Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
CASE NO.:
Appeal (civil) 5824 of 2002
PETITIONER:
Haryana Urban Development Authority
RESPONDENT:
Smt. Suman Bansal
DATE OF JUDGMENT: 28/07/2004
BENCH:
S. N. VARIAVA & ARIJIT PASAYAT.
JUDGMENT:
J U D G M E N T
S. N. VARIAVA, J.
Before this Court a large number of Appeals have been
filed by the Haryana Urban Development Authority and/or the
Ghaziabad Development Authority challenging Orders of the National
Consumer Disputes Redressal Commission, granting to Complainants,
interest at the rate of 18% per annum irrespective of the fact of each
case. This Court has, in the case of Ghaziabad Development Authority
vs. Balbir Singh reported in (2004) 5 SCC 65, deprecated this practice.
This Court has held that interest at the rate of 18% cannot be granted
in all cases irrespective of the facts of the case. This Court has held
that the Consumer Forums could grant damages/compensation for
mental agony/harassment where it finds misfeasance in public office.
This Court has held that such compensation is a recompense for the
loss or injury and it necessarily has to be based on a finding of loss or
injury and must co-relate with the amount of loss or injury. This Court
has held that the Forum or the Commission thus had to determine that
there was deficiency in service and/or misfeasance in public office and
that it has resulted in loss or injury. This Court has also laid down
certain other guidelines which the Forum or the Commission has to
follow in future cases.
This Court is now taking up the cases before it for disposal as
per principles set out in earlier judgment. On taking the cases we find
that the copies of the Claim/Petitions made by the
Respondent/Complainant and the evidence, if any, led before the
District Forum are not placed in the paper book. This Court has before
it the Order of the District Forum. The facts are thus taken from that
Order.
In this case the Respondent was allotted a plot bearing No. 77,
Sector 21, Panchkula, in the year 1987. The Respondent paid all dues.
The plot allotted turned out to be encroached upon. Thus Complainant
could not take possession. In spite of several requests and letters the
Appellants did not remove the encroachments and/or take any steps to
give possession. Thus the Respondent filed a complaint before the
District Forum.
The District Forum directed delivery of possession and awarded
interest on the compensation amount at the rate of 15% p.a. from 1st
August, 1990 till payment. The District Forum also directed payment
of Rs.20,000/- on account of mental agony and harassment and costs
of Rs.1,000/-. We are told that possession has since been given.
The State Forum confirmed the Award in the Appeal filed by the
Appellants. The Appellants filed a Revision before the National
Commission. The National Commission has increased the rate of
interest to 18% p.a.
For reasons set out in the Judgment in the case Ghaziabad
Development Authority vs. Balbir Singh (supra), the order of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
National Commission cannot be sustained. As stated above, the
relevant papers regarding the claim made, the affidavits filed, the
evidence submitted before the District Forum are not produced before
this Court. In this case, the District Forum has ensured that the
possession is given at the old rate. Where possession is given at old
rate the party has got benefit of escalation in price of land, thus there
cannot and should not also be award of interest on the money.
However, considering the fact that the allotment was in 1987 and
possession given very late, i.e., only in 1998, compensation towards
mental agony/harassment is very low. Compensation should have
been awarded for escalation in costs of construction. The finding of
the District Forum that there was no proof is not correct. It is a fact of
which judicial notice should have been taken, that construction costs
have gone up. In future compensation must be given under this head.
On an ad hoc basis we maintain the Award of interest at 15% instead
of increasing compensation for mental agony and harassment and
awarding compensation for escalation in costs of construction. We
thus see no reason to interfere in this case.
We clarify that this Order shall not be taken as a precedent in
any other matter as it has been passed by taking into account special
features of the case. The Forum/Commission will follow the principles
laid down by this Court in the case of Ghaziabad Development
Authority vs. Balbir Singh (supra) in future cases.
The Appeal is disposed off in above terms. There will be no
order as to costs.