M/S TULSI NARAYAN GARG vs. THE M.P. ROAD DEVELOPMENT AUTHORITY

Case Type: Civil Appeal

Date of Judgment: 30-08-2019

Preview image for M/S TULSI NARAYAN GARG vs. THE M.P. ROAD DEVELOPMENT AUTHORITY

Full Judgment Text

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION      CIVIL APPEAL NO(S).6726­6729 OF 2019 (Arising out of SLP(C ) No(s). 1436­1439 of 2019)              M/S. TULSI NARAYAN GARG, SARAWAGI MOHALLA, SHEOPUR THROUGH ITS PROPRIETOR TULSI NARAYAN GARG          …..APPELLANT(S) VERSUS THE M.P. ROAD DEVELOPMENT AUTHORITY, BHOPAL & OTHERS …..RESPONDENT(S) O R D E R Rastogi, J. 1. The   instant   appeals   are   directed   against   the   common th judgment dated 26  February, 2018 and order in review petitions th dated 7  September, 2018 of the High Court of Madhya Pradesh filed   at   the   instance   of   the   present   appellant   quantifying   the liquidated damages assessed by the officer of the respondents to Signature Not Verified be recoverable pending adjudication before the Arbitral Tribunal Digitally signed by SATISH KUMAR YADAV Date: 2019.09.07 12:57:52 IST Reason: constituted under the Madhya Pradesh Madhyastham Adhikaran 1 Adhiniyam,   1983(hereinafter   being   referred   to   as   “Adhiniyam, 1983”). 2. The facts in brief culled out from the record and relevant for the   purpose   are   that   the   appellant   is   a   proprietorship   firm registered   as   Class   ‘A’   contractor.     In   response   to   the   notice inviting tender for construction and maintenance of rural road under the Pradhan Mantri Gram Sadak Yojna for package no. 3712   and   package   no.   3714   consisting   of   two   roads(i.e. constructed one way relating to Vijaypur to Chota Kheda way (2 km) and second, relating to Sonthava to Advad way (7.750 km) change   5240   meter   in   DPR   slab   culvert   and   protection   wall, tender  was   awarded   to   the   appellant  and  in   furtherance,   the th work   order   was   issued   on   6   October,   2008   and   pursuant thereto, agreement no. 11 and agreement no. 12 was executed between the appellant and the first respondent.  As per the work st order, the date of completion was twelve months, i.e. till 21 October, 2009.   The first respondent, invoking clause 52 of the work agreement nos. 11 and 12, terminated the agreement for th th slow progress of work on 7   October, 2013 and 27   October, 2014 respectively.  2 3. The first respondent invoking clause 44.1 and 53.1 of the th agreement served a notice to the appellant on 9  October, 2015 for   determining   the   liquidated   damages   that   came   to   be challenged by the appellant by filing of a Writ Petition No. 7003 of 2015 before the High Court of Madhya Pradesh.   In the first instance, that writ petition came to be disposed of vide order th dated   6   September,   2016   with   liberty   to   the   appellant   to challenge order of termination before the Arbitral Tribunal under the provisions of the Adhiniyam, 1983.   In terms of the liberty afforded,   the   appellant   filed   a   reference   petition   against   the termination   of   agreement   and   damages   claimed   by   the   first respondent before the Madhya Pradesh Arbitral Tribunal under Section 7 of the Adhiniyam, 1983 and as informed to this Court that is still pending adjudication before the Arbitral Tribunal. 4. Pending adjudication before the Arbitral Tribunal, the first th respondent issued notice to the appellant dated 17  March, 2017 for package 3712 and package 3714 to recover alleged damages. In furtherance thereof, respondent no. 2(General Manager of the st 1   respondent)   issued   the   communication   in   which   he   asked respondent   no.   3(Collector,   Sheopur,   M.P.)   to   take   steps   in 3 respect   of   agreement   no.   11   and   agreement   no.   12   towards alleged liquidation damages as arrears of land revenue for the aforesaid packages that came to be challenged by the appellant by filing the Writ Petition Nos. 4087 and 4088 of 2017 and it was specifically stated in Para XIX of the petition indicating that what has been claimed by the respondents as liquidated damages is sub judice before the Arbitral Tribunal and action taken by the respondents pending arbitral proceedings is unwarranted. 5. After hearing the parties, petitions came to be dismissed by th the High Court vide judgment impugned dated 26   February, st 2018 on the premise that General Manager of the 1  respondent has initiated the proceedings under clause 53.1 of the agreement and once the liquidated damages have been quantified by the authority,  the  action  cannot be faulted  with for  initiating  the recovery   proceedings   distinguishing   the   judgment   of   the   full Bench of the Madhya Pradesh High Court on which the reliance was placed by the appellant in   B.B. Verma and another  Vs. State of M.P. and another   AIR 2008 MP 202(FB) which is a subject matter of challenge in the instant appeals. 4 6. The main thrust of the submission of learned counsel for the   appellant   is   that   when   the   alleged   liquidated   damages st quantified   by   the   General   Manager   of   the   1   respondent   are pending   adjudication   before   the   Arbitral  Tribunal,   the   further action which has been initiated for making recovery pursuant to the notice served as an arrears of land revenue is unwarranted and in support of his submission, reliance has been placed not only on the full Bench judgment of the High Court of Madhya Pradesh   but   also   on   the   Order   of   this   Court   passed   in   Civil th Appeal   No.   5169   of   2016   dated   13   May,   2016   and   taking assistance   thereof,   learned   counsel   submits   that   the   recovery proceedings   initiated   by   the   respondents   pursuant   to   the damages quantified invoking clause 53.1 of the contract pending adjudication are unjustified and such action initiated deserves to be quashed and set aside.  However, what being claimed by the respondents will always be open to be examined by the Arbitral Tribunal   and   obviously   the   outcome   will   be   binding   on   the parties subject to their rights available under the law. 7. Per   contra,   learned   counsel   for   the   respondents,   on   the other   hand,   while   supporting   the   finding   of   the   impugned 5 judgment submits that once the adjudication has been made by the General Manager of the Authority after the show cause notice being served and liquidated damages having been quantified, no error was committed by the respondents in initiating the recovery proceedings and the judgment on which the appellant has placed reliance of which a reference has been made has no application in the instant cases and this what the High Court has observed in the impugned judgment needs no interference. 8. We have considered the submissions made by the parties and   with   their   assistance   perused   the   material   available   on record. 9. It is not disputed that the termination of the agreement no. 11 and agreement no. 12 and consequential liquidated damages claimed   by   the   respondents   have   been   questioned   by   the appellant   in   reference   petitions   filed   under   Section   7   of   the th th Adhiniyam,   1983   on   5   October,   2016   and   20   March   2017 respectively   and   both  the  references   are   pending   adjudication before the Arbitral Tribunal where the dispute in reference to the claim   of   liquidated   damages   of   the   respondents   is   yet   to   the 6 adjudicated.  It will be appropriate, at this stage, to take note of the clauses of the agreement relevant for the present purpose which are extracted as under:­ “24. Dispute Redressal System  If any dispute or difference of any kind what­so­ever shall arises in connection with or arising out of this Contract or the execution of Works or maintenance of the   Works   thereunder,   whether   before   its commencement   or   during   the   progress   of   Works   or after the termination, abandonment or breach of the Contract, it shall, in the first instance, be referred for settlement to the competent authority, described along with their powers in the Contract Data, above the rank of the Engineer. The competent authority shall, within a period of 45 days after being requested in writing by the Contractor  to do so, convey  his decision to the Contractor. Such decision in respect of every matter so referred   shall,   subject   to   review   as   hereinafter provided, be final and binding upon the Contractor. In case the Work is already in progress, the Contractor shall   proceed   with   the   execution   of   the   Works, including maintenance thereof, pending receipt of the decision   of   the   competent   authority   as   aforesaid, with all due diligence.   25. Arbitration  Either party will have the right of appeal against the decision of the competent authority, nominated under Clause 24, to the Madhya Pradesh Arbitration Tribunal constituted   under   Madhya   Pradesh   Madhyastham Adhikaran   Adhiniyam   1983   provided   the   amount   of claim is more than Rs. 50,000/­. 44.  Liquidated Damages  44.1  The Contractor shall pay liquidated damages to the Employer at the rate per week or part thereof stated in the Contract Data  for  the  period  that  the Completion Data is later than the Intended Completion Date. Liquidated damages at the same rate shall be withheld   if   the   Contractor   fails   to   achieve   the milestones prescribed in the Contract Data. However, 7 in case the Contractor achieves the next milestone the amount   of   the   liquidated   damages   already   withheld shall be restored to the Contractor by adjustment in the   next   payment   certificate.   The   total   amount   of liquidated   damages   shall   not   exceed   the   amount defined   in   the   Contract   Data.   The   Employer   may deduct liquidated damages from payments due to the Contractor. Payment of liquidated damages shall not affect the Contractor’s other liabilities. 53.  Payment upon Termination  53.1  If   the   contract   is   terminated   because   of   a fundamental breach of contract by the contractor, the Engineer shall issue a certificate for value of the work done and materials ordered less liquidated damages, if any, less advance payments received up to the date of the issue of the certificate and less the percentage to apply   to   the   value   of   the   work   not   completed   as indicated in the Contract Data. If the total amount due to   the   Employer   exceeds   any   payment   due   to   the Contractor, the difference shall be recovered from the security   deposit   and   performance   security,   if   any amount   is   still   left   un­recovered   it   will   be   a   debt payable to the Employer.”  10. In   terms   of   the   clauses   44.1   read   with   53.1   of   the agreement, it emerges that if there are liquidated damages to be payable upon termination of contract by the contractor, inbuilt redressal system has been provided under Clause 24 which, in the instant cases, was invoked through the General Manager of st the 1  respondent and the party aggrieved thereof can certainly approach   to   the   Arbitral   Tribunal   constituted   under   the Adhiniyam, 1983 in terms of clause 25 of the agreement. 8 11. Indisputedly,   in   the   instant   cases,   for   both   the   two st agreement   nos.   11   and   12,   the   general   manager   of   the   1 respondent quantified the liquidated damages as alleged and that has been the subject matter of challenge raised by the appellant in the reference petitions filed before the Arbitral Tribunal under Section   7   of   the   Adhiniyam,   1983   which   is   still   pending adjudication and once the remedial mechanism provided under the Adhiniyam, 1983 has been availed by the appellant which is pending   adjudication,   the   respondents   were   not   justified   in initiating the recovery proceedings without awaiting the outcome of the arbitral proceedings.  It is the settled principles of law that a party to an agreement cannot be an arbiter in his own cause. 12. This exposition of law has been considered by this Court in State   of   Karnataka  Vs.  Shree   Rameshwara   Rice   Mills 1987(2) SCC 160.  Relevant para 7 is extracted as Thirthahalli   under:­  On   a   consideration   of   the   matter   we   find “7. ourselves   unable   to  accept   the   contentions   of   Mr Iyenger. The terms of clause 12 do not afford scope for a liberal construction being made regarding the powers of the Deputy Commissioner to adjudicate upon a disputed question of breach as well as to assess  the damages arising   from  the breach. The 9 crucial words in clause 12 are “and for any breach of conditions set forth hereinbefore, the first party shall be liable to pay damages to the second party as may be assessed by the second party”. On a plain reading of the words it is clear that the right of the second party   to   assess   damages   would   arise   only   if   the breach of conditions is admitted or if no issue is made of it. If is was the intention of the parties that the officer  acting on behalf of the State was also entitled to adjudicate upon a dispute regarding the breach of conditions the wording of clause 12 would have been entirely different. It cannot also be argued that a right to adjudicate upon an issue relating to a breach of conditions of the contract would flow from or is inhered in the right conferred to assess the damages arising from a breach of conditions. The power to assess damages, as pointed out by the Full Bench, is a subsidiary and consequential power and not   the   primary   power.  Even   assuming   for argument's sake that the terms of clause 12 afford scope for being construed as empowering the officer of the State to decide upon the question of breach as well as assess the quantum of damages, we do not think that adjudication by the officer regarding the breach of the contract can be sustained under law because   a   party   to   the   agreement   cannot   be   an arbiter in his own cause. Interests of justice and equity   require   that   where   a   party   to   a   contract disputes the committing of any breach of conditions the   adjudication   should   be   by   an   independent person or body and not by the other party to the contract.   The   position   will,   however,   be   different where   there   is   no   dispute   or   there   is   consensus between the contracting parties regarding the breach of conditions. In such a case the officer of the State, even   though   a   party   to   the   contract   will   be   well within   his   rights   in   assessing   the   damages occasioned   by   the   breach   in   view   of   the   specific terms of clause 12.” (emphasis supplied) 13. Taking assistance of the judgment of this Court, the full Bench   of   the   Madhya   Pradesh   High   Court   also   in   the   case reported in   B.B. Verma and another (supra) observed that the 10 Government or its officers were not justified to initiate recovery proceedings   which   is   disputed   by   the   contractor   as   payable under the contract by the State Government pending decision of the Arbitral Tribunal constituted under the Adhiniyam, 1983.  It goes   without   saying   that   when   the   contractor   disputes   the damages claimed by the Authority or any Officer in its behalf, such an amount cannot be said to be due under the contract and cannot be recovered as arrear of land revenue until adjudicated in the pending reference before the Arbitral Tribunal. 14. In  Virendra Sharma Vs. State of Madhya Pradesh and th Ors.  (Civil Appeal No. 5169 of 2016 decided on 13  May, 2016), in   the   similar   circumstances,   this   Court   has   considered   the terms and conditions of the contract of which a reference has been made where the contract was terminated on the ground that the contractor could not complete the work within the stipulated period   and   the   department   suffered   huge   losses.     When   the demand was raised by the department that was challenged by the contractor   invoking   arbitration   and   pending   adjudication,   the recovery   which   was   invoked   by   the   respondents   was   not 11 considered to be legally sustainable in law.   The extract of the order is as under:­ O R D E R “Leave granted.  Admitted   facts   are   that   the   appellant   was awarded   a   contract   by   the   respondents.   The contract was terminated on the ground that the appellant could not complete the work within the stipulated   period.   The   Superintendent   Engineer also arrived at a conclusion that because of the alleged   breach   of   contract   by   the   appellant, Department had suffered loss and the amount of such loss be returned. The appellant did not agree with the same and as per the procedure prescribed in the contract, invoked arbitration.  Admittedly,   the   matter   is   before   the Arbitrator and no adjudication has taken place. It has yet to determine as to whether the decision of the Superintendent Engineer that the Department has suffered the loss, is correct or not.  In   these   circumstances,   inasmuch   as   the amount   becomes   due   and   payable   only   after adjudication, we are of the view that the recovery of the said amount cannot be made invoking the procedure   of   Land   Revenue   Act.   The   recovery orders   are,   accordingly,   set   aside.   It   would, however,   be   open   to   the   Department   to   take further steps only after the Award is rendered by the   Arbitrator   depending   upon   the   outcome thereof.  The appeal stands disposed of.” 15. We are also of the considered view that once the dispute is pending   adjudication   before   the   Arbitral   Tribunal   constituted 12 under   the   Adhiniyam,   1983   in   terms   of   clause   25   of   the agreement, the respondent, in the facts and circumstances, was not justified to raise demand on termination of contract claiming liquidated damages and the respondent cannot become an arbiter in its own cause and unless the dispute is settled by a procedure prescribed under the law, the respondents would not be held to be   justified   in   initiating   recovery   proceedings   invoking   the procedure under the Land Revenue Act. 16.  The submission of the learned counsel for the respondents that   the   liquidated   damages   were   determined   by   the   General st Manager   of   the   1   respondent   after   adjudication   in   terms   of clause 24   of   the   agreement   and   accordingly,   the   respondents were   justified   in   initiating   recovery   proceedings   is   without substance   for   the   reason   that   clause   24   of   the   agreement provides an inbuilt mechanism but the decision of the competent authority is to be examined invoking clause 25 for arbitration by the Arbitral Tribunal on a reference if made under Section 7 of the Adhiniyam, 1983. 17. Indisputedly, in the instant cases, the reference petition is pending before the Arbitral Tribunal in reference to the liquidated damages claimed by the respondents.   As long as the dispute 13 remained pending adjudication, it was not justified on the part of the   respondents   to   initiate   recovery   proceedings   invoking   the procedure   under   the   Land   Revenue   Act   without   awaiting   the outcome of the arbitral proceedings. 18. Consequently,   the   appeals   succeed   and   are   accordingly th allowed.  The judgments of the High Court impugned dated 26 th February, 2018 & 7  September, 2018 are hereby quashed and set aside.  It is further made clear that what has been observed by us is only for the purpose of disposal of the instant appeals and the Arbitral Tribunal may not be influenced/inhibited by the observations   made   and   decide   the   pending   reference   petition independently in accordance with law.  No costs. 19. Pending application(s), if any, stand disposed of. …………………………J. (N.V. RAMANA) …………………………J. (INDIRA BANERJEE) ..……………………….J. (AJAY RASTOGI) NEW DELHI th 30  August, 2019 14   15