1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 10143 OF 2016
(@ S.L.P. (C) No. 29297 of 2016)
Montecarlo Ltd. …Appellant(s)
VERSUS
NTPC Ltd. …Respondent(s)
J U D G M E N T
Dipak Misra, J.
The respondent, NTPC Limited, had issued separate
invitation for bids for development and operation of three coal
JUDGMENT
mines, viz., Dulanga Coal Block, Chatti Bariatu and Talaipalli
in the State of Odisha. Online bids were invited on Single
Stage Two Envelope Bidding basis (Envelope-I:
Techno-Commercial Bid and Envelope-II: Price Bid). There was
stipulation for Reverse Auction from the eligible bidders. It was
also stated in the Invitation For Bids (IFB) issued on
22.01.2016 that the bids shall be received on 17.03.2016 and
Page 1
2
Envelope-I, that is, Techno-Commercial Bid will be opened on
17.03.2016. The date of opening of Envelope-II, that is, Price
Proposal shall be intimated separately. Clause 5 of the IFB
stipulated Qualifying Requirements (QR). Clauses 5.1 and
5.1.2 dealt with technical criteria.
2. The respondent had also issued “Instructions To Bidders”
(ITB) which contain clauses as to how the proposal shall be
conducted. Clause 6.3.1 of ITB deals with Preliminary
Examination of Techno-Commercial Proposals. We think it
appropriate to reproduce the same:-
“6.3.1 Preliminary Examination of
Techno-Commercial Proposals:
(a) OWNER will examine the Project Proposals to
determine whether they are complete, whether
required securities have been furnished, whether
the documents have been properly signed and
whether the bids are generally in order.
JUDGMENT
(b) Prior to the detailed evaluation, OWNER will
initially determine whether each Techno
Commercial Proposal is of acceptable quality, is
generally complete and is substantially responsive
to the bidding documents. For purposes of this
determination, a substantially responsive Proposal
is one that conforms to all the terms, conditions and
specifications of the bidding documents without
material deviations, objections, conditionalities or
reservations. A material deviation, objection,
conditionality or reservation is one (i) that affects in
any substantial way the scope, quality or
Page 2
3
performance of the contract; (ii) that limits in any
substantial way, inconsistent with the bidding
documents, the Owner’s rights or the successful
Bidder’s obligations under the contract; or (iii)
whose rectification would unfairly affect the
competitive position of other Bidders who are
presenting substantially responsive Proposals.
(c) OWNER’s determination of a Techno Commercial
Proposal’s responsiveness is to be based on the
contents of the Techno Commercial Proposal itself
without recourse to extrinsic evidence. If a Techno
Commercial Proposal is not substantially
responsive, it will be rejected by OWNER, and may
not subsequently be made responsive by the Bidder
by correction of the nonconformity.”
3. Clauses 6.3.2 6.3.2.1, 6.3.2.2 and 6.3.4 provide for
Evaluation of Responsive Techno-Commercial Proposal,
Evaluation of Qualification Proposals, Evaluation of Technical
Proposals and Clarification Meeting. Clause 6.3.5 deals with
the steps where the responsive Techno-Commercial Proposal
JUDGMENT
which meets the QR specified in Chapter 7 and Technical
Requirements specified in Chapter 8 of REF Documents and
stipulates that they shall be considered for Price Proposal
Phase of the Bidding Process. It has also been provided therein
that the bidders who meet QR specified in Chapter 7 and
Technical Requirements specified in Chapter 8 of REP
documents shall be terms as “shortlisted bidders”. Chapter 7
Page 3
4
of ITB deals with technical criteria. Clauses 7.1.1 and 7.1.2,
being significant, are extracted below:-
“7.1.1 The Bidder should have, in the preceding 7
(seven) years reckoned from the date of opening of
the Techno-commercial Bids developed & operated
single coal/lignite mine having coal/lignite reserves
of at least 150 million tonnes & annual capacity of
at least 6 MTPA and produced at least 2 million
tonnes of coal/lignite from such mine.
OR
7.1.2 The Bidder should have, in the preceding 7
(seven) years reckoned from the date of opening of
the Techno-commercial Bids, operated and
produced:
a) At least 23 Million SCM of aggregated volume of
overburden and/or coal/lignite from a maximum of
seven open cast mines of Coal/Lignite, in any year.
b) At least 11.5 Million SCM of composite volume of
overburden and coal/lignite from single open cast
mine in any year, out of which at least 3 million
tonnes shall be coal/lignite.
JUDGMENT
The qualifying works at clause 7.1.2(a) can be from
same mine or different mines including the mine
considered to meet qualifying requirement at clause
7.1.2(b).”
4. At this stage, it is necessary to refer to Notes appended to
Clause 7.3.3 that deals with route-3. Notes are as under:-
“i. The word “operated” means that the Bidder
should have performed the necessary activities of
drilling, excavation, hauling etc. on its own or
through sub-contracting.
Page 4
5
ii. The word “developed” means that the Bidder
should have performed the necessary activities of
Land Acquisition/assisted in Land Acquisition,
Statutory clearances/assisted in Statutory
clearances and carried out ‘Infrastructure
development’ on its own or through
sub-contracting.”
5. Chapter 9 of the ITB deals with Evaluation Methodology
for Techno- Commercial Proposal (Qualification Proposal and
Technical Proposal). Clause 9.1 deals with Evaluation of
Qualification Proposal and Clause 9.2 deals with Evaluation of
Technical Proposal. They read as under:-
“9. Evaluation Methodology for Techno Commercial
Proposal (Qualification Proposal and Technical
Proposal)
9.1 Evaluation of Qualification Proposal:
The Techno-Commercial Proposal shall be
scrutinized to establish “responsiveness” as per
Clause 6.3.1.
JUDGMENT
The Responsive Techno-Commercial Proposal shall
be evaluated in detail to determine their fulfillment
of Qualifying requirements specified in Chapter 7 of
this RFP document.
During the bid evaluation, NTPC may, at its
discretion, ask the Bidder for a clarification of its
Qualification Proposal including documentary
evidence pertaining to only the reference mines
declared in the Qualification Proposal for the
purpose of meeting Qualifying Requirement
specified in Chapter 7 of this RFP document. The
request for clarification and the response shall be in
Page 5
6
writing and no change in the substance of the
TECHNO-COMMERCIAL Proposal including
substitution of reference mines in the Qualification
Proposal by new/additional mines for conforming to
Qualifying Requirement shall be sought, offered or
permitted.
9.2 Evaluation of Technical Proposal:
The Technical Proposals shall be evaluated to
determine their compliance with the Technical
Proposal Requirements. For this purpose, NTPC
shall use the supporting documents and/or
information available with or obtained by NTPC.
9.2.1 During evaluation NTPC may seek clarification
from the Bidders, may conduct discussions with the
Bidders, and may ask the bidder to make Technical
presentation.
Technical proposal shall include details as has been
sought vide Chapter 8.
JUDGMENT
9.2.2 The Technical Proposals without sufficient
information as per the terms of Chapter 8 of this
document shall be deemed “Non Responsive
Technical Proposal”.
9.2.3 The Responsive Technical Proposals meeting
the requirements to the satisfaction of Owner shall
be considered for further detailed Technical
Evaluation.”
[emphasis added]
Page 6
7
6. Clause 9.3 provides how detailed evaluation of technical
proposals submitted by the bidder shall take place. Clauses
9.3.1 and 9.3.2 which are relevant for the present purpose are
reproduced below:-
“9.3.1 The purpose of technical evaluation is to
check responsive and assess the compliance with
the requirements of NTPC.
9.3.2 To ensure effective evaluation of Technical
Proposals the Bidders shall provide the necessary
details as specified in Clause 8.4. The Technical
evaluation will be for evaluating whether the
Technical Proposal of the Bidder meets the following
criteria.
(a) Time Schedule to Achieve First Year Coal
Production Target – NTPC shall evaluate the PERT
chart submitted by the Bidder, to determine its
completeness; reasonableness; and achievability.
(b) Adequacy of the Equipment Plan – The Bidder
shall submit an equipment plan giving details of the
equipment that shall be used by the Mine Operator
to provide Mining Services which shall be not less
than the Minimum Equipment to be deployed as
specified by NTPC at Schedule 6 of Project
Agreement. NTPC shall evaluate the adequacy of
equipment to meet the criteria imposed by NTPC in
terms of quantity of production, quality of coal
produced etc.”
JUDGMENT
[emphasis supplied]
7. The controversy in the instant case basically pertains to
whether the appellant meets the qualification criteria as
provided under the heading Technical Criteria that occurs in
Page 7
8
Clauses 7.1 and 7.2 of QR. To appreciate the same, it is
essential to have a look at the bid submitted by the appellant.
The appellant had uploaded the proposal on 26.4.2016 by
| es in sup<br>have bee | port of it<br>n referre |
|---|
| e three mines tha<br>Mata No Madh, | | | |
|---|
| | | |
| ne Kundada OCP of Western Coalfield Limited (Mine 2)<br>Khadia OCP, Northern Coalfield Limited (Mine 3).<br>ards the Mine No. 1, the appellant declaring the scop<br>rk in the aforesaid Mine had furnished the following deta<br>“Sl Particulars Mine 1 (Lignite Project,<br>. Mata No Madh, Kutch)<br>No.<br>10. Brief description of Turnkey mining Contract<br>scope of work involving overburden/inter<br>burden removal,<br>excavation and/or loading<br>JUDGMENT<br>of lignite from mines face<br>and ancillary activities<br>11. Drilling Yes/No<br>Carried out Drilling Our own/subcontracting<br>on our own or<br>through<br>subcontracting<br>Excavation Yes/No<br>Carried out Our own/subcontracting<br>Excavation on our<br>own or through<br>subcontracting<br>Hauling Yes/No. | | | |
| “Sl<br>.<br>No. | Particulars | Mine 1 (Lignite Project,<br>Mata No Madh, Kutch) | |
| 10. | Brief description of<br>scope of work i<br>JUDG | Turnkey mining Contract<br>nvolving overburden/inter<br>burden removal,<br>excavation and/or loading<br>MENT<br>of lignite from mines face<br>and ancillary activities | |
| 11. | Drilling | Yes/No | |
| Carried out Drilling<br>on our own or<br>through<br>subcontracting | Our own/subcontracting | |
| Excavation | Yes/No | |
| Carried out<br>Excavation on our<br>own or through<br>subcontracting | Our own/subcontracting | |
| Hauling | Yes/No. | |
Page 8
9
| Carried out<br>Excavation on our<br>own or through<br>subcontracting | Our own/subcontracting” |
|---|
8. As the proposal would reflect, the appellant had not
provided the information that it had carried out the drilling in
the aforesaid Mine, namely, Mata No Madh. The
respondent-owner sent a communication on 17.5.2016 seeking
certain clarification pertaining to the QR and other aspects.
The High Court has referred to the said communication and we
think it necessary to reproduce the same:-
“Ref:01/CS-7014-602(R1)-9-PAA Dated: 17.05.2016
To,
M/s. Montecarlo Limited,
706, Ship Building, Near Municipal Market,
C.G. Road, Navrangpura, Ahmedabad-380 009,
Gujarat, India
Kind Attn. Sh. Shekhar Shanna, Sr. General
Manager
JUDGMENT
Sub: Development and Operation of Dulanga Coal
Block as per IFB No. 40051319; Bid Doc.
No.CS-7014-802(R1)-9
Dear Sir,
1.0 This has reference to your Project Proposal
(Techno-Commercial Bid) against IFB No.40051319
for the subject package. You are requested to
Page 9
10
furnish the following information with respect to the
details/documents furnished in the bid for
qualification requirement data:
(i) Against QR requirement of Clause 7.1.2 of
ITB : It is observed in the Contract Agreement dtd.
11.02.2014 submitted by the bidder in support of
meeting qualifying requirement for Lignite project
Mata No Madh, Kutch, Gujrat that the necessary
activity of drilling as per stipulations of QR (sr.no. i
of Notes) is not mentioned. The same may please be
clarified with supporting documents.
(ii) Against QR requirement of Clause 7.2 of ITB:
Details of Other non cash expenses in Million for
calculating Annual Cash Accrual for three year viz.
2013-14, 2014-15 & 2015-16
2.0 It is requested that the requisite information
along with necessary documents be furnished to us
at the earliest, preferably by 24.05.2016.
3.0 It may please be noted that seeking the above
clarifications should not be construed that the bid
submitted by you is considered techno commercially
responsive and/or meeting the Qualification
requirements (QR).”
JUDGMENT
9. The response that was given by the appellant on
21.5.2016 is to the following effect:-
“A) Para 1.0 (i) of your above letter against QR of
Clause 7.1.2 of ITB: We are attaching the followings:
a) A certificate from GMDC (client of our Lignite
Project at Mata No Math) Vide
No.GMDC/MMLG/298/2016-17 dated 18.05.2016
mentioning our scope on this Turnkey Project which
includes activities of Mine Planning, Quality
Control, Drilling, Ripping, Dust suppression, Nala
Page 10
11
Diversion, preparation of Garland drain, dewatering
of Monsoon and seepage water, preparation and
monitoring of haul road for better hauling as
required to complete the mining process.
b) Certificates from Northern Coalfields Ltd. (NCL)
and Western Coalfields Ltd. (WCL) are also attached
herewith mentioning drilling as part of the Mining
Process of these projects as ready reference:
i) NCL Certificate No.GM/KSL/2016/460 dated
31.03.2016
ii) NCL Certificate No.GM/KSL/25 dated 24.04.2016
iii)NCL Certificate No.GM/KHD/OS/2016/43 dated
23.04.2015
iv)WCL Certificate No.
WCL/MA/MGR/JKOC/2015/400 dated 04.12.2015
v) WCL Certificate No.
WCL/MA/MGR/JKOC/2015/27 dated 14.04.2016
Further, as you are kindly aware that Indian Lignite
deposits occur in the Tertiary sediments in southern
and western parts of peninsular shield particularly
in Tamilnadu, Rajasthan and Gujarat. The
Overburden and interburden comprises of Clay,
Claystone, mudstone and as well as lignite
[Geologically younger sediments (Formations) then
occurrences of Coal] which can be excavated by
hydraulic Shovel dumper combination. As such, in
lignite deposits of Tamilnadu, Gujarat and
Rajasthan, Blast hole drilling is normally not
required.
JUDGMENT
B) Para 1.0 (ii) of your above letter against QR of
Clause 7.2 of ITB:
We are attaching the following:
a) Financial certificate of last 3 years
We hope that the above submission clarifies your
points on QR requirement;
Page 11
12
If your require further clarification/information in
this regard, kindly inform us. We shall be pleased to
provide the same at your convenience.”
10. To the said letter, a document issued by the Gujarat
| MDC) dated<br>as follows:- |
|---|
| neral Development Corporation Ltd (GMD<br>s enclosed. The said certificate reads as fo<br>“GMDC/MMLG/298/2016-17 Dated<br>To Whom It May Concern<br>This is to certify that the Turnkey Mi<br>involving Overburden/Inter burde<br>Excavation and/or Loading of Lignite<br>face and ancillary activities at Lignite<br>No Madh Vide Tender Notice No. (R1)/<br>dated 30.08.2013, has been awar<br>Montecarlo Limited, having registered<br>Floor, Shilp Building, Nr. Municipal<br>Road, Navrangpura, Ahmedabad – 380 | MD<br>as fo |
Name of Work: Turnkey Mining Contract involving
Overburden/Inter burden removal, Excavation
and/or loading of Lignite from mines face and
ancillary activities at Lignite project, Mata No Madh.
JUDGMENT
Name of Contractor : M/s. Montecarlo Limited
LOI No. : GMDC/LP/13306/13-14
Dated: 15/01/2014
Estimated Cost/
Contract Value : 663.04 Cr.
Awarded Quantity : Over Burden (1109.00)
Lac CUM
Lignite (148.00) Lac MT
Contract Period : 28.01.2014 to 27.01.2019
Page 12
13
The scope of Project is to carry out mining operation
on Turnkey basis comprising of removal of over
burden, inter burden and lignite and/or loading
from mines faces using hydraulic showel and
dumper combination and other activities like Mine
Planning, Quality control, Drilling, Ripping, Dust
suppression, Nala Diversion, preparation of Garland
drain, dewatering of Monsoon and seepage water,
preparation and monitoring of haul road for better
hauling etc. as required to complete the mining
process.
Quantities Executed (year-wise) by M/s. Montecarlo
Limited are shown below:
| Sr.<br>No | Period | Over Burd<br>Removal<br>(cum) | en Lignite<br>Dispatched<br>(MT) | Total Work<br>Done Amount<br>(Rs.) |
|---|
| 1 | 28.01.2014<br>To<br>31.03.2014 | 18,24,674.0 | 3 7,64,791.18 | 33,59,23,240.<br>00 |
| 2 | 01.04.2014<br>To<br>31.03.2015 | 1,37,54,520<br>6 | .7 32,10,961.46 | 135,57,06,36<br>4.00 |
| 3 | 01.04.2015<br>To<br>31.03.2016 | 1,45,66,445<br>2 | .2 13,68,861.67 | 55,38,02.,253<br>.00 |
JUDGMENT
M/s. Montecarlo Limited successfully carried out
Dewatering of Mine. Yearwise details are shown for
dewatering by deploying high capacities of Diesel
and Electrical operated pump:
| Sr. No. | Period | Dewatering in Lac m3 |
|---|
| 1. | 01.04.2015<br>To<br>31.03.2016 | 65.0 |
Page 13
14
This certificate is issued as per their request vide
letter no. ML(P)/mn/4190/clt/2016-17/020 date:
18.05.16 for applying tender.”
11. On the basis of the said communications, the respondent
formed an opinion that the bid of the appellant was technically
non-responsive. The reason for arriving at the said conclusion
by the respondent was that the appellant did not have
necessary experience of drilling for blasting purposes. As the
appellant was regarded as technically non-responsive, it
invoked the jurisdiction of the High Court challenging the said
determination made by the respondent. It was contended
before the High Court that the tender documents that
contained QR was of the experience of a bidder in only drilling,
excavation and hauling, etc. and not blasting or drilling for
blasting purposes. It was further urged that the scope of work
JUDGMENT
for Dulanga Mines projects which was taken into consideration
by the respondent in evaluating the technical proposal of the
petitioner as being non-responsive had been wrongly
understood. The stand of NTPC before the High Court was that
the assessment by the Technical Committee was absolutely
justified and the writ petitioner therein did not meet the QR
and, therefore, was treated as non-responsive.
Page 14
15
12. The High Court referred to how tender documents that
reflected the nature of mine operations, how blasting is an
inherent part and drilling is differently understood in the sense
that the appellant had understood. Thereafter, placing reliance
1
on Tata Cellular v. Union of India and Michigan Rubber
2
(India) Ltd. v. State of Karnataka and Ors. , it came to hold
that the decision taken by the owner was correct and did not
adversely affect public interest but subserved the public
purpose. Being of this view, the High Court dismissed the writ
petition. Hence, the present appeal by special leave.
13. We have heard Mr. P. Chidambram and Mr. Harin P.
Raval, learned senior counsel with Mr. Sandeep Singh, learned
counsel for the appellant and Mr. Vikas Singh, learned senior
counsel with Mr. Ankit Jain, learned counsel for the
JUDGMENT
respondent.
14. The dispute and the dissention between the parties rest
on how the Chapter 7 (QR) of ITB that contains Clause 7.2 that
deals with technical criteria is to be understood. We are not
1
(1994) 6 SCC 651
2
(2012) 8 SCC 216
Page 15
16
really concerned with Clause 7.1. The centrality of controversy
hinges on the interpretation to be placed on Clause 7.1.2. It is
submitted by Mr. Chidambram, learned senior counsel
appearing for the appellant that the appellant satisfied the
condition as postulated in the QR under Clause 7.1.2 (a) and
Clause 7.1.2 (a) stipulates that 23 Million BCM of aggregated
volume of overburden and/or coal/lignite from a maximum of
seven open cast mines of coal/Lignite, in any year and clause
7.1.2. (b) lays down that at least 11.5 Million BCM of composite
volume of overburden and coal/lignite from single open cast
mine in any year, out of which at least 3 million tones shall be
coal/lignite. Learned senior counsel would lay emphasis on
the documents which the appellant had filed to show that it
had operated and produced from single mine 11.5 Million BCM
JUDGMENT
of composite volume of overburden and coal/lignite from single
open cast mine in a year. Mr. Singh, learned senior counsel
resisting the said stance would urge that the appellant does not
satisfy the condition of drilling as is required under the QR
regard being had to the nature of work. In this context, we may
usefully take note of the definition of “operated”. The said
term, as defined, means activities of drilling and excavation.
Page 16
17
The documents produced by the appellant indicate the scope of
work including activities of operation of coal/lignite mine. It
reads as follows:-
| | | | |
|---|
| “10. | The scope of work includes the following activities of<br>operation of the Coal/Lignite Mine | | | |
| Drilling | Yes/No | Yes/No | Yes/No |
| Carried out<br>Drilling on<br>our own or<br>through<br>sub<br>contracting | Our own/sub<br>contracting | Our own/<br>sub<br>contracting | Our<br>own/sub<br>contracting |
| Excavation | Yes/No | Yes/No | Yes/No |
| Carried out<br>Excavation<br>on our own<br>or through<br>sub<br>contracting | Our own/ su<br>contracting | b Our own/sub<br>contracting | Our own/<br>sub<br>contracting |
| Hauling | Yes/No | Yes/No | Yes/No |
| Carried out<br>Hauling on<br>our own or<br>through<br>sub<br>contracting | Our own/sub<br>contracting<br>JUDG | Our own/<br>sub<br>contracting<br>MENT | Our own/<br>sub<br>contracting |
| S.<br>No. | Particulars | Mine 1 | Mine 2 | Mine 3 |
|---|
| 11 | Annual<br>Production<br>in Million<br>Bank<br>Cubic | Year (From<br>01.04.2014<br>to<br>31.03.2015) | Year (From<br>01.04.2014<br>to<br>31.03.2015) | Year (From<br>01.04.2014<br>to<br>31.03.2015) |
Page 17
18
| Meters.<br>Bidder to<br>refer Note<br>(vii) of the<br>Qualifyin<br>g<br>Requirem<br>ents of<br>Chapter 7 | Coal/<br>Lignite<br>(in<br>MT) | Overbur<br>(in<br>Million<br>BCM) | den Coal/<br>Lignite<br>(in MT) | Overb<br>urden<br>(in<br>Million<br>BCM) | Coal<br>/Lig<br>nite<br>(in<br>MT) | Over<br>burden<br>(in<br>Million<br>BCM) |
|---|
| | 3.210<br>Million<br>Tonne | 13.754 | 1.221<br>Million<br>Tonne | 3.386 | - | 12.707” |
| 15. We have already analysed what is covered by the word<br>“operated” as per ITB. In this regard, the High Court has<br>referred to Schedule II that deals with description of mining<br>services. Clause 5 deals with the Mine Operations. We think it<br>appropriate to reproduce Clauses 5.1, 5.9 and 5.10 of the | | | | | | | |
JUDGMENT
“5.1. The Mine Operator shall construct and operate
the Site in accordance with the following scope:
(a) Plan the mine (Site), its development and
construction
(b) Strip OB and store such OB on dumps
(c) Mine and extract coal in accordance with the
requirements of Owner
(d) Make provisions for HEMM, other mining
machinery and its effective maintenance
(e) Implement, and comply with EMP and
environmental clearances;
Page 18
19
(f) Construction, maintenance and operation of mine
dewatering plant, sump, and garland drains with
de-silting provisions
(g) Construct and maintain all access ways and haul
roads
(h) Arrangement and use of explosives, as per
Indian Explosives Act
(i) Drilling and blasting
(j) Construction and maintenance of wokshops,
stores etc as per the requirement.
(k) Construction, Operation and maintenance of
complete power supply system.
(l) Mine illumination as per prevalent laws
(m) Arrangement of petrol/diesel, oil and lubricants.
(n) (if applicable) control any spontaneous
combustion on Site
(o) Conduct advance infill drilling.
(p) OB dump management including rehandling of
internal dump as per Environmental Clearance.
(q) Progressive mine closure with effective land
reclamation plan in accordance with approved mine
closure plan. The Mine Operator shall submit to
the Owner the annual financial statement of cost
incurred towards progressive mine closure activities
duly certified by National Environmental
Engineering Research Institute (NEERI) or Central
Mine Planning & Design Institute Limited (CMPDIL)
or any other institute as may be notified by the
Government for these purpose to an acceptable level
by the Coal Controller.
JUDGMENT
(r) POL Store shed
(s) Development of Power Supply Distribution
System beyond 33KV switchgear breaker terminals
Page 19
20
of Darlipalli STPP for various equipments/facilities
included in Mine Operator’s scope.
x x x
5.9 Blasting:
Blasting shall be required for coal and selectively for
overburden with the objective of achieving good
fragmentation so that the excavators can operate at
high levels of efficiency.
5.10 Overburden and Inter burden Removal:
The terms overburden and interburden are each
included in the term overburden below unless noted
otherwise. The Mine Operator shall ensure the
following in respect of Overburden removal:
(a) The Mine Operator shall assess the admissibility
of accommodation of OB volume in the external
dump/in-pit-dump and accordingly if warranted,
notify or seek necessary clearances/ approvals from
appropriate authority, keeping in view the
stipulation of MoEF, contained in Forest Clearance
Stage – 1, dated 10.01.2014.
(b) The Mine Operator’s daily and weekly scheduling
shall be consistent with the AAPP. All levels,
benches, haul roads, and highwalls shall be
consistent with the Monthly Production Plans and
the statutory requirements.
JUDGMENT
(c) Weekly digging plans shall contain recommended
methods for excavation and removal of overburden
including blasting plans if needed.
(d) The Owner shall not be responsible for any costs
associated with the Mine Operator inefficiently
scheduling daily and weekly activities.
(e) The Mine Operator considers itself fully aware of
conditions of the Overburden in the mining area. No
claim for lack of knowledge of the site conditions
shall be allowed.
Page 20
21
(f) Reasonable efforts shall be made to keep coal
clean and free from soil, overburden, rock, clay,
parting bands, steel, stones, timber, rags,
equipment parts or any other deleterious material.
(g) The Mine Operator shall ensure the quality of the
coal is not affected by its mining methods which
cause coal ash to rise above the target levels
presented in AAPP.
(h) Water in the pit shall be kept to a minimum.
(i) Fires or hot spots in the coal shall be handled
expeditiously and not transported to the crusher.
The Owner shall be notified of any significant
occurrence. Oxidized coal shall be treated as
Overburden for compensation purposes.
(j) Any equipment repairs on the coal bench shall be
cleaned after use to prevent contamination.
(k) All equipment shall undergo pre shift inspections
including loose bucket teeth or other parts.
(l) The Mine Operator shall be responsible to provide
equipment to suit the varying thickness of the
seams and partings which must be mined.
(m) The Owner may instruct the Mine Operator to
maintain an overburden or inter burden cover over
in-pit coal inventory prior to mining.
JUDGMENT
(n) If, during the excavation or overburden, any coal
is found, the Mine Operator shall inform the Owner
and seek instructions before proceeding.
Overburden shall be hauled and placed in areas as
shown in the Mining Plan.
(o) Reject coal placed in overburden or interburden
dumps shall be buried in 5 meter lifts and
compacted to ensure no ingress of air which could
cause spontaneous combustion. The Mine Operator
shall be required, at its own expense, to dig out,
compact and replace any smouldering dump area.
Page 21
22
(p) Placement of overburden shall be carried out
with due regard to water run off, final topography,
and long term ground stabilization.
(q) Any erosion or land slip in areas of placed
materials shall be rectified by the Mine Operator at
its own expense.”
16. Clause 5.7.2. deals with drilling and blasting. It is as
follows:-
“5.7.2. Drilling & Blasting
Crawler-mounted pneumatically operated down the
hold drilling rigs are capable to meet the future
requirement of 8 m/hr will be deployed for OB.
R.B.H. drills will be used for drilling about 160 mm
dia. holes in coal.
After shot holes are drilled into the horizontal bench
cut by the shovel, the faces are blasted using
explosives and detonators. Coal is also extracted
after blasting off the coal faces.
Drilling & Blasting would be required both in OB
and Coal, benches, before excavation by shovel.
Except for coal benched which will be mined by
CSMs Heavy ANFO type/Slurry Emulsion is
proposed to be used based on the daily
requirement. However, flexibility may have to be
provided for usage of suitable alternative/available
explosives as per the requirement.”
JUDGMENT
17. We have referred to these clauses which are technical but
they are fundamental to understand the QR. They clearly
demonstrate that drilling is imperative. Mr. Chidambram,
learned senior counsel for the appellant would argue with all
Page 22
23
the conviction at his command that the appellant is engaged in
drilling in Lignite and the tender requirement was coal/lignite.
According to the learned senior counsel, drilling in lignite
would meet the requirement but the owner has travelled
beyond the postulates of the QR to insist on drilling for the
purpose of blasting. We have already referred to the certificate
issued by GMDC in favour of the appellant and the documents
filed by the appellant. The High Court has considered the
documents and opined that the documents filed in support of
the QR are substantially inadequate. Adverting to the facet of
drilling, the writ court has opined that there is specific use of
the words “drilling for the purposes of blasting”. It is urged by
Mr. Chidambram and Mr. Raval, learned senior counsel that in
the absence of a definitive prescription, the court cannot add
JUDGMENT
an attribute or quality component to the qualifying clause. In
this regard, we may usefully refer to certain authorities. In
Sterling Computers Limited v. M/s M & N Publications
3
Limited & Ors , the Court has held that under some special
circumstances a discretion has to be conceded to the
authorities who have to enter into contract giving them liberty
3
(1993) 1 SCC 445
Page 23
24
to assess the overall situation for purpose of taking a decision
as to whom the contract be awarded and at what terms. It has
also been observed that by way of judicial review the court
cannot examine the details of the terms of the contract which
have been entered into by the public bodies or the State.
Courts have inherent limitations on the scope of any such
enquiry.
18. In Tata Cellular (supra) a three-Judge Bench after
referring to earlier decisions culled out certain principles,
namely, (a) the modern trend points to judicial restraint in
administrative action, (b) the court does not sit as a court of
appeal but merely reviews the manner in which the decision
was made, (c) the court does not have the expertise to correct
the administrative decision. If a review of the administrative
JUDGMENT
decision is permitted it will be substituting its own decision,
without the necessary expertise which itself may be fallible,
and (d) the Government must have freedom of contract and
that permits a fair play in the joints as a necessary
concomitant for an administrative body functioning in an
administrative sphere or quasi-administrative sphere. Hence,
the Court has laid down that the decision must not only be
Page 24
25
tested by the application of Wednesbury principle of
reasonableness (including its other facts pointed out above) but
must be free from arbitrariness not affected by bias or actuated
by mala fides.
4
19. In Jagdish Mandal v. State of Orissa and Ors the
Court has held that a contract is a commercial transaction.
Evaluating tenders and awarding contracts are essentially
commercial functions. Principles of equity and natural justice
stay at a distance. If the decision relating to award of contract
is bona fide and is in public interest, courts will not, in exercise
of power of judicial review, interfere even if a procedural
aberration or error in assessment or prejudice to a tenderer, is
made out.
20. In Master Marine Services (P) Ltd. v. Metcalfe &
JUDGMENT
5
Hodgkinson (P) Ltd and Anr , it has been ruled that the State
can choose its own method to arrive at a decision and it is free
to grant any relaxation for bona fide reasons, if the tender
conditions permit such a relaxation. It has been further held
that the State, its corporations, instrumentalities and agencies
4
(2007) 14 SCC 517
5
(2005) 6 SCC 138
Page 25
26
have the public duty to be fair to all concerned. Even when
some defect is found in the decision-making process, the court
must exercise its discretionary powers under Article 226 with
great caution and should exercise it only in furtherance of
public interest and not merely on the making out of a legal
point.
21. In B.S.N. Joshi & Sons Ltd. v. Nair Coal Services Ltd .
6
and Ors. a two-Judge Bench, after referring to series of
judgments has culled out certain principles which include the
one that where a decision has been taken purely on public
interest, the court ordinarily should apply judicial restraint.
22. In Michigan Rubber (India) Ltd. (supra) the Court
referred to the earlier judgments and opined that before a court
interferes in tender or contractual matters, in exercise of power
JUDGMENT
of judicial review should pose to itself the question whether the
process adopted or decision made by the authority is mala fide
or intended to favour someone or whether the process adopted
or decision made is so arbitrary and irrational that the judicial
conscience cannot countenance. Emphasis was laid on the
6
( 2006) 11 SCC 548
Page 26
27
test, that is, whether award of contract is against public
interest.
23. Recently in Afcons Infrastructure Ltd. v. Nagpur Metro
7
Rail Corporation Ltd. a two-Judge Bench eloquently
exposited the test which is to the following effect:-
“We may add that the owner or the employer of a
project, having authored the tender documents, is
the best person to understand and appreciate its
requirements and interpret its documents. The
constitutional Courts must defer to this
understanding and appreciation of the tender
documents, unless there is mala fide or perversity
in the understanding or appreciation or in the
application of the terms of the tender conditions. It
is possible that the owner or employer of a project
may give an interpretation to the tender documents
that is not acceptable to the constitutional Courts
but that by itself is not a reason for interfering with
the interpretation given.”
24. We respectfully concur with the aforesaid statement of
law. We have reasons to do so. In the present scenario, tenders
JUDGMENT
are floated and offers are invited for highly complex technical
subjects. It requires understanding and appreciation of the
nature of work and the purpose it is going to serve. It is
common knowledge in the competitive commercial field that
technical bids pursuant to the notice inviting tenders are
7
2016 (8) SCALE 765
Page 27
28
scrutinized by the technical experts and sometimes third party
assistance from those unconnected with the owner’s
organization is taken. This ensures objectivity. Bidder’s
expertise and technical capability and capacity must be
assessed by the experts. In the matters of financial
assessment, consultants are appointed. It is because to check
and ascertain that technical ability and the financial feasibility
have sanguinity and are workable and realistic. There is a
multi-prong complex approach; highly technical in nature. The
tenders where public largesse is put to auction stand on a
different compartment. Tender with which we are concerned,
is not comparable to any scheme for allotment. This arena
which we have referred requires technical expertise.
Parameters applied are different. Its aim is to achieve high
JUDGMENT
degree of perfection in execution and adherence to the time
schedule. But, that does not mean, these tenders will escape
scrutiny of judicial review. Exercise of power of judicial review
would be called for if the approach is arbitrary or malafide or
procedure adopted is meant to favour one. The decision making
process should clearly show that the said maladies are kept at
bay. But where a decision is taken that is manifestly in
Page 28
29
consonance with the language of the tender document or
subserves the purpose for which the tender is floated, the court
should follow the principle of restraint. Technical evaluation or
comparison by the court would be impermissible. The principle
that is applied to scan and understand an ordinary instrument
relatable to contract in other spheres has to be treated
differently than interpreting and appreciating tender
documents relating to technical works and projects requiring
special skills. The owner should be allowed to carry out the
purpose and there has to be allowance of free play in the joints.
25. In view of the aforesaid analysis, we do not perceive any
infirmity in the judgment and order passed by the High Court
and, accordingly, the appeal stands dismissed. In the facts
and circumstances of the case, there shall be no order as to
JUDGMENT
costs.
..............................J.
(Dipak Misra)
..............................J.
(Uday Umesh Lalit)
New Delhi;
October 18, 2016.
Page 29