Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 14
CASE NO.:
Appeal (civil) 2754 of 2002
PETITIONER:
Chairman & M.D., N.T.P.C. Ltd.
RESPONDENT:
M/s. Reshmi Constructions, Builders & Contractors
DATE OF JUDGMENT: 05/01/2004
BENCH:
CJI & S.B. Sinha.
JUDGMENT:
J U D G M E N T
V.N. KHARE, CJI.
This appeal which arises out of a judgment and order dated
23-11-2001 passed by the High Court of Kerala at Ernakulam revolves
round the question as to whether an arbitration clause in a
contract agreement survives despite purported satisfaction thereof.
The parties to this appeal entered into an agreement for a
project at Kayamkulam. Upon completion of the work the respondent
herein submitted final bill which was allegedly not accepted by the
appellant, whereafter they themselves prepared the final bill and
forwarded the same along with a printed format being a "No Demand
Certificate". The said "No Demand Certificate" was signed by
the respondent herein which is in the following terms:
NO DEMAND CERTIFICATE
Name of package : Earth filling in Temporary
Township Part \026 II
Letter of award : LOA No. KYM/CS/89/022/NIT-
005/LOA-065 dated 19.3.90
Name of the Contractor : Reshmi Construction, T.C. 4/1298,
Keston Road, Kowdiar, P.O. Trivandrum \026 3
1. This is to certify that we have received all payment in
full and final settlement of the supplied and services
rendered and/ or all work performed by us in respect of
the above referred LOA/ Contract and we have no other
claims whatsoever final or otherwise outstanding against
NTPC. We further confirm that we shall have no claim/
demands in future in respect of this contract of
whatsoever nature, final or otherwise."
2. We would now request you to please release our security
deposit/ contract performance Guarantee."
However, on the same day a letter dated 20-12-1990 was
written by the respondent to the appellant stating:
"We have completed the aforementioned work
in the Kayamkulam Super Thermal Power
Project’s temporary township area at
Nangiarkulangara by the end of November 1990
itself. We had submitted a pre-final bill
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 14
in November itself but the authorities
denied the bill and insisted final bill.
But when the alleged final bill was prepared
the authorities insisted that a "No Demand
Certificate" should be executed by us in
favour of the Corporation. They served us
with a printed specimen of the document and
insisted that it should be typed in our own
letterhead and submitted to the N.T.P.C. We
refused to submit such a document.
But the authorities of N.T.P.C. threatened
that unless and until we execute the said
document in favour of the Corporation, the
N.T.P.C. would not effect payment of our
bill. More than six lakhs of Rupees is
pending for payment vide the alleged final
bill. We have incurred huge losses in the
execution of the work purely due to the
latches and lapses of the corporation. More
over lakhs and lakhs of rupees has to be
paid to our Bankers, creditors suppliers,
workers, truck owners etc. etc. Under such
a situation we have no other way other than
budging to the coercion of the authorities
of N.T.P.C. ltd. to get whatever they give
merely for the necessity of our survival.
We have to comply with the instructions of
authorities of N.T.P.C. Ltd. out of our
helplessness in order to receive payment.
Hence this letter.
The certificates, undertakings, etc. as
aforesaid have been executed without
prejudice to our rights and claims
whatsoever on account of the alleged final
bill.
The money invested in the work comprises
loans from the Federal Bank Ltd., private
financiers, etc. as well the Firm’s own
funds. Those additional sums raised by
loans have to be paid to the Bank,
financiers, etc. hence under duress,
coerction and under undue influence we are
signing the bill and execute such documents
as aforesaid to receive payment. Under such
coercive circumstances the alleged final
bill cannot be constructed as final bill.
We are signing the alleged final bill under
coerction, under undue influence and under
protest only without prejudice to our rights
and claims whatsoever. There is no accord
and satisfaction between the contracting
parties.
You are therefore requested to kindly pass
the final bill incorporating all the
measurements of the items such as sinkage,
in and under water execution of works,
compensation for suspension of works,
reimbursement of cost escalation due to
price hike of petroleum products, cost of
idling, enhanced rates for quantities
executed beyond the contractual period,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 14
market rate for excess quantities, extra
additional items etc. besides the losses and
damages by way of idling of tools and
plants, workmen, staff, establishment costs,
capital outlay, interest etc. as per
actuals. We hope and request that your
goodself may do the needful in the matter."
[Emphasis supplied]
The respondent thereafter invoked the arbitration clause by
reason of a letter through his advocate dated 21.12.91 wherein the
claims under several heads as enumerated in clause (a) to (p)
thereof. Therein a request was made to refer all the disputes and
differences to a sole arbitrator for adjudication with a direction
to make and publish the award within the statutory period.
The appellant herein thereafter discussed the matter at the
company level and in its proceedings it was recorded:
"4.0 In case of M/s. Reshmi Constructions,
Trivandrum Kerala (1(c) above) and M/s. C.S.
Prakash, (1(d) above) of Perumbavoor,
Kerala, the total payment for the works done
were effected, the final bills have been
settled without protest and the no-dues
certificate in the standard proforma have
been submitted by the contractors.
5.0 To seek legal opinion in the matter, we
have approached Mr. B.S. Krishnan, a leading
advocate from Cochin. On detailed study of
the claims of the agencies and considering
legal conditions, the advocate has advised
us to appoint arbitrator/s nominated by CMD
of NTPC, immediately. Accordingly our
advocate has written suitable replies to the
contractor’s advocate Shri NT John, of
Trivandrum, informing them that they will
hear from NTPC regarding appointment of an
arbitrator in terms of the contract
conditions.
6.0 Submitted to appoint arbitrator/s for
the four contract packages at para 1.0
above, please."
The appellant thereafter by its letter dated 13th February,
1992 replied thereto stating:
"My client acting upon the notice, though
defective, takes it that all your claims are
disputed ones and hence are to be resolved
by Arbitration. Please note that the
reference to arbitration does not mean that
there is admission that the disputes are
arbitrable. Many of the claims raised are
beyond the terms of the contract and the
Arbitrator will have not jurisidiction to
deal with them. This is a matter which has
to be taken up later and not at the stage of
appointment of an Arbitrator.
As appointing authority, my client
refrains from commenting upon in any manner,
on the merits or otherwise of the disputes
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 14
which your notice has set out.
It may be noticed that your client has
already taken the final bill and has issued
’no dues’ certificate. This is not merely
accord and satisfaction, but bringing the
contract to an end.
Your client will hear from my client as
regards the appointment of the Arbitrator in
terms of the contract conditions shortly."
[Emphasis supplied]
A purported correction in the said notice was issued by the
advocate of the appellant stating:
"Sub: Correction in the notice is issued by
way of Reply notice is signed on behalf of
M/s. Rashmi Constructions, Trivandrum \026 reg.
Ref: My Regd. Notice No. P3-G1/92/582 dt.
13.2.92.
Under instructions from my clients, the
Chairman & Managing Director, National
Thermal Power Corporation Ltd. NTPC Bhavan,
New Delhi \026 110 003, I issue the following
notice:
In the reply notice issued by me under
reference number cited above, it was stated
that the notice issued by you on behalf of
your clients M/s. Rashmi Constructions,
Trivandrum was returned since it was not
signed by you and that the notice is sent
back as the same was signed on your behalf
by your client. On scrutiny I find that the
notice is returned by you after the same is
signed by you and not by your client on your
behalf. In paragraph 2 of the reply notice,
I stated that the notice is defective. It
was so stated because of the mistaken
impression that the notice is signed by your
client and not by you. I stated that the
mistake is in advert at and the same is
regretted. I would like to bring to your
notice one more fact which was omitted to be
stated in the reply notice sent earlier. I
have already stated that your client has
issued ’no dues’ certificate. The final
bill is accepted by your client without any
protest. This is further followed up by
your client receiving the security deposit
released on 21.1.92; that is after the
expiry of the stipulated period reckoned
from the date when the contract came to an
end.
In all other respects the reply notice
earlier sent stands."
The respondent herein filed an application under Section 20
of the Arbitration Act, 1940 before the Hon’ble Subordinate Judge’s
Court Mavelikkara and in terms of a judgment and order dated
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 14
30.6.1994 the said application was dismissed. Aggrieved, the
respondent herein preferred an appeal before the High Court of
Kerala which was allowed by reason of the impugned order.
Mr. Bhatt, the learned counsel appearing on behalf of the
appellant urged that as the contract itself came to an end upon
execution of the "No Demand Certificate" and together with the
same the arbitration clause also perished. In support of the said
contention, reliance has been placed on M/s. P.K. Ramaiah and
Company Vs. Chairman & Managing Director, National Thermal Power
Corpn. [1994 Supp (3) SCC 126] and Nathani Steels Ltd. Vs.
Associated Constructions [1995 Supp (3) SCC 324].
Mr. Bhatt further urged that as in its application under
Section 20 of the Arbitration Act, the respondent did not raise a
plea that they had been coerced to submit the "No Demand
Certificate", the High Court committed a manifest error in passing
the impugned judgment.
The learned counsel appearing on behalf of the respondent, on
the other hand, submitted that in the facts and circumstances of
the case neither any new contract has come into being nor there was
any accord and satisfaction of the contract agreement.
The learned counsel appearing on behalf of the respondent
also contended that despite coming to an end of the contract, the
arbitration clause survives and all questions arising out of or in
relation to the execution of the contract are referable to
arbitration. Reliance in this connection has been placed on
Damodar Valley Vs. K.K. Kar [(1974) 1 SCC 141], M/s. Bharat Heavy
Electricals Limited Vs. M/s. Amar Nath Bhan Prakash [(1982) 1 SCC
625], Union of India and Another Vs. M/s. L.K. Ahuja and Co.
[(1988) 3 SCC 76] and Jayesh Engineering Works Vs. New India
Assurance Co. Ltd. [(2000) 10 SCC 178].
On the arguments of learned counsel for the parties, the
questions that arise for our consideration are:
(i) Whether after the contract comes to an end by completion
of the contract work and acceptance of the final bill in
full and final satisfaction and after issuing a No Demand
Certificate by the contractor, can any party to the
contract raise any dispute for reference to arbitration?
(ii) Whether in view of letter dated 20.12.1990 sent by the
respondent contractor the arbitration clause contained in
the agreement can be invoked ?
(iii) Whether the arbitration clause in the agreement has
perished with the contract?
In this context it is relevant to refer the arbitration clause
contained in the agreement which runs as under:
"56. Except where otherwise provided for in
the contract all questions and disputes
relating to the meaning of the
specifications, designs, drawing and
instructions herein before mentioned and as
to the quality of workmanship or materials
used on the work or as to any other
question, claim, right, matter or thing
whatsoever in any way arising out of or
relating to the contract, designs drawing,
specifications, estimates, instructions,
orders or these conditions or otherwise
concerning the works; or the execution or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 14
failure to execute the same whether arising
during the progress of the work or after the
completion or abandonment thereof shall be
referred to the sole arbitration of the
General Manager of National Thermal Power
Corporation Ltd.; and if the General Manager
is unable or unwilling to act: to the sole
arbitration of some other person appointed
by the Chairman and Managing Director;
National Thermal Power Corporation Ltd.
willing to act as such arbitrator. There
will be no objection if the arbitrator so
appointed is an employee of National Thermal
Power Corporation Ltd. and that he had to
deal with the matters to which the contract
relates and that in the course his duties as
such he had expressed views on all or any of
the matters in dispute or difference. The
arbitrator to whom the matter is originally
referred being transferred or vacating his
office or being unable to act for any reason
as aforesaid should act as arbitrator and if
for any reason, that is not possible; the
matter is not to be referred to arbitration
at all.
Subject as aforesaid the provision of the
Arbitration Act, 1940 or any statutory
modification or reenactment thereof and the
rules made thereunder and for the time being
in force shall apply to the arbitration
proceeding under this clause.
It is a term of the contract that the party
invoking arbitration shall specify the
disputes or disputes to be referred to
arbitration under this clause together with
the amount or amounts claimed in respect of
each such dispute.
The arbitrator(s) may from time to time with
consent of the parties enlarge the time, for
making and publishing the award.
The work under the Contract shall, if
reasonable possible, continue during the
arbitration proceedings and no payment due
or payable to the Contractor shall be
withheld on account of such proceedings.
The Arbitrator shall be deemed to have
entered on the reference on the date he
issues notice to both the parties fixing the
date of the first hearing.
The Arbitrator shall give a separate award
in respect of each dispute or difference
referred to him.
The venue of arbitration shall be such place
as may be fixed by the Arbitrator in his
sole discretion.
The award of the arbitrator shall be final,
conclusive and binding on the all parties to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 14
this contract.
The cost of arbitration shall be borne by
the parties to the dispute, as may be
decided by the arbitrator (s).
In the event of disputes or differences
arising between one public sector enterprise
and a Govt. Department or between two public
sector enterprises the above stipulations
shall not apply, the provisions of B.P.E.
Office Memorandum No. BPE/GL-001/76/MAN/2
(110-75-BPE(GM-1) dated 1st January 1976 or
its amendments for arbitration shall be
applicable."
Clause 52 of the agreement reads as follows:
"52. The final bill shall be submitted by
the contractor within three months of
physical completion of the works. No
further claims shall be made by the
contractor after submission of the final
bill and these shall be deemed to have been
waived and extinguished. Payment of those
items of the bill in respect of which there
is no dispute and of items in dispute, for
quantities and at rates as approved by
Engineer-in-Charge, shall be made within the
period specified hereunder, the period being
reckoned from the date of receipt of the
bill by the Engineer-in-Charge:
(a) Contract amount not exceeding Rs. 5
lakhs \026Four months.
(b) Contract Amount exceeding Rs. 5
lakhs \026 Six months.
After payment of the amount of the final
bills payable as aforesaid has been made,
the Contractor may if he so desires,
reconsider his position in respect of the
disputed portion of the final bill and if he
fails to do so within 90 days, his disputed
claim shall be dealt with as provided in
contract."
[Emphasis supplied]
The issues are required to be determined having regard to the
facts as which arise for consideration whether by reason of the
act of the parties the old contract was substituted by a new
contract. Only in the event a new contract came into being, the
arbitration agreement cannot be invoked.
In Damodar Valley Corporation vs. K.K. Kar [(1974) 1 SCC
141],this Court held:
"It appears to us that the question whether
there has been a full and final settlement
of a claim under the contract is itself a
dispute arising ’upon’ or ’in relation to’
or ’in connection with’ the contract. These
words are wide enough to cover the dispute
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 14
sought to be referred."
Normally, an accord and satisfaction by itself would not
affect the arbitration clause but if the dispute is that the
contract itself does not subsist, the question of invoking the
arbitration clause may not arise. But in the event it be held that
the contract survives, recourse to the arbitration clause may be
taken. [See Union of India Vs. Kishorilal Gupta (AIR 1959 SC 1362)
and Majhati Jute Mills Vs. Khvalirsa (AIR 1968 SC 522).
In Bharat Heavy Electricals Limited (supra) this Court
observed that whether there was discharge of the contract by accord
and satisfaction or not is a dispute arising out of a contract and
is liable to be referred to arbitration.
Yet again in L.K. Ahuja (supra) Sabyasachi Mukharji, J., as
the learned Chief Justice then was, laid down the ingredients of
Section 20 of the Arbitration Act stating:
6. It appears that these questions were
discussed in the decision of the Calcutta
High Court in Jiwnani Engineering Works Pvt.
Ltd. v. Union of India [AIR 1978 Cal 228]
where one of us (Sabyasachi Mukharji, J.)
was a party and which held after discussing
all these authorities that the question
whether the claim sought to be raised was
barred by limitation or not, was not
relevant for an order under Section 20 of
the Act. Therefore, there are to aspects.
One is whether the claim made in the
arbitration is barred by limitation under
the relevant provisions of the Limitation
Act and secondly, whether the claim made for
application under Section 20 is barred. In
order to be a valid claim for reference
under Section 20 of the Arbitration Act,
1940, it is necessary that there should be
an arbitration agreement and secondly
differences must arise to which the
agreement in question applied and, thirdly,
that must be within time as stipulated in
Section 20 of the Act.
It was held that having regard to the fact that the existence
of an arbitration agreement was not denied and there had been an
assertion of claim and denial thereof, the matter would be
arbitrable. It was observed:
In order to be entitled to ask for a
reference under Section 20 of the Act, there
must be an entitlement to money and a
difference or dispute in respect of the
same. It is true that on completion of the
work, right to get payment would normally
arise and it is also true that on settlement
of the final bill, the right to get further
payment get weakened but the claim subsists
and whether it does subsist, is a matter
which is arbitrable.
[Emphasis supplied]
This aspect of the matter has also been considered in Jayesh
Engineerng Works (supra) wherein following L.K. Ahuja (supra) it
was held:
"Whether any amount is due to be paid and
how far the claim made by the appellant is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 14
tenable are matters to be considered by the
arbitrator. In fact, whether the contract
has been fully worked out and whether the
payments have been made in full and final
settlement are questions to be considered by
the arbitrator when there is a dispute
regarding the same."
In M/s. P.K. Ramaiah and Company (supra) the amount was
received unconditionally. The full and final satisfaction was
acknowledged by a separate receipt in writing. In that situation
the following finding was recorded :
"Thus there is accord and satisfaction by
final settlement of the claims. The
subsequent allegation of coercion is an
afterthought and a devise to get over the
settlement of the dispute, acceptance of the
payment and receipt voluntarily given."
We, however, may observe that the quotation from Russell on
Arbitration may not be apt inasmuch as at the stage of reference
what would be a good defence is not a matter to be taken into
consideration.
Yet again in Nathani Steels Ltd. (supra) the disputes and
differences were amicably settled by and between the parties and in
that view of the matter it was held that unless and until the
statement is set aside, the arbitration clause cannot be invoked.
Such is not the position here.
The appellant herein did not raise a question that there has
been a novation of contract. The conduct of the parties as
evidenced in their letters, as noticed hereinbefore, clearly go to
show that not only the final bill submitted by the respondent was
rejected but another final bill was prepared with a printed format
that a "No Demand Certificate" has been executed as other final
bill would not be paid. The respondent herein, as noticed
hereinbefore, categorically stated in its letter dated 20.12.1990
that as to under what circumstances they were compelled to sign the
said printed letter. It appeares from the appendix appended to
the judgment of the learned Trial Judge that the said letter was
filed even before the trial court. It is, therefore, not a case
whether the respondent’s assertion of "under influence or coercion"
can be said to have been taken by way of an afterthought.
Even when rights and obligations of the parties are worked
out the contract does not come to an end inter alia for the purpose
of determination of the disputes arising thereunder, and, thus,
the arbitration agreement can be invoked. Although it may not be
strictly in place but we cannot shut our eyes to the ground reality
that in the cases where a contractor has made huge investment, he
cannot afford not to take from the employer the amount under the
bills, for various reasons which may include discharge of his
liability towards the banks, financial institutions and other
persons. In such a situation, the public sector undertakings would
have an upper hand. They would not ordinarily release the money
unless a ’No Demand Certificate’ is signed. Each case, therefore,
is required to be considered on its own facts.
Further, necessitas non habet legem is an old age maxim which
means necessity knows no law. A person may sometimes have to
succumb to the pressure of other party to the bargain who is on a
stronger position.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 14
We may, however, hasten to add that such a case has to be
made out and proved before the Arbitrator for obtaining an award.
At this stage, the Court, however, will only be concerned
with the question whether triable issues have been raised which are
required to be determined by the Arbitrators.
Circumstances leading to passing an order by the courts of
law directing the parties to get their disputes determined by
domestic tribunal selected by them having regard to the
correspondences exchanged between the solicitors came up for
consideration in Goodman Vs. Winchester and Alton Rly [(1984) 3 All
ER 594] wherein it was held:
"As I have already recounted, the
plaintiff’s solicitor may have had in mind
that if there were an arbitration clause
various matters could be sorted out cheaply
and quickly under it. There is no evidence,
in my judgment, that when he drafted the
terms of the arbitration clause he had in
mind that it would not apply to a
repudiation of the contract by the
defendants. He is a solicitor; he is
clearly an experienced solicitor; and he
should have appreciated (and I feel certain
he did) that the arbitration clause which he
drafted, and which was accepted by the
defendants, would cover every aspect of the
contract, including repudiation. But, apart
altogether from what the plaintiff’s
solicitor had in mind, there is no evidence
at all as to what the defendant company had
in mind when it agreed to accept the
arbitration clause, and it was wrong, in my
judgment, for the Judge to say that neither
party had in mind that it would apply to the
summary dismissal of the plaintiff. It
follows, therefore, that at the very
beginning of his judgment the judge
misdirected himself as to the construction
of the arbitration clause and what it was
mended to deal with."
Even correspondences marked as without prejudice may have to
be interpreted differently in different situations.
What would be the effect of without prejudice offer has been
considered in Cutts Vs. Head and Another [(1984) 2 WLR 349] wherein
Oliver L.J. speaking for the Court of Appeals held:
"In the end, I think that the question of
what meaning is given to the words "without
prejudice" is a matter of interpretation
which is capable of variation according to
usage in the profession. It seems to be
that, no issue of public policy being
involved, it would be wrong to say that the
words were given a meaning in 1889 which
isimmutable ever after, bearing in mind that
the precise question with which we are
concerned in this case did not arise in
Walker v. Wilsher, 23 Q.B.D. 335, and the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 14
court did not deal with it. I think that
the wide body of practice which undoubtedly
exists must be treated as indicating that
the meaning to be given to the words is
altered if the offer contains the
reservation relating to the use of the offer
in relation to costs."
Yet again in Rush & Tompkins Ltd. Vs. Greater London Council
and Another [(1988) 1 All ER 549]:
"The rule which gives the protection of
privilege to ’without prejudice’
correspondence ’depends partly on public
policy, namely the need to facilitate
compromise, and partly on ’implied
agreement’ as Parker LJ stated in South
Shropshire DC v Amos [1987] 1 All ER 340 at
343, [1986] 1 WLR 1271 at 1277. The nature
of the implied agreement must depend on the
meaning which is conventionally attached to
the phrase ’without prejudice’. The classic
definition of the phrase is contained in the
judgment of Lindley LJ in Walker v. Wilsher
(1889) 23 QBD 335 at 337:
’What is the meaning of the words "without
prejudice"? I think they mean without
prejudice to the position of the writer of
the letter if the terms he proposes are not
accepted. If the terms proposed in the
letter are accepted a complete contract is
established, and the letter, although
written without prejudice, operates to alter
the old state of things and to establish a
new one.’
Although this definition was not necessary
for the facts of that particular case and
was therefore strictly obiter, it was
expressly approved by this court in Tomlin v
Standard Telephones and Cables Ltd. [1969] 3
All ER 201 at 204, 205, [1969] 1 WLR 1378 at
1383, 1385 per Danckwerts LJ and Ormrod J.
(Although he dissented in the result, on
this point Ormrod J agreed with the
majority.) The definition was further cited
with approval by both Oliver and Fox LJJ in
this court in Cutts v. Head [1984] 1 All ER
597 at 603, 610, [1984] Ch. 290 at 303, 313.
In our judgment, it may be taken as an
accurate statement of the meaning of
’without prejudice’, if that phrase be used
without more. It is open to the parties to
the correspondence to give the phrase a
somewhat different meaning, e.g. where they
reserve the right to bring an offer made
’without prejudice’ to the attention of the
court on the question of costs if the offer
be not accepted (See Cutts v. Head) but
subject to any such modification as may be
agreed between the parties, that is the
meaning of the phrase. In particular,
subject to any such modification, the
parties must be taken to have intended and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 14
agreed that the privilege will cease if and
when the negotiations ’without prejudice’
come to fruition in a concluded agreement."
Meaning the words "without prejudice" come up for
consideration before this Court in Superintendent (Tech. I) Central
Excise, I.D.D. Jabalpur and Others Vs. Pratap Rai [(1978) 3 SCC
113] wherein it has been held:
"The Appellate Collector has clearly used
the words "without prejudice" which also
indicate that the order of the Collector was
not final and irrevocable. The term
"without prejduce" has been defined in
Black’s Law Dictionary as follows:
Where an offer or admission is made ’without
prejduce’, or a motion is defined or a bill
in equity dismissed ’without prejudice’, it
is meant as a declaration that no rights or
privileges of the party concerned are to be
considered as thereby waived or lost, except
in so far as may be expressly conceded or
decided. See, also Dismissal Without
Prejudice.
Similarly, in Wharton’s Law Lexicon the
author while interpreting the term ’without
prejudice’ observed as follows:
The words import an understanding that if
the negotiation fails, nothing that has
passed shall be taken advantage of
thereafter; so, if a defendant offers,
’without prejudice’, to pay half the claim,
the plaintiff must not only rely on the
offer as an admission of his having a right
to some payment.
The rule is that nothing written or said
’without prejudice’ can be considered at the
trial without the consent of both parties \026
not even by a Judge in determining whether
or not there is good cause for depriving a
successful litigant of costs \005. The word is
also frequently used without the foregoing
implications in statutes and inter partes to
exclude or save transactions, acts and
rights from the consequences of a stated
proposition and so as to mean ’not
affecting’, ’saving’ or ’excepting’.
In short, therefore, the implication of
the term ’without prejudice’ means (1) that
the cause or the matter has not been decided
on merits, (2) that fresh proceedings
according to law were not barred."
The appellant has in its letter dated 20th December, 1990
has used the term ’without prejudice’. It has explained the
situation under which the amount under the ’No Demand Certificate’
had to be signed. The question may have to be considered from that
angle. Furthermore, the question as to whether the respondent has
waived its contractual right to receive the amount or is otherwise
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 14
estoppel from pleading otherwise will itself be a fact which has to
be determined by the arbitral tribunal.
In Halsbury’s Laws of England, 4th Edition, Vol.16
(Reissue) para 957 at page 844 it is stated:
"On the principle that a person may not
approbate and reprobate a special species of
estoppel has arisen. The principle that a
person may not approbate and reprobate
express two propositions:
(1) That the person in question, having a choice
between two courses of conduct is to be
treated as having made an election from
which he cannot resile.
(2) That he will be regarded, in general at any
rate, as having so elected unless he has
taken a benefit under or arising out of
the course of conduct, which he has first
pursued and with which his subsequent
conduct is inconsistent."
In American Jurisprudence, 2nd Edition, Volume 28, 1966,
Page 677-680 it is stated:
"Estoppel by the acceptance of benefits:
Estoppel is frequently based upon the
acceptance and retention, by one having
knowledge or notice of the facts, of
benefits from a transaction, contract,
instrument, regulation which he might have
rejected or contested. This doctrine is
obviously a branch of the rule against
assuming inconsistent positions.
As a general principle, one who knowingly
accepts the benefits of a contract or
conveyance is estopped to deny the validity
or binding effect on him of such contract or
conveyance.
This rule has to be applied to do equity and
must not be applied in such a manner as to
violate the principles of right and good
conscience."
The fact situation in the present case, would lead to the
conclusion that the arbitration agreement subsists because:
(i) Disputes as regard final bill arose prior to its
acceptance thereof in view the fact that the same was
prepared by the respondent but was not agreed upon in its
entirety by the appellant herein;
(ii) The appellant has not pleaded that upon submission of the
final bill by the respondent herein any negotiation or
settlement took place as a result whereof the final bill,
as prepared by the appellant, was accepted by the
respondent unequivocally and without any reservation
therefor;
(iii) The respondent herein immediately after receiving the
payment of the final bill, lodged its protest and
reiterated its claims.
(iv) Interpretation and/or application of clause 52 of the
agreement would constitute a dispute which would fall for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 14
consideration of the arbitrator.
(v) The effect of the correspondences between the parties
would have to be determined by the arbitrator,
particularly as regard the claim of the respondent that
the final bill was accepted by it without prejudice.
(vi) The appellant never made out a case that any novation of
the contract agreement took place or the the contract
agreement was substituted by a new agreement. Only in the
event, a case of creation of new agreement is made out the
question of challenging the same by the respondent would
have arisen.
(vii) The conduct of the appellant would show that on receipt of
the notice of the respondent through its advocate dated
21.12.1991 the same was not rejected outright but
existence of disputes was accepted and the matter was
sought to be referred to the arbitration.
(viii) Only when the clarificatory letter was issued the plea
of settlement of final bill was raised.
(ix) The finding of the High Court that a prima facie in the
sense that there are triable issues before the Arbitrator
so as to invoke the provisions of Section 20 of the
Arbitration Act, 1940 cannot be said to be perverse or
unreasonable so as to warrant interference in exercise of
extraordinary jurisdiction under Article 136 of the
Constitution of India.
(x) The jurisdiction of the arbitrator under the 1940 Act
although emanates from the reference, it is trite, that in
a given situation the arbitrator can determine all
questions of law and fact including the construction of
the contract agreement. (See Pure Helium India Pvt. Ltd.
Vs. Oil and Natural Gas Commission reported in 2003 (8)
SCALE 553).
(xi) The cases cited by the learned counsel for the appellant
[P.K. Ramaiah and Company (supra) and Nathani Steels
(supra)] would show that the decisions therein were
rendered having regard to the finding of fact that the
contract agreement containing the arbitrator clause was
substituted by another agreement. Such a question has to
be considered and determined in each individual case
having regard to the fact situation obtaining therein.
For the reasons aforementioned, we are of the opinion that
there is no infirmity in the impugned judgment. This appeal is,
therefore, dismissed. No Costs.