check the haphazard growth of houses and
to prevent substandard construction. Therefore, the
Government framed a scheme for "planned development of
Delhi". It was in order to implement the scheme of planned
development of Delhi that the Government decided to acquire
34,070 acres of land in 1959 and published the notification
under s. 4 specifying the public purpose as "the planned
development of Delhi".
807
Section 4 of the Act says that whenever it appears to the
appropriate Government that land in any locality is needed
or. is likely to be needed for any public purpose, a
notification to that effect shall be published in the
official Gazette and the Collector shall cause public notice
of the substance of such notification to be given at
convenient places in the said locality. According to the
section, therefore, it is only necessary to state in the
notification that the land is needed for a public purpose.
The wording of s. 5A would make it further clear that all
that is necessary to be specified in a notification under s.
4 is that the land is needed for a public purpose. One
reason for specification of the particular public purpose in
the, notification is to enable the person whose land is
sought to be acquired to file objection under s. 5A. Unless
a person is told about the specific purpose of the acquisi-
tion it may not be possible for him to file a meaningful
objection against the acquisition under s. 5A. This Court
has laid down that it is necessary to specify the particular
public purpose in the notification for which the land is
needed or likely to be needed as, otherwise, the matters
specified in sub-section (2) of s. 4 cannot be carried out.
in Munshi Singh and Others v. Union of India, etc.(1) the
Court said
"It is apparent from sub-section (2) of s. 4
that the public purpose which has to be stated
in sub-section (1) of s. 4 has to be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 12
particularized because, unless that is done,
the various matters which were mentioned in
sub-section (2) cannot be carried out and if
the public purpose stated in s. 4(1) is
planned development, without anything more, it
is extremely difficult to comprehend how all
the matters set out in sub-section (2) can be
carried out by the officer concerned."
We think that the question whether the purpose specified in
a notification under s. 4 is sufficient to enable an
objection to be filed under s. 5A would depend upon the
facts and circumstances of each case.
In Arnold Rodricks and Another v. State of Maharashtra and
Others(2), this Court held that a notification under s. 4 of
the Act which stated that the land was needed for
"Development and utilization of the said lands as an
industrial and residential area" was sufficient
specification of public purpose.
In the case of an acquisition of a large area of land
comprising several plots belonging to different persons, the
specification of the purpose can only be with reference to
the acquisition of the whole area. Unlike in the case of an
acquisition of a small area, it might be practically
difficult to specify the particular public purpose for which
each and every item of land comprised in the area is needed.
Assuming for the moment that the public purpose was not
sufficiently specified in the notification, did the
appellants make a grievance of it at the appropriate time?
If the appellants had really been prejudiced by the non-
specification of the public purpose for which the
(1) [1973] 1 SCR 973, at 975 and 984.
(2) [1966] 3 S.C.R. 885.
808
plots in which they were interested were needed, they should
have taken steps to have the notification quashed on that
ground within a reasonable time. They did not move in the
matter even after the declaration under r 6 was published in
1966. They approached the High Court with their writ
petitions only in 1970 when the notices under s. 9 were
issued to them. In the concluding portion of the judgment
in Munshi Singh & Others v. Union of India (supra), it was
observed :
"In matters of this nature we would have taken
due notice of laches on the part of the
appellants while granting the above relief but
we are satisfied that so far as the present
appellants are concerned they have not been
guilty of laches, delay or acquiescence, at
any stage."
We do not think that the appellants were vigilant.
That apart, the appellants did not contend before the High
Court that as the particulars of the public purpose were not
specified in the notification issued under s. 4, they were
prejudiced in that they could not effectively exercise their
right under s. 5A. As the plea was not raised by the
appellants in the writ petitions filed before the High
Court, we do not think that the appellants are entitled to
have the plea considered in these appeals.
Nor do we think that the petitioners in the writ petitions
should be allowed to raise this plea in view of their
conduct in not challenging the validity of the, notification
even after the publication of the declaration under s. 6 in
1966. Of the two writ petitions, one is filed by one of the
appellants. There was apparently no reason why the writ
petitioners should have waited till 1972 to come to this
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 12
Court for challenging the validity of the notification
issued in 1959 on the ground that the particulars of the,
public purpose were not specified. A valid notification
under s. 4 is a sine qua non for initiation of proceedings
for acquisition of property. To have sat on the fence and
allowed the Government to complete the, acquisition
proceedings on the basis that the notification under s. 4
and the declaration under s. 6 were valid and then to attack
the notification on grounds which were available to them at
the time when the notification was published would be,
putting a premium on dilatory tactics. The writ petitions
are liable to be dismissed on the ground of laches and delay
on the part of the petitioners (see Tilokchand Motichand and
Others v. H. B. Munshi and Another(1); and Rabindranath Bose
and Others v. Union of India & Others(2).
From the counter affidavit filed on behalf of the
Government, it is clear that the Government have allotted a
large portion of the land after the acquisition proceedings
were finalised to Cooperative lousing societies. To quash
the notification at this stage would disturb the rights of
third parties who are not before the Court.
(1) [1969] 2 S.C.R. 824. (2) [1970] 2 S.C.R. 697.
809
As regards the second contention that there, was inordinate
delay in finalizing the acquisition proceedings, and that
the appellants and writ petitioners were deprived of the
appreciation in value of the land in which they were
interested, it may be, noted that about 6,000 objections
were filed under s. 5A by persons interested in the
property. Several writ petitions were also filed in 1966
and 1967 challenging the validity of the acquisition
proceedings. The Government had necessarily to wait for the
disposal of the objections and petitions before proceeding
further in the matter. Both the learned Single Judge as
well as the Division Bench of the High Court were of the
view that there was no inordinate delay on the part of the
Government in completing the acquisition proceedings. We
are not persuaded to come to a different conclusion.
Linked with the above contention was the argument that the
provisions of s. 23 of the Act imposes unreasonable
restrictions upon the fundamental right of the appellants
and writ petitioners to hold and dispose of property under
Article 19(1)(f) of the, Constitution as compensation is
awardable only with reference to the value of the property
on the date of notification under s. 4 however long the pro-
ceedings for acquisition may drag on and not with reference
to the market value of property when it is taken possession
of. It was submitted that compensation should be paid with
reference to the value of the property as on the date when
possession of the, property is taken and the section’, as it
lays down that compensation should be fixed with reference
to the market value as on the date of the notification under
s. 4, abridges the fundamental right of a citizen under
Article 19 (1) (f). We find- that the argument is not
persuasive. Article 31(5) (a) provides :
"(5) Nothing in clause (2) shall affect--
(a) the provisions of any existing law other
than a law to which the provisions of clause
(6) apply,"
The, Land Acquisition Act is a pre-Constitution Act. Its
provisions are not, therefore, liable to be challenged on
the ground that they are not in conformity with the
requirement of article 31(2). What the appellants and writ
petitioners complain is, that their properties were acquired
by paying them compensation computed with reference to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 12
market value of the land as on the date of the notification
under s. 4 and that s. 23 is, therefore, bad. This, in
substance, is nothing but a challenge to the adequacy of
compensation. Such a challenge is precluded by reason of
Article 31(5). In other words, the appellants and the writ
petitioners cannot challenge the validity of s. 23 on the
ground that compensation payable under its provisions is in
any way inadequate, because, such a challenge would fly in
the face of Article 31(5).
It is noteworthy that s. 4(3) of the Land Acquisition
Amendment and Validation Act, 1957 provides for payment of
interest at 6 per cent of the market value after the expiry
of 3 years from the date of the notification under s. 4 to
the date of payment of compensation. Section 24 of the Act
provides that any outlay or improvements on,
810
or disposal of the land acquired, commenced, made or
effected without the sanction of the Collector after the
date of the publication of the notification under s. 4(1)
shall not be taken into consideration by the Court in
awarding compensation. This provision means that any outlay
or improvement made with the sanction of the Collector after
the date of the notification will be taken into
consideration in awarding compensation.
In R. C. Cooper v. Union of India(1), this Court has
observed that although a law for acquisition of property
must pass the test of Article 19(5), the challenge to the
law would ordinarily be limited to the question of
procedural unreasonableness. This is what the Court said
". . . Where the law provides for compulsory
acquisition of property for a public purpose,
it may be presumed that the acquisition or the
law relating thereto imposes a reasonable
restriction in the interest of the general
public. If there is no public purpose to
sustain compulsory acquisition, the law
violates Art. 31(2). If the acquisition is
for a public purpose, substantive
reasonableness of the restriction which
includes deprivation may, unless otherwise
established, be presumed, but enquiry into
reasonableness of the procedural provisions
will not be excluded. For instance, if a
tribunal is authorised by an Act to determine
compensation for property compulsorily
acquired, without hearing the owner of the
property, the Act would be liable to be struck
down under Art. 19(1)(f)."
It follows that although S. 23 of the Act can be challenged
on the ground that it violates the fundamental right of a
citizen to hold and dispose of property under Article 19 (1
) (f), the challenge would practically be limited to the
question of procedural reasonableness. But section 23 does
not deal with procedure and cannot, therefore, suffer from
any procedural unreasonableness. When it is seen that S. 23
is not liable to be challenged on the ground that the
compensation provided by its provisions is inadequate in
view of the provisions of Art. 31(5), there is no point in
the contention that it can be challenged for that very
reason on the basis that it imposes unreasonable restriction
upon a citizen’s right to hold and dispose of- property.
It was argued that there could be no planned development of
Delhi otherwise than in accordance with the provisions of
the Delhi Development Act and, therefore, the notification
under S. 4 of the Act should have been issued by the Central
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 12
Government in view of S. 15 of that Act and not by the
Chief Commissioner of Delhi.
Section 12 of the Delhi Development Act, 1957
provides :
"12(1) As soon as may be after the
commencement of this Act, the Central
Government may, by notification in the
(1) [1970] 3 S.C.R. 530, at 577.
811
official Gazette, declare any area in Delhi to
be a development area for the purposes of this
Act
Provided that no such declaration shall be
made unless a proposal for such declaration
has been referred by the Central Government to
the Authority and the Municipal Corporation of
Delhi for expressing their views thereon
within thirty days from the date of the
receipt of the reference or within such
further period as the Central Government may
allow and the period so specified or allowed
has expired.
(2) Save as otherwise provided in this Act, the Authority
shall not undertake or carry out any development of land in
any area which is not a development area.
(3) After the commencement of this Act no development of
land shall be undertaken or carried out in any area by any
person or body (including a department of Government)
unless,-
(i) where that area is a development area,
permission for such development has been
obtained in writing from the Authority in
accordance with the provisions of this Act;
(ii) where that area is an area other than a
development area, approval of, or sanction
for, such development has been obtained in
writing from the local authority concerned or
any officer or authority thereof empowered or
authorised in this behalf, in accordance with
the provisions made by or under the law
governing such authority or until such
provisions have been made, in accordance with
the provisions of the regulations relating to
the grant of permission for development made
under the Delhi (Control of Building
Operations) Act, 1955, and in force
immediately before the commencement of this
Act.
Provided that the local authority concerned may subject to
the provisions of s. 53A amend those regulations in their
application to such area.
(4) After the coming into operation of any of the plans in
any area no development shall be undertaken or carried out
in that area unless such development is also in accordance
with such plans.
(5) Notwithstanding anything contained in sub-sections (3)
and (4) development of any land begun by any department of
Government or any local authority before the commencement of
this Act may be completed by that department or local
authority without compliance with the requirements of those
sub-sections.
Section 15 of the Delhi Development Act, 1957
states
"15(1) If in the opinion of the Central
Government, any land is required for the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 12
purpose of development, or for any
812
other purpose, under this Act, the Central
Government may acquire such land under the
provisions of the Land Acquisition Act, 1894.
(2) Where any land has been acquired by the
Central Government, that Government may, after
it has taken possession of the land, transfer
the land to the Authority or any local
authority for the, purpose for Which the land
has been acquired on payment by the Authority
or the local authority of the compensation
awarded under that Act and of the charges
incurred by the Government in connection with
the acquisition."
Counsel contended that on the date when the notification
under s. 4 was published, the Government had not declared
any area in Delhi is a development area under s. 12(1) of
the Delhi Development Act, nor was there a master plan drawn
up in accordance with s. 7 of that Act and so the
acquisition of the property for planned development of Delhi
was illegal. Under s. 12(3) of the Delhi Development Act,
no development of land can be undertaken or carried out
except as provided in that clause. Section 2(d) states :
"development". with its grammatical variations means the
carrying out of building, engineering, mining or other
operations in, on, over or under land or’ the making of any
material change in any building or land includes re-
development. Section 2(e) states "development area"’ means
any area declared to be a development area under sub-section
(1) of s. 12.
The planned development of Delhi had been decided upon by
the Government before 1959, viz., even before the Delhi
Development Act came into force. It is true that there
could be no planned development of Delhi except in
accordance with the provisions of Delhi Development Act
after that Act came into force, but there was no inhibition
in acquiring land for planned development of Delhi under the
Act before the Master Plan was ready (see the decision in
Patna Improvement Trust v. Smt. Lakshmi Devi and Others(1).
In other words, the fact that actual development is
permissible in an area other than a development area with
the approval or sanction of the local authority did not
preclude the Central Government from acquiring the land for
planned development under the Act. Section 12 is concerned
only with the planned development. It has nothing to do
with acquisition of property; acquisition generally precedes
development. For planned development in an area other than
a development area it is only necessary to obtain the
sanction or approval of the local authority as provided in
S. 12(3). The Central Government could acquire any property
under the Act and develop it after obtaining the approval of
the local authority. We do not think it necessary to go
into the question whether the power to acquire the land
under s. 15 was delegated by the Central Government to the
Chief Commissioner of Delhi. We have already held that the
appellants and the writ petitioners cannot be allowed to
challenge the validity of the notification under s. 4 on the
ground of laches and acquiescence. The plea that the Chief
Commissioner of Delhi had no authority to initiate the
(1) [1963] Supp. 2 S.C.R. 812.
813
proceeding for acquisition by issuing the notification under
s. 4 of the Act as s. 15 of the Delhi Development Act gives
that-power only to the Central Government relates primarily
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 12
to the validity of the notification. Even assuming that the
Chief Commissioner of Delhi was not authorized by the
Central Government to issue the notification under s. 4 of
the Land Acquisition Act, since the appellants and the writ
petitioners are precluded by their laches and acquiescence
from questioning the notification, the contention must, in
any event, be negatived and we do so.
It was contended by Dr. Singhvi that the acquisition was
really for the cooperative housing societies which are
companies within the definition of the word company’ in s.
3(e) of the Act, and, therefore, the provisions of Part VII
of the Act should have been complied with. Both the learned
Single Judge and the Division Bench of the High Court were
of the view that the acquisition was not for company. We
see no reason to differ from their view. The mere fact that
after the acquisition the Government proposed to hand over,
or, in fact, handed over, a portion of the property acquired
for development to the cooperative housing societies would
not make the acquisition one for company’. Nor are we
satisfied that there is any merit in the contention that
compensation to be paid for the acquisition came from the
consideration paid by the cooperative societies. In the
light of the averments in the counter affidavit filed in the
writ petitions here, it is difficult to hold that it was
cooperatives which provided the fund for the acquisition.
Merely because the Government allotted a part of the
property to cooperative societies for development, it would
not follow that the acquisition was for cooperative
societies, and therefore, Part VII of the Act was attracted.
It may be noted that the validity of the notification under
s. 4 and the declaration under s. 6 was in issue in Udai Ram
Sharma and Others v. Union of India(1) and this Court upheld
their validity.
We see no merit in the appeals and the writ petitions. They
are, therefore, dismissed with costs.
Petitions dismissed.
(1) [1968] 3 S.C.R. 41.
814