NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6257 OF 2013
(Arising from SLP(C) No.8168 of 2013)
Orissa Power Transmission Corporation
Limited and others ..Appellants
versus
Asian School of Business Management
Trust and others ..Respondents
J U D G M E N T
G.S. SINGHVI, J.
JUDGMENT
1. Leave granted.
2. In exercise of the power vested in it under Section 29 of the
Electricity (Supply) Act, 1948 (for short, ‘the Act’), Orissa State Electricity
Board (for short, ‘the Board’) (predecessor of appellant No.1) framed about
50 transmission schemes, which were notified on 30.05.1991 to enable the
licensees and other interested persons to make representations. The
1
Page 1
notification was published in official gazette dated 20.7.1991. For the sake
of reference, the relevant portions of the notification are extracted below:
ASADHA 29, 1913
ORISSA STATE ELECTRICITY BOARD
BHUBANESWAR
NOTIFICATION
th
The 30 May 1991
No.4459- In accordance with Section-29 of Electricity
(Supply) Act, 1948, the following transmission schemes which
the Orissa State Electricity Board intends to undertake for
execution, are published for general information. It is also
notified in the interest of general public that any person
interested in making representation regarding the execution of
the above schemes, may submit such representation in writing
so as to reach the Secretary, Orissa State Electricity Board,
Bhubaneswar-751007 within 2 (two) months from the date of
publication. Full details of the schemes and the plan may be
seen in the Office of the Chief Engineer (Planning, Monitoring
and Coordination), Orissa State Electricity Board, Bhubaneswar
on any working day during office hours.
JUDGMENT
(A) 220 KV LINES
| Sl.<br>No. | Name of the Scheme | (Rs.In lakhs) |
|---|
| (1) | (2) | (3) |
| 2 | 220 KV DC line from<br>Meramundali to<br>Bhubaneswar<br>(Chandaka) 150 Kms @ | 2170.50 |
2
Page 2
(emphasis supplied)
That notification reads as under:
“The Orissa Gazette
EXTRAORDINARY PUBLISHED BY AUTHORITY
No.177 CUTTACK, THURSDAY FEBRUARY 15,
1996 / MEGHA 26, 1917
ORISSA STATE ELECTRICITY BOARD
BHUBANESWAR
NOTIFICATION
The 30th January, 1996
No. 589 - PL.II-PFC-18/95 - In partial modification of Schemes
against Sl.No. 2 of Gazette Notification No. 857, dated the 20th
July, 1991 and in accordance with Section 29 of Electricity
(Supply) Act, 1948, the following transmission schemes which
the Orissa State Electricity Board intends to undertake for
execution, are published for general information. It is also
notified in the interest of general public that any person
interested in making representation regarding the execution of
the above schemes, may submit such representation in writing
so as to reach the Secretary, Orissa State Electricity Board,
Bhubaneswar -751007 within two months from the date of
publication. Full details of the scheme and the plan may be seen
in the office of the Chief Engineer (Transmission Project),
O.S.E.B., Bidyut Bhawan, Sahidnagar, Bhubaneswar-751007
on any working day during office hours.
JUDGMENT
3
Page 3
Name of the Scheme :- Strengthening of transmission network
in and around Chandaka Command area (Bhubaneswar) and
Bidanasi (Cuttack) Command area as per the detail scope
furnished below:
| | mand area.<br>tage profile in Bhubane<br>ur Transmission System | | | |
| SlScope of S<br>Sl.No. | | cheme | | Approximate<br>estimated cost in<br>lakhs of rupees | |
| 12 | | | | 3 |
| 1M1.eramundali-Chandaka/Mendhasal<br>(bhubaneswar) 400 KV DC line. ( 110<br>Kms. ) with 220 KV bay extension at<br>Chandaka and IVIeramundali. | li-Chandaka/Mendhasal<br>ar) 400 KV DC line. ( 1 | | | 5,918.00 |
| JUDGMENT<br>2Chandaka(Bhubaneswar)-Bidanasi<br>(Cuttack) 220 KV DC line with bay<br>Extension(25 Kms.). | | | | 990.00 |
| 3Construction of 2 x 100 MVA, 220/132<br>KV substation at Bidanasif Cuttack). | | | | 1,368.00 |
| 4Bidanasi (Cuttack)-Nuapada (Cuttack)<br>132 KVDC link line with bay Extension<br>(13.6 Kms.) | | | | 880.00 |
| Total | | | | 9,156.00 lakhs |
(emphasis supplied)
4
Page 4
4. None of the licensees/other interested persons are shown to have made
representation against any of the schemes including the one mentioned at
item No.2 of notification dated 30.5.1991 and item No.1 of notification
5. After 14 years and 6 months of publication of the schemes, Human
Resources Development and Management Trust of India (for short, ‘the
Trust’) (predecessor of respondent No.1), who had purchased some parcels
of land in Mauza Andharua, Tahsil Bhubaneswar, District Khurda vide sale
deed dated 30.10.2005 raised objection against execution of the scheme
mentioned at item No.2 of notification dated 30.5.1991 on the ground that
two of the transmission towers proposed to be erected would cross the
building constructed by it. The Trust also requested appellant No.1 to shift
the transmission towers and line to an alternative site.
JUDGMENT
6. Appellant No.1 and its officers did not accept the
objection/representation of the Trust, who then filed Civil Suit No. 72 of
2006 in the Court of Civil Judge (Junior Division), Bhubaneswar and prayed
for grant of the following relief:
“The plaintiff therefore humbly prays that this Hon'ble Court
may graciously be pleased to pass a decree declaring that the
defendant has no right to enter into the suit schedule property
and also pass decree of permanent injunction permanently
5
Page 5
injunction the defendants from erecting/ constructing any tower
on the suit schedule property and decree the suit with cost to the
plaintiff.”
regarding construction be maintained. That order was made absolute on
26.4.2006 and the appellants were restrained from entering the suit land and
constructing any tower. That order was set aside by Ad-hoc Additional
District Judge, Bhubaneswar in FAO (Misc. Appeal) No.40/33 of 2006
decided on 4.10.2008. The Additional District Judge noted that all the
towers had already been erected on both sides of the disputed land and,
therefore, it is not possible for the appellant to erect any tower leaving the
suit land and thereby compromise the public interest. In the opinion of the
learned Additional District Judge, the Trust could be compensated by the
JUDGMENT
competent authority.
8. The Trust challenged the appellate order in Writ Petition (C)
No.14806 of 2008, the prayer clause of which reads as under:
“The petitioner therefore, humbly prays that this Hon'ble Court
may graciously be pleased to admit the writ application and call
for the records from the court below and upon hearing the
parties be pleased to issue a writ in nature of Certiorari or any
other appropriate writ(s), direction(s) quashing the impugned
order dtd. 04.10.2008 passed by the learned Adhoc Additional
6
Page 6
District Judge, F.T.C. No. 3, Bhubaneswar in F.A.O. (Misc.
appeal ) No. 40/33 of 2006 under Annexure - 9 and restrain the
opp. parties from entering the suit schedule property of the
petitioner and from erecting/constructing any tower on suit
schedule property, pending adjudication of the writ petition.
9. The learned Single Judge of the High Court dismissed the writ
petition vide order dated 21.11.2008, the relevant portions of which are
extracted below:
“17. As per the affidavit filed today, the entire work on either
side on the suit land was completed and, therefore, the
argument of the learned counsel for the respondent was that the
petitioner is not entitled to any order of injunction as every
work sought to be injuncted was already completed.
18. Further when once no objection was raised within the
statutory period, the subsequent belated correspondence by any
officer of Respondent may not act as an estoppel against them
because such officer is not entitled to forgo the statutory period
of prescribed for receiving objections or to extend it or even to
waive it. Moreover, after having purchased the land in
December, 2005, the building was constructed below the power
line by petitioner only in July 2006, after knowing fully well
that negotiation with officers of respondent failed.
JUDGMENT
19. In these circumstances, even assuming for argument
sake, that there is some illegality in the Scheme, then what is
provided in Section 12 of the Indian Electricity Act is only
compensation and not dismantling of the entire line of
numerous towers erected at the heavy cost of public money.
Moreover, the scheme involves public interest. When private
interest is at stake and especially when compensation is
awardable, no injunction could be granted especially when
7
Page 7
work sought to be injuncted has already been completed.
Viewed in this angle, I am not able to entertain the writ petition
and I find no error in the effect of the order of the lower
appellate court.”
“(I) Directing the Opposite Parties No.1 to 3 not to make any
construction of the transmission tower/line-within the premises
of the petitioner;
(II) Directing the Opposite Parties No.1to 3 to take a final
decision regarding re-routing/re-alignment of the 220/132 KV
Mendhasal – Bidanasi over head line within a stipulate time
after completion of the profile survey by the petitioner.”
11. The learned Single Judge noticed the prayer made in the civil suit, the
orders passed by the trial Court, the lower appellate Court and the High
Court in Writ Petition No.14806/2008, referred to the judgments of this
JUDGMENT
Court in K.S. Rashid and Son v. Income Tax Investigation Commission and
others, AIR 1954 SC 207, Bombay Metropolitan Region Development
Authority, Bombay v. Gokak Patel Volkart Limited and others (1995) 1
SCC 642, Jai Singh v. Union of India and others, AIR 1977 SC 898 and held
that the writ petition was not maintainable because the civil suit was pending
before the competent Court. The learned Single Judge then considered
whether the second writ petition was barred by res judicata and answered
8
Page 8
the same in the affirmative by observing that the cause of action for filing
the two petitions was the same and identical reliefs had been sought by
respondent No.1. The learned Single Judge relied upon the judgments in
1, State of Karnataka and another v. All India Manufacturers Organization
and others (2006) 4 SCC 683, Direct Recruit Class-II Engineering Officers’
Association v. State of Maharashtra and others (1990) 2 SCC 715 and
Forward Construction Co. and others v. Prabhat Mandal (Regd.), Andheri
and others AIR 1986 SC 391 and held that the prayer made in the second
writ petition does not merit consideration. The learned Single Judge also
adverted to the issue of public interest and observed:
“The paramount public interest in this case cannot be lost sight
of. On one hand, the larger interest of the State involving lakhs
of electricity consumers spreading over several districts of
Orissa and on the other hand the purported inconvenience of a
few hundred of students. Time and again, the apex Court has
deprecated the practice of the educational institutions acting in
violation of law and committing irregular and illegal acts and
thereafter, taking plea of career of the students. I am shocked
that in the case at hand even the threat of law and order
situation by the students has been argued. Plight of the students
is apparently due to improper action of the petitioner. If the
career of the students is at stake, the petitioner is solely and
wholly responsible for it.”
JUDGMENT
12. Having failed to convince the learned Single Judge to entertain its
prayer, respondent No.1 filed Writ Appeal No. 393 of 2010. During the
9
Page 9
pendency of the appeal, respondent No.1 filed an application in the name of
the Trust for withdrawal of the suit. The trial Court allowed the application
vide order dated 16.3.2011, which reads as under:
13. The Division Bench of the High Court reversed the findings recorded
by the learned Single Judge on the issue of maintainability of the writ
petition by observing that the reliefs claimed in the two writ petitions were
different. The Division Bench then referred to Sections 28 and 29 of the Act
and held that notifications dated 30.05.1991 and 30.01.1996 were ultra vires
JUDGMENT
the provisions of those sections because the procedure prescribed in those
sections had not been followed and concurrence of the competent authority
had not been obtained. The Division Bench also referred to interlocutory
orders passed by it for production of full details of the scheme and held that
the documents produced on behalf of the appellants herein were not
sufficient to prove that the scheme had been framed, published and modified
10
Page 10
in accordance with the provisions of the Act and that in the absence of
approval of the Central Government, the scheme cannot be implemented.
the Division Bench of the High Court on the validity of the scheme is ex-
facie erroneous and is untenable. Learned senior counsel pointed out that
notifications dated 30.5.1991 and 30.1.1996 were issued in accordance with
Section 29 of the Act and both the notifications contained a clear stipulation
that full details of the scheme and the plan can be seen in the office of the
Chief Engineer (Planning, Monitoring and Coordination) and argued that a
person who had purchased land after more than 14 years of the issue of first
notification and raised construction after the scheme had been substantially
executed could not have challenged the same on the ground of lack of
JUDGMENT
particulars/details or any error in the notifications because the landowner(s)
had neither made any representation nor filed objections. Shri Rao
emphasized that the approval of the Central Government was not necessary
because cost of the scheme was less than rupees hundred crores and as per
notification dated 28.12.1995 issued by the Government of India,
concurrence of the Central Electricity Authority was required only if the cost
of the scheme was more than hundred crores. Learned senior counsel then
11
Page 11
argued that the second writ petition filed by respondent No.1 should have
been dismissed by the High Court by invoking the doctrine of res judicata
because similar prayer had been rejected in the earlier round of litigation.
Mohanty, Assistant General Manager, EHT(Construction) before the High
Court to show that none of the three alternative proposals were feasible.
Shri Rao also invited the Court’s attention to additional affidavit dated
26.4.2013 of Shri Amar Nath Mohanty to show that height of the two towers
LOC 36 and LOC 37 has been so raised that the line will be 4.58 meters
(14.56 feet) above the existing line and there will be a clearance of 9 meters
(28.62 feet) between the highest point of existing three storey building in the
campus of respondent No.1 and the proposed line as against the requirement
of 5.4 meters (17.17 feet) in terms of Rule 80 of the Indian Electricity Rules,
JUDGMENT
1956. From the affidavit of Shri Amar Nath Monhanty, Shri Rao also
pointed out that tower Nos. LOC 1 to 35 and LOC 40 to 117 have already
been erected over a length of 31.124 kilometers by spending Rs.14.31
crores. In the end, the learned senior counsel submitted that even if there
was any mistake in the description of the scheme, the High Court should not
have interfered with the same because appellant No.1 had already erected
12
Page 12
towers by spending huge amount and it would not be in public interest to
change the route of the line by shifting/dismantling the existing towers.
Division Bench of the High Court did not commit any error by directing
appellant No.1 to re-align the transmission line by shifting the transmission
towers to some other area because construction thereof will be highly
detrimental to the people including the students living in the Campus. Dr.
Singhvi further argued that the scheme framed by the Board cannot be
executed because the same was not framed after following the procedure
prescribed under Sections 28 and 29 of the Act. Learned senior counsel
pointed out that the scheme mentioned at item No.2 of notification dated
30.5.1991 and at item No.1 of notification dated 30.1.1996 does not relate to
JUDGMENT
the area in which the land of respondent No.1 is situated and, therefore, the
appellants cannot erect transmission towers over the existing buildings.
Learned senior counsel then argued that the Division Bench of the High
Court rightly refused to apply the doctrine of res judicata because the reliefs
claimed in the two proceedings were entirely different. In support of this
argument, Dr. Singhvi relied upon the judgment of this Court in S.J.S.
Business Enterprises (P) Ltd. v. State of Bihar (2004) 7 SCC 166.
13
Page 13
16. We have considered the respective arguments. Sections 28 and 29 of
the Act, which have bearing on the decision of this appeal read as under:
| of its duti<br>, as the ca | es under th<br>se may be |
|---|
(2) The Board or, as the case may be, the Generating
Company which has prepared a scheme may, sanction such
scheme either generally or in respect of any part of the area
specified in the scheme and where a scheme has been
sanctioned in respect of any part of the area, such scheme may
subsequently be sanctioned in respect of any other part of that
area:
Provided that where the scheme is of the nature referred to in
subsection (1) of section 29, the scheme shall not be sanctioned
(generally or for part of an area) by the Board or the Generating
Company except with the previous concurrence of the
Authority.
JUDGMENT
(2A) The Board or, as the case may be, the Generating
Company shall, as soon as may be after it has sanctioned any
scheme which is not of the nature referred to in section 29,
forward the scheme to the Authority and, if required by the
Authority so to do, supply to the Authority any information
incidental or supplementary to the scheme within such period as
may be specified by the Authority.
(3) Every scheme sanctioned under this section shall be
published in the Official Gazette and in such local newspapers
as the Board or, as the case may be, the Generating Company
may consider necessary.
14
Page 14
(3) The Board or, as the case may be, the Generating
Company may, after considering the representations, if any, that
may have been received by it and after making such inquiries as
it thinks fit, modify the scheme and the scheme so finally
prepared (with or without modifications) shall be submitted by
it to the Authority along with the representations.
JUDGMENT
(4) A copy of the scheme finally prepared by the Board or,
as the case may be, the Generating Company under sub-section
(3) shall be forwarded to the State Government or State
Governments concerned:
Provided that where the scheme has been prepared by a
Generating Company in relation to which the Central
Government is the competent government or one of the
competent governments, a copy of the scheme finally prepared
shall be forwarded also to the Central Government.
15
Page 15
(5) The Authority may give such directions as to the form
and contents of a scheme and the procedure to be followed in,
and any other matter relating to, the preparation, submission
and approval of such scheme, as it may think fit.
| r sub-sectio<br>ting Com | n (1), the<br>pany shall |
|---|
17. An analysis of the above reproduced provisions makes it clear that the
Board or the Generating Company can prepare one or more schemes for
efficient performance of its duties under the Act. Such schemes may relate
to the establishment or acquisition of the generating stations, tie-lines, sub-
stations or transmission lines. By notification dated 28.12.1995 issued by
the Government of India in the context of Section 29(1) of the Act,
JUDGMENT
concurrence of the Central Electricity Authority was made mandatory for the
schemes involving capital expenditure of hundred crores. Therefore, no
scheme involving capital expenditure of rupees hundred crores or more can
be sanctioned by the Board or Generating Company except with the previous
concurrence of the Central Electricity Authority. In terms of Section 28(3),
the scheme is required to be published in the Official Gazette and in the
local newspapers. Section 29(2) requires that every scheme shall contain the
16
Page 16
estimates of the capital expenditure involved, salient features thereof and the
benefits likely to accrue therefrom. The scheme is required to be published
giving the licensees and other interested persons an opportunity to make
the Board or the Generating Company, as the case may be, before finalizing
the scheme. In terms of Section 29(5), the competent authority can give
appropriate direction in the matter of preparation of scheme or call upon the
Board or the Generating Company to supply information incidental or
supplementary to the scheme.
18. A reading of notification dated 30.5.1991 makes it clear that the
Board had notified almost 50 schemes and invited representations from
interested persons. Some of the schemes were subsequently modified by
notification dated 30.1.1996. In both the notifications, it was specifically
JUDGMENT
mentioned that full details of the schemes and the plans can be seen in the
office of the Chief Engineer (Planning, Monitoring and Coordination) /
Chief Engineer (Transmission Project). The landowner(s) from whom the
Trust purchased the land vide sale deed dated 30.10.2005 neither made any
representation nor filed objection against the scheme. Indeed, it is not even
the pleaded case of respondent No.1 that anyone else had made
representation or filed objection against any of the schemes. Therefore,
17
Page 17
neither the Trust nor respondent No.1, who constructed buildings knowing
fully well that the Board had already framed scheme for the area in which its
land was situated could object to erection of the remaining two towers or
commit any illegality by refusing to entertain the request of respondent No.1
for shifting of the transmission towers by diverting 220 KV line from the
existing alignment.
19. Unfortunately, the Division Bench of the High Court completely
overlooked the fact that respondent No.1 had stepped into the shoes of a
person who had no grievance against the scheme framed by the Board or
execution thereof by appellant No.1 and proceeded to decide the matter as if
execution of the scheme has commenced after construction of buildings by
respondent No.1. This is the first fatal flaw in the approach adopted by the
JUDGMENT
Division Bench of the High Court.
20. The exercise undertaken by the High Court for ascertaining the
availability of alternative route through which the transmission line could be
routed was totally unwarranted and half waked consideration of the
affidavits filed on behalf of the appellants has resulted in miscarriage of
justice. As noted above, the scheme was notified on 30.5.1991 and was
18
Page 18
modified on 30.1.1996. During this period, respondent No.1 was not in
picture. Admittedly, the Trust had purchased the land after more than 14
years and 6 months of initial publication of the scheme. Therefore, neither
alignment of the route and the Division Bench of the High Court committed
serious error by ordaining appellant No.1 to shift the transmission towers
from their present site completely ignoring the fact that almost 150 towers
had already been erected by appellant No.1 by spending more than rupees
fourteen crores. In paragraphs 8 to 15 of the additional affidavit filed by him
in Writ Appeal No.393/2010, Shri Amar Nath Mohanty spelt out the
following reasons for not accepting three alternatives suggested by
respondent No.1:
“ That in its sketch map produced in the Hon'ble Court on 18.02.2011
during hearing, the ASBM Trust has proposed three alternatives to
(a) divert/realign the now operating 220 KV Mendhasal-Chandaka
line and (b) divert /realign the ongoing 220 KV Mendhasal-Bidanasi
line in question to outside his premises identified in that sketch as:-
JUDGMENT
1 - Alternative-1
2 - Alternative-2
3 - Common to both Alternatives
1 -Alternative-1 line identified in the sketch as = A, IB, 1C
This diversion suggests to link the Bidanasi end at Point-A of
ongoing 220 KV Mendhasal-Bidanasi line with the existing
19
Page 19
operating 220 KV Mendhasal-Chandaka line towards Chandaka
end at Point-IC.
2 -Alternative-2 line identified in the sketch as = A 2B, 2C, 2D
| KV Men | dhasat-Bid |
| 20 KV M | endhasal- |
3- Line Common to both Alternatives identified in the sketch
as= 1,2,3
This diversion suggests to link the Mendhasal end at one of
existing tower location, of the on-going 220 KV Mendhasak
Bidanasi line through Point- 1 & 2 with the existing operating
220 KV Mendhasal -Chandaka line at its Chandaka end at
Point-3.
9. That all three proposals i.e Alternative 1(A, 1B,1C),
Alternative 2 (A,2B,2C,2D) and Common to both Alternative
(1,2 & 3) proposed by the ASBM Trust are not feasible to be
carried out.
(a) As per the proposal Alternative which is Common to both
Alternatives along with Alternative 2, if executed, will divert
the existing 220 KV Mendhasal-Chandaka line as well as the
220 KV Mendhasal-Bidanasi line in question from the premises
of ASBM. Any one such alternative can not divert either line. If
this proposal i.e Common Alternative with Alternative 2 is
worked out, it will involve erection of 7 Nos. of new towers
along with the transmission line in the proposed route and eight
Nos. of towers already constructed have to be
dismantled/abandoned. The cost of such diversion will involve
around Rs. 1 Crore excluding the amount of compensation payable
to the land owners over whose land the line and towers are to be
erected.
JUDGMENT
(b) As per the proposal the Alternative Common to both the
proposals can not be treated as a full-fledged Alternative unless
this is worked out along with the proposed Alternative 1. This
proposal will involve erection of six (6) new towers along with
20
Page 20
the transmission line and 5 Nos. of constructed towers have to
be abandoned/dismantled. The approximate cost of this
diversion will be little less than Rs.l crore besides compensation
payable to owners.
| ny private<br>over jungl | lands a<br>e lands and |
|---|
11. That as against the towers to be constructed on the land of
the ASBM, the diversion as proposed if worked out,
compensation payable will be much more since there will be
large number of owners as against the single owner ASBM
Trust.
12. That besides payment of compensation the proposed
diversion will also create series of Right of Way (ROW)
problems in view of the constructions and multistoried
buildings coming up over the route which will not be possible
in law without publishing fresh scheme in accordance with law.
This is highly impractical and hence not feasible.
JUDGMENT
13. That besides the above if the diversion of the line as
proposed in any Alternatives are accepted then necessary
statutory notification has to be published afresh in the state
gazette as well as in the local News Papers inviting objections
from the general public and in that event any person may
approach the Court of law and seek redressal of grievance
including any order of injunction. This will further inordinately
delay the already delayed construction of transmission line
which is very vital for power supply to Bhubaneswar, Cuttack,
Puri, Khurda, Jagatsingpur Command Areas.
21
Page 21
| nd on whic<br>itted that th | h these tw<br>e construc |
|---|
15. That the photographs filed herewith as Annexure K/l series
would show that the 220 KV Mendhasal-Chandaka
transmission line has passed through the compound of the
Appellant ASBM long since which is existing and ASBM has later
constructed its building and structures near the line.”
21. The reasons assigned by the concerned officer of appellant No.1 for
not accepting the alternatives suggested by respondent No.1 were germane
JUDGMENT
to the inability of appellant No.1 to change the alignment of the route and
shift the transmission towers and the Division Bench of the High Court
committed serious error by entertaining the prayer made by respondent
No.1.
22. A somewhat similar question was considered by this Court in
Ramakrishna Poultry (P) Limited v. R. Chellappan (2009) 16 SCC 743. The
appellant in that case had purchased land in June, 2004/November, 2004. At
22
Page 22
about the same time, the Power Grid Corporation of India Ltd. took up the
work of construction of 400 KV Perambalur-Pugalur D/C line as part of
Neyveli Thermal Station Expansion Project for evacuation of electricity
various locations, some of which were private lands including the land
belonging to the appellant. In the first round of litigation, the High Court
directed District Magistrate to hear the parties and decide the representation
to be made by the appellant. The District Magistrate directed the
Corporation to re-align the transmission line in such a way that it did not
pass above the poultry sheds constructed by the appellant. This affected the
respondent, who filed writ petition before the High Court. The learned
Single Judge dismissed the writ petition. The Division Bench held that the
District Magistrate did not have any power to direct change of alignment.
JUDGMENT
This Court took cognizance of the fact that the Corporation had agreed to
raise the height of the transmission lines and observed:
“38. Keeping aside the technical aspect of the matter as to
whether the order passed by the District Collector was one
under Section 16 or Section 17 of the Telegraph Act, 1885, in
order to arrive at a practical solution to the problem, the Power
Grid Corporation accepted the alternate suggestion made on
behalf of the appellant Company and raised the height of the
lowest point of sag of the transmission lines between the two
towers on either side of the poultry sheds of the appellant
Company from 46.5 m to 52 m, which in practical terms means
23
Page 23
| reproduc | tive syste |
|---|
| ing things | within that |
| m not only | |
| chickens but of all living things within that zone.<br>39. However, what goes against the case of the appellant<br>Company is the fact that the purchases of the land for starting<br>the poultry business and the erection of the poultry sheds were<br>effected at a point of time when the process of identifying the<br>route of the transmission lines was already in progress and<br>survey work was being undertaken. We find it difficult to<br>accept that the appellant Company did not have knowledge of<br>the ongoing project, which is for the benefit of a large number<br>of people of the area as against the interest of a single<br>individual.<br>40. In view of the objections on behalf of the Power Grid<br>Corporation that the deviation in the transmission lines, as<br>suggested on behalf of the appellant Company, could not be<br>practically achieved, we are left with the next best solution i.e. | zone.<br>se of the ap | pellant |
| | |
JUDGMENT
(emphasis supplied)
24
Page 24
23. We also agree with Shri P. P. Rao that the learned Single Judge of the
High Court had rightly refused to entertain the second writ petition and the
Division Bench committed an error by setting aside the order passed by him.
that substantially similar prayer had been made in both the cases. The first
petition which could be treated as one filed under Article 227 of the
Constitution was dismissed by the High Court by assigning detailed reasons
including the one that larger public interest outweighed the individual
interest of respondent No.1. However, while deciding the writ appeal filed
against the order passed in Writ Petition No.20659/2009, the Division Bench
overlooked this vital factor and ordered shifting of the transmission line.
24. In Ramchandra Dagdu Sonavane v. Vithu Hira Mahar (2009) 10 SCC
273, this Court discussed the doctrine of res judicata embodied in Section
JUDGMENT
11 of the Code of Civil Procedure and held:
“It is well known that the doctrine of res judicata is codified in
Section 11 of the Code of Civil Procedure. Section 11 generally
comes into play in relation to civil suits. But apart from the
codified law, the doctrine of res judicata or the principle of res
judicata has been applied since long in various other kinds of
proceedings and situations by courts in England, India and
other countries. The rule of constructive res judicata is
engrafted in Explanation IV of Section 11 of the Code of Civil
Procedure and in many other situations also principles not only
of direct res judicata but of constructive res judicata are also
25
Page 25
applied, if by any judgment or order any matter in issue has
been directly and explicitly decided, the decision operates as res
judicata and bars the trial of an identical issue in a subsequent
proceedings between the same parties.
| of a particu<br>to have | lar issue is<br>been nec |
|---|
25. The facts brought on record show that in the suit filed by the Trust,
the trial Court had granted an injunction, which was vacated by the lower
appellate Court and the petition filed against the order of the lower appellate
Court was dismissed by the High Court on the premise that respondent No.1
had purchased the land only in December, 2005 and the building was
JUDGMENT
constructed in July, 2006 knowing fully well that negotiations with the
officers of appellant No.1 had failed. The learned Single Judge further
observed that it would be against public interest to pass an order which may
necessitate dismantling of the entire line of numerous towers erected by
spending public money. Even after dismissal of the petition filed under
Article 227 of the Constitution and its failure to persuade the Court to
sustain the order of injunction passed by the trial Court, respondent No.1
26
Page 26
kept the suit pending and, at the same time, filed the second writ petition.
This was a clear case of abuse of the process of the Court. It is a different
thing that even in the second round, respondent No.1 could not persuade the
after the writ appeal was entertained by the Division Bench of the High
Court. This shows that respondent No.1 had availed parallel remedies and
gave up its pursuit before the Civil Court only after the Division Bench of
the High Court indicated its willingness to hear the writ appeal on merits.
26. The judgment in S.J.S. Business Enterprises (P) Ltd. v. State of Bihar
(supra), on which strong reliance has been placed by Dr. Singhvi, is clearly
distinguishable. The facts of that case were the appellant had filed suit on
4.4.2002 in the Court of Sub-Judge, Patna challenging the action taken by
Bihar State Industrial Credit and Investment Corporation Ltd. under Section
JUDGMENT
29 of the State Financial Corporations Act, 1951 for sale of its assets. On the
very next day a writ petition was filed by the appellant for the same relief.
While the Civil Court did not pass an interim order in terms of the prayer
made by the appellant, the learned Single of the Patna High Court granted
the prayer for stay of the auction proceedings subject to the condition of
payment of Rs.10 lakhs. However, when the pendency of suit was brought to
the notice of the learned Single Judge, he dismissed the writ petition by
27
Page 27
holding that the appellant had suppressed the factum of civil suit. The
Division Bench of the High Court dismissed the appeal filed against the
order of the learned Single Judge. A two Judge Bench of this Court referred
the District of Kensington (1917) 1 KB 486 and State of Haryana v. Karnal
Distillery Co. Ltd. (1977) 2 SCC 431 and observed:
“Assuming that the explanation given by the appellant that the
suit had been filed by one of the Directors of the Company
without the knowledge of the Director who almost
simultaneously approached the High Court under Article 226 is
unbelievable (sic), the question still remains whether the filing
of the suit can be said to be a fact material to the disposal of the
writ petition on merits. We think not. The existence of an
adequate or suitable alternative remedy available to a litigant is
merely a factor which a court entertaining an application under
Article 226 will consider for exercising the discretion to issue a
writ under Article 226 [A.N. Venkateswaran v. Ramchand
Sobhraj Wadhwani AIR 1961 SC 1506]. But the existence of
such remedy does not impinge upon the jurisdiction of the High
Court to deal with the matter itself if it is in a position to do so
on the basis of the affidavits filed. If, however, a party has
already availed of the alternative remedy while invoking the
jurisdiction under Article 226, it would not be appropriate for
the court to entertain the writ petition. The rule is based on
public policy but the motivating factor is the existence of a
parallel jurisdiction in another court. But this Court has also
held in Chandra Bhan Gosain v. State of Orissa (1964) 2 SCR
879 that even when an alternative remedy has been availed of
by a party but not pursued that the party could prosecute
proceedings under Article 226 for the same relief. This Court
has also held that when a party has already moved the High
Court under Article 226 and failed to obtain relief and then
moved an application under Article 32 before this Court for the
JUDGMENT
28
Page 28
| g the writ<br>d been ava | petition on<br>iled of, the |
|---|
In this case, admittedly, the appellant has withdrawn the suit
two weeks after the suit had been filed. In other words, the
appellant elected to pursue its remedies only under Article 226.
The pleadings were also complete before the High Court. No
doubt, the interim order which was passed by the High Court
was obtained when the suit was pending. But by the time the
writ petition was heard the suit had already been withdrawn a
year earlier. Although the appellant could not, on the High
Court’s reasoning, take advantage of the interim order, it was
not correct in rejecting the writ petition itself when the suit had
admittedly been withdrawn, especially when the matter was
ripe for hearing and all the facts necessary for determining the
writ petition on merits were before the Court, and when the
Court was not of the view that the writ petition was otherwise
not maintainable.”
JUDGMENT
27. The ratio of the above extracted observations is that the Court will not
allow a party to pursue two remedies simultaneously. The proposition laid
down by this Court does not help the cause of respondent No.1. Instead, the
same can be relied upon for holding that the Division Bench of the High
29
Page 29
Court committed an error by setting aside the order of the learned Single
Judge who had non-suited respondent No.1 on the ground that it had not
only availed parallel remedies but pursued the same till the writ appeal filed
28. The finding recorded by the Division Bench of the High Court that the
scheme was not in consonance with Sections 28 and 29 of the Act is also
erroneous. In response to the observation made by the High Court on
25.3.2011, Shri Amar Nath Mohanty filed further affidavit dated 29.3.2011,
paragraphs 3 to 6 of which are extracted below:
“ 3. That the nomenclature of the schemes like Chandaka-Bidanasi-
Mendhasal are only indicative in nature for internal project planning,
while actual construction takes place after survey of the line and
alignment and tower spotting are finalized in accordance with the
notified scheme. These details are kept in the office. In the instant
case, the land schedule etc., are not available but the profile of the
said portion is available which is enclosed herewith as Annexure-M/l
.
JUDGMENT
4. That there are several examples where the name of sub-station is
different from its specific site locations. For example the Chandaka
Grid Sub-station is in Patia Mouza written in brackets as Chandaka
Industrial Estate, the "Bargarh Grid Sub-station" in Bhubaneswar is
in Kesura Village and Jharsuguda Grid Sub-station is in Village
sarasmala.
5. That the line work has been completed from both Mendhasal and
Bidanasi end; except this small portion which is left out; the line
alignment is already fixed with two remaining towers coming in the
area of ASBM. So further change cannot be made.
30
Page 30
6. That the Appellants in course of arguments have also produced a
Map before this Hon'ble Court which has also been annexed by the
Respondents as Annexure-H/1 to the Affidavit filed by the
Respondents on 25.03.2011 and the said Map clearly discloses that
two towers are to be erected on the land of ASBM.”
the scheme in the notifications should have been accepted by the High Court
and there was no justification to direct re-routing of the transmission line on
the specious ground of non-compliance of the two provisions.
30. In the result, the appeal is allowed, the impugned judgment is set aside
and Writ Petition No.20659/2009 filed by respondent No.1 is dismissed.
Respondent No.1 shall pay cost of Rs.10 lakhs to appellant No.1 because
implementation of the scheme was frustrated due to unwarranted litigation
by the Trust and respondent No.1. The cost shall be paid to appellant No.1
within a period of three months from today.
JUDGMENT
................................................J.
(G.S. SINGHVI)
................................................J.
(V. GOPALA GOWDA)
New Delhi;
August 5, 2013.
31
Page 31